Duke Energy Progress; Combined License Applications for Shearon Harris Nuclear Plant Units 2 and 3, 4423-4425 [2017-00685]
Download as PDF
Federal Register / Vol. 82, No. 9 / Friday, January 13, 2017 / Notices
The schedule for Commission
meetings is subject to change on short
notice. For more information or to verify
the status of meetings, contact Denise
McGovern at 301–415–0981 or via email
at Denise.McGovern@nrc.gov.
*
*
*
*
*
The NRC Commission Meeting
Schedule can be found on the Internet
at: https://www.nrc.gov/public-involve/
public-meetings/schedule.html.
*
*
*
*
*
The NRC provides reasonable
accommodation to individuals with
disabilities where appropriate. If you
need a reasonable accommodation to
participate in these public meetings, or
need this meeting notice or the
transcript or other information from the
public meetings in another format (e.g.,
braille, large print), please notify
Kimberly Meyer, NRC Disability
Program Manager, at 301–287–0739, by
videophone at 240–428–3217, or by
email at Kimberly.Meyer-Chambers@
nrc.gov. Determinations on requests for
reasonable accommodation will be
made on a case-by-case basis.
*
*
*
*
*
Members of the public may request to
receive this information electronically.
If you would like to be added to the
distribution, please contact the Nuclear
Regulatory Commission, Office of the
Secretary, Washington, DC 20555 (301–
415–1969), or email
Brenda.Akstulewicz@nrc.gov or
Patricia.Jimenez@nrc.gov.
Dated: January 11, 2017.
Denise L. McGovern,
Policy Coordinator, Office of the Secretary.
[FR Doc. 2017–00875 Filed 1–11–17; 4:15 pm]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket Nos. 52–022 and 52–023; NRC–
2013–0261]
Duke Energy Progress; Combined
License Applications for Shearon
Harris Nuclear Plant Units 2 and 3
Nuclear Regulatory
Commission.
ACTION: Exemption; issuance.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is issuing an
exemption in response to an October 13,
2016, letter from Duke Energy Progress
(DEP). On May 2, 2013, DEP requested
that the NRC suspend review of its
combined license (COL) application
until further notice. On October 13,
2016, DEP requested an exemption from
certain regulatory requirements which,
asabaliauskas on DSK3SPTVN1PROD with NOTICES
SUMMARY:
VerDate Sep<11>2014
19:06 Jan 12, 2017
Jkt 241001
if granted, would allow them to revise
their COL application for Shearon
Harris Nuclear Plant (Harris) Units 2
and 3 in order to address enhancements
to the Emergency Preparedness (EP)
rules by December 31, 2019, rather than
by December 31, 2016, as the
regulations currently require. The NRC
staff reviewed this request and
determined that it is appropriate to
grant the exemption to the EP update
requirements until December 31, 2019,
but stipulated that the updates to the
Final Safety Analysis Report must be
submitted prior to requesting the NRC
resume its review of the COL
application, or by December 31, 2019,
whichever comes first.
DATES: The exemption is effective on
January 13, 2017.
ADDRESSES: Please refer to Docket ID
NRC–2013–0261 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly-available
information related to this document
using any of the following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2013–0261. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–415–3463;
email: Carol.Gallagher@nrc.gov. For
technical questions, contact the
individuals listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘ADAMS Public Documents’’ and then
select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The
ADAMS accession number for each
document referenced (if it available in
ADAMS) is provided the first time that
a document is referenced.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT:
Brian Hughes, Office of New Reactors,
U.S. Nuclear Regulatory Commission,
Washington, DC 20555–0001; telephone:
301–415–6582; email: Brian.Hughes@
nrc.gov.
SUPPLEMENTARY INFORMATION:
PO 00000
Frm 00145
Fmt 4703
Sfmt 4703
4423
I. Background
On February 18, 2008, DEP submitted
to the NRC a COL application for two
units of Westinghouse Electric
Company’s AP1000 advanced
pressurized water reactors to be
constructed and operated at the existing
Shearon Harris Nuclear Plant (Harris)
site (ADAMS Accession No.
ML080580078). The NRC docketed the
Harris Units 2 and 3 COL application
(Docket Nos. 52–022 and 52–023) on
April 23, 2008. On May 2, 2013
(ADAMS Accession No. ML13123A344),
DEP requested that the NRC suspend
review of the Harris Units 2 and 3 COL
application. The NRC granted DEP’s
request for suspension and all review
activities related to the Harris Units 2
and 3 COL application were suspended
while the application remained
docketed.
