Merchant Hydro Developers, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 11214-11215 [2017-03324]
Download as PDF
11214
Federal Register / Vol. 82, No. 33 / Tuesday, February 21, 2017 / Notices
Comments on EA or draft EA or draft
EIS—June 2018
Commission issues final EA of final
EIS—August 2018
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of the notice of ready for
environmental analysis.
Dated: February 14, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017–03325 Filed 2–17–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
sradovich on DSK3GMQ082PROD with NOTICES
Combined Notice of Filings #2
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER17–753–001.
Applicants: PJM Interconnection,
L.L.C.
Description: Tariff Amendment: Errata
to Correct RTEP Approved by Board in
Dec 2016 submitted in ER17–753–000 to
be effective 4/6/2017.
Filed Date: 2/14/17.
Accession Number: 20170214–5073.
Comments Due: 5 p.m. ET 3/16/17.
Docket Numbers: ER17–969–000.
Applicants: Southwest Power Pool,
Inc.
Description: § 205(d) Rate Filing: 3165
Otter Tail Power Company NITSA and
NOA Notice of Cancellation to be
effective 2/1/2017.
Filed Date: 2/14/17.
Accession Number: 20170214–5070.
Comments Due: 5 p.m. ET 3/7/17.
Docket Numbers: ER17–970–000.
Applicants: Northern States Power
Company, a Minnesota corporation.
Description: § 205(d) Rate Filing:
CAPX-Multi-Hawks Nest Const-647–
0.0.0 to be effective 1/25/2017.
Filed Date: 2/14/17.
Accession Number: 20170214–5124.
Comments Due: 5 p.m. ET 3/7/17.
Take notice that the Commission
received the following qualifying
facility filings:
Docket Numbers: QF17–676–000.
Applicants: City of Charlotte, North
Carolina.
Description: Form 556 of City of
Charlotte.
Filed Date: 2/9/17.
Accession Number: 20170209–5306.
Comments Due: None Applicable.
The filings are accessible in the
Commission’s eLibrary system by
VerDate Sep<11>2014
17:15 Feb 17, 2017
Jkt 241001
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: February 14, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017–03318 Filed 2–17–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings
Take notice that the Commission has
received the following Part 284 Natural
Gas Pipeline Rate filings:
Filings Instituting Proceedings
Docket Number: PR17–22–000.
Applicants: New Mexico Gas
Company, Inc.
Description: Tariff filing per
284.123(b), (e)+(g): NGPA Section 311
Periodic Rate Review Certification to be
effective 2/1/2012; Filing Type: 1300.
Filed Date: 2/1/17.
Accession Number: 201702015214.
Comments Due: 5 p.m. ET 2/22/17.
284.123(g) Protests Due: 5 p.m. ET 4/
3/17.
Docket Number: PR17–23–000.
Applicants: Regency DeSoto Pipeline
LLC.
Description: Tariff filing per
284.123(e)+(g): Cancellation of GT&C
Eff. 4.1.2017 to be effective 4/1/2017;
Filing Type: 1290.
Filed Date: 2/1/17.
Accession Number: 201702015265.
Comments Due: 5 p.m. ET 2/22/17.
284.123(g) Protests Due: 5 p.m. ET 4/
3/17.
Docket Number: PR17–24–000.
Applicants: Atmos Energy
Corporation.
Description: Tariff filing per
284.123(b),(e)+(g): Request for Change in
Rates Based on State Rate Election to be
effective 3/1/2017; Filing Type: 1300.
PO 00000
Frm 00044
Fmt 4703
Sfmt 4703
Filed Date: 2/2/17.
Accession Number: 201702025130.
Comments Due: 5 p.m. ET 2/23/17.
284.123(g) Protests Due: 5 p.m. ET 4/
3/17.
Docket Number: PR17–25–000.
Applicants: Columbia Gas of Ohio,
Inc.
Description: Tariff filing per
284.123(b),(e)/: COH SOC Effective 1–
31–2017; Filing Type: 980.
Filed Date: 2/3/17.
Accession Number: 201702035078.
Comments/Protests Due: 5 p.m. ET 2/
24/17.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified date(s). Protests
may be considered, but intervention is
necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: February 7, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017–03349 Filed 2–17–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14809–000]
Merchant Hydro Developers, LLC;
Notice of Preliminary Permit
Application Accepted for Filing and
Soliciting Comments, Motions To
Intervene, and Competing Applications
On December 19, 2016, Merchant
Hydro Developers, LLC, filed an
application for a preliminary permit,
pursuant to section 4(f) of the Federal
Power Act (FPA), proposing to study the
feasibility of the Shenandoah Pumped
Storage Hydroelectric Project to be
located near Shenandoah Borough in
Schuylkill County, Pennsylvania. The
sole purpose of a preliminary permit, if
issued, is to grant the permit holder
priority to file a license application
E:\FR\FM\21FEN1.SGM
21FEN1
sradovich on DSK3GMQ082PROD with NOTICES
Federal Register / Vol. 82, No. 33 / Tuesday, February 21, 2017 / Notices
during the permit term. A preliminary
permit does not authorize the permit
holder to perform any land-disturbing
activities or otherwise enter upon lands
or waters owned by others without the
owners’ express permission.
