Riverdale Power & Electric Co., Inc.; Notice of Application Tendered for Filing With the Commission and Establishing Procedural Schedule for Licensing and Deadline for Submission of Final Amendments, 21383-21384 [2017-09249]
Download as PDF
Federal Register / Vol. 82, No. 87 / Monday, May 8, 2017 / Notices
associated with, but not a part of, the
decisional record of the proceeding.
Unless the Commission determines that
the prohibited communication and any
responses thereto should become a part
of the decisional record, the prohibited
off-the-record communication will not
be considered by the Commission in
reaching its decision. Parties to a
proceeding may seek the opportunity to
respond to any facts or contentions
made in a prohibited off-the-record
communication, and may request that
the Commission place the prohibited
communication and responses thereto
in the decisional record. The
Commission will grant such a request
only when it determines that fairness so
requires. Any person identified below as
having made a prohibited off-the-record
communication shall serve the
document on all parties listed on the
official service list for the applicable
proceeding in accordance with Rule
2010, 18 CFR 385.2010.
Exempt off-the-record
communications are included in the
decisional record of the proceeding,
unless the communication was with a
cooperating agency as described by 40
CFR 1501.6, made under 18 CFR
385.2201(e)(1)(v).
The following is a list of off-therecord communications recently
Docket No.
received by the Secretary of the
Commission. The communications
listed are grouped by docket numbers in
ascending order. These filings are
available for electronic review at the
Commission in the Public Reference
Room or may be viewed on the
Commission’s Web site at https://
www.ferc.gov using the eLibrary link.
Enter the docket number, excluding the
last three digits, in the docket number
field to access the document. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov or toll free at (866) 208–3676, or
for TTY, contact (202) 502–8659.
File date
Prohibited:
1. CP14–529–000 ...................................................................................................
Exempt:
1. P–2100–000 ........................................................................................................
2. CP14–529–000 ...................................................................................................
3. P–13212–000 ......................................................................................................
2. P–2413–000 ........................................................................................................
3. CP14–529–000 ...................................................................................................
21383
Presenter or requester
4–28–2017
FERC Staff.1
4–18–2017
4–19–2017
4–21–2017
4–25–2017
4–26–2017
State of California Legislature.2
U.S. Senate.3
FERC Staff.4
U.S. Senator Johnny Isakson.
U.S. House Representative Richard E. Neal.
1 Phone
Memorandum reporting conversation on April 21, 2017 with Laura Friedman.
James Gallagher and Senator Jim Nielsen.
Elizabeth Warren and Edward J. Markey.
4 Telephone Conversation Memo dated April 21, 2017 reporting teleconference with Cory Warnock of Kenai Hydro, LLC.
2 Assemblyman
3 Senators
Dated: May 2, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017–09250 Filed 5–5–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 9100–040]
asabaliauskas on DSK3SPTVN1PROD with NOTICES
Riverdale Power & Electric Co., Inc.;
Notice of Application Tendered for
Filing With the Commission and
Establishing Procedural Schedule for
Licensing and Deadline for
Submission of Final Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Subsequent
Minor License.
b. Project No.: 9100–040.
c. Date Filed: April 27, 2017.
d. Applicant: Riverdale Power &
Electric Co., Inc. (Riverdale Power).
e. Name of Project: Riverdale Mills
Hydroelectric Project.
f. Location: On the Blackstone River
in Worcester County, Massachusetts.
There are no federal or tribal lands
within the project boundary.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)—825(r).
VerDate Sep<11>2014
18:27 May 05, 2017
Jkt 241001
h. Applicant Contact: Mr. Kevin
Young, Young Energy Services, LLC,
2112 Talmage Drive, Leland, NC 28451;
(617) 645–3658.
i. FERC Contact: Dr. Nicholas Palso,
(202) 502–8854 or nicholas.palso@
ferc.gov.
j. Cooperating agencies: Federal, state,
local, and tribal agencies with
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
document should follow the
instructions for filing such requests
described in item l below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See, 94
FERC 61,076 (2001).
k. Pursuant to section 4.32(b)(7) of the
Commission’s regulations, if any
resource agency, Indian Tribe, or person
believes that an additional scientific
study should be conducted in order to
form an adequate factual basis for a
complete analysis of the application on
its merit, the resource agency, Indian
Tribe, or person must file a request for
a study with the Commission not later
than 60 days from the date of filing of
the application, and serve a copy of the
request on the applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: June 26, 2017.