On July 29, 2013 (ADAMS Accession
No. ML13212A361), DEP requested an
exemption from the requirements in
part 50, appendix E, Section I.5 of title
10 of the Code of Federal Regulations
(10 CFR), as referenced by 10 CFR
52.79(a)(21), to submit an update to the
COL application, addressing the
enhancements to the EP rules by
December 31, 2013, which the NRC
granted through December 31, 2014. On
August 1, 2014 (ADAMS Accession No.
ML14216A432), DEP requested another
exemption from the requirements of 10
CFR part 50, appendix E, Section I.5, as
referenced by 10 CFR 52.79(a)(21), to
submit an update to the COL
application, addressing the
enhancements to the EP rules by
December 31, 2014, which the NRC
granted through December 31, 2015. On
August 12, 2015 (ADAMS Accession
No. ML15226A352), DEP requested
another exemption from the
requirements of 10 CFR part 50,
appendix E, Section I.5, as referenced by
10 CFR 52.79(a)(21), to submit an
update to the COL application,
addressing the enhancements to the EP
rules by December 31, 2016. On October
13, 2016 (ADAMS Accession No.
ML16288A816) DEP requested another
exemption from the requirements of 10
CFR part 50, appendix E, Section I.5, as
referenced by 10 CFR 52.79(a)(21), to
submit annual updates to the COL
application during the years 2016, 2017,
and 2018, addressing the enhancements
to the EP rules by December 31, 2019.
II. Request/Action
Part 50, appendix E, Section 1.5,
requires that an applicant for a COL
under Subpart C of 10 CFR part 52
whose application was docketed prior to
December 23, 2011, must revise their
E:\FR\FM\13JAN1.SGM
13JAN1
4424
Federal Register / Vol. 82, No. 9 / Friday, January 13, 2017 / Notices
COL application to comply with the EP
rules published in the Federal Register
(76 FR 72560) on November 23, 2011.
An applicant that does not receive a
COL before December 31, 2013, shall
revise its COL application to comply
with these changes no later than
December 31, 2013.
Since DEP will not hold a COL prior
to December 31, 2013, it is therefore
required to revise its application to be
compliant with the new EP rules.
Similar to an earlier exemption request
it submitted, as described above, by
letter dated October 13, 2016 (ADAMS
Accession No. ML16288A815), DEP
requested another exemption from the
requirements of 10 CFR part 50,
appendix E, Section I.5, to submit the
required COL application revision to
comply with the new EP rules. The
requested exemption would allow DEP
to revise its COL application, and
comply with the new EP rules on or
before December 31, 2019, rather than
the initial December 31, 2013, date
required by 10 CFR part 50, appendix E,
Section I.5. The current requirement to
comply with the new EP rule could not
be changed, absent the exemption.
asabaliauskas on DSK3SPTVN1PROD with NOTICES
III. Discussion
Pursuant to 10 CFR 50.12(a), the
Commission may, upon application by
any interested person or upon its own
initiative, grant exemptions from the
requirements of 10 CFR part 50,
including 10 CFR part 50, appendix E,
Section I.5, when: (1) The exemption(s)
are authorized by law, will not present
an undue risk to public health or safety,
and are consistent with the common
defense and security; and (2) special
circumstances are present. As relevant
to the requested exemption, special
circumstances exist if: Application of
the regulation in the particular
circumstances would not serve the
underlying purpose of the rule or is not
necessary to achieve the underlying
purpose of the rule (10 CFR
50.12(a)(2)(ii)).
Authorized by Law
The exemption is a one-time schedule
exemption from the requirements of 10
CFR part 50, appendix E, Section I.5.
The exemption would allow DEP to
revise its COL application, and comply
with the new EP rules on or before
December 31, 2019, in lieu of the initial
December 31, 2013, the date required by
10 CFR part 50, appendix E, Section I.5.
As stated above, 10 CFR 50.12 allows
the NRC to grant exemptions from the
requirements of 10 CFR part 50 . The
NRC staff has determined that granting
DEP the requested one-time exemption
from the requirements of 10 CFR part
VerDate Sep<11>2014
19:06 Jan 12, 2017
Jkt 241001
50, appendix E, Section I.5 will not
result in a violation of the Atomic
Energy Act of 1954, as amended, or
NRC’s regulations. Therefore, the
exemption is authorized by law.
