Download as PDF sradovich on DSK3GMQ082PROD with NOTICES 14890 Federal Register / Vol. 82, No. 55 / Thursday, March 23, 2017 / Notices concrete-lined power shaft penstock; (5) a 1,420-foot-long 30-foot-diameter, concrete-lined, power tunnel penstock that will split into three 16-footdiameter penstocks approximately 450foot-long, that will extend to the powerhouse; (6) an underground powerhouse/pump station, containing three reversible pump-turbine generating units, with a total generating capacity of 600 megawatts; (7) a 6,620 foot-long tailrace tunnel to; the existing Corps Lake Dardanelle as its lower reservoir; (8) an intake/outlet structure located on the south shore of Lake Dardanelle; (9) a 8,000-foot-long, 500kilovolt overhead transmission line from the powerhouse to (10) a proposed substation at the point of interconnection with an existing utility transmission line. The proposed project would have an annual energy generation of 640,000 megawatt-hours. Applicant Contact: Curtis Warner, Arkansas Electric Cooperative Corporation, 1 Cooperative Way, Little Rock, Arkansas 72209; phone (501) 570– 2462. FERC Contact: Chris Casey, christiane.casey@ferc.gov, (202) 502– 8577. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Competing applications and notices of intent must meet the requirements of 18 CFR 4.36. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at 1–866–208–3676, or for TTY, (202) 502–8659. Although the Commission strongly encourages electronic filing, documents may also be paper-filed. To paper-file, mail an original and five copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s Web site at https:// www.ferc.gov/docs-filing/elibrary.asp. VerDate Sep<11>2014 17:13 Mar 22, 2017 Jkt 241001 Enter the docket number (P–14813) in the docket number field to access the document. For assistance, contact FERC Online Support. Dated: March 16, 2017. Kimberly D. Bose, Secretary. [FR Doc. 2017–05792 Filed 3–22–17; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP17–58–000] Transcontinental Gas Pipe Line Company, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed St. James Supply Project and Request for Comments on Environmental Issues The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the St. James Supply Project involving construction and operation of facilities by Transcontinental Gas Pipe Line Company, LLC (Transco) in St. James, Pointe Coupee, and St. Helena Parishes, Louisiana. The Commission will use this EA in its decision-making process to determine whether the project is in the public convenience and necessity. This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies on the project. You can make a difference by providing us with your specific comments or concerns about the project. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. Your input will help the Commission staff determine what issues they need to evaluate in the EA. To ensure that your comments are timely and properly recorded, please send your comments so that the Commission receives them in Washington, DC on or before April 14, 2017. If you sent comments on this project to the Commission before the opening of this docket on February 6, 2017, you will need to file those comments in Docket No. CP17–58–000 to ensure they are considered as part of this proceeding. This notice is being sent to the Commission’s current environmental mailing list for this project. State and local government representatives should PO 00000 Frm 00026 Fmt 4703 Sfmt 4703 notify their constituents of this proposed project and encourage them to comment on their areas of concern. If you are a landowner receiving this notice, a pipeline company representative may contact you about the acquisition of an easement to construct, operate, and maintain the proposed facilities. The company would seek to negotiate a mutually acceptable agreement. However, if the Commission approves the project, that approval conveys with it the right of eminent domain. Therefore, if easement negotiations fail to produce an agreement, the pipeline company could initiate condemnation proceedings where compensation would be determined in accordance with state law. Transco provided landowners with a fact sheet prepared by the FERC entitled ‘‘An Interstate Natural Gas Facility On My Land? What Do I Need To Know?’’ This fact sheet addresses a number of typically asked questions, including the use of eminent domain and how to participate in the Commission’s proceedings. It is also available for viewing on the FERC Web site (www.ferc.gov). Public Participation For your convenience, there are three methods you can use to submit your comments to the Commission. The Commission encourages electronic filing of comments and has expert staff available to assist you at (202) 502–8258 or efiling@ferc.gov. Please carefully follow these instructions so that your comments are properly recorded. (1) You can file your comments electronically using the eComment feature on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. This is an easy method for submitting brief, text-only comments on a project; (2) You can file your comments electronically by using the eFiling feature on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ If you are filing a comment on a particular project, please select ‘‘Comment on a Filing’’ as the filing type; or (3) You can file a paper copy of your comments by mailing them to the following address. Be sure to reference the project docket number (CP17–58– 000) with your submission: Kimberly D. Bose, Secretary, Federal Energy E:\FR\FM\23MRN1.SGM 23MRN1 Federal Register / Vol. 