Notice of Availability of the Draft Environmental Impact Statement for the Proposed Atlantic Coast Pipeline, Supply Header Project, and Capacity Lease Proposal, 2348-2350 [2017-00068]
Download as PDF
2348
Federal Register / Vol. 82, No. 5 / Monday, January 9, 2017 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Availability of the Draft
Environmental Impact Statement for
the Proposed Atlantic Coast Pipeline,
Supply Header Project, and Capacity
Lease Proposal
Docket Nos.
Atlantic Coast Pipeline,
LLC.
sradovich on DSK3GMQ082PROD with NOTICES
Dominion Transmission,
Inc.
Piedmont Natural Gas
Company, Inc.
CP15–554–000,
CP15–554–
001
CP15–555–000
CP15–556–000
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) has prepared a draft
environmental impact statement (EIS)
for the Atlantic Coast Pipeline (ACP)
and Supply Header Project (SHP) as
proposed by Atlantic Coast Pipeline,
LLC (Atlantic) and Dominion
Transmission, Inc. (DTI), respectively,
in the above-referenced dockets.
Atlantic and DTI request authorization
to construct and operate a total of 641.3
miles of natural gas transmission
pipeline and associated facilities, and
three new natural gas-fired compressor
stations, and to modify four existing
compressor stations. The projects would
provide about 1.44 billion cubic feet per
day of natural gas to electric generation,
distribution, and end use markets in
Virginia and North Carolina. In
addition, Atlantic and Piedmont Natural
Gas Co., Inc. (Piedmont) request
authorization to allow Atlantic to lease
capacity on Piedmont’s existing
pipeline distribution system in North
Carolina for use by Atlantic (Capacity
Lease Proposal). No construction or
facility modifications are proposed with
the Capacity Lease Proposal.
The draft EIS assesses the potential
environmental effects of the
construction and operation of the
projects in accordance with the
requirements of the National
Environmental Policy Act (NEPA). The
FERC staff concludes that approval of
the projects would have some adverse
and significant environmental impacts;
however, the majority of impacts would
be reduced to less-than-significant
levels with the implementation of the
Atlantic’s and DTI’s proposed
mitigation and the additional measures
recommended in the draft EIS.
The U.S. Department of Agriculture—
Forest Service (FS); U.S. Army Corps of
Engineers; U.S. Environmental
Protection Agency; U.S. Fish and
VerDate Sep<11>2014
21:14 Jan 06, 2017
Jkt 241001
Wildlife Service—Great Dismal Swamp
National Wildlife Refuge; West Virginia
Department of Environmental
Protection; and West Virginia Division
of Natural Resources participated as
cooperating agencies in the preparation
of the draft EIS. Cooperating agencies
have jurisdiction by law or special
expertise with respect to resources
potentially affected by the proposals
and participate in the NEPA analysis.
Further, the FS may use the EIS when
it considers amendments to Land and
Resource Management Plans (LRMPs)
for the proposed crossings of the
Monongahela National Forest (MNF)
and George Washington National Forest
(GWNF). Although the cooperating
agencies provide input to the
conclusions and recommendations
presented in the draft EIS, each agency
will present its own conclusions and
recommendations in its respective
record of decision or determination for
the projects.
The draft EIS addresses the potential
environmental effects of the
construction and operation of the
following proposed project facilities:
The ACP includes:
• 519.1 miles of new 42- and 36-inchdiameter natural gas pipeline in West
Virginia, Virginia, and North Carolina;
• 84.6 miles of 20- and 16-inchdiameter natural gas pipeline in Virginia
and North Carolina;
• three new compressor station in
Lewis County, West Virginia;
Buckingham County, Virginia; and
Northampton County, North Carolina;
and
• nine meter stations, along with pig
launchers/receivers and mainline
valves.
The SHP includes:
• 37.5 miles of new 36-inch-diameter
natural gas pipeline in Pennsylvania
and West Virginia;
• modifications at four existing
compressor stations in Westmoreland
and Green Counties Pennsylvania and
Marshall and Wetzel Counties West
Virginia;
• abandonment of existing
compressor units and associated
facilities in Wetzel County, West
Virginia; and
• one meter station, along with pig
launchers/receivers and mainline
valves.
