Texas Eastern Transmission, L.P.; Brazoria Interconnector Gas Pipeline, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Stratton Ridge Expansion Project, and Request for Comments on Environmental Issues, 16187-16189 [2017-06418]
Download as PDF
Federal Register / Vol. 82, No. 62 / Monday, April 3, 2017 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. CP17–56–000; CP17–57–000]
mstockstill on DSK3G9T082PROD with NOTICES
Texas Eastern Transmission, L.P.;
Brazoria Interconnector Gas Pipeline,
LLC; Notice of Intent To Prepare an
Environmental Assessment for the
Proposed Stratton Ridge Expansion
Project, and Request for Comments on
Environmental Issues
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Stratton Ridge Expansion Project
(Project) involving construction and
operation of facilities by Texas Eastern
Transmission, L.P. (Texas Eastern), and
Brazoria Interconnector Gas Pipeline,
LLC (BIG) (referred to as Applicants) in
Brazoria, Chambers, San Jacinto, Waller,
Shelby, and Lavaca Counties, Texas.
The Commission will use this EA in its
decision-making process to determine
whether the project is in the public
convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the project.
You can make a difference by providing
us with your specific comments or
concerns about the project. Your
comments should focus on the potential
environmental effects, reasonable
alternatives, and measures to avoid or
lessen environmental impacts. Your
input will help the Commission staff
determine what issues they need to
evaluate in the EA. To ensure that your
comments are timely and properly
recorded, please send your comments so
that the Commission receives them in
Washington, DC on or before April 24,
2017.
If you sent comments on this project
to the Commission before the opening of
this docket on February 2, 2017, you
will need to file those comments in
Docket Nos. CP17–56–000 and CP17–
57–000 to ensure they are considered as
part of this proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives should
notify their constituents of this
proposed project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
VerDate Sep<11>2014
18:32 Mar 31, 2017
Jkt 241001
proposed facilities. The company would
seek to negotiate a mutually acceptable
agreement. However, if the Commission
approves the project, that approval
conveys with it the right of eminent
domain. Therefore, if easement
negotiations fail to produce an
agreement, the pipeline company could
initiate condemnation proceedings
where compensation would be
determined in accordance with state
law.
The Applicants provided landowners
with a fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ This fact sheet addresses a
number of typically asked questions,
including the use of eminent domain
and how to participate in the
Commission’s proceedings. It is also
available for viewing on the FERC Web
site (www.ferc.gov).
Public Participation
For your convenience, there are three
methods you can use to submit your
comments to the Commission. The
Commission encourages electronic filing
of comments and has expert staff
available to assist you at (202) 502–8258
or efiling@ferc.gov. Please carefully
follow these instructions so that your
comments are properly recorded.
(1) You can file your comments
electronically using the eComment
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. This is an easy
method for submitting brief, text-only
comments on a project;
(2) You can file your comments
electronically by using the eFiling
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. With eFiling,
you can provide comments in a variety
of formats by attaching them as a file
with your submission. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ If you are filing
a comment on a particular project,
please select ‘‘Comment on a Filing’’ as
the filing type; or
(3) You can file a paper copy of your
comments by mailing them to the
following address. Be sure to reference
the project docket numbers (CP17–56–
000, and CP17–57–000) with your
submission: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE., Room
1A, Washington, DC 20426.
Summary of the Proposed Project
The Project is designed to provide the
capacity necessary for Texas Eastern to
transport up to 322,000 dekatherms per
day of natural gas on a firm basis from
PO 00000
Frm 00032
Fmt 4703
Sfmt 4703
16187
certain of Texas Eastern’s existing
interconnections to a delivery point on
the BIG pipeline near Stratton Ridge,
Texas.