82, No. 55 / Thursday, March 23, 2017 / Notices Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 20426. Summary of the Proposed Project The St. James Supply Project would deliver 161,500 dekatherms per day of firm transportation capacity from Transco’s existing mainline Compressor Station 65 in St. Helena Parish, Louisiana to the planned Yuhuang Chemical Plant in St. James Parish, Louisiana. Transco would use its existing Southeast Lateral Pipeline (SELA) to deliver gas to the chemical plant. Proposed construction would provide bi-directional flow of natural gas on the SELA pipeline and a secondary source of natural gas to the chemical plant using an existing interconnection on Transco’s mainline with the Texas Eastern Transmission Company Pipeline in Pointe Coupee Parish, Louisiana. The St. James Supply Project would consist of the following facilities: • 0.7 mile of 20-inch-diameter pipeline; • one new pig receiver site; 1 • two new meter and regulating (M&R) stations (Old River Road and Cajun Road M&R Stations); • a new interconnection to the chemical plant site; • one new valve and piping to tie the Old River Road M&R Station into the SELA pipeline; and • piping and valve modifications at existing Transco Compressor Stations 63 and 65. The general location of the project facilities is shown in appendix 1.2 Land Requirements for Construction Construction of the proposed facilities would disturb about 77.8 acres of land for the aboveground facilities and the pipeline. Following construction, Transco would maintain about 12.0 acres for permanent operation of the project’s facilities; the remaining acreage would be restored and revert to former uses. The EA Process sradovich on DSK3GMQ082PROD with NOTICES The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental 1 A ‘‘pig’’ is a tool that the pipeline company inserts into and pushes through the pipeline for cleaning the pipeline, conducting internal inspections, or other purposes. 2 The appendices referenced in this notice will not appear in the Federal Register. Copies of appendices were sent to all those receiving this notice in the mail and are available at www.ferc.gov using the link called ‘‘eLibrary’’ or from the Commission’s Public Reference Room, 888 First Street NE., Washington, DC 20426, or call (202) 502–8371. For instructions on connecting to eLibrary, refer to the last page of this notice. VerDate Sep<11>2014 17:13 Mar 22, 2017 Jkt 241001 impacts that could result from an action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. NEPA also requires us 3 to discover and address concerns the public may have about proposals. This process is referred to as ‘‘scoping.’’ The main goal of the scoping process is to focus the analysis in the EA on the important environmental issues. By this notice, the Commission requests public comments on the scope of the issues to address in the EA. We will consider all filed comments during the preparation of the EA. In the EA we will discuss impacts that could occur as a result of the construction and operation of the proposed project under these general headings: • Geology and soils; • water resources and wetlands; • fisheries, vegetation, and wildlife; • endangered and threatened species; • land use; • cultural resources; • air quality and noise; • public safety; and • cumulative impacts. We will also evaluate reasonable alternatives to the proposed project or portions of the project, and make recommendations on how to lessen or avoid impacts on the various resource areas. The EA will present our independent analysis of the issues. The EA will be available in the public record through eLibrary. Depending on the comments received during the scoping process, we may also publish and distribute the EA to the public for an allotted comment period. We will consider all comments on the EA before making our recommendations to the Commission. To ensure we have the opportunity to consider and address your comments, please carefully follow the instructions in the Public Participation section, beginning on page 2. With this notice, we are asking agencies with jurisdiction by law and/ or special expertise with respect to the environmental issues of this project to formally cooperate with us in the preparation of the EA.4 Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice. 3 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the environmental staff of the Commission’s Office of Energy Projects. 4 The Council on Environmental Quality regulations addressing cooperating agency responsibilities are at Title 40, Code of Federal Regulations, Part 1501.6. PO 00000 Frm 00027 Fmt 4703 Sfmt 4703 14891 Consultations Under Section 106 of the National Historic Preservation Act In accordance with the Advisory Council on Historic Preservation’s implementing regulations for section 106 of the National Historic Preservation Act, we are using this notice to initiate consultation with the applicable State Historic Preservation Office (SHPO), and to solicit their views and those of other government agencies, interested Indian tribes, and the public on the project’s potential effects on historic properties.5 We will define the project-specific Area of Potential Effects (APE) in consultation with the SHPO as the project develops. On natural gas facility projects, the APE at a minimum encompasses all areas subject to ground disturbance (examples include construction right-of-way, contractor/ pipe storage yards, compressor stations, and access roads). Our EA for this project will document our findings on the impacts on historic properties and summarize the