Combined Notice of Filings #2, 3302-3303 [2017-00378]
Download as PDF
3302
Federal Register / Vol. 82, No. 7 / Wednesday, January 11, 2017 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2576–171]
sradovich on DSK3GMQ082PROD with NOTICES
FirstLight Hydro Generating Company;
Notice of Application Accepted for
Filing and Soliciting Comments,
Motions To Intervene, and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Application Type: Non-Project Use
of Project Lands.
b. Project No: 2576–171.
c. Date Filed: October 6, 2016 and
supplemented on December 22, 2016.
d. Applicant: FirstLight Hydro
Generating Company.
e. Name of Project: Housatonic River
Project.
f. Location: The project is located on
the Housatonic River, in Fairfield, New
Haven, and Litchfield counties,
Connecticut.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
h. Applicant Contact: Stuart H.
Piermarini, Plant Manager; (860) 350–
3617; 143 West Street, Suite E, New
Milford, CT 06776.
i. FERC Contact: Krista.Sakallaris,
(202) 502–6302, Krista.Sakallaris@
ferc.gov.
j. Deadline for filing comments,
motions to intervene, and protests:
February 6, 2017.
The Commission strongly encourages
electronic filing. Please file motions to
intervene, protests, comments, or
recommendations using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–2576–171.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person whose name appears on the
official service list for the project.
Further, if an intervenor files comments
VerDate Sep<11>2014
19:05 Jan 10, 2017
Jkt 241001
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. Description of Request: FirstLight
Hydro Generating Company is
requesting permission to issue a permit
to reconfigure existing docks at the
O&M Enterprises Chatterton Marina,
located in Fairfield County,
Connecticut. The permit would
authorize the Chatterton Marina to
reduce the three existing docks to two
while maintaining docks to
accommodate 75-watercraft. One of the
docks would be relocated approximately
20 feet westward and be reconfigured to
have slips on both sides, increasing its
capacity to 36-watercraft. The filings
include a request and a detailed
justification for a waiver from the
Shoreline Management Plans 50-footwide shoreline buffer zone requirement,
which requires abutting landowners
who occupy project lands to install a 50foot-wide shoreline vegetative buffer
zone when, among other things, there is
a request for reconfiguration of an
existing structure or the installation of
a new structure.
l. Locations of the Application: A
copy of the application is available for
inspection and reproduction at the
Commission’s Public Reference Room,
located at 888 First Street NE., Room
2A, Washington, DC 20426, or by calling
(202) 502–8371. This filing may also be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. You may also register online
at https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208–3676 or
email FERCOnlineSupport@ferc.gov, for
TTY, call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item (h)
above. Agencies may obtain copies of
the application directly from the
applicant.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214,
respectively. In determining the
appropriate action to take, the
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
for the particular application.
o. Filing and Service of Documents:
Any filing must (1) bear in all capital
letters the title ‘‘COMMENTS’’,
‘‘PROTEST’’, or ‘‘MOTION TO
INTERVENE’’ as applicable; (2) set forth
in the heading the name of the applicant
and the project number of the
application to which the filing
responds; (3) furnish the name, address,
and telephone number of the person
commenting, protesting or intervening;
and (4) otherwise comply with the
requirements of 18 CFR 385.2001
through 385.2005. All comments,
motions to intervene, or protests must
set forth their evidentiary basis. Any
filing made by an intervenor must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
385.2010.
Dated: January 4, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017–00386 Filed 1–10–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #2
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER10–1942–014;
ER10–1862–016; ER10–1877–004;
ER10–1893–016; ER10–1934–016;
ER10–1938–017; ER10–2042–022;
ER10–2985–020; ER10–3049–021;
ER10–3051–021; ER17–696–002.
