Virginia Electric and Power Company; North Anna Unit 3, 27296-27297 [2017-12271]

Download as PDF 27296 Federal Register / Vol. 82, No. 113 / Wednesday, June 14, 2017 / Notices should be emailed to the DFO one day before the meeting. If an electronic copy cannot be provided within this timeframe, presenters should provide the DFO with a CD containing each presentation at least thirty minutes before the meeting. Electronic recordings will be permitted only during those portions of the meeting that are open to the public. Detailed procedures for the conduct of and participation in ACRS meetings were published in the Federal Register on October 17, 2016, (81 FR 71543). Detailed meeting agendas and meeting transcripts are available on the NRC Web site at https://www.nrc.gov/readingrm/doc-collections/acrs. Information regarding topics to be discussed, changes to the agenda, whether the meeting has been canceled or rescheduled, and the time allotted to present oral statements can be obtained from the Web site cited above or by contacting the identified DFO. Moreover, in view of the possibility that the schedule for ACRS meetings may be adjusted by the Chairman as necessary to facilitate the conduct of the meeting, persons planning to attend should check with these references if such rescheduling would result in a major inconvenience. If attending this meeting, please enter through the One White Flint North Building, 11555 Rockville Pike, Rockville, Maryland 20852. After registering with Security, please contact Mr. Theron Brown (Telephone 240– 888–9835) to be escorted to the meeting room. Dated: June 2, 2017. Mark L. Banks, Chief, Technical Support Branch, Advisory Committee on Reactor Safeguards. [FR Doc. 2017–12268 Filed 6–13–17; 8:45 am] BILLING CODE 7590–01–P NUCLEAR REGULATORY COMMISSION [Docket No. 52–017; NRC–2008–0066] Virginia Electric and Power Company; North Anna Unit 3 Nuclear Regulatory Commission. ACTION: Combined licenses and record of decision; issuance. mstockstill on DSK30JT082PROD with NOTICES AGENCY: The U.S. Nuclear Regulatory Commission (NRC) has issued a combined license (No. NPF–103) to Virginia Electric and Power Company (doing business as Dominion Virginia Power) for North Anna Unit 3. In addition, the NRC has prepared a SUMMARY: VerDate Sep<11>2014 17:36 Jun 13, 2017 Jkt 241001 Summary Record of Decision (ROD) that supports the NRC’s decision to issue the above-named combined license. DATES: Combined license NPF–103 became effective on June 2, 2017. ADDRESSES: Please refer to Docket ID NRC–2008–0066 when contacting the NRC about the availability of information regarding this document. You may obtain publicly-available information related to this document using any of the following methods: • Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC–2008–0066. Address questions about NRC dockets to Carol Gallagher; telephone: 301–415–3463; email: Carol.Gallagher@nrc.gov. For technical questions, contact the individuals listed in the FOR FURTHER INFORMATION CONTACT section of this document. • NRC’s Agencywide Documents Access and Management System (ADAMS): You may obtain publiclyavailable documents online in the ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/ adams.html. To begin the search, select ‘‘ADAMS Public Documents’’ and then select ‘‘Begin Web-based ADAMS Search.’’ For problems with ADAMS, please contact the NRC’s Public Document Room (PDR) reference staff at 1–800–397–4209, 301–415–4737, or by email to pdr.resource@nrc.gov. For the convenience of the reader, the ADAMS accession numbers are provided in a table in the ‘‘Availability of Documents’’ section of this document. • NRC’s PDR: You may examine and purchase copies of public documents at the NRC’s PDR, Room O1–F21, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852. FOR FURTHER INFORMATION CONTACT: James Shea, telephone: 301–415–1388, email: James.Shea@nrc.gov regarding safety matters; or Tamsen Dozier, telephone: 301–415–2272, email: Tamsen.Dozier@nrc.gov regarding environmental matters. Both are staff of the Office of New Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555–0001. SUPPLEMENTARY INFORMATION: I. Introduction Under section 2.106 of title 10 of the Code of Federal Regulations (10 CFR), the NRC is providing notice of the issuance of combined license NPF–103 to Virginia Electric and Power Company. Under 10 CFR 50.102(c), the NRC is providing notice of the Commission’s Memorandum and Order documenting its final decision on the uncontested hearing, which serves as PO 00000 Frm 00073 Fmt 4703 Sfmt 4703 the ROD in this proceeding. With respect to the application for combined licenses