The Applicant’s Project would consist
of the following facilities:
• The new Angleton Compressor
Station, consisting of a 12,500
horsepower electric motor-driven
compressor, as well as metering and
regulation facilities, at an existing site
owned by Texas Eastern;
• a new 0.5 mile, 30-inch-diameter
pipeline lateral in Brazoria County,
Texas to interconnect with the BIG
intrastate pipeline system;
• a new aboveground wire-line
launcher/receiver assembly site and
interconnect valve site near milepost 0.5
of the BIG Interconnect;
• Clean Burn equipment for one unit
at Texas Eastern’s existing Mont Belvieu
Compressor Station in Chambers
County, Texas;
• modified station piping for pressure
regulation at Texas Eastern’s Joaquin
Compressor Station in Shelby County,
Texas;
• modified existing launcher and
receiver facilities at Texas Eastern’s
existing Huntsville Compressor Station,
in San Jacinto County, Texas;
• modified existing launcher and
receiver facilities at Texas Eastern’s
Hempstead and Provident City station
sites; in Waller and Lavaca County,
Texas; and
• replacement of existing 16-inch
crossover piping and valve with new 24inch crossover piping and valve at an
existing facility approximately 0.2 mile
southwest of the Provident City station
site in Lavaca County, Texas.
The general location of the project
facilities is shown in appendix 1.1
Land Requirements for Construction
Construction of the proposed facilities
would disturb about 143 acres of land
for the aboveground facilities and the
pipeline. Following construction, the
Applicants would maintain about 48
acres for permanent operation of the
project’s facilities; the remaining
acreage would be restored and revert to
former uses.
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
1 The appendices referenced in this notice will
not appear in the Federal Register. Copies of
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’ or from the
Commission’s Public Reference Room, 888 First
Street NE., Washington, DC 20426, or call (202)
502–8371. For instructions on connecting to
eLibrary, refer to the last page of this notice.
E:\FR\FM\03APN1.SGM
03APN1
mstockstill on DSK3G9T082PROD with NOTICES
16188
Federal Register / Vol. 82, No. 62 / Monday, April 3, 2017 / Notices
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us 2 to
discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping.’’ The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
notice, the Commission requests public
comments on the scope of the issues to
address in the EA. We will consider all
filed comments during the preparation
of the EA.
In the EA we will discuss impacts that
could occur as a result of the
construction and operation of the
proposed project under these general
headings:
• Geology and soils;
• land use;
• water resources, fisheries, and
wetlands;
• cultural resources;
• vegetation and wildlife;
• socioeconomics;
• air quality and noise;
• endangered and threatened species;
• public safety; and
• cumulative impacts
We will also evaluate reasonable
alternatives to the proposed project or
portions of the project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
The EA will present our independent
analysis of the issues. Depending on the
comments received during the scoping
process, we may also publish and
distribute the EA to the public for an
allotted comment period. We will
consider all comments on the EA before
making our recommendations to the
Commission. To ensure we have the
opportunity to consider and address
your comments, please carefully follow
the instructions in the Public
Participation section, beginning on page
2.
With this notice, we are asking
agencies with jurisdiction by law and/
or special expertise with respect to the
environmental issues of this project to
formally cooperate with us in the
preparation of the EA.3 Agencies that
would like to request cooperating
agency status should follow the
instructions for filing comments
2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the
environmental staff of the Commission’s Office of
Energy Projects.
3 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at Title 40, Code of Federal
Regulations, part 1501.6.
VerDate Sep<11>2014
18:32 Mar 31, 2017
Jkt 241001
provided under the Public Participation
section of this notice.
Consultations Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, we are using this
notice to initiate consultation with the
applicable State Historic Preservation
Office (SHPO), and to solicit their views
and those of other government agencies,
interested Indian tribes, and the public
on the project’s potential effects on
historic properties.4 We will define the
project-specific Area of Potential Effects
(APE) in consultation with the SHPO as
the project develops. On natural gas
facility projects, the APE at a minimum
encompasses all areas subject to ground
disturbance (examples include
construction right-of-way, contractor/
pipe storage yards, compressor stations,
and access roads). Our EA for this
project will document our findings on
the impacts on historic properties and
summarize the status of consultations
under section 106.
Currently Identified Environmental
Issues
We have already identified several
issues that we think deserve attention
based on a preliminary review of the
proposed facilities and the
environmental information provided by
the Applicants.