The proposed project would consist of
the following: (1) As many as two new
upper reservoirs with a combined
surface area of 470 acres and a
combined storage capacity of 7,050 acrefeet at a surface elevation of
approximately 1,750 feet above mean
sea level (msl) created through
construction of new roller-compacted
concrete or rock-filled dams and/or
dikes; (2) a new lower reservoir,
including an existing abandoned mine
pit, with a surface area of 105 acres and
a total storage capacity of 7,200 acre-feet
at a surface elevation of 1,210 feet msl;
(3) as many as three new 3,387-footlong, 48-inch-diameter penstocks
connecting the upper and lower
reservoirs; (4) a new 150-foot-long, 50foot-wide powerhouse containing two
turbine-generator units with a total rated
capacity of 405 megawatts; (5) a new
transmission line connecting the
powerhouse to a nearby electric grid
interconnection point with options to
evaluate multiple grid interconnection
locations; and (6) appurtenant facilities.
Possible initial fill water and make-up
water would come from local inflow to
the abandoned mine pit, including
groundwater. The proposed project
would have an annual generation of
1,181,385 megawatt-hours.
Applicant Contact: Adam Rousselle,
Merchant Hydro Developers, LLC, 5710
Oak Crest Drive, Doylestown, PA 18902;
phone: 267–254–6107.
FERC Contact: Monir Chowdhury;
phone: (202) 502–6736.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
VerDate Sep<11>2014
17:15 Feb 17, 2017
Jkt 241001
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–14809–000.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P–14809) in
the docket number field to access the
document. For assistance, contact FERC
Online Support.
Dated: February 14, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017–03324 Filed 2–17–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
Filings Instituting Proceedings
Docket Numbers: RP17–376–000.
Applicants: Equitrans, L.P.
Description: Tariff Cancellation:
Terminate Negotiated Rate Service
Agreement—Range Resources
Appalachia LLC to be effective
2/1/2017.
Filed Date: 1/31/17.
Accession Number: 20170131–5484.
Comments Due: 5 p.m. ET 2/13/17.
Docket Numbers: RP17–350–001.
Applicants: Eastern Shore Natural Gas
Company.
Description: Compliance filing Errata
to Filing to Comply with Order in
Docket Nos. CP15–18–000, 001 to be
effective 3/1/2017.
Filed Date: 2/1/17.
Accession Number: 20170201–5137.
Comments Due: 5 p.m. ET 2/13/17.
Docket Numbers: RP17–383–000.
Applicants: Northern Natural Gas
Company.
Description: § 4(d) Rate Filing:
20170201 Miscellaneous Filing to be
effective 3/4/2017.
Filed Date: 2/1/17.
Accession Number: 20170201–5104.
Comments Due: 5 p.m. ET 2/13/17.
Docket Numbers: RP17–384–000.
Applicants: Natural Gas Pipeline
Company of America.
Description: § 4(d) Rate Filing:
Negotiated Rate Filing—Nicor to be
effective 2/1/2017.
PO 00000
Frm 00045
Fmt 4703
Sfmt 4703
11215
Filed Date: 2/1/17.
Accession Number: 20170201–5128.
Comments Due: 5 p.m. ET 2/13/17.
Docket Numbers: RP17–385–000.
Applicants: Northern Natural Gas
Company.
Description: § 4(d) Rate Filing:
20170201 Annual PRA Fuel Rates to be
effective 4/1/2017.
Filed Date: 2/1/17.
Accession Number: 20170201–5148.
Comments Due: 5 p.m. ET 2/13/17.
Docket Numbers: RP17–386–000.
Applicants: Enable Gas Transmission,
LLC.
Description: § 4(d) Rate Filing:
Negotiated Rate Filing—February 2017
Spire 1005896 to be effective 2/1/2017.
Filed Date: 2/1/17.
Accession Number: 20170201–5201.
Comments Due: 5 p.m. ET 2/13/17.
Docket Numbers: RP17–387–000.
Applicants: Dauphin Island Gathering
Partners.
Description: § 4(d) Rate Filing:
Negotiated Rate Filing 2–1–2017 to be
effective 2/1/2017.
Filed Date: 2/1/17.
Accession Number: 20170201–5221.
Comments Due: 5 p.m. ET 2/13/17.
