Eastern Shore Natural Gas Company; Notice of Schedule for Environmental Review of the 2017 Expansion Project, 14216-14217 [2017-05308]
Download as PDF
14216
Federal Register / Vol. 82, No. 51 / Friday, March 17, 2017 / Notices
category was averaged over 2014–2016.3
The response requirements included in
this category were complete within 18
months of the effective date of the
standard 4 or by 10/1/2015. Due to
completion, the corresponding 304
annual burden hours are now being
removed.
Type of Respondents: NERC
Registered entities (specifically
balancing authorities, generator owners,
generator operators).
Estimate of Annual Burden: 5 The
Commission estimates the annual public
reporting burden for the information
collection as:
FERC–725T (MANDATORY RELIABILITY STANDARDS FOR THE BULK-POWER SYSTEM: TRE RELIABILITY STANDARDS)
Number of
respondents
Annual
number of
responses per
respondent
Total number
of responses
Average
burden and
cost per
response 6
Total annual
burden hours
and total
annual cost
Cost per
respondent
($)
(1)
(2)
(1) * (2) = (3)
(4)
(3) * (4) = (5)
(5) ÷ (1)
Maintenance and Submission of
Event Log Data.
Evidence Retention ...................
71
1
1
16 hrs.; $1,029 ......
16 hrs.; $1,029 ......
$1,029
8 130
1
130
2 hrs.; $76 .............
260 hrs.; $9,815 ....
$76
Total ...................................
........................
........................
131
...............................
276 hrs.; $10,844 ..
........................
In an order issued on October 8, 2004,
the Commission set forth a guideline for
Other Federal Agencies (OFAs) to
submit their costs related to
Administering Part I of the Federal
Power Act. Order On Rehearing
Consolidating Administrative Annual
Charges Bill Appeals And Modifying
Annual Charges Billing Procedures, 109
FERC 61,040 (2004) (October 8 Order).
The Commission required OFAs to
submit their costs using the OFA Cost
Submission Form. The October 8 Order
also announced that a technical
conference would be held for the
purpose of reviewing the submitted cost
forms and detailed supporting
documentation.
The Commission will hold a technical
conference for reviewing the submitted
OFA costs. The purpose of the
conference will be for OFAs and
licensees to discuss costs reported in the
forms and any other supporting
documentation or analyses.
The technical conference will be held
on April 6, 2017, in Conference Room
3M–1 at the Commission’s headquarters,
888 First Street NE., Washington, DC.
The technical conference will begin at
2:00 p.m. (EST).
The technical conference will also be
transcribed. Those interested in
obtaining a copy of the transcript
immediately for a fee should contact the
Ace-Federal Reporters, Inc., at 202–347–
3700, or 1–800–336–6646. Two weeks
after the post-forum meeting, the
transcript will be available for free on
the Commission’s e-library system.
Anyone without access to the
Commission’s Web site or who has
3 The total annual figure for this response
category was 304 hours.
4 The effective date of the standard was 4/1/2014.
5 Burden is defined as the total time, effort, or
financial resources expended by persons to
generate, maintain, retain, or disclose or provide
information to or for a Federal agency. For further
explanation of what is included in the information
collection burden, reference 5 Code of Federal
Regulations 1320.3.
6 The estimates for cost per hour are based on
2015 wage figures and derived as follows:
• $64.29/hour, the average salary plus benefits
per engineer (from Bureau of Labor Statistics at
https://www.bls.gov/oes/current/naics2_22.htm)
• $37.75/hour, the salary plus benefits per
information and record clerks (from Bureau of
Comments: Comments are invited on:
(1) Whether the collection of
information is necessary for the proper
performance of the functions of the
Commission, including whether the
information will have practical utility;
(2) the accuracy of the agency’s estimate
of the burden and cost of the collection
of information, including the validity of
the methodology and assumptions used;
(3) ways to enhance the quality, utility
and clarity of the information collection;
and (4) ways to minimize the burden of
the collection of information on those
who are to respond, including the use
of automated collection techniques or
other forms of information technology.