PO 00000
Frm 00020
Fmt 4703
Sfmt 4703
The Commission strongly encourages
electronic filing. Please file additional
study requests and requests for
cooperating agency status using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY). In lieu of
electronic filing, please send a paper
copy to: Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426. The first
page of any filing should include docket
number P–9100–040.
m. This application is not ready for
environmental analysis at this time.
n. The existing Riverdale Mills
Hydroelectric Project consists of: (1) A
10-foot-high, 142-foot-long dam with six
bays containing numerous stoplogs or
flashboards with a crest elevation of
262.35 feet above mean sea level; (2) an
11.8-acre impoundment; (3) three
sluiceways, one that is currently in use;
(4) a 150-kilowatt turbine-generator unit
located in a mill building; (5) a 231-footlong tailrace; and (6) appurtenant
facilities.
Riverdale Power operates the project
in a run-of-river mode with an annual
average generation of approximately 785
megawatt-hours. Riverdale Power is not
proposing any new project facilities or
changes in project operation.
E:\FR\FM\08MYN1.SGM
08MYN1
21384
Federal Register / Vol. 82, No. 87 / Monday, May 8, 2017 / Notices
o. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at
Riverdale Power’s office at 130
Riverdale Street, Northbridge, MA
01534.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. Procedural schedule and final
amendments: The application will be
processed according to the following
preliminary Hydro Licensing Schedule.
Revisions to the schedule will be made
as appropriate.
Issue Deficiency Letter (if necessary) ............................................................................................................................
Request Additional Information ......................................................................................................................................
Issue Acceptance Letter .................................................................................................................................................
Issue Scoping Document 1 for comments .....................................................................................................................
Request Additional Information (if necessary) ...............................................................................................................
Issue Scoping Document 2 ............................................................................................................................................
Issue notice of ready for environmental analysis ...........................................................................................................
Commission issues EA or draft EA ................................................................................................................................
Comments on EA or draft EA .........................................................................................................................................
Commission issues final EA ...........................................................................................................................................
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of the notice of ready for
environmental analysis.
of issuance of the Commission staff’s
Environmental Assessment (EA) for the
Project. This instant notice identifies the
FERC staff’s planned schedule for
completion of the EA for the Project.
Dated: May 2, 2017.
Kimberly D. Bose,
Secretary.
Schedule for Environmental Review
Issuance of the EA June 27, 2017
90-day Federal Authorization Decision
Deadline September 25, 2017
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the Project’s
progress.
[FR Doc. 2017–09249 Filed 5–5–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP17–15–000]
asabaliauskas on DSK3SPTVN1PROD with NOTICES
Dominion Cove Point LNG, LP; Notice
of Schedule for Environmental Review
of the Eastern Market Access Project
On November 15, 2016, Dominion
Cove Point LNG, LP (Dominion) filed an
application in Docket No. CP17–15–000
requesting a Certificate of Public
Convenience and Necessity pursuant to
section 7(c) of the Natural Gas Act to
construct and operate certain natural gas
pipeline facilities. DCP’s proposed
Eastern Market Access Project (Project)
in Maryland and Virginia would
transport about 294 million cubic feet
per day of firm natural gas service to
Washington Gas Light Company and
provide fuel to Mattawoman Energy,
LLC’s Mattawoman Energy Center
(power generation facility).
On November 30, 2016, the Federal
Energy Regulatory Commission (FERC
or Commission) issued its Notice of
Application for the Project. Among
other things, that notice alerted other
agencies issuing federal authorizations
of the requirement to complete all
necessary reviews and to reach a final
decision on the request for a federal
authorization within 90 days of the date
VerDate Sep<11>2014
18:27 May 05, 2017
Jkt 241001
Project Description
The Eastern Market Access Project
consists of a new 24,370 horsepower
(hp) compressor station and installation
of two new taps at an existing
Washington Gas Light Company
Interconnect in Charles County,
Maryland; one new 7,000 hp electricdriven compressor and replacement of
three existing gas coolers and
compression cylinders at the existing
Loudoun County Compressor Station,
and a new meter building to enclose
existing equipment at the Loudoun
Meter & Regulating Station in Loudoun
County, Virginia; and re-wheeling of the
compressor on a 17,400 hp electric unit
and upgrading two gas coolers at the
Pleasant Valley Compressor Station in
Fairfax County, Virginia.
Background
On February 15, 2017, the
Commission issued a Notice of Intent to
Prepare an Environmental Assessment
for the Proposed Eastern Market Access
Project, Request for Comments on
Environmental Issues, and Notice of
Public Scoping Session (NOI). The NOI
was sent to affected landowners; federal,
state, and local government agencies;
elected officials; environmental and
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
July 2017.
July 2017.
October 2017.
October 2017.
December 2017.
December 2017.
March 2018.
September 2018.
October 2018.
