Notice of Authorization for Continued Project Operation; Riverdale Power & Electric Co., Inc., 26924 [2017-12054]
Download as PDF
asabaliauskas on DSKBBXCHB2PROD with NOTICES
26924
Federal Register / Vol. 82, No. 111 / Monday, June 12, 2017 / Notices
flashboards; (2) an approximately 12acre impoundment having a storage
capacity of 135-acre-feet at a normal
maximum elevation of 668.38 feet above
mean sea level; (3) an 18.5-foot-wide
headworks structure with two
headgates; (4) a 290-foot-long partially
covered, power canal; (5) a gatehouse
with two 15-foot-wide trashracks with
1.5-inch clear spacing; (6) a 200-footlong, 6- to 10-foot-diameter metal
penstock that bifurcates before entering
two powerhouses; (7) a 47-foot-long, 25foot-wide powerhouse containing a
1,350 kilowatt (kW) horizontal turbinegenerator unit and a 40-foot-long, 40foot-wide powerhouse containing two
350 kW horizontal turbine-generator
units for a total capacity of 2,050 kW;
(8) a 350-foot-long, 2.4-kilovolt (kV)
above-ground generator lead that
connects the turbine-generator units to a
step-up transformer; (9) a 1.75-milelong, 12.5-kV above-ground
transmission line; and (10) appurtenant
facilities.
The Village of Lyndonville Electric
Department operates the project in a
run-of-river mode with an annual
average generation of approximately
3,960 megawatt-hours. The Village of
Lyndonville Electric Department is not
proposing any new project facilities or
changes in project operation.
o. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h above.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. With this notice, we are designating
Lyndonville Electric Department as the
Commission’s non-federal
representative for carrying out informal
consultation pursuant to section 7 of the
Endangered Species Act and
consultation pursuant to section 106 of
the National Historic Preservation Act.
q. Procedural schedule and final
amendments: The application will be
processed according to the following
preliminary Hydro Licensing Schedule.
Revisions to the schedule will be made
as appropriate.
Issue Acceptance or Deficiency Letter—
August 2017
VerDate Sep<11>2014
17:28 Jun 09, 2017
Jkt 241001
Request Additional Information—
August 2017
Issue Acceptance Letter—November
2017
Issue Scoping Document 1 for
Comments—December 2017
Request Additional Information (if
necessary)—February 2018
Issue Scoping Document 2—March 2018
Issue notice of ready for environmental
analysis—March 2018
Commission issues EA or draft EA—
September 2018
Comments on EA or draft EA—October
2018
Commission issues final EA—December
2018
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of the notice of ready for
environmental analysis.
Dated: June 5, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017–12053 Filed 6–9–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 9100–000]
Notice of Authorization for Continued
Project Operation; Riverdale Power &
Electric Co., Inc.
On April 27, 2017 Riverdale Power &
Electric Co., Inc., licensee for the
Riverdale Mills Hydroelectric Project,
filed an Application for a New License
pursuant to the Federal Power Act
(FPA) and the Commission’s regulations
thereunder. The Riverdale Mills
Hydroelectric Project facilities are
located on the Blackstone River in
Worcester County, Massachusetts.
The license for Project No. 9100 was
issued for a period ending May 31,
2017. Section 15(a)(1) of the FPA, 16
U.S.C. 808(a)(1), requires the
Commission, at the expiration of a
license term, to issue from year-to-year
an annual license to the then licensee
under the terms and conditions of the
prior license until a new license is
issued, or the project is otherwise
disposed of as provided in section 15 or
any other applicable section of the FPA.
If the project’s prior license waived the
applicability of section 15 of the FPA,
then, based on section 9(b) of the
Administrative Procedure Act, 5 U.S.C.