status of consultations under section 106. Environmental Mailing List The environmental mailing list includes federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission’s regulations) who are potential right-of-way grantors, whose property may be used temporarily for project purposes, or who own homes within certain distances of aboveground facilities, and anyone who submits comments on the project. We will update the environmental mailing list as the analysis proceeds to ensure that we send the information related to this environmental review to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed project. If we publish and distribute the EA, copies will be sent to the environmental mailing list for public review and comment. If you would prefer to receive a paper copy of the document instead of the CD version or would like to remove your name from the mailing list, please return the attached Information Request (appendix 2). 5 The Advisory Council on Historic Preservation’s regulations are at Title 36, Code of Federal Regulations, Part 800. Those regulations define historic properties as any prehistoric or historic district, site, building, structure, or object included in or eligible for inclusion in the National Register of Historic Places. E:\FR\FM\23MRN1.SGM 23MRN1 14892 Federal Register / Vol. 82, No. 55 / Thursday, March 23, 2017 / Notices Becoming an Intervenor DEPARTMENT OF ENERGY In addition to involvement in the EA scoping process, you may want to become an ‘‘intervenor’’ which is an official party to the Commission’s proceeding. Intervenors play a more formal role in the process and are able to file briefs, appear at hearings, and be heard by the courts if they choose to appeal the Commission’s final ruling. An intervenor formally participates in the proceeding by filing a request to intervene. Instructions for becoming an intervenor are in the ‘‘Document-less Intervention Guide’’ under the ‘‘e-filing’’ link on the Commission’s Web site. Motions to intervene are more fully described at https://www.ferc.gov/ resources/guides/how-to/intervene.asp. Federal Energy Regulatory Commission Additional Information sradovich on DSK3GMQ082PROD with NOTICES Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC Web site at www.ferc.gov using the ‘‘eLibrary’’ link. Click on the eLibrary link, click on ‘‘General Search’’ and enter the docket number, excluding the last three digits in the Docket Number field (i.e., CP17–058). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/docsfiling/esubscription.asp. Finally, public sessions or site visits will be posted on the Commission’s calendar located at www.ferc.gov/ EventCalendar/EventsList.aspx along with other related information. Dated: March 17, 2017. Kimberly D. Bose, Secretary. [FR Doc. 2017–05781 Filed 3–22–17; 8:45 am] BILLING CODE 6717–01–P VerDate Sep<11>2014 17:13 Mar 22, 2017 Jkt 241001 [Docket No. CP17–71–000] ANR Storage Company; Notice of Request Under Blanket Authorization Take notice that on March 7, 2017 ANR Storage Company (ANR Storage), 700 Louisiana Street, Houston, Texas 77002–2700, filed in Docket No. CP17– 71–000 a prior notice request pursuant to sections 157.205 and 157.216 of the Commission’s regulations under the Natural Gas Act (NGA) and ANR Storage’s authorization in Docket No. CP82–523–000, 21 FERC ¶ 62,109 (1982), for authorization to abandon one injection/withdrawal (I/W) well at its Cold Springs 12 Storage Field in Kalkaska County, Michigan, all as more fully set forth in the application which is on file with the Commission and open to public inspection. The filing may also be viewed on the web at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at (866) 208–3676, or TTY, contact (202) 502–8659. Any questions concerning this application may be directed to Linda Farquhar, Manager, Project Determinations & Regulatory Administration, ANR Storage Company, 700 Louisiana Street, Suite 700, Houston, Texas, 77002–2700, at (832) 320–5685 or fax (832) 320–6685 or linda_farquhar@transcanada.com. Any person or the Commission’s staff may, within 60 days after issuance of the instant notice by the Commission, file pursuant to Rule 214 of the Commission’s Procedural Rules (18 CFR 385.214) a motion to intervene or notice of intervention and pursuant to section 157.205 of the regulations under the NGA (18 CFR 157.205), a protest to the request. If no protest is filed within the time allowed therefore, the proposed activity shall be deemed to be authorized effective the day after the time allowed for filing a protest. If a protest is filed and not withdrawn within 30 days after the allowed time for filing a protest, the instant request shall be treated as an application for authorization pursuant to section 7 of the NGA. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete PO 00000 Frm 00028 Fmt 4703 Sfmt 9990 its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commenter’s will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission’s environmental review process. Environmental commenter’s will not be required to serve copies of filed documents on all other parties. However, the non-party commentary, will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests, and interventions via the internet in lieu of paper. See 18 CFR 385.2001(a) (1) (iii) and the instructions on the Commission’s Web site (www.ferc.gov) under the ‘‘e-Filing’’ link. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. Dated: March 16, 2017. Kimberly D. Bose, Secretary. [FR Doc. 2017–05793 Filed 3–22–17; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\23MRN1.SGM 23MRN1