Actions of the Forest Service
The FS’s purpose and need for the
proposed action is to respond to a
special use application submitted by
Atlantic on November 12, 2015, to allow
the construction and operation of the
ACP on national forest system (NFS)
lands managed by the MNF and the
PO 00000
Frm 00040
Fmt 4703
Sfmt 4703
GWNF. If the FS decides to authorize
the pipeline crossing of NFS lands and
issue a special use permit, the FS has
determined that amendments to each
national forest LRMP would be needed.
Project-specific plan amendments
would be needed to deviate from the
precise wording of forest plan standards
for the construction and operation of the
ACP. These amendments are considered
‘‘project-specific’’ amendments because
they would not change FS requirements
for other projects or authorize any other
actions. Additionally, if the proposed
route is authorized and a special use
permit issued, the GWNF LRMP would
need to be amended to change the
current management prescriptions in
the pipeline’s operational corridor to
Management Prescription Area (Rx) 5CDesignated Utility Corridors. The MNF
does not have LRMP direction that
would require a similar plan
amendment to reallocate management
prescriptions. Therefore, this
amendment is considered a ‘‘plan-level’’
amendment and would change future
management direction for the lands
reallocated to the new management
prescription. The FS has also identified
other potential amendments that may be
required, pending survey information
and analyses that are not currently
available.
Pursuant to Title 40 of the Code of
Federal Regulations, Part 1506.3(c) (40
CFR 1506.3(c)), the FS may adopt and
use the EIS developed by FERC to
consider authorization for the
construction and operation of the ACP
crossing NFS lands. Further, the FS may
use this EIS when it considers
amendments to the LRMPs that would
be required for the proposed crossings
of the MNF and GWNF. The FS will
prepare separate Records of Decision for
the authorization decision and for the
plan amendments decisions, after
issuance of the FERC final EIS.
The following amendments have been
proposed by the FS as part of the
proposed action in the FERC draft EIS:
Monongahela National Forest
The type of amendment applicable to
the MNF would be a project-specific
amendment. This amendment would
not change FS requirements for other
projects or authorize any other actions.
Potential Amendment 1: The MNF
LRMP may need to be amended to allow
construction of the ACP to temporarily
exceed standards identified under
management direction for soils and
water, specifically forest-wide standards
SW06 and SW07, provided that design
criteria, mitigation measures, project
requirements, and/or monitoring
activities agreed upon by the FS are
E:\FR\FM\09JAN1.SGM
09JAN1
Federal Register / Vol. 82, No. 5 / Monday, January 9, 2017 / Notices
sradovich on DSK3GMQ082PROD with NOTICES
implemented as needed to achieve
adequate slope and soil stability.
Other potential amendments may be
needed pending the outcome of ongoing
analyses and development of project
design and mitigation.
George Washington National Forest
The first type of LRMP amendment
applicable to the GWNF would be a
plan-level amendment that would
change land allocations. This would
change future management direction for
the lands reallocated to the new Rx and
is required by LRMP Standards FW–243
and FW–244.
Proposed Amendment 1: The LRMP
would be amended to reallocate 102.3
acres to the Rx 5C-Designated Utility
Corridors from these Rxs: 7E1-Dispersed
Recreation Areas (7 acres), and 13Mosaics of Habitat (95 acres). Rx 11Riparian Corridors would remain
embedded within the new Rx 5C area.
Rx 5C-Designated Utility Corridors
contains special uses which serve a
public benefit by providing a reliable
supply of electricity, natural gas, or
water essential to local, regional, and
national economies. The new Rx 5C
land allocation would be 53.5 feet wide,
the width of the final operational rightof-way of the ACP. The area would not
cross into the Rx 4A-Appalachian
National Scenic Area but would stop
and start at the existing Rx 4A
boundary. The Rx4A would continue to
be managed for the Appalachian
National Scenic Trail.
The second type of amendment
applicable to the GWNF would be a
project-specific amendment that would
apply only to the construction and
operation of the ACP. The following
standards would require a temporary
waiver to allow the project to proceed.
These amendments would not change
LRMP requirements for other projects or
authorize any other actions.