558(c), and as set forth at 18 CFR
16.21(a), if the licensee of such project
has filed an application for a subsequent
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
license, the licensee may continue to
operate the project in accordance with
the terms and conditions of the license
after the minor or minor part license
expires, until the Commission acts on
its application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 9100
is issued to the licensee for a period
effective June 1, 2017 through May 31,
2018 or until the issuance of a new
license for the project or other
disposition under the FPA, whichever
comes first. If issuance of a new license
(or other disposition) does not take
place on or before May 31, 2018, notice
is hereby given that, pursuant to 18 CFR
16.18(c), an annual license under
section 15(a)(1) of the FPA is renewed
automatically without further order or
notice by the Commission, unless the
Commission orders otherwise.
If the project is not subject to section
15 of the FPA, notice is hereby given
that the licensee, Riverdale Power &
Electric Co., Inc., is authorized to
continue operation of the Riverdale
Mills Hydroelectric Project, until such
time as the Commission acts on its
application for a subsequent license.
Dated: June 6, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017–12054 Filed 6–9–17; 8:45 am]
BILLING CODE 6717–01–P
FEDERAL COMMUNICATIONS
COMMISSION
[OMB 3060–xxxx]
Information Collection Being Reviewed
by the Federal Communications
Commission
Federal Communications
Commission.
ACTION: Notice and request for
comments.
AGENCY:
As part of its continuing effort
to reduce paperwork burdens, and as
required by the Paperwork Reduction
Act of 1995 (PRA), the Federal
Communications Commission (FCC or
Commission) invites the general public
and other Federal agencies to take this
opportunity to comment on the
following information collections.
Comments are requested concerning:
SUMMARY:
E:\FR\FM\12JNN1.SGM
12JNN1
Agencies
[Federal Register Volume 82, Number 111 (Monday, June 12, 2017)]
[Notices]
[Page 26924]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-12054]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 9100-000]
Notice of Authorization for Continued Project Operation;
Riverdale Power & Electric Co., Inc.
On April 27, 2017 Riverdale Power & Electric Co., Inc., licensee
for the Riverdale Mills Hydroelectric Project, filed an Application for
a New License pursuant to the Federal Power Act (FPA) and the
Commission's regulations thereunder. The Riverdale Mills Hydroelectric
Project facilities are located on the Blackstone River in Worcester
County, Massachusetts.
The license for Project No. 9100 was issued for a period ending May
31, 2017. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), requires
the Commission, at the expiration of a license term, to issue from
year-to-year an annual license to the then licensee under the terms and
conditions of the prior license until a new license is issued, or the
project is otherwise disposed of as provided in section 15 or any other
applicable section of the FPA. If the project's prior license waived
the applicability of section 15 of the FPA, then, based on section 9(b)
of the Administrative Procedure Act, 5 U.S.C. 558(c), and as set forth
at 18 CFR 16.21(a), if the licensee of such project has filed an
application for a subsequent license, the licensee may continue to
operate the project in accordance with the terms and conditions of the
license after the minor or minor part license expires, until the
Commission acts on its application. If the licensee of such a project
has not filed an application for a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b), to continue project operations
until the Commission issues someone else a license for the project or
otherwise orders disposition of the project.
If the project is subject to section 15 of the FPA, notice is
hereby given that an annual license for Project No. 9100 is issued to
the licensee for a period effective June 1, 2017 through May 31, 2018
or until the issuance of a new license for the project or other
disposition under the FPA, whichever comes first. If issuance of a new
license (or other disposition) does not take place on or before May 31,
2018, notice is hereby given that, pursuant to 18 CFR 16.18(c), an
annual license under section 15(a)(1) of the FPA is renewed
automatically without further order or notice by the Commission, unless
the Commission orders otherwise.
If the project is not subject to section 15 of the FPA, notice is
hereby given that the licensee, Riverdale Power & Electric Co., Inc.,
is authorized to continue operation of the Riverdale Mills
Hydroelectric Project, until such time as the Commission acts on its
application for a subsequent license.
Dated: June 6, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-12054 Filed 6-9-17; 8:45 am]
BILLING CODE 6717-01-P