Magnolia Water, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments and Motions To Intervene, 17421-17422 [2017-07243]
Download as PDF
Federal Register / Vol. 82, No. 68 / Tuesday, April 11, 2017 / Notices
performance. The information is
compiled using a standard chart of
accounts contained in the Commission’s
Uniform System of Accounts (USofA).2
The forms contain schedules which
include a basic set of financial
statements: Comparative Balance Sheet,
Statement of Income and Retained
Earnings, Statement of Cash Flows, and
the Statement of Comprehensive Income
and Hedging Activities. Supporting
schedules containing supplementary
information are filed, including
revenues and the related quantities of
products sold or transported; account
balances for various operating and
maintenance expenses; selected plant
cost data; and other information.
The information collected in the
forms is used by Commission staff, state
regulatory agencies and others in the
review of the financial condition of
regulated companies. The information is
also used in various rate proceedings,
industry analyses and in the
Commission’s audit programs and, as
appropriate, for the computation of
annual charges based on Page 520 of the
forms. The Commission provides the
information to the public, interveners
and all interested parties to assist in the
proceedings before the Commission.
Print versions of the Forms No. 2 and
2A are located on the Commission’s
Web site at https://www.ferc.gov/docsfiling/forms.asp#2.
17421
Type of Respondent: Each natural gas
company whose combined gas
transported or stored for a fee exceed 50
million dekatherms in each of the
previous three years must file the Form
2. Each natural gas company not
meeting the filing threshold for the
Form 2 but having total gas sales or
volume transactions exceeding 200,000
dekatherms in each of the previous
three calendar years must submit the
Form 2A.
Estimate of Annual Burden: 3 The
Commission estimates the annual public
reporting burden for the information
collection as:
FERC FORM NO. 2: ANNUAL REPORT OF MAJOR NATURAL GAS COMPANIES AND FERC FORM NO. 2A: ANNUAL REPORT
OF NON-MAJOR NATURAL GAS COMPANIES
Number of
respondents
Annual
number of
responses per
respondent
Total
number of
responses
Average
burden
hours and
cost per
response 4
Total annual
burden hours
and total
annual cost
Cost per
respondent
($)
(1)
(2)
(1) * (2) = (3)
(4)
(3) * (4) = (5)
(5) ÷ (1)
FERC Form No. 2 ................................
92
1
92
FERC Form No. 2A .............................
66
1
66
Comments: Comments are invited on:
(1) Whether the collection of
information is necessary for the proper
performance of the functions of the
Commission, including whether the
information will have practical utility;
(2) the accuracy of the agency’s estimate
of the burden and cost of the collection
of information, including the validity of
the methodology and assumptions used;
(3) ways to enhance the quality, utility
and clarity of the information collection;
and (4) ways to minimize the burden of
the collection of information on those
who are to respond, including the use
of automated collection techniques or
other forms of information technology.
Dated: April 5, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017–07241 Filed 4–10–17; 8:45 am]
srobinson on DSK5SPTVN1PROD with NOTICES
BILLING CODE 6717–01–P
2 See
18 CFR part 201.
Commission defines burden as the total
time, effort, or financial resources expended by
persons to generate, maintain, retain, or disclose or
provide information to or for a Federal agency. For
3 The
VerDate Sep<11>2014
20:18 Apr 10, 2017
Jkt 241001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14802–000]
Magnolia Water, LLC; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments and Motions To Intervene
On September 23, 2016, Magnolia
Water, LLC filed an application for a
preliminary permit, pursuant to section
4(f) of the Federal Power Act (FPA),
proposing to study the feasibility of the
Magnolia Water Pumped Storage
Hydroelectric Project (project) to be
located on Long Creek and the Kiamichi
River in Pushmataha County,
Oklahoma. The sole purpose of a
preliminary permit, if issued, is to grant
the permit holder priority to file a
license application during the permit
term. A preliminary permit does not
authorize the permit holder to perform
any land-disturbing activities or
otherwise enter upon lands or waters
further explanation of what is included in the
information collection burden, reference 5 Code of
Federal Regulations 1320.3.
4 The estimates for cost per response are derived
using the following formula: 2017 Average Burden
PO 00000
Frm 00015
Fmt 4703
Sfmt 4703
1,629
$124,619
253.39
$19,384
149,868
$11,464,902
16,724
$1,279,366
$124,619
19,384
owned by others without the owners’
express permission.