Dated: March 10, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017–05309 Filed 3–16–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. AD17–1–000]
asabaliauskas on DSK3SPTVN1PROD with NOTICES
Review of Cost Submittals by Other
Federal Agencies for Administering
Part I of the Federal Power Act; Notice
of Technical Conference
VerDate Sep<11>2014
20:02 Mar 16, 2017
Jkt 241001
PO 00000
Frm 00019
Fmt 4703
Sfmt 4703
questions about the technical
conference should contact Norman
Richardson at (202) 502–6219 or via
email at annualcharges@ferc.gov.
FERC conferences are accessible
under section 508 of the Rehabilitation
Act of 1973. For accessibility
accommodations please send an email
to accessibility@ferc.gov or call toll free
(866) 208–3372 (voice), (202) 208–8659
(TTY), or send a FAX to 202–208–2106
with the required accommodations.
Dated: March 10, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017–05306 Filed 3–16–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP17–28–000]
Eastern Shore Natural Gas Company;
Notice of Schedule for Environmental
Review of the 2017 Expansion Project
On December 30, 2016, Eastern Shore
Natural Gas Company (Eastern Shore)
filed an application in Docket No.
CP17–28–000 requesting a Certificate of
Public Convenience and Necessity
pursuant to Section 7(c) of the Natural
Gas Act to construct and operate certain
natural gas pipeline facilities. Eastern
Shore’s proposal is known as the 2017
Labor Statistics at https://www.bls.gov/oes/current/
naics2_22.htm)
All calculated wage figures within the burden
table are rounded to the nearest dollar.
7 BA (balancing authority).
8 BA (balancing authority), GO (generator owner),
and GOP (generator operator).
E:\FR\FM\17MRN1.SGM
17MRN1
Federal Register / Vol. 82, No. 51 / Friday, March 17, 2017 / Notices
Expansion Project (Project), and would
involve construction of approximately
40 miles of pipeline and appurtenant
facilities located in Pennsylvania,
Maryland, and Delaware to provide
61,162 dekatherms per day of additional
firm transportation service.
On January 11, 2017, the Federal
Energy Regulatory Commission
(Commission or FERC) issued its Notice
of Application for the Project. Among
other things, that notice alerted agencies
issuing federal authorizations of the
requirement to complete all necessary
reviews and to reach a final decision on
a request for a federal authorization
within 90 days of the date of issuance
of the Commission staff’s Environmental
Assessment (EA) for the Project. This
instant notice identifies the FERC staff’s
planned schedule for the completion of
the EA for the Project.
Schedule for Environmental Review
Issuance of EA—May 12, 2017.
90-day Federal Authorization
Decision Deadline—August 10, 2017.
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the Project’s
progress.
Additional Information
asabaliauskas on DSK3SPTVN1PROD with NOTICES
Project Description
The facilities to be constructed and
operated under Section 7(c) include: (1)
Six pipeline loop segments totaling 22.7
miles; (2) one 10-inch-diameter 16.9mile-long mainline extension; (3)
upgrades to an existing Meter and
Regulator Station in Lancaster County,
Pennsylvania; (4) installation of an
additional 3,750 horsepower
compressor unit at the existing Daleville
Compressor Station in Chester County,
Pennsylvania; and (5) the addition of
two pressure control stations in Sussex
County, Delaware.
Background
On August 1, 2016, the Commission
issued a Notice of Intent To Prepare an
Environmental Assessment for the
Proposed 2017 Expansion Project and
Request for Comments on
Environmental Issues (NOI). The NOI
was issued during the pre-filing review
of the Project in Docket no. PF16–7 and
was sent to federal, state, and local
government representatives and
agencies; elected officials; Native
American tribes; potentially affected
landowners; and other interested
individuals and groups in the Project
area. In response to the Notice of Intent,
the Commission received comments
from the Pennsylvania Department of
Environmental Protection, West
Sadsbury Township, the Chester Water
VerDate Sep<11>2014
20:02 Mar 16, 2017
Jkt 241001
Authority, the Maryland Historical
Trust, the Delaware Department of
Natural Resources and Environmental
Control—Division of Fish and Wildlife,
the Franklin Township Historical
Commission, and the National Park
Service. The primary concerns raised
were regarding wetland and waterbody
impacts; potential damage to water
mains; impacts on the White Clay Creek
National Wild and Scenic River;
potential impacts on bog turtles and
their habitat; and potential impacts on
historic, scenic, or cultural resources.
