Town of Carbondale, Colorado; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene, 14712-14713 [2017-05669]

Download as PDF 14712 Federal Register / Vol. 82, No. 54 / Wednesday, March 22, 2017 / Notices 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. The first page of any filing should include docket number P–2302–085. k. Description of Request: The licensee requests to remove the Canal System and its four non-operating canal generating facilities from the Lewiston Falls Project and convey the canals and the conveyance facilities to the City of Lewiston for non-hydropower redevelopment and public use. This would reduce the project’s installed capacity from 35.6 MW to 28 MW, but the operation of the project would remain unchanged. l. This filing may be viewed on the Commission’s Web site at https:// www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1–866–208–3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. A copy is also available for inspection and reproduction in the Commission’s Public Reference Room located at 888 First Street NE., Room 2A, Washington, DC 20426, or by calling (202) 502–8371. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .212 and .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Responsive Documents: Any filing must (1) bear in all capital letters the title ‘‘COMMENTS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’ as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). All comments, motions to intervene, or protests should relate to project works which are the subject of the license amendment. Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application. If an intervener files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010. Dated: March 13, 2017. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2017–05674 Filed 3–21–17; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CD17–8–000] Town of Carbondale, Colorado; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene On March 9, 2017, the Town of Carbondale, Colorado, filed a notice of intent to construct a qualifying conduit hydropower facility, pursuant to section 30 of the Federal Power Act (FPA), as amended by section 4 of the Hydropower Regulatory Efficiency Act of 2013 (HREA). The proposed Town of Carbondale Nettle Creek WTP Hydro Project would have an installed capacity of 28 kilowatts (kW), and would be located along an existing raw water pipeline adjacent to the applicant’s water treatment plant. The project would be located near the Town of Carbondale in Pitkin County, Colorado. Applicant Contact: Mark O’Meara, Utility Director, Town of Carbondale, 511 Colorado Avenue, Carbondale, CO 81623 Phone No. (970) 963–3140. FERC Contact: Christopher Chaney, Phone No. (202) 502–6778, email: Christopher.Chaney@ferc.gov. Qualifying Conduit Hydropower Facility Description: The proposed project would consist of: (1) An new pressure reduction valve vault containing one turbine/generating unit with an installed capacity of 28 kW; (2) a short, 10-inch-diameter penstock teeing off the existing raw water pipeline; (3) a short, 10-inch-diameter discharge pipe returning water to the existing raw water pipeline; and (4) appurtenant facilities. The proposed project would have an estimated annual generating capacity of 190,000 kilowatthours. A qualifying conduit hydropower facility is one that is determined or deemed to meet all of the criteria shown in the table below. TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY asabaliauskas on DSK3SPTVN1PROD with NOTICES Statutory provision Description Satisfies (Y/N) FPA 30(a)(3)(A), as amended by HREA .. The conduit the facility uses is a tunnel, canal, pipeline, aqueduct, flume, ditch, or similar manmade water conveyance that is operated for the distribution of water for agricultural, municipal, or industrial consumption and not primarily for the generation of electricity. The facility is constructed, operated, or maintained for the generation of electric power and uses for such generation only the hydroelectric potential of a non-federally owned conduit. The facility has an installed capacity that does not exceed 5 megawatts .................. Y FPA 30(a)(3)(C)(i), as amended by HREA FPA 30(a)(3)(C)(ii), HREA. VerDate Sep<11>2014 as amended 18:14 Mar 21, 2017 by Jkt 241001 PO 00000 Frm 00040 Fmt 4703 Sfmt 4703 E:\FR\FM\22MRN1.SGM 22MRN1 Y Y Federal Register / Vol. 82, No. 54 / Wednesday, March 22, 2017 / Notices 14713 TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY—Continued Description Satisfies (Y/N) On or before August 9, 2013, the facility is not licensed, or exempted from the licensing requirements of Part I of the FPA. Y Statutory provision asabaliauskas on DSK3SPTVN1PROD with NOTICES FPA 30(a)(3)(C)(iii), HREA. as amended by Preliminary Determination: The proposed addition of the hydroelectric project along the existing raw water pipeline will not alter its primary purpose. Therefore, based upon the above criteria, Commission staff preliminarily determines that the proposal satisfies the requirements for a qualifying conduit hydropower facility, which is not required to be licensed or exempted from licensing. Comments and Motions To Intervene: Deadline for filing comments contesting whether the facility meets the qualifying criteria is 45 days from the issuance date of this notice. Deadline for filing motions to intervene is 30 days from the issuance date of this notice. Anyone may submit comments or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210 and 385.214. Any motions to intervene must be received on or before the specified deadline date for the particular proceeding. Filing and Service of Responsive Documents: All filings must (1) bear in all capital letters the ‘‘COMMENTS CONTESTING QUALIFICATION FOR A CONDUIT HYDROPOWER FACILITY’’ or ‘‘MOTION TO INTERVENE,’’ as applicable; (2) state in the heading the name of the applicant and the project number of the application to which the filing responds; (3) state the name, address, and telephone number of the person filing; and (4) otherwise comply with the requirements of sections 385.2001 through 385.2005 of the Commission’s regulations.1 All comments contesting Commission staff’s preliminary determination that the facility meets the qualifying criteria must set forth their evidentiary basis. The Commission strongly encourages electronic filing. Please file motions to intervene and comments using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, 1 18 CFR 385.2001–2005 (2016). VerDate Sep<11>2014 18:14 Mar 21, 2017 Jkt 241001 please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010. Locations of Notice of Intent: Copies of the notice of intent can be obtained directly from the applicant or such copies can be viewed and reproduced at the Commission in its Public Reference Room, Room 2A, 888 First Street NE., Washington, DC 20426. The filing may also be viewed on the web at https:// www.ferc.gov/docs-filing/elibrary.asp using the ‘‘eLibrary’’ link. Enter the docket number (i.e., CD17–8) in the docket number field to access the document. For assistance, call toll-free 1–866–208–3676 or email FERCOnlineSupport@ferc.gov. For TTY, call (202) 502–8659. Dated: March 13, 2017. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2017–05669 Filed 3–21–17; 8:45 am] BILLING CODE 6717–01–P ENVIRONMENTAL PROTECTION AGENCY [EPA–HQ–ORD–2015–0765; FRL–9960–04– ORD] Board of Scientific Counselors Homeland Security Subcommittee; Notification of Public Teleconference and Public Comment Environmental Protection Agency (EPA). ACTION: Notification of public meeting and public comment. AGENCY: Pursuant to the Federal Advisory Committee Act, Public Law 92–463, the U.S. Environmental Protection Agency hereby provides notice that the Board of Scientific Counselors (BOSC) Homeland Security Subcommittee (HSS) will host a public SUMMARY: PO 00000 Frm 00041 Fmt 4703 Sfmt 4703 teleconference. The meeting will be held on Tuesday, March 28, 2017 from 11:00 a.m. to 12:30 p.m. All times noted are Eastern Time and are approximate. The primary discussions will focus on finalizing the draft report on the effective and efficient tools, strategies and methods to characterize and assess exposure and decontamination following a biological contamination incident. There will be a public comment period at 11:15 a.m. For information on registering to participate on the call or to provide public comment, please see the SUPPLEMENTARY INFORMATION section below. Due to unforeseen administrative circumstances, EPA is announcing this meeting with less than fifteen calendar days’ notice. DATES: The BOSC HSS meeting will be held on Tuesday, March 28, 2017 from 11:00 a.m. to 12:30 p.m. All times noted are Eastern Time and are approximate. FOR FURTHER INFORMATION CONTACT: Questions or correspondence concerning the meeting should be directed to Tom Tracy, Designated Federal Officer, Environmental Protection Agency, by mail at 1200 Pennsylvania Avenue NW., (MC 8104 R), Washington, DC 20460; by telephone at 202–564–6518; fax at 202–565–2911; or via email at tracy.tom@epa.gov. SUPPLEMENTARY INFORMATION: The Charter of the BOSC states that the advisory committee shall provide independent advice to the Administrator on technical and management aspects of the ORD’s research program. Additional information about the BOSC is available at: https://www2.epa.gov/bosc. Registration: In order to participate in the meeting, you must register at the following site: https://us-epa-2017-boschs-subcommitteeteleconference.eventbrite.com. Once you have completed the online registration, you will be contacted and provided with the meeting information. Registration will close on March 27, 2017. Oral Statements: Members of the public who wish to provide oral comment during the meeting must preregister. Individuals or groups making remarks during the public comment period will be limited to five E:\FR\FM\22MRN1.SGM 22MRN1