No Undue Risk to Public Health and
Safety
The underlying purpose of the
enhancements to EP found in 10 CFR
part 50, appendix E, is to amend certain
EP requirements to enhance protective
measures in the event of a radiological
emergency; address, in part,
enhancements identified after the
terrorist events of September 11, 2001;
clarify regulations to effect consistent
Emergency Plan implementation among
licensees; and modify certain
requirements to be more effective and
efficient. Since plant construction
cannot proceed until the NRC review of
the application is completed, a
mandatory hearing is completed and a
license is issued, the exemption does
not increase the probability of
postulated accidents. Additionally,
based on the nature of the requested
exemption as described above, no new
accident precursors are created by the
exemption; thus neither the probability,
nor the consequences of postulated
accidents are increased. Therefore, there
is no undue risk to public health and
safety.
Consistent With Common Defense and
Security
The requested exemption would
allow DEP to submit the revised COL
application prior to requesting the NRC
to resume the review and, in any event,
on or before December 31, 2019. This
schedule change has no relation to
security issues. Therefore, the common
defense and security is not impacted.
Special Circumstances
Special Circumstances, in accordance
with 10 CFR 50.12(a)(2(ii) are present
whenever: (1) Application of the
regulation in the particular
circumstances would not serve the
underlying purpose of the rule or is not
necessary to achieve the underlying
purpose of the rule (10 CFR 50.12(a)(ii);
or (2) The exemption would only
provide temporary relief from the
applicable regulation or the applicant
has made good faith efforts to comply
with the regulation (10 CFR
50.12(a)(2)(v)).
The purpose of 10 CFR part 50,
appendix E, Section I.5 is to ensure that
applicants and new COL holders
updated their COL applications or COLs
to allow the NRC to review them
efficiently and effectively, and to bring
the applicants or licensees into
PO 00000
Frm 00146
Fmt 4703
Sfmt 4703
compliance prior to receiving a license,
or, for licensees, prior to operating the
plant. If the NRC were to grant this
exemption, and DEP were then required
to update its application to comply with
the EP rule enhancements by December
31, 2019, or prior to any request to
restart their review, the purpose of the
rule would still be achieved because the
applicant will be required to make
required updates to the emergency plan
to facilitate NRC review of the
application at the appropriate time. For
this reason, the application of 10 CFR
part 50, appendix E, Section I.5, for the
suspended Harris 2 and 3 COL
application is deemed unnecessary and,
therefore, special circumstances are
present.
Eligibility for Categorical Exclusion
From Environmental Review
With respect to the exemption’s
impact on the quality of the human
environment, the NRC has determined
that this specific exemption request is
eligible for categorical exclusion as
identified in 10 CFR 51.22(c)(25) and
justified by the NRC staff as follows:
The following categories of actions are
categorical exclusions provided that:
(i) There is no significant hazards
consideration;
The criteria for determining whether
there is no significant hazards
consideration are found in 10 CFR
50.92. The proposed action involves
only a schedule change regarding the
submission of an update to the
application for which the licensing
review has been suspended. Therefore,
there are no significant hazards
considerations because granting the
proposed exemption would not:
(1) Involve a significant increase in
the probability or consequences of an
accident previously evaluated; or
(2) Create the possibility of a new or
different kind of accident from any
accident previously evaluated; or
(3) Involve a significant reduction in
a margin of safety.
(ii) There is no significant change in
the types or significant increase in the
amounts of any effluents that may be
released offsite;
The proposed action involves only a
schedule change which is
administrative in nature, and does not
involve any changes to be made in the
types or significant increase in the
amounts of effluents that may be
released offsite.
(iii) There is no significant increase in
individual or cumulative public or
occupational radiation exposure;
Since the proposed action involves
only a schedule change which is
administrative in nature, it does not
E:\FR\FM\13JAN1.SGM
13JAN1
Federal Register / Vol. 82, No. 9 / Friday, January 13, 2017 / Notices
contribute to any significant increase in
occupational or public radiation
exposure.
(iv) There is no significant
construction impact;
The proposed action involves only a
schedule change which is
administrative in nature; the application
review is suspended until further
notice, and there is no consideration of
any construction at this time, and hence
the proposed action does not involve
any construction impact.