Proposed Amendment 2: The LRMP
would be amended to allow
construction of the ACP to exceed
restrictions on soil conditions and
riparian corridor conditions as
described in LRMP Standards FW–5,
FW–15, FW–16, FW–17, and 11–019,
provided that mitigation measures or
project requirements agreed upon by the
FS are implemented as needed.
Proposed Amendment 3: The LRMP
would be amended to allow the ACP to
cross the Appalachian National Scenic
Trail in Augusta County, Virginia
(reference LRMP Standard 4A–025).
Potential Amendment 4: The LRMP
may need to be amended to allow the
removal of old growth trees within the
construction corridor of ACP (reference
LRMP Standard FW–85).
VerDate Sep<11>2014
21:14 Jan 06, 2017
Jkt 241001
Potential Amendment 5: The LRMP
may need to be amended to allow major
reconstruction of a NFS road within the
Rx 2C3 area to provide access for
pipeline construction. This is
contingent on the final location of
access roads (reference LRMP Standard
2C3–015).
Potential Amendment 6: The LRMP
may need to be amended to allow the
ACP to not immediately meet Scenic
Integrity Objectives; however,
mitigation measures, including
vegetation management and restoration
actions, are expected to improve visual
quality over an extended timeframe
(reference LRMP Standard FW–182).
The FS is requesting public comments
on the authorization of the ACP on NFS
lands and the draft proposed and
potential amendments of the LRMPs
that would allow the ACP to cross the
MNF and GWNF. All comments must be
submitted to the FERC as directed in
this notice. The FS decision to authorize
the ACP will be subject to FS
predecisional administrative review
procedures established in 36 CFR 218.
The MNF Potential Amendment 1,
GWNF Proposed Amendments 2 and 3,
and Potential Amendments 4, 5, and 6
were developed in accordance with 36
CFR 219 (2012 version) regulations but
will be subject to the administrative
review procedures under 36 CFR 218
regulations Subparts A and B, per 36
CFR 219.59(b). GWNF Proposed
Amendment 1 was developed in
accordance to 36 CFR 219 (2012)
regulations and will be subject to the
administrative review procedures under
36 CFR 219 Subpart B. Refer to the
applicable administrative review
regulations for eligibility requirements.
All comments must be submitted to
the FERC, the lead federal agency,
within the timeframe stated in this
Notice of Availability. Refer to Docket
No. CP15–554–000 (ACP) in all
correspondence to ensure that your
comments are correctly filed in the
record. You may submit your comments
to the FERC using one of the four
methods listed below.
Distribution and Comments on the Draft
Environmental Impact Statement
The FERC staff mailed copies of the
draft EIS to federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American tribes;
potentially affected landowners and
other interested individuals and groups;
newspapers and libraries in the project
areas; and parties to this proceeding.
Paper copy versions of this draft EIS
were mailed to those specifically
PO 00000
Frm 00041
Fmt 4703
Sfmt 4703
2349
requesting them; all others received a
CD version. In addition, the draft EIS is
available for public viewing on the
FERC’s Web site (www.ferc.gov) using
the eLibrary link. A limited number of
copies of the draft EIS are available for
distribution and public inspection at:
Federal Energy Regulatory Commission,
Public Reference Room, 888 First
Street NE., Room 2A, Washington, DC
20426, (202) 502–8371.
Any person wishing to comment on
the draft EIS may do so. To ensure
consideration of your comments on the
proposals in the final EIS, it is
important that the Commission receive
your comments by April 6, 2017.
For your convenience, there are four
methods you can use to submit your
comments to the Commission. In all
instances, please reference the
appropriate docket numbers (CP15–
554–000 and CP15–554–001 for ACP;
CP15–555–000 for SHP; or CP15–556–
000 for Capacity Lease) with your
submission. The Commission
encourages electronic filing of
comments and has expert staff available
to assist you at (202) 502–8258 or
efiling@ferc.gov. Please carefully follow
these instructions so that your
comments are properly recorded.
(1) You can file your comments
electronically using the eComment
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. This is an easy
method for submitting brief, text-only
comments on a project.
(2) You can file your comments
electronically by using the eFiling
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. With eFiling,
you can provide comments in a variety
of formats by attaching them as a file
with your submission. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ If you are filing
a comment on a particular project,
please select ‘‘Comment on a Filing’’ as
the filing type.