Applicants: Calpine Construction
Finance Company, L.P., Calpine Energy
Services, L.P., Calpine Energy Solutions,
LLC, Calpine Power America–CA, LLC,
CES Marketing IX, LLC, CES Marketing
X, LLC, Champion Energy Marketing
LLC, Champion Energy Services, LLC,
Champion Energy, LLC, Hermiston
Power, LLC, Power Contract Financing,
L.L.C.
Description: Updated Market Power
Analysis for the Northwest Region of the
Calpine Corporation MBR Sellers.
Filed Date: 12/30/16.
Accession Number: 20161230–5127.
E:\FR\FM\11JAN1.SGM
11JAN1
Federal Register / Vol. 82, No. 7 / Wednesday, January 11, 2017 / Notices
sradovich on DSK3GMQ082PROD with NOTICES
Comments Due: 5 p.m. ET 2/28/17.
Docket Numbers: ER11–4717–002.
Applicants: International Paper
Company.
Description: Notice of Non-Material
Change in Status of International Paper
Company.
Filed Date: 12/30/16.
Accession Number: 20161230–5043.
Comments Due: 5 p.m. ET 1/20/17.
Docket Numbers: ER15–2582–002;
ER10–1851–007; ER10–1852–015;
ER10–1930–007; ER10–1931–008;
ER15–2101–004; ER12–2226–007;
ER12–2225–007; ER14–2138–004;
ER10–1966–008; ER10–1976–008;
ER10–1985–008; ER10–1971–034;
ER11–4462–025.
Applicants: Carousel Wind Farm,
LLC, ESI Vansycle Partners, L.P.,
Florida Power & Light Company, FPL
Energy Stateline II, Inc., FPL Energy
Vansycle, L.L.C, Golden West Power
Partners, LLC, Limon Wind, LLC, Limon
Wind II, LLC, Limon Wind III, LLC,
Logan Wind Energy LLC, Northern
Colorado Wind Energy, LLC, Peetz
Table Wind Energy, LLC, NextEra
Energy Power Marketing, LLC, NEPM II,
LLC.
Description: Triennial Market Power
Update for the Northwest Region of
NextEra Companies.
Filed Date: 12/30/16.
Accession Number: 20161230–5176.
Comments Due: 5 p.m. ET 2/28/17.
Docket Numbers: ER17–696–001.
Applicants: Calpine Energy Solutions,
LLC.
Description: Notification of Change in
Status of Calpine Energy Solutions, LLC.
Filed Date: 12/30/16.
Accession Number: 20161230–5113.
Comments Due: 5 p.m. ET 1/20/17.
Docket Numbers: ER17–715–000.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: § 205(d) Rate Filing:
2016–12–30_SA 2988 MidAmericanMidAmerican GIA (J500) to be effective
12/31/2016.
Filed Date: 12/30/16.
Accession Number: 20161230–5023.
Comments Due: 5 p.m. ET 1/20/17.
Docket Numbers: ER17–716–000.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: Compliance filing: 2016–
12–30 _Order 828 Compliance Filing to
be effective N/A.
Filed Date: 12/30/16.
Accession Number: 20161230–5025.
Comments Due: 5 p.m. ET 1/20/17.
Docket Numbers: ER17–717–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Queue Position AB2–048, Original
VerDate Sep<11>2014
19:05 Jan 10, 2017
Jkt 241001
Service Agreement No. 4597 to be
effective 11/30/2016.
Filed Date: 12/30/16.
Accession Number: 20161230–5028.
Comments Due: 5 p.m. ET 1/20/17.
Docket Numbers: ER17–718–000
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Revisions to MISO–PJM JOA, Article IX
sections 9.3 and 9.4 to be effective 12/
31/9998.
Filed Date: 12/30/16.
Accession Number: 20161230–5057.
Comments Due: 5 p.m. ET 1/20/17.
Docket Numbers: ER17–719–000.
Applicants: PJM Interconnection,
L.L.C., Metropolitan Edison Company,
American Transmission Systems,
Incorporated.
Description: § 205(d) Rate Filing:
ATSI et. al. submits OIA SA No. 2852
& ECSA SA No. 4554 to be effective
1/1/2017.