(v) There is no significant increase in
the potential for or consequences from
radiological accidents;
The proposed action involves only a
schedule change which is
administrative in nature, and does not
impact the probability or consequences
of accidents.
(vi) The requirements from which an
exemption is sought involve:
(B) Reporting requirements;
The exemption request involves
submitting an updated COL application
by DEP
and
(G) Scheduling requirements;
The proposed exemption relates to the
schedule for submitting a COL
application update to the NRC.
asabaliauskas on DSK3SPTVN1PROD with NOTICES
IV. Conclusion
Accordingly, the Commission has
determined that, pursuant to 10 CFR
50.12(a), the exemption is authorized by
law, will not present an undue risk to
the public health and safety, and is
consistent with the common defense
and security. Also special circumstances
are present. Therefore, the Commission
hereby grants DEP a one-time exemption
from the requirements of 10 CFR part 50
Appendix E, Section I.5 pertaining to
the Harris Units 2 and 3 COL
application to allow submittal of the
revised COL application that complies
with the enhancements to the EP rules
prior to any request to the NRC to
resume the review, and in any event, no
later than December 31, 2019.
Pursuant to 10 CFR 51.22, the
Commission has determined that the
exemption request meets the applicable
categorical exclusion criteria set forth in
10 CFR 51.22(c)(25), and the granting of
this exemption will not have a
significant effect on the quality of the
human environment.
This exemption is effective upon
issuance.
Dated at Rockville, Maryland, this 4th day
of January 2017.
VerDate Sep<11>2014
19:06 Jan 12, 2017
Jkt 241001
For The Nuclear Regulatory Commission.
Francis M. Akstulewicz,
Director, Division of New Reactor Licensing,
Office of New Reactors.
[FR Doc. 2017–00685 Filed 1–12–17; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket Nos. 52–025 and 52–026; NRC–
2008–0252]
Southern Nuclear Operating Company,
Inc., Vogtle Electric Generating Plant,
Units 3 and 4; Debris Screen Related
Dimensions
Nuclear Regulatory
Commission.
ACTION: Exemption and combined
license amendment; issuance.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is granting an
exemption to allow a departure from the
certification information of Tier 1 of the
generic design control document (DCD)
and is issuing License Amendment No.
63 to Combined Licenses (COL), NPF–
91 and NPF–92. The COLs were issued
to Southern Nuclear Operating
Company, Inc., and Georgia Power
Company, Oglethorpe Power
Corporation, MEAG Power SPVM, LLC,
MEAG Power SPVJ, LLC, MEAG Power
SPVP, LLC, Authority of Georgia, and
the City of Dalton, Georgia (the
licensee); for construction and operation
of the Vogtle Electric Generating Plant
(VEGP) Units 3 and 4, located in Burke
County, Georgia.
The granting of the exemption allows
the changes to Tier 1 information asked
for in the amendment. Because the
acceptability of the exemption was
determined in part by the acceptability
of the amendment, the exemption and
amendment are being issued
concurrently.
DATES: The exemption and amendment
were issued on December 29, 2016.
ADDRESSES: Please refer to Docket ID
NRC–2008–0252 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly-available
information related to this document
using any of the following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2008–0252. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–415–3463;
email: Carol.Gallagher@nrc.gov. For
technical questions, contact the
individual listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
SUMMARY:
PO 00000
Frm 00147
Fmt 4703
Sfmt 4703
4425
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘ADAMS Public Documents’’ and then
select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The
ADAMS accession number for each
document referenced (if it is available in
ADAMS) is provided the first time that
it is mentioned in this document. The
request for the amendment and
exemption was submitted by letter
dated August 11, 2016 (ADAMS
Accession No. ML16224B122).