Agencies

[Federal Register Volume 82, Number 55 (Thursday, March 23, 2017)]
[Notices]
[Pages 14890-14892]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-05781]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP17-58-000]


Transcontinental Gas Pipe Line Company, LLC; Notice of Intent To 
Prepare an Environmental Assessment for the Proposed St. James Supply 
Project and Request for Comments on Environmental Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the St. James Supply Project 
involving construction and operation of facilities by Transcontinental 
Gas Pipe Line Company, LLC (Transco) in St. James, Pointe Coupee, and 
St. Helena Parishes, Louisiana. The Commission will use this EA in its 
decision-making process to determine whether the project is in the 
public convenience and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the project. You can make a difference by providing us with 
your specific comments or concerns about the project. Your comments 
should focus on the potential environmental effects, reasonable 
alternatives, and measures to avoid or lessen environmental impacts. 
Your input will help the Commission staff determine what issues they 
need to evaluate in the EA. To ensure that your comments are timely and 
properly recorded, please send your comments so that the Commission 
receives them in Washington, DC on or before April 14, 2017.
    If you sent comments on this project to the Commission before the 
opening of this docket on February 6, 2017, you will need to file those 
comments in Docket No. CP17-58-000 to ensure they are considered as 
part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this proposed 
project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the proposed facilities. The company 
would seek to negotiate a mutually acceptable agreement. However, if 
the Commission approves the project, that approval conveys with it the 
right of eminent domain. Therefore, if easement negotiations fail to 
produce an agreement, the pipeline company could initiate condemnation 
proceedings where compensation would be determined in accordance with 
state law.
    Transco provided landowners with a fact sheet prepared by the FERC 
entitled ``An Interstate Natural Gas Facility On My Land? What Do I 
Need To Know?'' This fact sheet addresses a number of typically asked 
questions, including the use of eminent domain and how to participate 
in the Commission's proceedings. It is also available for viewing on 
the FERC Web site (www.ferc.gov).

Public Participation

    For your convenience, there are three methods you can use to submit 
your comments to the Commission. The Commission encourages electronic 
filing of comments and has expert staff available to assist you at 
(202) 502-8258 or efiling@ferc.gov. Please carefully follow these 
instructions so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
``eRegister.'' If you are filing a comment on a particular project, 
please select ``Comment on a Filing'' as the filing type; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address. Be sure to reference the project docket number 
(CP17-58-000) with your submission: Kimberly D. Bose, Secretary, 
Federal Energy

[[Page 14891]]

Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 
20426.

Summary of the Proposed Project

    The St. James Supply Project would deliver 161,500 dekatherms per 
day of firm transportation capacity from Transco's existing mainline 
Compressor Station 65 in St. Helena Parish, Louisiana to the planned 
Yuhuang Chemical Plant in St. James Parish, Louisiana. Transco would 
use its existing Southeast Lateral Pipeline (SELA) to deliver gas to 
the chemical plant. Proposed construction would provide bi-directional 
flow of natural gas on the SELA pipeline and a secondary source of 
natural gas to the chemical plant using an existing interconnection on 
Transco's mainline with the Texas Eastern Transmission Company Pipeline 
in Pointe Coupee Parish, Louisiana.
    The St. James Supply Project would consist of the following 
facilities:
     0.7 mile of 20-inch-diameter pipeline;
     one new pig receiver site; \1\
---------------------------------------------------------------------------