Filed Date: 12/30/16.
Accession Number: 20161230–5059.
Comments Due: 5 p.m. ET 1/20/17.
Docket Numbers: ER17–720–000.
Applicants: Midcontinent
Independent System Operator, Inc.,
Ameren Illinois Company.
Description: § 205(d) Rate Filing:
2016–12–30_SA 2991 Ameren IllinoisPrairie Power CA (Shelbyville
Substation) to be effective 12/1/2016.
Filed Date: 12/30/16.
Accession Number: 20161230–5060.
Comments Due: 5 p.m. ET 1/20/17.
Docket Numbers: ER17–721–000.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: § 205(d) Rate Filing:
2016–12–30_Targeted Market Efficiency
Amendments to MISO–PJM JOA to be
effective 6/28/2017.
Filed Date: 12/30/16.
Accession Number: 20161230–5066.
Comments Due: 5 p.m. ET 1/20/17.
Docket Numbers: ER17–722–000.
Applicants: ITC Midwest LLC.
Description: § 205(d) Rate Filing:
Second Amended and Restated Corn
Belt Interconnection Agreement to be
effective 3/1/2017.
Filed Date: 12/30/16.
Accession Number: 20161230–5078.
Comments Due: 5 p.m. ET 1/20/17.
Docket Numbers: ER17–723–000.
Applicants: NRG Power Marketing
LLC.
Description: § 205(d) Rate Filing:
Tariff Filing to be effective 2/1/2017.
Filed Date: 12/30/16.
Accession Number: 20161230–5106.
Comments Due: 5 p.m. ET 1/20/17.
Docket Numbers: ER17–724–000.
Applicants: Palouse Wind, LLC.
PO 00000
Frm 00024
Fmt 4703
Sfmt 9990
3303
Description: Market-Based Triennial
Review Filing: Northwest Triennial to
be effective 12/31/2016.
Filed Date: 12/30/16.
Accession Number: 20161230–5133.
Comments Due: 5 p.m. ET 2/28/17.
Docket Numbers: ER17–725–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Revisions to OATT Sch 12-Appdx and
Appdx A for 2017 RTEP Annual Cost
Allocations to be effective 1/1/2017.
Filed Date: 12/30/16.
Accession Number: 20161230–5154.
Comments Due: 5 p.m. ET 1/20/17.
Docket Numbers: ER17–726–000.
Applicants: California Independent
System Operator Corporation.
Description: § 205(d) Rate Filing:
2016–12–30 Amdt 1 to CAISO and
BANC Dynamic Transfer Balancing
Authority Agmt to be effective 3/1/2017.
Filed Date: 12/30/16.
Accession Number: 20161230–5175.
Comments Due: 5 p.m. ET 1/20/17.
Docket Numbers: ER17–727–000.
Applicants: Valley Electric
Association, Inc.
Description: § 205(d) Rate Filing:
Revisions to Transmission Revenue
Requirement to be effective 3/1/2017.
Filed Date: 12/30/16.
Accession Number: 20161230–5178.
Comments Due: 5 p.m. ET 1/20/17.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: December 30, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017–00378 Filed 1–10–17; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\11JAN1.SGM
11JAN1
Agencies
[Federal Register Volume 82, Number 7 (Wednesday, January 11, 2017)]
[Notices]
[Pages 3302-3303]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-00378]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings #2
Take notice that the Commission received the following electric
rate filings:
Docket Numbers: ER10-1942-014; ER10-1862-016; ER10-1877-004; ER10-
1893-016; ER10-1934-016; ER10-1938-017; ER10-2042-022; ER10-2985-020;
ER10-3049-021; ER10-3051-021; ER17-696-002.