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT:
Ruth Reyes, Office of New Reactors,
U.S. Nuclear Regulatory Commission,
Washington, DC 20555–0001; telephone:
301–415–3249; email: Ruth.Reyes@
nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Introduction
The NRC is granting an exemption
from Paragraph B of Section III, ‘‘Scope
and Contents,’’ of appendix D, ‘‘Design
Certification Rule for the AP1000,’’ to
part 52 of title 10 of the Code of Federal
Regulations (10 CFR), and issuing
License Amendment No. 63 to COLs,
NP–91 and NPF–92, to the licensee. The
exemption is required by Paragraph A.4
of Section VIII, ‘‘Processes for Changes
and Departures,’’ appendix D, to 10 CFR
part 52 to allow the licensee to depart
from Tier 1 information. With the
requested amendment, the licensee
sought proposed changes that would
revise the Updated Final Safety
Analysis Report in the form of
departures from the incorporated plantspecific DCD Tier 2 information. The
proposed amendment also involves
related changes to plant-specific Tier 1
information, with corresponding
changes to the associated COL
Appendix C information. The proposed
changes are to information identifying
the frontal face area and screen surface
area for the In-Containment Refueling
Water Storage Tank (IRWST) screens,
the location and dimensions of the
protective plate located above the
containment recirculation (CR) screens,
and increasing the maximum Normal
E:\FR\FM\13JAN1.SGM
13JAN1
Agencies
[Federal Register Volume 82, Number 9 (Friday, January 13, 2017)]
[Notices]
[Pages 4423-4425]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-00685]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 52-022 and 52-023; NRC-2013-0261]
Duke Energy Progress; Combined License Applications for Shearon
Harris Nuclear Plant Units 2 and 3
AGENCY: Nuclear Regulatory Commission.
ACTION: Exemption; issuance.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing an
exemption in response to an October 13, 2016, letter from Duke Energy
Progress (DEP). On May 2, 2013, DEP requested that the NRC suspend
review of its combined license (COL) application until further notice.
On October 13, 2016, DEP requested an exemption from certain regulatory
requirements which, if granted, would allow them to revise their COL
application for Shearon Harris Nuclear Plant (Harris) Units 2 and 3 in
order to address enhancements to the Emergency Preparedness (EP) rules
by December 31, 2019, rather than by December 31, 2016, as the
regulations currently require. The NRC staff reviewed this request and
determined that it is appropriate to grant the exemption to the EP
update requirements until December 31, 2019, but stipulated that the
updates to the Final Safety Analysis Report must be submitted prior to
requesting the NRC resume its review of the COL application, or by
December 31, 2019, whichever comes first.
DATES: The exemption is effective on January 13, 2017.
ADDRESSES: Please refer to Docket ID NRC-2013-0261 when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly-available information related to this document
using any of the following methods:
Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2013-0261. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: Carol.Gallagher@nrc.gov. For technical questions, contact
the individuals listed in the FOR FURTHER INFORMATION CONTACT section
of this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly-available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS,
please contact the NRC's Public Document Room (PDR) reference staff at
1-800-397-4209, 301-415-4737, or by email to pdr.resource@nrc.gov. The
ADAMS accession number for each document referenced (if it available in
ADAMS) is provided the first time that a document is referenced.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: Brian Hughes, Office of New Reactors,
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001;
telephone: 301-415-6582; email: Brian.Hughes@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Background
On February 18, 2008, DEP submitted to the NRC a COL application
for two units of Westinghouse Electric Company's AP1000 advanced
pressurized water reactors to be constructed and operated at the
existing Shearon Harris Nuclear Plant (Harris) site (ADAMS Accession
No. ML080580078). The NRC docketed the Harris Units 2 and 3 COL
application (Docket Nos. 52-022 and 52-023) on April 23, 2008. On May
2, 2013 (ADAMS Accession No. ML13123A344), DEP requested that the NRC
suspend review of the Harris Units 2 and 3 COL application. The NRC
granted DEP's request for suspension and all review activities related
to the Harris Units 2 and 3 COL application were suspended while the
application remained docketed.
On July 29, 2013 (ADAMS Accession No. ML13212A361), DEP requested
an exemption from the requirements in part 50, appendix E, Section I.5
of title 10 of the Code of Federal Regulations (10 CFR), as referenced
by 10 CFR 52.79(a)(21), to submit an update to the COL application,
addressing the enhancements to the EP rules by December 31, 2013, which
the NRC granted through December 31, 2014. On August 1, 2014 (ADAMS
Accession No. ML14216A432), DEP requested another exemption from the
requirements of 10 CFR part 50, appendix E, Section I.5, as referenced
by 10 CFR 52.79(a)(21), to submit an update to the COL application,
addressing the enhancements to the EP rules by December 31, 2014, which
the NRC granted through December 31, 2015. On August 12, 2015 (ADAMS
Accession No. ML15226A352), DEP requested another exemption from the
requirements of 10 CFR part 50, appendix E, Section I.5, as referenced
by 10 CFR 52.79(a)(21), to submit an update to the COL application,
addressing the enhancements to the EP rules by December 31, 2016. On
October 13, 2016 (ADAMS Accession No. ML16288A816) DEP requested
another exemption from the requirements of 10 CFR part 50, appendix E,
Section I.5, as referenced by 10 CFR 52.79(a)(21), to submit annual
updates to the COL application during the years 2016, 2017, and 2018,
addressing the enhancements to the EP rules by December 31, 2019.