This preliminary list of issues may be
changed based on your comments and
our analysis.
• Operational noise impacts
• Socioeconomic impacts
• Cumulative impacts
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
4 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
PO 00000
Frm 00033
Fmt 4703
Sfmt 4703
comments on the project. We will
update the environmental mailing list as
the analysis proceeds to ensure that we
send the information related to this
environmental review to all individuals,
organizations, and government entities
interested in and/or potentially affected
by the proposed project.
If we publish and distribute the EA,
copies of the EA will be sent to the
environmental mailing list for public
review and comment. If you would
prefer to receive a paper copy of the
document instead of the CD version or
would like to remove your name from
the mailing list, please return the
attached Information Request (appendix
2).
Becoming an Intervenor
In addition to involvement in the EA
scoping process, you may want to
become an ‘‘intervenor’’ which is an
official party to the Commission’s
proceeding. Intervenors play a more
formal role in the process and are able
to file briefs, appear at hearings, and be
heard by the courts if they choose to
appeal the Commission’s final ruling.
An intervenor formally participates in
the proceeding by filing a request to
intervene. Instructions for becoming an
intervenor are in the ‘‘Document-less
Intervention Guide’’ under the ‘‘e-filing’’
link on the Commission’s Web site.
Motions to intervene are more fully
described at https://www.ferc.gov/
resources/guides/how-to/intervene.asp.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC Web
site at www.ferc.gov using the
‘‘eLibrary’’ link. Click on the eLibrary
link, click on ‘‘General Search’’ and
enter the docket number, excluding the
last three digits in the Docket Number
field (i.e., CP17–56, CP17–57). Be sure
you have selected an appropriate date
range.
For assistance, please contact FERC
Online Support at FercOnlineSupport@
ferc.gov or toll free at (866) 208–3676, or
for TTY, contact (202) 502–8659. The
eLibrary link also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
E:\FR\FM\03APN1.SGM
03APN1
Federal Register / Vol. 82, No. 62 / Monday, April 3, 2017 / Notices
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Finally, public sessions or site visits
will be posted on the Commission’s
calendar located at www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Dated: March 24, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017–06418 Filed 3–31–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2520–076]
mstockstill on DSK3G9T082PROD with NOTICES
Great Lakes Hydro America, LLC;
Notice of Application Accepted for
Filing, Soliciting Motions To Intervene
and Protests, Ready for Environmental
Analysis, and Soliciting Comments,
Recommendations, Preliminary Terms
and Conditions, and Preliminary
Fishway Prescriptions
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Major License.
b. Project No.: 2520–076.
c. Date filed: August 31, 2016.
d. Applicant: Great Lakes Hydro
America, LLC (Great Lakes Hydro).
e. Name of Project: Mattaceunk
Hydroelectric Project.
f. Location: The existing project is
located on the Penobscot River in
Aroostook and Penobscot Counties,
Maine. The project does not affect
federal lands.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Kevin Bernier,
Senior Compliance Specialist, Great
Lakes Hydro America, LLC, 1024
Central Street, Millinocket, Maine
04462; Telephone (207) 723–4341, x118.
i. FERC Contact: Adam Peer, (202)
502–8449 or adam.peer@ferc.gov.
j. Deadline for filing motions to
intervene and protests, comments,
recommendations, preliminary terms
and conditions, and preliminary
prescriptions: 60 days from the issuance
date of this notice; reply comments are
due 105 days from the issuance date of
this notice.