Agencies

[Federal Register Volume 82, Number 54 (Wednesday, March 22, 2017)]
[Notices]
[Pages 14712-14713]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-05669]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CD17-8-000]


Town of Carbondale, Colorado; Notice of Preliminary Determination 
of a Qualifying Conduit Hydropower Facility and Soliciting Comments and 
Motions To Intervene

    On March 9, 2017, the Town of Carbondale, Colorado, filed a notice 
of intent to construct a qualifying conduit hydropower facility, 
pursuant to section 30 of the Federal Power Act (FPA), as amended by 
section 4 of the Hydropower Regulatory Efficiency Act of 2013 (HREA). 
The proposed Town of Carbondale Nettle Creek WTP Hydro Project would 
have an installed capacity of 28 kilowatts (kW), and would be located 
along an existing raw water pipeline adjacent to the applicant's water 
treatment plant. The project would be located near the Town of 
Carbondale in Pitkin County, Colorado.
    Applicant Contact: Mark O'Meara, Utility Director, Town of 
Carbondale, 511 Colorado Avenue, Carbondale, CO 81623 Phone No. (970) 
963-3140.
    FERC Contact: Christopher Chaney, Phone No. (202) 502-6778, email: 
Christopher.Chaney@ferc.gov.
    Qualifying Conduit Hydropower Facility Description: The proposed 
project would consist of: (1) An new pressure reduction valve vault 
containing one turbine/generating unit with an installed capacity of 28 
kW; (2) a short, 10-inch-diameter penstock teeing off the existing raw 
water pipeline; (3) a short, 10-inch-diameter discharge pipe returning 
water to the existing raw water pipeline; and (4) appurtenant 
facilities. The proposed project would have an estimated annual 
generating capacity of 190,000 kilowatt-hours.
    A qualifying conduit hydropower facility is one that is determined 
or deemed to meet all of the criteria shown in the table below.