Docket Numbers: RP17–388–000.
Applicants: Northern Border Pipeline
Company.
Description: § 4(d) Rate Filing: James
Valley Ethanol Neg Rate Agmt Revision
to be effective 2/1/2017.
Filed Date: 2/1/17.
Accession Number: 20170201–5235.
Comments Due: 5 p.m. ET 2/13/17.
Docket Numbers: RP17–389–000.
Applicants: Cimarron River Pipeline,
LLC.
Description: § 4(d) Rate Filing: Fuel
Tracker 2017—Summer Season Rates to
be effective 4/1/2017.
Filed Date: 2/1/17.
Accession Number: 20170201–5254.
Comments Due: 5 p.m. ET 2/13/17.
Docket Numbers: RP17–390–000.
Applicants: Questar Overthrust
Pipeline, LLC.
Description: § 4(d) Rate Filing:
Statement of Negotiated Rates Version
7.0.0, Simplot Phosphates to be effective
3/1/2017.
Filed Date: 2/1/17.
Accession Number: 20170201–5259.
Comments Due: 5 p.m. ET 2/13/17.
Docket Numbers: RP17–391–000.
Applicants: Cimarron River Pipeline,
LLC.
Description: § 4(d) Rate Filing:
Negotiated Rates 2017–02–01 to be
effective 2/1/2017.
Filed Date: 2/1/17.
Accession Number: 20170201–5264.
Comments Due: 5 p.m. ET 2/13/17.
E:\FR\FM\21FEN1.SGM
21FEN1
Agencies
[Federal Register Volume 82, Number 33 (Tuesday, February 21, 2017)]
[Notices]
[Pages 11214-11215]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-03324]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 14809-000]
Merchant Hydro Developers, LLC; Notice of Preliminary Permit
Application Accepted for Filing and Soliciting Comments, Motions To
Intervene, and Competing Applications
On December 19, 2016, Merchant Hydro Developers, LLC, filed an
application for a preliminary permit, pursuant to section 4(f) of the
Federal Power Act (FPA), proposing to study the feasibility of the
Shenandoah Pumped Storage Hydroelectric Project to be located near
Shenandoah Borough in Schuylkill County, Pennsylvania. The sole purpose
of a preliminary permit, if issued, is to grant the permit holder
priority to file a license application
[[Page 11215]]
during the permit term. A preliminary permit does not authorize the
permit holder to perform any land-disturbing activities or otherwise
enter upon lands or waters owned by others without the owners' express
permission.
The proposed project would consist of the following: (1) As many as
two new upper reservoirs with a combined surface area of 470 acres and
a combined storage capacity of 7,050 acre-feet at a surface elevation
of approximately 1,750 feet above mean sea level (msl) created through
construction of new roller-compacted concrete or rock-filled dams and/
or dikes; (2) a new lower reservoir, including an existing abandoned
mine pit, with a surface area of 105 acres and a total storage capacity
of 7,200 acre-feet at a surface elevation of 1,210 feet msl; (3) as
many as three new 3,387-foot-long, 48-inch-diameter penstocks
connecting the upper and lower reservoirs; (4) a new 150-foot-long, 50-
foot-wide powerhouse containing two turbine-generator units with a
total rated capacity of 405 megawatts; (5) a new transmission line
connecting the powerhouse to a nearby electric grid interconnection
point with options to evaluate multiple grid interconnection locations;
and (6) appurtenant facilities. Possible initial fill water and make-up
water would come from local inflow to the abandoned mine pit, including
groundwater. The proposed project would have an annual generation of
1,181,385 megawatt-hours.
Applicant Contact: Adam Rousselle, Merchant Hydro Developers, LLC,
5710 Oak Crest Drive, Doylestown, PA 18902; phone: 267-254-6107.
FERC Contact: Monir Chowdhury; phone: (202) 502-6736.
Deadline for filing comments, motions to intervene, competing
applications (without notices of intent), or notices of intent to file
competing applications: 60 days from the issuance of this notice.
Competing applications and notices of intent must meet the requirements
of 18 CFR 4.36.
The Commission strongly encourages electronic filing. Please file
comments, motions to intervene, notices of intent, and competing
applications using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief
comments up to 6,000 characters, without prior registration, using the
eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You
must include your name and contact information at the end of your
comments. For assistance, please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to:
Secretary, Federal Energy Regulatory Commission, 888 First Street NE.,
Washington, DC 20426. The first page of any filing should include
docket number P-14809-000.
More information about this project, including a copy of the
application, can be viewed or printed on the ``eLibrary'' link of
Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P-14809) in the docket number field to access
the document. For assistance, contact FERC Online Support.
Dated: February 14, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-03324 Filed 2-17-17; 8:45 am]