The Commission strongly encourages
electronic filing. Please file motions to
intervene, protests, comments,
recommendations, preliminary terms
and conditions, and preliminary
fishway prescriptions using the
VerDate Sep<11>2014
18:32 Mar 31, 2017
Jkt 241001
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–2520–076.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. This application has been accepted
for filing and is now ready for
environmental analysis.
l. The existing Mattaceunk
Hydroelectric Project consists of: (1) A
1,060-foot-long, 45-foot-high dam
(Weldon Dam) with a crest elevation of
236.0 feet (USGS datum), and includes:
(i) A 110-foot-long earthen embankment
extending to the left abutment; (ii) a
combined intake and powerhouse
structure; (iii) an upstream fish ladder;
(iv) a 10-foot-wide log sluice structure,
controlled by an 8-foot-high vertical
slide gate; (v) a 90-foot-long, 19-foothigh gated spillway with a single roller
gate; (vi) a 657.5-foot-long, 70-foot high
concrete gravity overflow spillway with
4-foot-high flashboards to create a
maximum flashboard crest elevation of
240.0 feet; and (vii) a retaining wall at
the right abutment; (2) a 1,664-acre
reservoir with a total storage capacity of
20,981 acre-feet at a normal pool
elevation of 240.00 feet (USGS datum);
(3) a 142-foot-long, 99-foot-wide
powerhouse (Weldon Station) integral to
the dam containing two Kaplan turbines
rated at 5,479 kilowatt (kW) and two
fixed-blade propeller turbines rated at
5,489 kW, each driving a 6,000 kilovoltampere (kVA), 4,800 kW vertical
synchronous generator for an authorized
installed capacity of 19.2 megawatts
(MW); (4) a downstream fishway; (5) an
outdoor substation adjacent to the
powerhouse; (6) a 9-mile-long, 34.5kilovolt (kV) transmission line within a
120-foot-wide right of way; and (7)
PO 00000
Frm 00034
Fmt 4703
Sfmt 4703
16189
appurtenant facilities. The project
generates about 123,332 megawatt-hours
(MWh) annually.
The Mattaceunk Project is operated
with minimal fluctuations of the
reservoir surface elevation. Flexibility
on reservoir elevations is required to
provide for safe installation of the
project’s flashboards and to allow an
adequate margin for wave action, debris
loads, or sudden pool increases that
might cause flashboard failure. The
existing license requires a reservoir
surface elevation no lower than 1.0 foot
below the dam crest elevation of 236.0
feet when the 4-foot-high flashboards
are not in use, and no lower than 2.0
feet below the top of flashboard
elevation of 240.0 feet when the 4-foothigh flashboards are in use. The existing
license also requires a year-round
continuous minimum flow of 1,674
cubic feet per second (cfs) or inflow,
whichever is less, and a daily average
minimum flow of 2,392 cfs from July 1
through September 30 and 2,000 cfs
from October 1 through June 30, unless
inflow is less than the stated daily
average minimum flows (in which case
outflow from the project must equal the
inflow to the project). Great Lakes
Hydro proposes to: (1) Install a seasonal
upstream eel ramp; (2) install an
upstream passage structure for
American shad, alewife, and blueback
herring; (3) install trashracks having 1inch clear spacing to the full depth of
the turbine intakes during the fish
passage season; and (4) improve the
recreation facility at the downstream
angler access area.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h above.
Register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Anyone may submit comments, a
protest, or a motion to intervene in
accordance with the requirements of
Rules of Practice and Procedure, 18 CFR
385.210, .211, and .214. In determining
the appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
E:\FR\FM\03APN1.SGM
03APN1
Agencies
[Federal Register Volume 82, Number 62 (Monday, April 3, 2017)]
[Notices]
[Pages 16187-16189]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-06418]
[[Page 16187]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket Nos. CP17-56-000; CP17-57-000]
Texas Eastern Transmission, L.P.; Brazoria Interconnector Gas
Pipeline, LLC; Notice of Intent To Prepare an Environmental Assessment
for the Proposed Stratton Ridge Expansion Project, and Request for
Comments on Environmental Issues
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Stratton Ridge Expansion
Project (Project) involving construction and operation of facilities by
Texas Eastern Transmission, L.P. (Texas Eastern), and Brazoria
Interconnector Gas Pipeline, LLC (BIG) (referred to as Applicants) in
Brazoria, Chambers, San Jacinto, Waller, Shelby, and Lavaca Counties,
Texas. The Commission will use this EA in its decision-making process
to determine whether the project is in the public convenience and
necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the project. You can make a difference by providing us with
your specific comments or concerns about the project. Your comments
should focus on the potential environmental effects, reasonable
alternatives, and measures to avoid or lessen environmental impacts.