      Table 1--Criteria for Qualifying Conduit Hydropower Facility
------------------------------------------------------------------------
      Statutory provision              Description       Satisfies (Y/N)
------------------------------------------------------------------------
FPA 30(a)(3)(A), as amended by   The conduit the                      Y
 HREA.                            facility uses is a
                                  tunnel, canal,
                                  pipeline, aqueduct,
                                  flume, ditch, or
                                  similar manmade water
                                  conveyance that is
                                  operated for the
                                  distribution of water
                                  for agricultural,
                                  municipal, or
                                  industrial
                                  consumption and not
                                  primarily for the
                                  generation of
                                  electricity.
FPA 30(a)(3)(C)(i), as amended   The facility is                      Y
 by HREA.                         constructed,
                                  operated, or
                                  maintained for the
                                  generation of
                                  electric power and
                                  uses for such
                                  generation only the
                                  hydroelectric
                                  potential of a non-
                                  federally owned
                                  conduit.
FPA 30(a)(3)(C)(ii), as amended  The facility has an                  Y
 by HREA.                         installed capacity
                                  that does not exceed
                                  5 megawatts.

[[Page 14713]]

 
FPA 30(a)(3)(C)(iii), as         On or before August 9,               Y
 amended by HREA.                 2013, the facility is
                                  not licensed, or
                                  exempted from the
                                  licensing
                                  requirements of Part
                                  I of the FPA.
------------------------------------------------------------------------

    Preliminary Determination: The proposed addition of the 
hydroelectric project along the existing raw water pipeline will not 
alter its primary purpose. Therefore, based upon the above criteria, 
Commission staff preliminarily determines that the proposal satisfies 
the requirements for a qualifying conduit hydropower facility, which is 
not required to be licensed or exempted from licensing.
    Comments and Motions To Intervene: Deadline for filing comments 
contesting whether the facility meets the qualifying criteria is 45 
days from the issuance date of this notice.
    Deadline for filing motions to intervene is 30 days from the 
issuance date of this notice.
    Anyone may submit comments or a motion to intervene in accordance 
with the requirements of Rules of Practice and Procedure, 18 CFR 
385.210 and 385.214. Any motions to intervene must be received on or 
before the specified deadline date for the particular proceeding.
    Filing and Service of Responsive Documents: All filings must (1) 
bear in all capital letters the ``COMMENTS CONTESTING QUALIFICATION FOR 
A CONDUIT HYDROPOWER FACILITY'' or ``MOTION TO INTERVENE,'' as 
applicable; (2) state in the heading the name of the applicant and the 
project number of the application to which the filing responds; (3) 
state the name, address, and telephone number of the person filing; and 
(4) otherwise comply with the requirements of sections 385.2001 through 
385.2005 of the Commission's regulations.\1\ All comments contesting 
Commission staff's preliminary determination that the facility meets 
the qualifying criteria must set forth their evidentiary basis.
---------------------------------------------------------------------------

    \1\ 18 CFR 385.2001-2005 (2016).
---------------------------------------------------------------------------

    The Commission strongly encourages electronic filing. Please file 
motions to intervene and comments using the Commission's eFiling system 
at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the 
end of your comments. For assistance, please contact FERC Online 
Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or 
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper 
copy to: Secretary, Federal Energy Regulatory Commission, 888 First 
Street NE., Washington, DC 20426. A copy of all other filings in 
reference to this application must be accompanied by proof of service 
on all persons listed in the service list prepared by the Commission in 
this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
    Locations of Notice of Intent: Copies of the notice of intent can 
be obtained directly from the applicant or such copies can be viewed 
and reproduced at the Commission in its Public Reference Room, Room 2A, 
888 First Street NE., Washington, DC 20426. The filing may also be 
viewed on the web at https://www.ferc.gov/docs-filing/elibrary.asp using 
the ``eLibrary'' link. Enter the docket number (i.e., CD17-8) in the 
docket number field to access the document. For assistance, call toll-
free 1-866-208-3676 or email FERCOnlineSupport@ferc.gov. For TTY, call 
(202) 502-8659.

    Dated: March 13, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017-05669 Filed 3-21-17; 8:45 am]
 BILLING CODE 6717-01-P