Applicants: Calpine Construction Finance Company, L.P., Calpine
Energy Services, L.P., Calpine Energy Solutions, LLC, Calpine Power
America-CA, LLC, CES Marketing IX, LLC, CES Marketing X, LLC, Champion
Energy Marketing LLC, Champion Energy Services, LLC, Champion Energy,
LLC, Hermiston Power, LLC, Power Contract Financing, L.L.C.
Description: Updated Market Power Analysis for the Northwest Region
of the Calpine Corporation MBR Sellers.
Filed Date: 12/30/16.
Accession Number: 20161230-5127.
[[Page 3303]]
Comments Due: 5 p.m. ET 2/28/17.
Docket Numbers: ER11-4717-002.
Applicants: International Paper Company.
Description: Notice of Non-Material Change in Status of
International Paper Company.
Filed Date: 12/30/16.
Accession Number: 20161230-5043.
Comments Due: 5 p.m. ET 1/20/17.
Docket Numbers: ER15-2582-002; ER10-1851-007; ER10-1852-015; ER10-
1930-007; ER10-1931-008; ER15-2101-004; ER12-2226-007; ER12-2225-007;
ER14-2138-004; ER10-1966-008; ER10-1976-008; ER10-1985-008; ER10-1971-
034; ER11-4462-025.
Applicants: Carousel Wind Farm, LLC, ESI Vansycle Partners, L.P.,
Florida Power & Light Company, FPL Energy Stateline II, Inc., FPL
Energy Vansycle, L.L.C, Golden West Power Partners, LLC, Limon Wind,
LLC, Limon Wind II, LLC, Limon Wind III, LLC, Logan Wind Energy LLC,
Northern Colorado Wind Energy, LLC, Peetz Table Wind Energy, LLC,
NextEra Energy Power Marketing, LLC, NEPM II, LLC.
Description: Triennial Market Power Update for the Northwest Region
of NextEra Companies.
Filed Date: 12/30/16.
Accession Number: 20161230-5176.
Comments Due: 5 p.m. ET 2/28/17.
Docket Numbers: ER17-696-001.
Applicants: Calpine Energy Solutions, LLC.
Description: Notification of Change in Status of Calpine Energy
Solutions, LLC.
Filed Date: 12/30/16.
Accession Number: 20161230-5113.
Comments Due: 5 p.m. ET 1/20/17.
Docket Numbers: ER17-715-000.
Applicants: Midcontinent Independent System Operator, Inc.
Description: Sec. 205(d) Rate Filing: 2016-12-30_SA 2988
MidAmerican-MidAmerican GIA (J500) to be effective 12/31/2016.
Filed Date: 12/30/16.
Accession Number: 20161230-5023.
Comments Due: 5 p.m. ET 1/20/17.
Docket Numbers: ER17-716-000.
Applicants: Midcontinent Independent System Operator, Inc.
Description: Compliance filing: 2016-12-30 _Order 828 Compliance
Filing to be effective N/A.
Filed Date: 12/30/16.
Accession Number: 20161230-5025.
Comments Due: 5 p.m. ET 1/20/17.
Docket Numbers: ER17-717-000.
Applicants: PJM Interconnection, L.L.C.
Description: Sec. 205(d) Rate Filing: Queue Position AB2-048,
Original Service Agreement No. 4597 to be effective 11/30/2016.
Filed Date: 12/30/16.
Accession Number: 20161230-5028.
Comments Due: 5 p.m. ET 1/20/17.
Docket Numbers: ER17-718-000
Applicants: PJM Interconnection, L.L.C.
Description: Sec. 205(d) Rate Filing: Revisions to MISO-PJM JOA,
Article IX sections 9.3 and 9.4 to be effective 12/31/9998.
Filed Date: 12/30/16.
Accession Number: 20161230-5057.
Comments Due: 5 p.m. ET 1/20/17.
Docket Numbers: ER17-719-000.
Applicants: PJM Interconnection, L.L.C., Metropolitan Edison
Company, American Transmission Systems, Incorporated.
