Littleville Power Company, Inc.; Hitchcock Hydro, LLC; Notice of Application for Transfer of License and Soliciting Comments, Motions To Intervene, and Protests, 14887 [2017-05791]
Download as PDF
Federal Register / Vol. 82, No. 55 / Thursday, March 23, 2017 / Notices
Dated: March 15, 2017.
Kimberly D. Bose,
Secretary .
[FR Doc. 2017–05780 Filed 3–22–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2801–040]
sradovich on DSK3GMQ082PROD with NOTICES
Littleville Power Company, Inc.;
Hitchcock Hydro, LLC; Notice of
Application for Transfer of License and
Soliciting Comments, Motions To
Intervene, and Protests
On February 9, 2017, Littleville Power
Company, Inc. (transferor) and
Hitchcock Hydro, LLC (transferee) filed
an application for the transfer of license
of the Glendale Hydroelectric Project
No. 2801. The project is located on the
Housatonic River in Berkshire County,
Massachusetts. The project does not
occupy Federal lands.
The applicants seek Commission
approval to transfer the license for the
Glendale Hydroelectric Project from the
transferor to the transferee.
Applicant’s Contacts: For Transferor:
Mr. Stephen Pike, Vice President,
Operations, Littleville Power Company,
Inc., c/o Enel Green Power North
America, Inc., 1 Tech Drive, Suite 220,
Andover, MA 01810, Email:
Stephen.Pike@enel.com, Vice President,
Power Supply & General Counsel, Green
Mountain Power Corporation, 163
Acorn Lane, Colchester; VT 05446; Ms.
Elizabeth Kohler, Esq., Downs Rachlin
Martin PLLC, 199 Main Street, P.O. Box
190, Burlington, VT 05402; and General
Counsel, Enel Green Power North
America, Inc., 1 Tech Drive, Suite 220,
Andover, MA 01810, Email:
generalcounsel@enel.com.
For Transferee: Mr. Mark J.
Boumansour, Chief Operating Officer,
Hitchcock Hydro, LLC, c/o Gravity
Renewables, Inc., 1401 Walnut Street,
Suite 220, Boulder, CO 80302, Phone:
(303) 440–3378, Email:
mark@gravityrenewables.com; Mr. Karl
F. Kumli, III, Dietze and Davis, P.C.,
2060 Broadway, Suite 400, Boulder, CO
80302; and Mr. Robert A. Panasci, Esq.,
Young/Sommer, LLC, Executive Woods,
Palisades Drive, Albany, NY 12205.
FERC Contact: Patricia W. Gillis, (202)
502–8735, patricia.gillis@ferc.gov.
Deadline for filing comments, motions
to intervene, and protests: 30 days from
the date that the Commission issues this
notice. The Commission strongly
encourages electronic filing. Please file
comments, motions to intervene, and
VerDate Sep<11>2014
17:13 Mar 22, 2017
Jkt 241001
protests using the Commission’s eFiling
system at https://www.ferc.gov/docsfiling/efiling.asp. Commenters can
submit brief comments up to 6,000
characters, without prior registration,
using the eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–2801–040.
Dated: March 16, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017–05791 Filed 3–22–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No., 14839–000]
Village of North Bennington; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
On February 28, 2017, the Village of
North Bennington, Vermont, filed an
application for a preliminary permit,
pursuant to section 4(f) of the Federal
Power Act (FPA), proposing to study the
feasibility of the Lake Paran Dam
Hydroelectric Project (Lake Paran
Project or project) to be located on Paran
Creek, near the Village of North
Bennington, in Bennington County,
Vermont. The sole purpose of a
preliminary permit, if issued, is to grant
the permit holder priority to file a
license application during the permit
term. A preliminary permit does not
authorize the permit holder to perform
any land-disturbing activities or
otherwise enter upon lands or waters
owned by others without the owners’
express permission.
