Download as PDF 3306 Federal Register / Vol. 82, No. 7 / Wednesday, January 11, 2017 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CD17–7–000] Mountain Regional Water Special Services District; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene On December 30, 2016, Mountain Regional Water Special Services District filed a notice of intent to construct a qualifying conduit hydropower facility, pursuant to section 30 of the Federal Power Act (FPA), as amended by section 4 of the Hydropower Regulatory Efficiency Act of 2013 (HREA). The proposed Silver Creek Hydro Energy Recovery Facility Project would have a maximum installed capacity of 200 kilowatts (kW) and would be located on Signal Hill Water Treatment Plant’s proposed 14-inch-diameter water transmission pipe, in an existing pump station. The project would be located in Park City, in Summit County, Utah. Applicant Contact: Doug Evans— Water and Energy Manager, Mountain Regional Water Special Services District, P.O. Box 982320, 6421 N Business Park Loop Road, Suite A, Park City, UT 84098, Phone No. (435) 940– 1916, Extension 313. FERC Contact: Robert Bell, Phone No. (202) 502–6062, email: robert.bell@ ferc.gov. Qualifying Conduit Hydropower Facility Description: The proposed project would consist of: (1) Two proposed generating units with a maximum installed capacity of 200-kW on a proposed 14-inch-diameter, 5,800 foot-long water distribution pipe, located in an existing pump station, discharging into a new 2 million gallon water storage tank; and (2) appurtenant facilities. The proposed project would have an initial estimated annual generating capacity of 250 megawatthours, and increase to approximately 1,000 megawatt-hours by 2022. A qualifying conduit hydropower facility is one that is determined or deemed to meet all of the criteria shown in the table below. TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY Statutory provision Description Satisfies (Y/N) FPA 30(a)(3)(A), as amended by HREA ... The conduit is a tunnel, canal, pipeline, aqueduct, flume, ditch, or similar manmade water conveyance that is operated for the distribution of water for agricultural, municipal, or industrial consumption and not primarily for the generation of electricity. The facility is constructed, operated, or maintained for the generation of electric power and uses for such generation only the hydroelectric potential of a non-federally owned conduit. The facility has an installed capacity that does not exceed 5 megawatts ..................... On or before August 9, 2013, the facility is not licensed, or exempted from the licensing requirements of Part I of the FPA. Y FPA 30(a)(3)(C)(i), as amended by HREA sradovich on DSK3GMQ082PROD with NOTICES FPA 30(a)(3)(C)(ii), as amended by HREA FPA 30(a)(3)(C)(iii), as amended by HREA. Preliminary Determination: Based upon the above criteria, Commission staff has preliminarily determined that the proposal satisfies the requirements for a qualifying conduit hydropower facility under 16 U.S.C. 823a, and is exempted from the licensing requirements of the FPA. Comments and Motions to Intervene: The deadline for filing comments contesting whether the facility meets the qualifying criteria is 45 days from the issuance date of this notice. The deadline for filing motions to intervene is 30 days from the issuance date of this notice. Anyone may submit comments or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210 and 385.214. Any motions to intervene must be received on or before the specified deadline date for the particular proceeding. Filing and Service of Responsive Documents: All filings must (1) bear in all capital letters the ‘‘COMMENTS CONTESTING QUALIFICATION FOR A CONDUIT HYDROPOWER FACILITY’’ or ‘‘MOTION TO INTERVENE,’’ as applicable; (2) state in the heading the name of the applicant and the project number of the application to which the VerDate Sep<11>2014 19:05 Jan 10, 2017 Jkt 241001 filing responds; (3) state the name, address, and telephone number of the person filing; and (4) otherwise comply with the requirements of sections 385.2001 through 385.2005 of the Commission’s regulations.1 All comments contesting Commission staff’s preliminary determination that the facility meets the qualifying criteria must set forth their evidentiary basis. The Commission strongly encourages electronic filing. Please file motions to intervene and comments using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. A copy of all other filings in reference to this application must be accompanied 1 18 PO 00000 Fmt 4703 Sfmt 9990 Y Y by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010. Locations of Notice of Intent: Copies of the notice of intent can be obtained directly from the applicant or such copies can be viewed and reproduced at the Commission in its Public Reference Room, Room 2A, 888 First Street NE., Washington, DC 20426. The filing may also be viewed on the web at https:// www.ferc.gov/docs-filing/elibrary.asp using the ‘‘eLibrary’’ link. Enter the docket number (e.g., CD17–7–000) in the docket number field to access the document. For assistance, call toll-free 1–866–208–3676 or email FERCOnlineSupport@ferc.gov. For TTY, call (202) 502–8659. Dated: January 4, 2017. Kimberly D. Bose, Secretary. [FR Doc. 2017–00379 Filed 1–10–17; 8:45 am] BILLING CODE 6717–01–P CFR 385.2001–2005 (2015). Frm 00027 Y E:\FR\FM\11JAN1.SGM 11JAN1

Agencies

[Federal Register Volume 82, Number 7 (Wednesday, January 11, 2017)]
[Notices]
[Page 3306]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-00379]



[[Page 3306]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CD17-7-000]


Mountain Regional Water Special Services District; Notice of 
Preliminary Determination of a Qualifying Conduit Hydropower Facility 
and Soliciting Comments and Motions To Intervene