Five private landowners filed comments
expressing questions or concerns
regarding the right-of-way acquisition
process, overall public safety and
pipeline reliability, restoration efforts,
and the procedures to be used should
future roadway widening occur where
the pipeline is installed under the
highway.
The U.S. Army Corps of Engineers
and the U.S. Department of Agriculture
Natural Resources Conservation Service
are cooperating agencies in the
preparation of the EA.
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp. Additional
information about the Project is
available from the Commission’s Office
of External Affairs at (866) 208–FERC or
on the FERC Web site (www.ferc.gov).
Using the ‘‘eLibrary’’ link, select
‘‘General Search’’ from the eLibrary
menu, enter the selected date range and
‘‘Docket Number’’ excluding the last
three digits (i.e., CP17–28), and follow
the instructions. For assistance with
access to eLibrary, the helpline can be
reached at (866) 208–3676, TTY (202)
502–8659, or at FERCOnlineSupport@
ferc.gov. The eLibrary link on the FERC
Web site also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rule makings.
Dated: March 10, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017–05308 Filed 3–16–17; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00020
Fmt 4703
Sfmt 4703
14217
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2787–007]
Green Mountain Power; Ottauquechee
Hydro Company, Inc.; Notice of
Transfer of Exemption
1. By letter filed February 21, 2017
and supplemented on March 2, 2017,
Enel Green Power North America, Inc.
informed the Commission that the
exemption from licensing for the
Ottauquechee Woolen Mill Project No.
2787, originally issued August 13,
1982 1 has been transferred to the Green
Mountain Power, effective January 29,
2017. The project is located on the
Ottauquechee River in Windsor County,
Vermont. The transfer of an exemption
does not require Commission approval.
2. Green Mountain Power is now the
exemptee of the Ottauquechee Woolen
Mill Project No. 2787. All
correspondence should be forwarded to:
Green Mountain Power, 163 Acorn
Lane, Colchester, VT 05446.
Dated: March 10, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017–05310 Filed 3–16–17; 8:45 am]
BILLING CODE 6717–01–P
ENVIRONMENTAL PROTECTION
AGENCY
[ER–FRL–9032–2]
Environmental Impact Statements;
Notice of Availability
Responsible Agency: Office of Federal
Activities, General Information (202)
564–7146 or https://www.epa.gov/nepa.
Weekly receipt of Environmental Impact
Statements (EISs),
Filed 03/06/2017 Through 03/10/
2017.
Pursuant to 40 CFR 1506.9.
Notice
Section 309(a) of the Clean Air Act
requires that EPA make public its
comments on EISs issued by other
Federal agencies. EPA’s comment letters
on EISs are available at: https://
www.epa.gov/compliance/nepa/
eisdata.html.
EIS No. 20170032, Draft, USFS, OR,
Ringo Project, Comment Period Ends:
05/01/2017, Contact: Lillian Cross,
541–433–3200.
1 Order Granting Exemption from Licensing of a
Small Hydroelectric Project of 5 MW or Less. White
Current Corporation, 20 FERC ¶ 62,271 (1982).
E:\FR\FM\17MRN1.SGM
17MRN1
Agencies
[Federal Register Volume 82, Number 51 (Friday, March 17, 2017)]
[Notices]
[Pages 14216-14217]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-05308]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP17-28-000]
Eastern Shore Natural Gas Company; Notice of Schedule for
Environmental Review of the 2017 Expansion Project
On December 30, 2016, Eastern Shore Natural Gas Company (Eastern
Shore) filed an application in Docket No. CP17-28-000 requesting a
Certificate of Public Convenience and Necessity pursuant to Section
7(c) of the Natural Gas Act to construct and operate certain natural
gas pipeline facilities. Eastern Shore's proposal is known as the 2017
[[Page 14217]]
Expansion Project (Project), and would involve construction of
approximately 40 miles of pipeline and appurtenant facilities located
in Pennsylvania, Maryland, and Delaware to provide 61,162 dekatherms
per day of additional firm transportation service.