filed by Virginia Electric and Power Company, the NRC finds that the applicable standards and requirements of the Atomic Energy Act of 1954, as amended, (AEA) and the Commission’s regulations have been met. The NRC finds that any required notifications to other agencies or bodies have been duly made and that there is reasonable assurance that the facilities will be constructed and will operate in conformity with the license, the provisions of the AEA, and the Commission’s regulations. Furthermore, the NRC finds that Virginia Electric and Power Company is technically and financially qualified to engage in the activities authorized, and that issuance of the licenses will not be inimical to the common defense and security or to the health and safety of the public. Finally, the NRC has determined that the findings required by subpart A of 10 CFR part 51 have been made. Accordingly, the combined license was issued on June 2, 2017, and became effective immediately. II. Further Information The NRC has prepared a Final Safety Evaluation Report (FSER) and Final Supplemental Environmental Impact Statement (FSEIS) that document the information reviewed and the NRC’s conclusion. The Commission has also issued its memorandum and order documenting its final decision on the uncontested hearing held on March 23, 2017, which serves as the ROD in this proceeding. The NRC also prepared a document summarizing the ROD to accompany its actions on the combined license application; this ‘‘Summary ROD’’ incorporates by reference materials contained in the FSEIS. The FSER, FSEIS, Summary ROD, and accompanying documentation included in the combined license package, as well as the Commission’s hearing decision and Summary ROD, are available online in the ADAMS Public Document collection at https:// www.nrc.gov/reading-rm/adams.html. From this site, persons can access the NRC’s ADAMS, which provides text and image files of NRC’s public documents. III. Availability of Documents The documents identified in the following table are available to interested persons through the ADAMS Public Documents collection. A copy of the combined license application is also available for public inspection at the NRC’s PDR and at https://www.nrc.gov/ reactors/new-reactors/col.html. E:\FR\FM\14JNN1.SGM 14JNN1 27297 Federal Register / Vol. 82, No. 113 / Wednesday, June 14, 2017 / Notices Document ADAMS Accession No. Final Safety Evaluation Report for Combined License for North Anna Unit 3 ................................................................................... Final Supplemental Environmental Impact Statement for Combined License (COL) for North Anna Unit 3 ..................................... Commission’s Memorandum and Order on the uncontested hearing (Record of Decision) .............................................................. Summary Record of Decision ............................................................................................................................................................. Letter transmitting Combined License No. NPF–103 and accompanying documentation ................................................................. Combined License No. NPF–103 ....................................................................................................................................................... ML16259A210 ML100680117 ML17151A406 ML17121A548 ML17128A500 ML17095A813 Dated at Rockville, Maryland, this 2nd day of June 2017. For the Nuclear Regulatory Commission. Francis M. Akstulewicz, Director, Division of New Reactor Licensing, Office of New Reactors. [FR Doc. 2017–12271 Filed 6–13–17; 8:45 am] BILLING CODE 7590–01–P NUCLEAR REGULATORY COMMISSION Atomic Safety and Licensing Board [Docket Nos. 52–040–COL and 52–041– COL; ASLBP No. 10–903–02–COL–BD01] In the Matter of Florida Power & Light Company (Turkey Point Units 6 and 7) June 8, 2017. Before Administrative Judges: E. Roy Hawkens, Chairman, Dr. Michael F. Kennedy, Dr. William C. Burnett Notice and Order (Scheduling and Providing Instructions for Oral Argument) Pending before this Licensing Board is a request for a hearing and petition to intervene submitted on April 18, 2017 by the City of Miami, the Village of Pinecrest, and the City of South Miami (Petitioners).1 Petitioners’ proffered contention alleges that: The [Final Safety Evaluation Report (FSER)] is deficient in concluding that [Florida Power & Light Company (FPL)] has demonstrated that it possesses or has reasonable assurance of obtaining the funds necessary to cover estimated construction costs and related fuel cycle costs and FPL has failed to indicate source(s) of funds to cover these costs.2 After reviewing the petition and the subsequently filed related pleadings,3 mstockstill on DSK30JT082PROD with NOTICES 1 See Petition for Leave to Intervene in a Hearing on [FPL’s] Combined Construction and Operating License Application for Turkey Point Units 6 & 7 and File a New Contention (Apr. 18, 2017) [hereinafter Petition]. 