    On December 30, 2016, Mountain Regional Water Special Services 
District filed a notice of intent to construct a qualifying conduit 
hydropower facility, pursuant to section 30 of the Federal Power Act 
(FPA), as amended by section 4 of the Hydropower Regulatory Efficiency 
Act of 2013 (HREA). The proposed Silver Creek Hydro Energy Recovery 
Facility Project would have a maximum installed capacity of 200 
kilowatts (kW) and would be located on Signal Hill Water Treatment 
Plant's proposed 14-inch-diameter water transmission pipe, in an 
existing pump station. The project would be located in Park City, in 
Summit County, Utah.
    Applicant Contact: Doug Evans--Water and Energy Manager, Mountain 
Regional Water Special Services District, P.O. Box 982320, 6421 N 
Business Park Loop Road, Suite A, Park City, UT 84098, Phone No. (435) 
940-1916, Extension 313.
    FERC Contact: Robert Bell, Phone No. (202) 502-6062, email: 
robert.bell@ferc.gov.
    Qualifying Conduit Hydropower Facility Description: The proposed 
project would consist of: (1) Two proposed generating units with a 
maximum installed capacity of 200-kW on a proposed 14-inch-diameter, 
5,800 foot-long water distribution pipe, located in an existing pump 
station, discharging into a new 2 million gallon water storage tank; 
and (2) appurtenant facilities. The proposed project would have an 
initial estimated annual generating capacity of 250 megawatt-hours, and 
increase to approximately 1,000 megawatt-hours by 2022.
    A qualifying conduit hydropower facility is one that is determined 
or deemed to meet all of the criteria shown in the table below.

      Table 1--Criteria for Qualifying Conduit Hydropower Facility
------------------------------------------------------------------------
                                                            Satisfies (Y/
       Statutory provision               Description             N)
------------------------------------------------------------------------
FPA 30(a)(3)(A), as amended by    The conduit is a tunnel,            Y
 HREA.                             canal, pipeline,
                                   aqueduct, flume, ditch,
                                   or similar manmade
                                   water conveyance that
                                   is operated for the
                                   distribution of water
                                   for agricultural,
                                   municipal, or
                                   industrial consumption
                                   and not primarily for
                                   the generation of
                                   electricity.
FPA 30(a)(3)(C)(i), as amended    The facility is                     Y
 by HREA.                          constructed, operated,
                                   or maintained for the
                                   generation of electric
                                   power and uses for such
                                   generation only the
                                   hydroelectric potential
                                   of a non-federally
                                   owned conduit.
FPA 30(a)(3)(C)(ii), as amended   The facility has an                 Y
 by HREA.                          installed capacity that
                                   does not exceed 5
                                   megawatts.
FPA 30(a)(3)(C)(iii), as amended  On or before August 9,              Y
 by HREA.                          2013, the facility is
                                   not licensed, or
                                   exempted from the
                                   licensing requirements
                                   of Part I of the FPA.
------------------------------------------------------------------------

    Preliminary Determination: Based upon the above criteria, 
Commission staff has preliminarily determined that the proposal 
satisfies the requirements for a qualifying conduit hydropower facility 
under 16 U.S.C. 823a, and is exempted from the licensing requirements 
of the FPA.
    Comments and Motions to Intervene: The deadline for filing comments 
contesting whether the facility meets the qualifying criteria is 45 
days from the issuance date of this notice.
    The deadline for filing motions to intervene is 30 days from the 
issuance date of this notice.
    Anyone may submit comments or a motion to intervene in accordance 
with the requirements of Rules of Practice and Procedure, 18 CFR 
385.210 and 385.214. Any motions to intervene must be received on or 
before the specified deadline date for the particular proceeding.
    Filing and Service of Responsive Documents: All filings must (1) 
bear in all capital letters the ``COMMENTS CONTESTING QUALIFICATION FOR 
A CONDUIT HYDROPOWER FACILITY'' or ``MOTION TO INTERVENE,'' as 
applicable; (2) state in the heading the name of the applicant and the 
project number of the application to which the filing responds; (3) 
state the name, address, and telephone number of the person filing; and 
(4) otherwise comply with the requirements of sections 385.2001 through 
385.2005 of the Commission's regulations.\1\ All comments contesting 
Commission staff's preliminary determination that the facility meets 
the qualifying criteria must set forth their evidentiary basis.
---------------------------------------------------------------------------

    \1\ 18 CFR 385.2001-2005 (2015).
---------------------------------------------------------------------------

    The Commission strongly encourages electronic filing. Please file 
motions to intervene and comments using the Commission's eFiling system 
at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the 
end of your comments. For assistance, please contact FERC Online 
Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or 
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper 
copy to: Secretary, Federal Energy Regulatory Commission, 888 First 
Street NE., Washington, DC 20426. A copy of all other filings in 
reference to this application must be accompanied by proof of service 
on all persons listed in the service list prepared by the Commission in 
this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
    Locations of Notice of Intent: Copies of the notice of intent can 
be obtained directly from the applicant or such copies can be viewed 
and reproduced at the Commission in its Public Reference Room, Room 2A, 
888 First Street NE., Washington, DC 20426. The filing may also be 
viewed on the web at https://www.ferc.gov/docs-filing/elibrary.asp using 
the ``eLibrary'' link. Enter the docket number (e.g., CD17-7-000) in 
the docket number field to access the document. For assistance, call 
toll-free 1-866-208-3676 or email FERCOnlineSupport@ferc.gov. For TTY, 
call (202) 502-8659.

    Dated: January 4, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-00379 Filed 1-10-17; 8:45 am]
 BILLING CODE 6717-01-P