II. Request/Action
Part 50, appendix E, Section 1.5, requires that an applicant for a
COL under Subpart C of 10 CFR part 52 whose application was docketed
prior to December 23, 2011, must revise their
[[Page 4424]]
COL application to comply with the EP rules published in the Federal
Register (76 FR 72560) on November 23, 2011. An applicant that does not
receive a COL before December 31, 2013, shall revise its COL
application to comply with these changes no later than December 31,
2013.
Since DEP will not hold a COL prior to December 31, 2013, it is
therefore required to revise its application to be compliant with the
new EP rules. Similar to an earlier exemption request it submitted, as
described above, by letter dated October 13, 2016 (ADAMS Accession No.
ML16288A815), DEP requested another exemption from the requirements of
10 CFR part 50, appendix E, Section I.5, to submit the required COL
application revision to comply with the new EP rules. The requested
exemption would allow DEP to revise its COL application, and comply
with the new EP rules on or before December 31, 2019, rather than the
initial December 31, 2013, date required by 10 CFR part 50, appendix E,
Section I.5. The current requirement to comply with the new EP rule
could not be changed, absent the exemption.
III. Discussion
Pursuant to 10 CFR 50.12(a), the Commission may, upon application
by any interested person or upon its own initiative, grant exemptions
from the requirements of 10 CFR part 50, including 10 CFR part 50,
appendix E, Section I.5, when: (1) The exemption(s) are authorized by
law, will not present an undue risk to public health or safety, and are
consistent with the common defense and security; and (2) special
circumstances are present. As relevant to the requested exemption,
special circumstances exist if: Application of the regulation in the
particular circumstances would not serve the underlying purpose of the
rule or is not necessary to achieve the underlying purpose of the rule
(10 CFR 50.12(a)(2)(ii)).
Authorized by Law
The exemption is a one-time schedule exemption from the
requirements of 10 CFR part 50, appendix E, Section I.5. The exemption
would allow DEP to revise its COL application, and comply with the new
EP rules on or before December 31, 2019, in lieu of the initial
December 31, 2013, the date required by 10 CFR part 50, appendix E,
Section I.5. As stated above, 10 CFR 50.12 allows the NRC to grant
exemptions from the requirements of 10 CFR part 50 . The NRC staff has
determined that granting DEP the requested one-time exemption from the
requirements of 10 CFR part 50, appendix E, Section I.5 will not result
in a violation of the Atomic Energy Act of 1954, as amended, or NRC's
regulations. Therefore, the exemption is authorized by law.
No Undue Risk to Public Health and Safety
The underlying purpose of the enhancements to EP found in 10 CFR
part 50, appendix E, is to amend certain EP requirements to enhance
protective measures in the event of a radiological emergency; address,
in part, enhancements identified after the terrorist events of
September 11, 2001; clarify regulations to effect consistent Emergency
Plan implementation among licensees; and modify certain requirements to
be more effective and efficient. Since plant construction cannot
proceed until the NRC review of the application is completed, a
mandatory hearing is completed and a license is issued, the exemption
does not increase the probability of postulated accidents.
Additionally, based on the nature of the requested exemption as
described above, no new accident precursors are created by the
exemption; thus neither the probability, nor the consequences of
postulated accidents are increased. Therefore, there is no undue risk
to public health and safety.
Consistent With Common Defense and Security
The requested exemption would allow DEP to submit the revised COL
application prior to requesting the NRC to resume the review and, in
any event, on or before December 31, 2019. This schedule change has no
relation to security issues. Therefore, the common defense and security
is not impacted.