2 Petition at 7. 3 See NRC Staff’s Response to New Arguments Raised in Petitioners’ Reply (June 1, 2017); Petitioners’ Reply to NRC Staff and FPL’s Answers to Petition for Leave to Intervene in a Hearing on [FPL’s] Combined Construction and Operating License Application for Turkey Point Units 6 & 7 VerDate Sep<11>2014 17:36 Jun 13, 2017 Jkt 241001 the Board has determined that oral argument will assist it in resolving the issues presented. The Board will hold a telephonic oral argument concerning contention admissibility on Tuesday, June 20, 2017, at 2:00 p.m. EDT. The Board will hear argument from counsel for the parties in the following order: (1) Petitioners; (2) FPL; and (3) the NRC Staff. Petitioners will have 60 minutes of argument time, and they may reserve up to 20 minutes of that time for rebuttal. FPL and the NRC Staff will each have 30 minutes of argument time. The following list includes topics the parties should address during oral argument. This list is not intended to be exclusive. • Whether Westinghouse’s bankruptcy filing, the resulting alleged termination of its Reservation Agreement with FPL, or the lack of a construction agreement between Westinghouse and FPL raise a genuine dispute on a material issue of law or fact with FPL’s application for a combined license • Whether FPL’s ability to recover costs is material to the NRC Staff’s determination of FPL’s financial qualifications • Whether Westinghouse’s bankruptcy raises a genuine dispute on a material issue if FPL’s ability to recover costs is not material to the NRC Staff’s determination of FPL’s financial qualifications • The extent of the NRC Staff’s review of an applicant’s financial qualifications and the degree to which an applicant must be financially qualified to engage in construction of new nuclear units • The feasibility of the Turkey Point project following Westinghouse’s bankruptcy • The effect on the petition of FPL’s May 1 filing to the Florida Public Service Commission to request a deferral of nuclear cost recovery • The effect on the petition of FPL’s May 1 representation to the Florida Public Service Commission that the Turkey Point project is on a ‘‘pause’’ On or before Friday, June 16, parties shall provide by email to the Board and the service list the name of the attorney and File a New Contention (May 22, 2017); NRC Staff Answer to Petition for Leave to Intervene and [File] New Contention (May 15, 2017); [FPL’s] Answer Opposing [Petitioners’] Petition to Intervene and Request for Hearing Regarding the Combined Construction and Operating License Application for Turkey Point Units 6 & 7 (May 15, 2017). PO 00000 Frm 00074 Fmt 4703 Sfmt 4703 who will present oral argument. The Board’s law clerk, Kimberly Hsu, will provide the dial-in number and passcode to be used by counsel for the oral argument. No witnesses, other representatives of the parties, or members of the public will be heard during the argument. However, individuals who wish to hear the oral argument live on the listen-only telephone line may do so, and should contact Ms. Hsu at Kimberly.Hsu@ nrc.gov or (301) 415–5939 for the dialin number and passcode. It is so ordered. Rockville, Maryland. Dated: June 8, 2017. For the Atomic Safety and Licensing Board. E. Roy Hawkens, Chairman, Administrative Judge. [FR Doc. 2017–12358 Filed 6–13–17; 8:45 am] BILLING CODE 7590–01–P NUCLEAR REGULATORY COMMISSION [Docket Nos. 72–1014, 72–59, and 50–271; NRC–2017–0134] Entergy Nuclear Operations, Inc.; Vermont Yankee Nuclear Power Station; Independent Spent Fuel Storage Installation Nuclear Regulatory Commission. ACTION: Exemption; issuance. AGENCY: The U.S. Nuclear Regulatory Commission (NRC) is issuing an exemption in response to a request submitted by Entergy Nuclear Operations, Inc. (Entergy) on November 9, 2016, and supplemented on January 9, 2017, for its general license to operate an independent spent fuel storage installation (ISFSI) at the Vermont Yankee Nuclear Power Station (VYNPS). This exemption would permit the VYNPS to load and store certain lowenriched channeled undamaged fuel assemblies with higher enriched fuel assemblies in the same HI–STORM 100 multi-purpose canister (MPC)–68M using Certificate of Compliance (CoC) No. 1014, Amendment No. 10. SUMMARY: E:\FR\FM\14JNN1.SGM 14JNN1