Your input will help the Commission staff determine what issues they
need to evaluate in the EA. To ensure that your comments are timely and
properly recorded, please send your comments so that the Commission
receives them in Washington, DC on or before April 24, 2017.
If you sent comments on this project to the Commission before the
opening of this docket on February 2, 2017, you will need to file those
comments in Docket Nos. CP17-56-000 and CP17-57-000 to ensure they are
considered as part of this proceeding.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this proposed
project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the proposed facilities. The company
would seek to negotiate a mutually acceptable agreement. However, if
the Commission approves the project, that approval conveys with it the
right of eminent domain. Therefore, if easement negotiations fail to
produce an agreement, the pipeline company could initiate condemnation
proceedings where compensation would be determined in accordance with
state law.
The Applicants provided landowners with a fact sheet prepared by
the FERC entitled ``An Interstate Natural Gas Facility On My Land? What
Do I Need To Know?'' This fact sheet addresses a number of typically
asked questions, including the use of eminent domain and how to
participate in the Commission's proceedings. It is also available for
viewing on the FERC Web site (www.ferc.gov).
Public Participation
For your convenience, there are three methods you can use to submit
your comments to the Commission. The Commission encourages electronic
filing of comments and has expert staff available to assist you at
(202) 502-8258 or efiling@ferc.gov. Please carefully follow these
instructions so that your comments are properly recorded.
(1) You can file your comments electronically using the eComment
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. This is an easy method for submitting brief,
text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. With eFiling, you can provide comments in a
variety of formats by attaching them as a file with your submission.
New eFiling users must first create an account by clicking on
``eRegister.'' If you are filing a comment on a particular project,
please select ``Comment on a Filing'' as the filing type; or
(3) You can file a paper copy of your comments by mailing them to
the following address. Be sure to reference the project docket numbers
(CP17-56-000, and CP17-57-000) with your submission: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 888 First Street NE.,
Room 1A, Washington, DC 20426.
Summary of the Proposed Project
The Project is designed to provide the capacity necessary for Texas
Eastern to transport up to 322,000 dekatherms per day of natural gas on
a firm basis from certain of Texas Eastern's existing interconnections
to a delivery point on the BIG pipeline near Stratton Ridge, Texas.
The Applicant's Project would consist of the following facilities:
The new Angleton Compressor Station, consisting of a
12,500 horsepower electric motor-driven compressor, as well as metering
and regulation facilities, at an existing site owned by Texas Eastern;
a new 0.5 mile, 30-inch-diameter pipeline lateral in
Brazoria County, Texas to interconnect with the BIG intrastate pipeline
system;
a new aboveground wire-line launcher/receiver assembly
site and interconnect valve site near milepost 0.5 of the BIG
Interconnect;
Clean Burn equipment for one unit at Texas Eastern's
existing Mont Belvieu Compressor Station in Chambers County, Texas;
modified station piping for pressure regulation at Texas
Eastern's Joaquin Compressor Station in Shelby County, Texas;
modified existing launcher and receiver facilities at
Texas Eastern's existing Huntsville Compressor Station, in San Jacinto
County, Texas;
modified existing launcher and receiver facilities at
Texas Eastern's Hempstead and Provident City station sites; in Waller
and Lavaca County, Texas; and
replacement of existing 16-inch crossover piping and valve
with new 24-inch crossover piping and valve at an existing facility
approximately 0.2 mile southwest of the Provident City station site in
Lavaca County, Texas.
The general location of the project facilities is shown in appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of appendices were sent to all those
receiving this notice in the mail and are available at www.ferc.gov
using the link called ``eLibrary'' or from the Commission's Public
Reference Room, 888 First Street NE., Washington, DC 20426, or call
(202) 502-8371. For instructions on connecting to eLibrary, refer to
the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the proposed facilities would disturb about 143
acres of land for the aboveground facilities and the pipeline.