Special Circumstances
Special Circumstances, in accordance with 10 CFR 50.12(a)(2(ii) are
present whenever: (1) Application of the regulation in the particular
circumstances would not serve the underlying purpose of the rule or is
not necessary to achieve the underlying purpose of the rule (10 CFR
50.12(a)(ii); or (2) The exemption would only provide temporary relief
from the applicable regulation or the applicant has made good faith
efforts to comply with the regulation (10 CFR 50.12(a)(2)(v)).
The purpose of 10 CFR part 50, appendix E, Section I.5 is to ensure
that applicants and new COL holders updated their COL applications or
COLs to allow the NRC to review them efficiently and effectively, and
to bring the applicants or licensees into compliance prior to receiving
a license, or, for licensees, prior to operating the plant. If the NRC
were to grant this exemption, and DEP were then required to update its
application to comply with the EP rule enhancements by December 31,
2019, or prior to any request to restart their review, the purpose of
the rule would still be achieved because the applicant will be required
to make required updates to the emergency plan to facilitate NRC review
of the application at the appropriate time. For this reason, the
application of 10 CFR part 50, appendix E, Section I.5, for the
suspended Harris 2 and 3 COL application is deemed unnecessary and,
therefore, special circumstances are present.
Eligibility for Categorical Exclusion From Environmental Review
With respect to the exemption's impact on the quality of the human
environment, the NRC has determined that this specific exemption
request is eligible for categorical exclusion as identified in 10 CFR
51.22(c)(25) and justified by the NRC staff as follows:
The following categories of actions are categorical exclusions
provided that:
(i) There is no significant hazards consideration;
The criteria for determining whether there is no significant
hazards consideration are found in 10 CFR 50.92. The proposed action
involves only a schedule change regarding the submission of an update
to the application for which the licensing review has been suspended.
Therefore, there are no significant hazards considerations because
granting the proposed exemption would not:
(1) Involve a significant increase in the probability or
consequences of an accident previously evaluated; or
(2) Create the possibility of a new or different kind of accident
from any accident previously evaluated; or
(3) Involve a significant reduction in a margin of safety.
(ii) There is no significant change in the types or significant
increase in the amounts of any effluents that may be released offsite;
The proposed action involves only a schedule change which is
administrative in nature, and does not involve any changes to be made
in the types or significant increase in the amounts of effluents that
may be released offsite.
(iii) There is no significant increase in individual or cumulative
public or occupational radiation exposure;
Since the proposed action involves only a schedule change which is
administrative in nature, it does not
[[Page 4425]]
contribute to any significant increase in occupational or public
radiation exposure.
(iv) There is no significant construction impact;
The proposed action involves only a schedule change which is
administrative in nature; the application review is suspended until
further notice, and there is no consideration of any construction at
this time, and hence the proposed action does not involve any
construction impact.
(v) There is no significant increase in the potential for or
consequences from radiological accidents;
The proposed action involves only a schedule change which is
administrative in nature, and does not impact the probability or
consequences of accidents.
(vi) The requirements from which an exemption is sought involve:
(B) Reporting requirements;
The exemption request involves submitting an updated COL
application by DEP
and
(G) Scheduling requirements;
The proposed exemption relates to the schedule for submitting a COL
application update to the NRC.
IV. Conclusion
Accordingly, the Commission has determined that, pursuant to 10 CFR
50.12(a), the exemption is authorized by law, will not present an undue
risk to the public health and safety, and is consistent with the common
defense and security. Also special circumstances are present.
Therefore, the Commission hereby grants DEP a one-time exemption from
the requirements of 10 CFR part 50 Appendix E, Section I.5 pertaining
to the Harris Units 2 and 3 COL application to allow submittal of the
revised COL application that complies with the enhancements to the EP
rules prior to any request to the NRC to resume the review, and in any
event, no later than December 31, 2019.
Pursuant to 10 CFR 51.22, the Commission has determined that the
exemption request meets the applicable categorical exclusion criteria
set forth in 10 CFR 51.22(c)(25), and the granting of this exemption
will not have a significant effect on the quality of the human
environment.
This exemption is effective upon issuance.
Dated at Rockville, Maryland, this 4th day of January 2017.
For The Nuclear Regulatory Commission.
Francis M. Akstulewicz,
Director, Division of New Reactor Licensing, Office of New Reactors.
[FR Doc. 2017-00685 Filed 1-12-17; 8:45 am]
BILLING CODE 7590-01-P