On January 11, 2017, the Federal Energy Regulatory Commission
(Commission or FERC) issued its Notice of Application for the Project.
Among other things, that notice alerted agencies issuing federal
authorizations of the requirement to complete all necessary reviews and
to reach a final decision on a request for a federal authorization
within 90 days of the date of issuance of the Commission staff's
Environmental Assessment (EA) for the Project. This instant notice
identifies the FERC staff's planned schedule for the completion of the
EA for the Project.
Schedule for Environmental Review
Issuance of EA--May 12, 2017.
90-day Federal Authorization Decision Deadline--August 10, 2017.
If a schedule change becomes necessary, additional notice will be
provided so that the relevant agencies are kept informed of the
Project's progress.
Project Description
The facilities to be constructed and operated under Section 7(c)
include: (1) Six pipeline loop segments totaling 22.7 miles; (2) one
10-inch-diameter 16.9-mile-long mainline extension; (3) upgrades to an
existing Meter and Regulator Station in Lancaster County, Pennsylvania;
(4) installation of an additional 3,750 horsepower compressor unit at
the existing Daleville Compressor Station in Chester County,
Pennsylvania; and (5) the addition of two pressure control stations in
Sussex County, Delaware.
Background
On August 1, 2016, the Commission issued a Notice of Intent To
Prepare an Environmental Assessment for the Proposed 2017 Expansion
Project and Request for Comments on Environmental Issues (NOI). The NOI
was issued during the pre-filing review of the Project in Docket no.
PF16-7 and was sent to federal, state, and local government
representatives and agencies; elected officials; Native American
tribes; potentially affected landowners; and other interested
individuals and groups in the Project area. In response to the Notice
of Intent, the Commission received comments from the Pennsylvania
Department of Environmental Protection, West Sadsbury Township, the
Chester Water Authority, the Maryland Historical Trust, the Delaware
Department of Natural Resources and Environmental Control--Division of
Fish and Wildlife, the Franklin Township Historical Commission, and the
National Park Service. The primary concerns raised were regarding
wetland and waterbody impacts; potential damage to water mains; impacts
on the White Clay Creek National Wild and Scenic River; potential
impacts on bog turtles and their habitat; and potential impacts on
historic, scenic, or cultural resources. Five private landowners filed
comments expressing questions or concerns regarding the right-of-way
acquisition process, overall public safety and pipeline reliability,
restoration efforts, and the procedures to be used should future
roadway widening occur where the pipeline is installed under the
highway.
The U.S. Army Corps of Engineers and the U.S. Department of
Agriculture Natural Resources Conservation Service are cooperating
agencies in the preparation of the EA.
Additional Information
In order to receive notification of the issuance of the EA and to
keep track of all formal issuances and submittals in specific dockets,
the Commission offers a free service called eSubscription. This can
reduce the amount of time you spend researching proceedings by
automatically providing you with notification of these filings,
document summaries, and direct links to the documents. Go to
www.ferc.gov/docs-filing/esubscription.asp. Additional information
about the Project is available from the Commission's Office of External
Affairs at (866) 208-FERC or on the FERC Web site (www.ferc.gov). Using
the ``eLibrary'' link, select ``General Search'' from the eLibrary
menu, enter the selected date range and ``Docket Number'' excluding the
last three digits (i.e., CP17-28), and follow the instructions. For
assistance with access to eLibrary, the helpline can be reached at
(866) 208-3676, TTY (202) 502-8659, or at FERCOnlineSupport@ferc.gov.
The eLibrary link on the FERC Web site also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rule makings.
Dated: March 10, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-05308 Filed 3-16-17; 8:45 am]
BILLING CODE 6717-01-P