Following construction, the Applicants would maintain about 48 acres
for permanent operation of the project's facilities; the remaining
acreage would be restored and revert to former uses.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental
[[Page 16188]]
impacts that could result from an action whenever it considers the
issuance of a Certificate of Public Convenience and Necessity. NEPA
also requires us \2\ to discover and address concerns the public may
have about proposals. This process is referred to as ``scoping.'' The
main goal of the scoping process is to focus the analysis in the EA on
the important environmental issues. By this notice, the Commission
requests public comments on the scope of the issues to address in the
EA. We will consider all filed comments during the preparation of the
EA.
---------------------------------------------------------------------------
\2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EA we will discuss impacts that could occur as a result of
the construction and operation of the proposed project under these
general headings:
Geology and soils;
land use;
water resources, fisheries, and wetlands;
cultural resources;
vegetation and wildlife;
socioeconomics;
air quality and noise;
endangered and threatened species;
public safety; and
cumulative impacts
We will also evaluate reasonable alternatives to the proposed
project or portions of the project, and make recommendations on how to
lessen or avoid impacts on the various resource areas.
The EA will present our independent analysis of the issues.
Depending on the comments received during the scoping process, we may
also publish and distribute the EA to the public for an allotted
comment period. We will consider all comments on the EA before making
our recommendations to the Commission. To ensure we have the
opportunity to consider and address your comments, please carefully
follow the instructions in the Public Participation section, beginning
on page 2.
With this notice, we are asking agencies with jurisdiction by law
and/or special expertise with respect to the environmental issues of
this project to formally cooperate with us in the preparation of the
EA.\3\ Agencies that would like to request cooperating agency status
should follow the instructions for filing comments provided under the
Public Participation section of this notice.
---------------------------------------------------------------------------
\3\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, part 1501.6.
---------------------------------------------------------------------------
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, we are using this notice to initiate consultation
with the applicable State Historic Preservation Office (SHPO), and to
solicit their views and those of other government agencies, interested
Indian tribes, and the public on the project's potential effects on
historic properties.\4\ We will define the project-specific Area of
Potential Effects (APE) in consultation with the SHPO as the project
develops. On natural gas facility projects, the APE at a minimum
encompasses all areas subject to ground disturbance (examples include
construction right-of-way, contractor/pipe storage yards, compressor
stations, and access roads). Our EA for this project will document our
findings on the impacts on historic properties and summarize the status
of consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Currently Identified Environmental Issues
We have already identified several issues that we think deserve
attention based on a preliminary review of the proposed facilities and
the environmental information provided by the Applicants.
This preliminary list of issues may be changed based on your
comments and our analysis.
Operational noise impacts
Socioeconomic impacts
Cumulative impacts
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project. We will update the environmental mailing list
as the analysis proceeds to ensure that we send the information related
to this environmental review to all individuals, organizations, and
government entities interested in and/or potentially affected by the
proposed project.
If we publish and distribute the EA, copies of the EA will be sent
to the environmental mailing list for public review and comment. If you
would prefer to receive a paper copy of the document instead of the CD
version or would like to remove your name from the mailing list, please
return the attached Information Request (appendix 2).
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an ``intervenor'' which is an official party to the
Commission's proceeding. Intervenors play a more formal role in the
process and are able to file briefs, appear at hearings, and be heard
by the courts if they choose to appeal the Commission's final ruling.
An intervenor formally participates in the proceeding by filing a
request to intervene. Instructions for becoming an intervenor are in
the ``Document-less Intervention Guide'' under the ``e-filing'' link on
the Commission's Web site. Motions to intervene are more fully
described at https://www.ferc.gov/resources/guides/how-to/intervene.asp.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number,
excluding the last three digits in the Docket Number field (i.e., CP17-
56, CP17-57). Be sure you have selected an appropriate date range.
For assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the
[[Page 16189]]
documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
Finally, public sessions or site visits will be posted on the
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Dated: March 24, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-06418 Filed 3-31-17; 8:45 am]
BILLING CODE 6717-01-P