Columbia Gas Transmission, LLC; Notice of Revised Schedule for Environmental Review of the B-System Project, 11568 [2017-03565]

Download as PDF 11568 Federal Register / Vol. 82, No. 36 / Friday, February 24, 2017 / Notices asabaliauskas on DSK3SPTVN1PROD with NOTICES proceeding can ask for court review of Commission orders in the proceeding. However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission’s rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commentors will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission’s environmental review process. Environmental commentors will not be required to serve copies of filed documents on all other parties. However, the non-party commentors will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically should submit an original and 7 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. Comment Date: March 10, 2017. Dated: February 17, 2017. Nathaniel J. Davis, Sr., Deputy Secretary. DEPARTMENT OF ENERGY DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Federal Energy Regulatory Commission [Docket Nos. CP16–498–000; PF16–4–000 ] [Project No. 7656–013] Columbia Gas Transmission, LLC; Notice of Revised Schedule for Environmental Review of the B-System Project John A. Dodson; Village of Highland Falls High-Point Utility, LDC; Notice of Application for Transfer of License and Soliciting Comments, Motions To Intervene, and Protests This notice identifies the Federal Energy Regulatory Commission staff’s revised schedule for the completion of the environmental assessment (EA) for Columbia Gas Transmission, LLC’s (Columbia) B-System Project. The original notice of schedule, issued on December 20, 2016, identified March 13, 2017 as the EA issuance date. Due to updated B-System Project information filed by Columbia on February 7, 2017, staff has revised the schedule for issuance of the EA. Schedule for Environmental Review Issuance of EA—April 28, 2017 90-day Federal Authorization Decision Deadline—July 27, 2017 If a schedule change becomes necessary, an additional notice will be provided so that the relevant agencies are kept informed of the project’s progress. Additional Information In order to receive notification of the issuance of the EA and to keep track of all formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription (https://www.ferc.gov/docs-filing/ esubscription.asp). Additional information about the project may be obtained by contacting the Environmental Project Manager, Kenneth Warn, by telephone at 202– 502–6859 or by electronic mail at kenneth.warn@ferc.gov. Dated: February 16, 2017. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2017–03565 Filed 2–23–17; 8:45 am] BILLING CODE 6717–01–P [FR Doc. 2017–03591 Filed 2–23–17; 8:45 am] BILLING CODE 6717–01–P VerDate Sep<11>2014 17:20 Feb 23, 2017 Jkt 241001 PO 00000 Frm 00046 Fmt 4703 Sfmt 4703 On August 11, 2016, and supplemented on November 28, 2016 and January 24, 2017, Mr. John A. Dodson (transferor) and the Village of Highland Falls High-Point Utility, LDC (transferee) filed an application to transfer the license for the Buttermilk Falls Hydroelectric Project No. 7656. The project is located on Buttermilk Falls Brook in Orange County, New York. The above parties seek Commission approval to transfer the license for the project from the transferor to the transferee. Applicants’ Contact: For Transferor: Mr. John A. Dodson, 27 Webb Lane, Highland Falls, NY 10928, Phone: (914) 446–7704, Email: thayerenergy@ gmail.com. For Transferee: Mr. William J. Florence, Jr., Village of Highland Falls High-Point Utility, LDC, 303 Main Street, Highland Falls, NY 10928, Phone: (914) 737–7001, Email: williamflorence@mac.com. FERC Contact: Ashish Desai, (202) 502–8370, Ashish.Desai@ferc.gov. Deadline for filing comments, motions to intervene, and protests: 30 days from the issuance date of this notice by the Commission. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, and protests using the Commission’s eFiling system at https://www.ferc.gov/docsfiling/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. The first page of any filing should include docket number P–7656–013. E:\FR\FM\24FEN1.SGM 24FEN1

Agencies

[Federal Register Volume 82, Number 36 (Friday, February 24, 2017)]
[Notices]
[Page 11568]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-03565]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. CP16-498-000; PF16-4-000 ]


Columbia Gas Transmission, LLC; Notice of Revised Schedule for 
Environmental Review of the B-System Project

    This notice identifies the Federal Energy Regulatory Commission 
staff's revised schedule for the completion of the environmental 
assessment (EA) for Columbia Gas Transmission, LLC's (Columbia) B-
System Project. The original notice of schedule, issued on December 20, 
2016, identified March 13, 2017 as the EA issuance date. Due to updated 
B-System Project information filed by Columbia on February 7, 2017, 
staff has revised the schedule for issuance of the EA.

Schedule for Environmental Review

Issuance of EA--April 28, 2017
90-day Federal Authorization Decision Deadline--July 27, 2017

    If a schedule change becomes necessary, an additional notice will 
be provided so that the relevant agencies are kept informed of the 
project's progress.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription (https://www.ferc.gov/docs-filing/esubscription.asp). Additional information 
about the project may be obtained by contacting the Environmental 
Project Manager, Kenneth Warn, by telephone at 202-502-6859 or by 
electronic mail at kenneth.warn@ferc.gov.

    Dated: February 16, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017-03565 Filed 2-23-17; 8:45 am]
 BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.