    \1\ A ``pig'' is a tool that the pipeline company inserts into 
and pushes through the pipeline for cleaning the pipeline, 
conducting internal inspections, or other purposes.
---------------------------------------------------------------------------

     two new meter and regulating (M&R) stations (Old River 
Road and Cajun Road M&R Stations);
     a new interconnection to the chemical plant site;
     one new valve and piping to tie the Old River Road M&R 
Station into the SELA pipeline; and
     piping and valve modifications at existing Transco 
Compressor Stations 63 and 65.
    The general location of the project facilities is shown in appendix 
1.\2\
---------------------------------------------------------------------------

    \2\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of appendices were sent to all those 
receiving this notice in the mail and are available at www.ferc.gov 
using the link called ``eLibrary'' or from the Commission's Public 
Reference Room, 888 First Street NE., Washington, DC 20426, or call 
(202) 502-8371. For instructions on connecting to eLibrary, refer to 
the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the proposed facilities would disturb about 77.8 
acres of land for the aboveground facilities and the pipeline. 
Following construction, Transco would maintain about 12.0 acres for 
permanent operation of the project's facilities; the remaining acreage 
would be restored and revert to former uses.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. NEPA also requires us 
\3\ to discover and address concerns the public may have about 
proposals. This process is referred to as ``scoping.'' The main goal of 
the scoping process is to focus the analysis in the EA on the important 
environmental issues. By this notice, the Commission requests public 
comments on the scope of the issues to address in the EA. We will 
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------

    \3\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EA we will discuss impacts that could occur as a result of 
the construction and operation of the proposed project under these 
general headings:
     Geology and soils;
     water resources and wetlands;
     fisheries, vegetation, and wildlife;
     endangered and threatened species;
     land use;
     cultural resources;
     air quality and noise;
     public safety; and
     cumulative impacts.
    We will also evaluate reasonable alternatives to the proposed 
project or portions of the project, and make recommendations on how to 
lessen or avoid impacts on the various resource areas.
    The EA will present our independent analysis of the issues. The EA 
will be available in the public record through eLibrary. Depending on 
the comments received during the scoping process, we may also publish 
and distribute the EA to the public for an allotted comment period. We 
will consider all comments on the EA before making our recommendations 
to the Commission. To ensure we have the opportunity to consider and 
address your comments, please carefully follow the instructions in the 
Public Participation section, beginning on page 2.
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the environmental issues of 
this project to formally cooperate with us in the preparation of the 
EA.\4\ Agencies that would like to request cooperating agency status 
should follow the instructions for filing comments provided under the 
Public Participation section of this notice.
---------------------------------------------------------------------------

    \4\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with the applicable State Historic Preservation Office (SHPO), and to 
solicit their views and those of other government agencies, interested 
Indian tribes, and the public on the project's potential effects on 
historic properties.\5\ We will define the project-specific Area of 
Potential Effects (APE) in consultation with the SHPO as the project 
develops. On natural gas facility projects, the APE at a minimum 
encompasses all areas subject to ground disturbance (examples include 
construction right-of-way, contractor/pipe storage yards, compressor 
stations, and access roads). Our EA for this project will document our 
findings on the impacts on historic properties and summarize the status 
of consultations under section 106.
---------------------------------------------------------------------------

    \5\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the project. We will update the environmental mailing list 
as the analysis proceeds to ensure that we send the information related 
to this environmental review to all individuals, organizations, and 
government entities interested in and/or potentially affected by the 
proposed project.
    If we publish and distribute the EA, copies will be sent to the 
environmental mailing list for public review and comment. If you would 
prefer to receive a paper copy of the document instead of the CD 
version or would like to remove your name from the mailing list, please 
return the attached Information Request (appendix 2).

[[Page 14892]]

Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want 
to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are in 
the ``Document-less Intervention Guide'' under the ``e-filing'' link on 
the Commission's Web site. Motions to intervene are more fully 
described at https://www.ferc.gov/resources/guides/how-to/intervene.asp.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number, 
excluding the last three digits in the Docket Number field (i.e., CP17-
058). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
    Finally, public sessions or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

    Dated: March 17, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-05781 Filed 3-22-17; 8:45 am]