The proposed project would consist of
the following: (1) A 1,970-foot-long,
360-foot-high earthen upper dam across
Tombstone Creek; (2) a 100-foot-long,
3,400-foot-wide rock-lined upper
emergency spillway connecting to the
lower reservoir; (3) a 190-acre upper
reservoir having a total storage capacity
of 22,800 acre-feet; (4) an intake/outlet
structure in the upper reservoir; (5) four
3,500-foot-long, 22-foot-diameter steel
and reinforced concrete, tunneled
penstocks extending to the powerhouse;
(6) a 250-foot-long, 120-foot-wide
powerhouse, containing four pumpturbine generating units, with a total
generating capacity of 1,200 megawatts;
(7) four 30-foot-long, 400-foot-wide
tailrace pipes; (8) a 9,800-foot-long, 80foot-high earthen lower dam; (9) a 375acre lower reservoir having a total
storage capacity of 22,500 acre-feet; (10)
a 100-foot-long, 3,400-foot-wide rocklined lower emergency spillway
connecting to a creek flowing into the
Kiamichi River; (11) a 200-foot-long, 5foot-high concrete overflow diversion
Hours per Response * $76.50 per Hour = Average
Cost per Response. The hourly cost figure of $76.50
is the average FERC employee wage plus benefits.
We assume that respondents earn at a similar rate.
E:\FR\FM\11APN1.SGM
11APN1
srobinson on DSK5SPTVN1PROD with NOTICES
17422
Federal Register / Vol. 82, No. 68 / Tuesday, April 11, 2017 / Notices
weir across the Kiamichi River to
supply water to the project; (12) a 5-acre
impoundment on the Kiamichi River
with a storage capacity of 25 acre-feet;
(13) a 200-foot-long, 200-foot-wide
duplex pump station; (14) a 10,000-footlong, 24-inch-diameter steel water
supply pipe to the lower reservoir; (15)
a 90-mile-long, 345 kilovolt
transmission line; and (16) two new
access roads; one 6,800-foot-long road to
access the lower reservoir site, and one
11,500-foot-long road to access the
upper reservoir site. Both roads would
be constructed on private property to
perform studies. The estimated annual
generation of the project would be 3,400
gigawatt-hours.
Applicant Contact: Mr. Fred Brown,
Magnolia Water, LLC, 4265 Kellway
Circle, Addison, TX 75001; phone: (972)
239–0707.
FERC Contact: Navreet Deo; phone:
(202) 502–6304.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
The first page of any filing should
include docket number P–14802–000.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P–14802) in
the docket number field to access the
document. For assistance, contact FERC
Online Support.
Dated: April 5, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017–07243 Filed 4–10–17; 8:45 am]
BILLING CODE 6717–01–P
VerDate Sep<11>2014
20:18 Apr 10, 2017
Jkt 241001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER16–1411–002.
Applicants: CNR Energy LLC.
Description: Notice of Change in
Status of CNR Energy LLC.
Filed Date: 4/3/17.
Accession Number: 20170403–5638.
Comments Due: 5 p.m. ET 4/24/17.
Docket Numbers: ER17–1379–000.
Applicants: Southwest Power Pool,
Inc.
Description: § 205(d) Rate Filing:
Revisions to Attachment AE Section 8.4
Re-Pricing Clarification to be effective 6/
3/2017.
Filed Date: 4/4/17.
Accession Number: 20170404–5247.
Comments Due: 5 p.m. ET 4/25/17.
Docket Numbers: ER17–1380–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing: ISA
Service Agreement No. 4663, Queue
Position AB1–181 to be effective 3/7/
2017.
Filed Date: 4/5/17.
Accession Number: 20170405–5167.
Comments Due: 5 p.m. ET 4/26/17.
Docket Numbers: ER17–1381–000.
Applicants: AEM Wind, LLC.
Description: Baseline eTariff Filing:
Application for Market Based Rate to be
effective 6/7/2017.
Filed Date: 4/5/17.
Accession Number: 20170405–5174.
Comments Due: 5 p.m. ET 4/26/17.
Docket Numbers: ER17–1382–000.
Applicants: Southern California
Edison Company.
Description: § 205(d) Rate Filing: Two
DSA’s Three Valley MWD Williams and
Fulton Projects SA Nos. 955–956 to be
effective 3/31/2017.
Filed Date: 4/5/17.
Accession Number: 20170405–5232.
Comments Due: 5 p.m. ET 4/26/17.
Docket Numbers: ER17–1383–000.
Applicants: Southern California
Edison Company.
Description: § 205(d) Rate Filing: GIA
& DSA SEPV Kennedy Project SA Nos.
953–954 to be effective 6/5/2017.
Filed Date: 4/5/17.
Accession Number: 20170405–5233.
Comments Due: 5 p.m. ET 4/26/17.
Docket Numbers: ER17–1384–000.
Applicants: Southern California
Edison Company.
Description: § 205(d) Rate Filing: GIA
& DSA Green Beanworks B Project SA
Nos. 931–932 to be effective 6/5/2017.
PO 00000
Frm 00016
Fmt 4703
Sfmt 4703
Filed Date: 4/5/17.
Accession Number: 20170405–5234.
Comments Due: 5 p.m. ET 4/26/17.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: April 5, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017–07239 Filed 4–10–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
Filings Instituting Proceedings
Docket Numbers: RP17–638–000.