January 2019.
public interest groups; Native American
tribes; local libraries and newspapers;
and other interested parties. In response
to the Notice of Application and the
NOI, the Commission received 336
comments, including comments from 2
federal agencies, 4 local agencies, 4 state
agencies, 3 non-governmental agencies,
14 companies (including 6 chambers of
commerce), and 328 individuals. The
primary issues raised during scoping
include impacts on: Drinking water
supplies, surface waterbodies, and
wetlands; forested areas and wildlife;
surrounding land use; visual resources;
historic properties and Native American
tribes; air quality and noise; and public
safety.
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC Web
site (www.ferc.gov). Using the eLibrary
link, select General Search from the
eLibrary menu, enter the selected date
range and ‘‘Docket Number’’ excluding
the last three digits (i.e., CP17–15), and
follow the instructions. For assistance
with access to eLibrary, the helpline can
be reached at (866) 208–3676, TTY (202)
502–8659, or at
FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC Web site also
E:\FR\FM\08MYN1.SGM
08MYN1
Agencies
[Federal Register Volume 82, Number 87 (Monday, May 8, 2017)]
[Notices]
[Pages 21383-21384]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-09249]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 9100-040]
Riverdale Power & Electric Co., Inc.; Notice of Application
Tendered for Filing With the Commission and Establishing Procedural
Schedule for Licensing and Deadline for Submission of Final Amendments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Subsequent Minor License.
b. Project No.: 9100-040.
c. Date Filed: April 27, 2017.
d. Applicant: Riverdale Power & Electric Co., Inc. (Riverdale
Power).
e. Name of Project: Riverdale Mills Hydroelectric Project.
f. Location: On the Blackstone River in Worcester County,
Massachusetts. There are no federal or tribal lands within the project
boundary.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)--825(r).
h. Applicant Contact: Mr. Kevin Young, Young Energy Services, LLC,
2112 Talmage Drive, Leland, NC 28451; (617) 645-3658.
i. FERC Contact: Dr. Nicholas Palso, (202) 502-8854 or
nicholas.palso@ferc.gov.
j. Cooperating agencies: Federal, state, local, and tribal agencies
with jurisdiction and/or special expertise with respect to
environmental issues that wish to cooperate in the preparation of the
environmental document should follow the instructions for filing such
requests described in item l below. Cooperating agencies should note
the Commission's policy that agencies that cooperate in the preparation
of the environmental document cannot also intervene. See, 94 FERC
61,076 (2001).
k. Pursuant to section 4.32(b)(7) of the Commission's regulations,
if any resource agency, Indian Tribe, or person believes that an
additional scientific study should be conducted in order to form an
adequate factual basis for a complete analysis of the application on
its merit, the resource agency, Indian Tribe, or person must file a
request for a study with the Commission not later than 60 days from the
date of filing of the application, and serve a copy of the request on
the applicant.
l. Deadline for filing additional study requests and requests for
cooperating agency status: June 26, 2017.
The Commission strongly encourages electronic filing. Please file
additional study requests and requests for cooperating agency status
using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support
at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202)
502-8659 (TTY). In lieu of electronic filing, please send a paper copy
to: Secretary, Federal Energy Regulatory Commission, 888 First Street
NE., Washington, DC 20426. The first page of any filing should include
docket number P-9100-040.
m. This application is not ready for environmental analysis at this
time.
n. The existing Riverdale Mills Hydroelectric Project consists of:
(1) A 10-foot-high, 142-foot-long dam with six bays containing numerous
stoplogs or flashboards with a crest elevation of 262.35 feet above
mean sea level; (2) an 11.8-acre impoundment; (3) three sluiceways, one
that is currently in use; (4) a 150-kilowatt turbine-generator unit
located in a mill building; (5) a 231-foot-long tailrace; and (6)
appurtenant facilities.
Riverdale Power operates the project in a run-of-river mode with an
annual average generation of approximately 785 megawatt-hours.
Riverdale Power is not proposing any new project facilities or changes
in project operation.
[[Page 21384]]
o. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support. A copy is also available for inspection and
reproduction at Riverdale Power's office at 130 Riverdale Street,
Northbridge, MA 01534.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
p. Procedural schedule and final amendments: The application will
be processed according to the following preliminary Hydro Licensing
Schedule. Revisions to the schedule will be made as appropriate.
------------------------------------------------------------------------
------------------------------------------------------------------------
Issue Deficiency Letter (if July 2017.
necessary).
Request Additional Information... July 2017.
Issue Acceptance Letter.......... October 2017.
Issue Scoping Document 1 for October 2017.
comments.
Request Additional Information December 2017.
(if necessary).
Issue Scoping Document 2......... December 2017.
Issue notice of ready for March 2018.
environmental analysis.
Commission issues EA or draft EA. September 2018.
Comments on EA or draft EA....... October 2018.
Commission issues final EA....... January 2019.
------------------------------------------------------------------------
Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: May 2, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-09249 Filed 5-5-17; 8:45 am]
BILLING CODE 6717-01-P