Description: Sec. 205(d) Rate Filing: ATSI et. al. submits OIA SA
No. 2852 & ECSA SA No. 4554 to be effective 1/1/2017.
Filed Date: 12/30/16.
Accession Number: 20161230-5059.
Comments Due: 5 p.m. ET 1/20/17.
Docket Numbers: ER17-720-000.
Applicants: Midcontinent Independent System Operator, Inc., Ameren
Illinois Company.
Description: Sec. 205(d) Rate Filing: 2016-12-30_SA 2991 Ameren
Illinois-Prairie Power CA (Shelbyville Substation) to be effective 12/
1/2016.
Filed Date: 12/30/16.
Accession Number: 20161230-5060.
Comments Due: 5 p.m. ET 1/20/17.
Docket Numbers: ER17-721-000.
Applicants: Midcontinent Independent System Operator, Inc.
Description: Sec. 205(d) Rate Filing: 2016-12-30_Targeted Market
Efficiency Amendments to MISO-PJM JOA to be effective 6/28/2017.
Filed Date: 12/30/16.
Accession Number: 20161230-5066.
Comments Due: 5 p.m. ET 1/20/17.
Docket Numbers: ER17-722-000.
Applicants: ITC Midwest LLC.
Description: Sec. 205(d) Rate Filing: Second Amended and Restated
Corn Belt Interconnection Agreement to be effective 3/1/2017.
Filed Date: 12/30/16.
Accession Number: 20161230-5078.
Comments Due: 5 p.m. ET 1/20/17.
Docket Numbers: ER17-723-000.
Applicants: NRG Power Marketing LLC.
Description: Sec. 205(d) Rate Filing: Tariff Filing to be
effective 2/1/2017.
Filed Date: 12/30/16.
Accession Number: 20161230-5106.
Comments Due: 5 p.m. ET 1/20/17.
Docket Numbers: ER17-724-000.
Applicants: Palouse Wind, LLC.
Description: Market-Based Triennial Review Filing: Northwest
Triennial to be effective 12/31/2016.
Filed Date: 12/30/16.
Accession Number: 20161230-5133.
Comments Due: 5 p.m. ET 2/28/17.
Docket Numbers: ER17-725-000.
Applicants: PJM Interconnection, L.L.C.
Description: Sec. 205(d) Rate Filing: Revisions to OATT Sch 12-
Appdx and Appdx A for 2017 RTEP Annual Cost Allocations to be effective
1/1/2017.
Filed Date: 12/30/16.
Accession Number: 20161230-5154.
Comments Due: 5 p.m. ET 1/20/17.
Docket Numbers: ER17-726-000.
Applicants: California Independent System Operator Corporation.
Description: Sec. 205(d) Rate Filing: 2016-12-30 Amdt 1 to CAISO
and BANC Dynamic Transfer Balancing Authority Agmt to be effective 3/1/
2017.
Filed Date: 12/30/16.
Accession Number: 20161230-5175.
Comments Due: 5 p.m. ET 1/20/17.
Docket Numbers: ER17-727-000.
Applicants: Valley Electric Association, Inc.
Description: Sec. 205(d) Rate Filing: Revisions to Transmission
Revenue Requirement to be effective 3/1/2017.
Filed Date: 12/30/16.
Accession Number: 20161230-5178.
Comments Due: 5 p.m. ET 1/20/17.
The filings are accessible in the Commission's eLibrary system by
clicking on the links or querying the docket number.
Any person desiring to intervene or protest in any of the above
proceedings must file in accordance with Rules 211 and 214 of the
Commission's Regulations (18 CFR 385.211 and 385.214) on or before 5:00
p.m. Eastern time on the specified comment date. Protests may be
considered, but intervention is necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed information relating to filing
requirements, interventions, protests, service, and qualifying
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676
(toll free). For TTY, call (202) 502-8659.
Dated: December 30, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017-00378 Filed 1-10-17; 8:45 am]
BILLING CODE 6717-01-P