CPV Maryland, LLC; Notice of Institution of Section 206 Proceeding and Refund Effective Date, 9376 [2017-02422]
Download as PDF
9376
Federal Register / Vol. 82, No. 23 / Monday, February 6, 2017 / Notices
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Amendment to WMPA SA No. 4469,
Queue No. AA1–106 to be effective 5/
3/2016.
Filed Date: 1/31/17.
Accession Number: 20170131–5089.
Comments Due: 5 p.m. ET 2/21/17.
Docket Numbers: ER17–897–000.
Applicants: Entergy Louisiana, LLC.
Description: Request for Limited
Waiver of Entergy Louisiana, LLC under
ER17–897.
Filed Date: 1/30/17.
Accession Number: 20170130–5394.
Comments Due: 5 p.m. ET 2/21/17.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: January 31, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017–02389 Filed 2–3–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. EL17–39–000]
sradovich on DSK3GMQ082PROD with NOTICES
CPV Maryland, LLC; Notice of
Institution of Section 206 Proceeding
and Refund Effective Date
On January 30, 2017, the Commission
issued an order in Docket No. EL17–39–
000, pursuant to section 206 of the
Federal Power Act (FPA), 16 U.S.C.
824e (2012), instituting an investigation
into whether the Rate Schedule for
Reactive Service of CPV Maryland, LLC
may be unjust, unreasonable, unduly
discriminatory or preferential. CPV
Maryland, LLC, 158 FERC 61,084 (2017).
The refund effective date in Docket
No. EL17–39–000, established pursuant
VerDate Sep<11>2014
16:03 Feb 03, 2017
Jkt 241001
to section 206(b) of the FPA, will be the
date of publication of this notice in the
Federal Register.
Any interested person desiring to be
heard in Docket No. EL17–39–000 must
file a notice of intervention or motion to
intervene, as appropriate, with the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426, in accordance with Rule 214 of
the Commission’s Rules of Practice and
Procedure, 18 CFR 385.214, within 21
days of the date of issuance of the order.
Dated: January 31, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017–02422 Filed 2–3–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 12756–007]
BOST3 Hydroelectric Company, LLC
(BOST3); Notice of Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene and
Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Non-Capacity
Amendment of License.
b. Project No.: P–12756–007.
c. Date filed: November 14, 2016 and
supplemented on January 30, 2017.
d. Applicant: BOST3 Hydroelectric
Company, LLC (BOST3).
e. Name of Project: Red River Lock &
Dam No. 3 Hydroelectric Project.
f. Location: The proposed project
would be located at the existing Army
Corps of Engineer’s (Corps) Red River
Lock & Dam No. 3 on the Red River, in
Natchitoches Parish near the City of
Colfax, Louisiana.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r
h. Applicant Contact: Mr. Douglas A.
Spalding, BOST3 Hydroelectric
Company, LLC, 8441 Wayzata Blvd.,
Suite 101, Golden Valley, MN 55426;
(952) 544–8133.
i. FERC Contact: M. Joseph Fayyad
(202) 502–8759, or by email at
mo.fayyad@ferc.gov.
j. Deadline for filing comments,
motions to intervene and protests is 30
days from the issuance of this notice by
the Commission. The Commission
strongly encourages electronic filing.
Please file comments, motions to
intervene, and protests using the
PO 00000
Frm 00007
Fmt 4703
Sfmt 4703
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/doc-sfiling/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–12756–007.
k. Description of Amendment: The
licensee proposes certain design
changes to the project’s powerhouse,
generating units, draft tube, switchyard
location and transmission line route, as
follows: (1) The powerhouse will be 93foot-long by 198-foot-wide by 83 foothigh, with five 7.2 MW Kaplan bulb
turbine-generator units: (2) five 70-footlong by 198-foot-wide by 73-foot-high
draft tubes that would convey water
from the turbines to the tailrace; (3)
move the location of the project’s
switchyard about 1400 feet southwest
from the current licensed location; and
(4) the transmission line would be about
2300-foot-long, 230-kV line connecting
the powerhouse to Central Louisiana
Electric Company at the project’s 100foot-long by 100-foot-wide switchyard.
The design changes would reduce the
total project’s hydraulic capacity from
19,085 cubic feet per second (cfs) to
19,055 cfs. The amount of federal lands
used by the project would increase from
61.8 acres to 76.31 acres.
l. Locations of the Applications: A
copy of the application is available for
inspection and reproduction at the
Commission’s Public Reference Room,
located at 888 First Street NE., Room
2A, Washington, DC 20426, or by calling
(202) 502–8371. The filing may also be
viewed on the Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
excluding the last three digits in the
docket number field to access the
document. You may also register online
at https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208–3676 or
email FERCOnlineSupport@ferc.gov, for
TTY, call (202) 502–8659.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
E:\FR\FM\06FEN1.SGM
06FEN1
Agencies
[Federal Register Volume 82, Number 23 (Monday, February 6, 2017)]
[Notices]
[Page 9376]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-02422]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. EL17-39-000]
CPV Maryland, LLC; Notice of Institution of Section 206
Proceeding and Refund Effective Date
On January 30, 2017, the Commission issued an order in Docket No.
EL17-39-000, pursuant to section 206 of the Federal Power Act (FPA), 16
U.S.C. 824e (2012), instituting an investigation into whether the Rate
Schedule for Reactive Service of CPV Maryland, LLC may be unjust,
unreasonable, unduly discriminatory or preferential. CPV Maryland, LLC,
158 FERC 61,084 (2017).
The refund effective date in Docket No. EL17-39-000, established
pursuant to section 206(b) of the FPA, will be the date of publication
of this notice in the Federal Register.
Any interested person desiring to be heard in Docket No. EL17-39-
000 must file a notice of intervention or motion to intervene, as
appropriate, with the Federal Energy Regulatory Commission, 888 First
Street NE., Washington, DC 20426, in accordance with Rule 214 of the
Commission's Rules of Practice and Procedure, 18 CFR 385.214, within 21
days of the date of issuance of the order.
Dated: January 31, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-02422 Filed 2-3-17; 8:45 am]