Applicants: Texas Gas Transmission,
LLC.
Description: Texas Gas Transmission,
LLC submits tariff filing per 154.204:
Cap Rel Neg Rate Agmts (SABIC 35303,
304, 305 to CIMA 36089, 105, 088) to be
effective 4/3/2017.
Filed Date: 04/04/2017.
Accession Number: 20170404–5020.
Comment Date: 5:00 p.m. Eastern
Time on Monday, April 17, 2017.
Docket Numbers: RP17–639–000.
Applicants: Texas Gas Transmission,
LLC.
Description: Texas Gas Transmission,
LLC submits tariff filing per 154.204:
Cap Rel Neg Rate Agmt (Gulfport 35446
to Eco-Energy 36159) to be effective 4/
4/2017.
Filed Date: 04/04/2017.
Accession Number: 20170404–5023.
Comment Date: 5:00 p.m. Eastern
Time on Monday, April 17, 2017.
Docket Numbers: RP17–640–000.
E:\FR\FM\11APN1.SGM
11APN1
Agencies
[Federal Register Volume 82, Number 68 (Tuesday, April 11, 2017)]
[Notices]
[Pages 17421-17422]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-07243]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 14802-000]
Magnolia Water, LLC; Notice of Preliminary Permit Application
Accepted for Filing and Soliciting Comments and Motions To Intervene
On September 23, 2016, Magnolia Water, LLC filed an application for
a preliminary permit, pursuant to section 4(f) of the Federal Power Act
(FPA), proposing to study the feasibility of the Magnolia Water Pumped
Storage Hydroelectric Project (project) to be located on Long Creek and
the Kiamichi River in Pushmataha County, Oklahoma. The sole purpose of
a preliminary permit, if issued, is to grant the permit holder priority
to file a license application during the permit term. A preliminary
permit does not authorize the permit holder to perform any land-
disturbing activities or otherwise enter upon lands or waters owned by
others without the owners' express permission.
The proposed project would consist of the following: (1) A 1,970-
foot-long, 360-foot-high earthen upper dam across Tombstone Creek; (2)
a 100-foot-long, 3,400-foot-wide rock-lined upper emergency spillway
connecting to the lower reservoir; (3) a 190-acre upper reservoir
having a total storage capacity of 22,800 acre-feet; (4) an intake/
outlet structure in the upper reservoir; (5) four 3,500-foot-long, 22-
foot-diameter steel and reinforced concrete, tunneled penstocks
extending to the powerhouse; (6) a 250-foot-long, 120-foot-wide
powerhouse, containing four pump-turbine generating units, with a total
generating capacity of 1,200 megawatts; (7) four 30-foot-long, 400-
foot-wide tailrace pipes; (8) a 9,800-foot-long, 80-foot-high earthen
lower dam; (9) a 375-acre lower reservoir having a total storage
capacity of 22,500 acre-feet; (10) a 100-foot-long, 3,400-foot-wide
rock-lined lower emergency spillway connecting to a creek flowing into
the Kiamichi River; (11) a 200-foot-long, 5-foot-high concrete overflow
diversion
[[Page 17422]]
weir across the Kiamichi River to supply water to the project; (12) a
5-acre impoundment on the Kiamichi River with a storage capacity of 25
acre-feet; (13) a 200-foot-long, 200-foot-wide duplex pump station;
(14) a 10,000-foot-long, 24-inch-diameter steel water supply pipe to
the lower reservoir; (15) a 90-mile-long, 345 kilovolt transmission
line; and (16) two new access roads; one 6,800-foot-long road to access
the lower reservoir site, and one 11,500-foot-long road to access the
upper reservoir site. Both roads would be constructed on private
property to perform studies. The estimated annual generation of the
project would be 3,400 gigawatt-hours.
Applicant Contact: Mr. Fred Brown, Magnolia Water, LLC, 4265
Kellway Circle, Addison, TX 75001; phone: (972) 239-0707.
FERC Contact: Navreet Deo; phone: (202) 502-6304.
Deadline for filing comments, motions to intervene, competing
applications (without notices of intent), or notices of intent to file
competing applications: 60 days from the issuance of this notice.
Competing applications and notices of intent must meet the requirements
of 18 CFR 4.36.
The Commission strongly encourages electronic filing. Please file
comments, motions to intervene, notices of intent, and competing
applications using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief
comments up to 6,000 characters, without prior registration, using the
eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You
must include your name and contact information at the end of your
comments. For assistance, please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to:
Secretary, Federal Energy Regulatory Commission, 888 First Street, NE.,
Washington, DC 20426. The first page of any filing should include
docket number P-14802-000.
More information about this project, including a copy of the
application, can be viewed or printed on the ``eLibrary'' link of
Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P-14802) in the docket number field to access
the document. For assistance, contact FERC Online Support.
Dated: April 5, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-07243 Filed 4-10-17; 8:45 am]