The proposed Lake Paran Project
would consist of: (1) The existing 120foot-long, 10-foot-concrete gravity Lake
Paran Dam and spillway; (2) an existing
35-acre impoundment with a normal
maximum water surface elevation
646.65 feet above mean sea level; (3) a
new intake structure; (4) a new 250-footlong, 36-inch diameter penstock; (5) a
new 20-foot-long, 10-foot-wide concrete
PO 00000
Frm 00023
Fmt 4703
Sfmt 9990
14887
and wood powerhouse containing a
single 58-kilowatt turbine-generator
unit; (6) a new 1,000-foot-long, 12.47kilovolt transmission line; and (7)
appurtenant facilities. The estimated
annual generation of the Lake Paran
Project would be 281.84 megawatthours.
Applicant Contact: William F. Scully,
P.O. Box 338, North Bennington,
Vermont 05257; phone: (802) 379–2469;
email: wfscully@gmail.com.
FERC Contact: Michael Watts; phone:
(202) 502–6123; email: michael.watts@
ferc.gov.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–14839–000.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P–14839) in
the docket number field to access the
document. For assistance, contact FERC
Online Support.
Dated: March 16, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017–05794 Filed 3–22–17; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\23MRN1.SGM
23MRN1
Agencies
[Federal Register Volume 82, Number 55 (Thursday, March 23, 2017)]
[Notices]
[Page 14887]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-05791]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2801-040]
Littleville Power Company, Inc.; Hitchcock Hydro, LLC; Notice of
Application for Transfer of License and Soliciting Comments, Motions To
Intervene, and Protests
On February 9, 2017, Littleville Power Company, Inc. (transferor)
and Hitchcock Hydro, LLC (transferee) filed an application for the
transfer of license of the Glendale Hydroelectric Project No. 2801. The
project is located on the Housatonic River in Berkshire County,
Massachusetts. The project does not occupy Federal lands.
The applicants seek Commission approval to transfer the license for
the Glendale Hydroelectric Project from the transferor to the
transferee.
Applicant's Contacts: For Transferor: Mr. Stephen Pike, Vice
President, Operations, Littleville Power Company, Inc., c/o Enel Green
Power North America, Inc., 1 Tech Drive, Suite 220, Andover, MA 01810,
Email: Stephen.Pike@enel.com, Vice President, Power Supply & General
Counsel, Green Mountain Power Corporation, 163 Acorn Lane, Colchester;
VT 05446; Ms. Elizabeth Kohler, Esq., Downs Rachlin Martin PLLC, 199
Main Street, P.O. Box 190, Burlington, VT 05402; and General Counsel,
Enel Green Power North America, Inc., 1 Tech Drive, Suite 220, Andover,
MA 01810, Email: generalcounsel@enel.com.
For Transferee: Mr. Mark J. Boumansour, Chief Operating Officer,
Hitchcock Hydro, LLC, c/o Gravity Renewables, Inc., 1401 Walnut Street,
Suite 220, Boulder, CO 80302, Phone: (303) 440-3378, Email:
mark@gravityrenewables.com; Mr. Karl F. Kumli, III, Dietze and Davis,
P.C., 2060 Broadway, Suite 400, Boulder, CO 80302; and Mr. Robert A.
Panasci, Esq., Young/Sommer, LLC, Executive Woods, Palisades Drive,
Albany, NY 12205.
FERC Contact: Patricia W. Gillis, (202) 502-8735,
patricia.gillis@ferc.gov.
Deadline for filing comments, motions to intervene, and protests:
30 days from the date that the Commission issues this notice. The
Commission strongly encourages electronic filing. Please file comments,
motions to intervene, and protests using the Commission's eFiling
system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can
submit brief comments up to 6,000 characters, without prior
registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information
at the end of your comments. For assistance, please contact FERC Online
Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper
copy to: Secretary, Federal Energy Regulatory Commission, 888 First
Street NE., Washington, DC 20426. The first page of any filing should
include docket number P-2801-040.
Dated: March 16, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-05791 Filed 3-22-17; 8:45 am]
BILLING CODE 6717-01-P