Agencies

[Federal Register Volume 82, Number 113 (Wednesday, June 14, 2017)]
[Notices]
[Pages 27296-27297]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-12271]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No. 52-017; NRC-2008-0066]


Virginia Electric and Power Company; North Anna Unit 3

AGENCY: Nuclear Regulatory Commission.

ACTION: Combined licenses and record of decision; issuance.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) has issued a 
combined license (No. NPF-103) to Virginia Electric and Power Company 
(doing business as Dominion Virginia Power) for North Anna Unit 3. In 
addition, the NRC has prepared a Summary Record of Decision (ROD) that 
supports the NRC's decision to issue the above-named combined license.

DATES: Combined license NPF-103 became effective on June 2, 2017.

ADDRESSES: Please refer to Docket ID NRC-2008-0066 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly-available information related to this document 
using any of the following methods:
     Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2008-0066. Address 
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: Carol.Gallagher@nrc.gov. For technical questions, contact 
the individuals listed in the FOR FURTHER INFORMATION CONTACT section 
of this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to pdr.resource@nrc.gov. For 
the convenience of the reader, the ADAMS accession numbers are provided 
in a table in the ``Availability of Documents'' section of this 
document.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

FOR FURTHER INFORMATION CONTACT: James Shea, telephone: 301-415-1388, 
email: James.Shea@nrc.gov regarding safety matters; or Tamsen Dozier, 
telephone: 301-415-2272, email: Tamsen.Dozier@nrc.gov regarding 
environmental matters. Both are staff of the Office of New Reactors, 
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001.

SUPPLEMENTARY INFORMATION:

I. Introduction

    Under section 2.106 of title 10 of the Code of Federal Regulations 
(10 CFR), the NRC is providing notice of the issuance of combined 
license NPF-103 to Virginia Electric and Power Company. Under 10 CFR 
50.102(c), the NRC is providing notice of the Commission's Memorandum 
and Order documenting its final decision on the uncontested hearing, 
which serves as the ROD in this proceeding. With respect to the 
application for combined licenses filed by Virginia Electric and Power 
Company, the NRC finds that the applicable standards and requirements 
of the Atomic Energy Act of 1954, as amended, (AEA) and the 
Commission's regulations have been met. The NRC finds that any required 
notifications to other agencies or bodies have been duly made and that 
there is reasonable assurance that the facilities will be constructed 
and will operate in conformity with the license, the provisions of the 
AEA, and the Commission's regulations. Furthermore, the NRC finds that 
Virginia Electric and Power Company is technically and financially 
qualified to engage in the activities authorized, and that issuance of 
the licenses will not be inimical to the common defense and security or 
to the health and safety of the public. Finally, the NRC has determined 
that the findings required by subpart A of 10 CFR part 51 have been 
made.
    Accordingly, the combined license was issued on June 2, 2017, and 
became effective immediately.

II. Further Information

    The NRC has prepared a Final Safety Evaluation Report (FSER) and 
Final Supplemental Environmental Impact Statement (FSEIS) that document 
the information reviewed and the NRC's conclusion. The Commission has 
also issued its memorandum and order documenting its final decision on 
the uncontested hearing held on March 23, 2017, which serves as the ROD 
in this proceeding. The NRC also prepared a document summarizing the 
ROD to accompany its actions on the combined license application; this 
``Summary ROD'' incorporates by reference materials contained in the 
FSEIS. The FSER, FSEIS, Summary ROD, and accompanying documentation 
included in the combined license package, as well as the Commission's 
hearing decision and Summary ROD, are available online in the ADAMS 
Public Document collection at https://www.nrc.gov/reading-rm/adams.html. 
From this site, persons can access the NRC's ADAMS, which provides text 
and image files of NRC's public documents.

III. Availability of Documents

    The documents identified in the following table are available to 
interested persons through the ADAMS Public Documents collection. A 
copy of the combined license application is also available for public 
inspection at the NRC's PDR and at https://www.nrc.gov/reactors/new-reactors/col.html.

[[Page 27297]]



------------------------------------------------------------------------
                   Document                        ADAMS Accession No.
------------------------------------------------------------------------
Final Safety Evaluation Report for Combined     ML16259A210
 License for North Anna Unit 3.
Final Supplemental Environmental Impact         ML100680117
 Statement for Combined License (COL) for
 North Anna Unit 3.
Commission's Memorandum and Order on the        ML17151A406
 uncontested hearing (Record of Decision).
Summary Record of Decision....................  ML17121A548
Letter transmitting Combined License No. NPF-   ML17128A500
 103 and accompanying documentation.
Combined License No. NPF-103..................  ML17095A813
------------------------------------------------------------------------


    Dated at Rockville, Maryland, this 2nd day of June 2017.

    For the Nuclear Regulatory Commission.
Francis M. Akstulewicz,
Director, Division of New Reactor Licensing, Office of New Reactors.
[FR Doc. 2017-12271 Filed 6-13-17; 8:45 am]