(3) You can file a paper copy of your
comments by mailing them to the
following address:
Nathaniel J. Davis, Sr., Deputy
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE.,
Room 1A, Washington, DC 20426.
(4) In lieu of sending written or
electronic comments, the Commission
invites you to attend one of the public
comment sessions its staff will conduct
in the project area to receive comments
on the draft EIS. We encourage
interested groups and individuals to
attend and present oral comments on
E:\FR\FM\09JAN1.SGM
09JAN1
2350
Federal Register / Vol. 82, No. 5 / Monday, January 9, 2017 / Notices
the draft EIS. The sessions are
scheduled as follows:
Date and time
Location
Monday, February 13, 2017, 5:00–9:00 p.m ......
Tuesday, February 14, 2017, 5:00–9:00 p.m .....
Wednesday, February 15, 2017, 5:00–9:00 p.m
Doubletree Hotel, 1965 Cedar Creek Road, Fayetteville, NC 28312.
Forest Hills Middle School, 1210 Forest Hills Road, Wilson, NC 27893.
Hilton Garden Inn Roanoke Rapids, 111 Carolina Crossroads Parkway, Roanoke Rapids, NC
27870.
Hilton Garden Inn Conference Center, 100 East Constance Road, Suffolk, VA 23434.
Moton Museum, 900 Griffin Boulevard, Farmville, VA 23901.
Nelson County High School, 6919 Thomas Nelson Highway, Route 29, Lovingston, VA 22949.
Holiday Inn Hotel and Conference, 152 Fairway Lane, Staunton, VA 24401.
Highland Center, 61 Highland Center Drive, Monterey, VA 24465.
Gandy Dance Theater, 359 Beverly Pike, Elkins, WV 26241.
Marlinton Community Wellness Center, 320 9th Street, Marlinton, WV 24954.
sradovich on DSK3GMQ082PROD with NOTICES
Thursday, February 16, 2017, 5:30–9:30 p.m ....
Tuesday, February 21, 2017, 5:00–9:00 p.m .....
Wednesday, February 22, 2017, 5:00–9:00 p.m
Thursday, February 23, 2017, 5:00–9:00 p.m ....
Tuesday, February 28, 2017, 5:00–9:00 p.m .....
Wednesday, March 1, 2017, 5:00–9:00 p.m ......
Thursday, March 2, 2017, 5:00–9:00 p.m ..........
There will not be a formal
presentation by Commission staff at any
of the ten public comment sessions,
although a format outline handout will
be made available. All sessions will
begin at 5:00 p.m., with the exception of
the session on Thursday, February 16,
2017, which will begin at 5:30 p.m. If
you wish to provide verbal comments,
the Commission staff will hand out
numbers in the order of your arrival.
Number distribution will be
discontinued at 8:00 p.m. in order to
ensure all comments are received by the
session closing time. Comments will be
taken until 9:00 p.m. (or 9:30 p.m. at the
February 16 session). However, if no
additional numbers have been handed
out and all individuals who wish to
provide comments have had an
opportunity to do so, staff may conclude
the session at 8:00 p.m., or after the last
comment is taken.
The primary goal of the public
sessions is to allow individuals to
provide verbal comments on the draft
EIS. Individual verbal comments will be
taken on a one-on-one basis with a
Court Reporter (with FERC staff or
representative present), called up in the
order of the numbers received. Because
we anticipate considerable interest from
concerned citizens, this format is
designed to receive the maximum
amount of verbal comments, in a
convenient way during the timeframe
allotted. If many people are interested in
providing verbal comments in the oneon-one setting at any particular session,
a time limit of 3 minutes may be
implemented for each commenter.
Your verbal comments will be
recorded by the Court Reporter.
Transcripts of all comments from the
sessions will be placed into the dockets
for the projects, which are accessible for
public viewing on the FERC’s Web site
(at www.ferc.gov) through our eLibrary
system.
Commission staff will be available at
each venue of the public sessions to
answer questions about our
VerDate Sep<11>2014
21:14 Jan 06, 2017
Jkt 241001
environmental review process. It is
important to note that written comments
mailed to the Commission and those
submitted electronically are reviewed
by staff with the same scrutiny and
consideration as the verbal comments
given at the public sessions.
Any person seeking to become a party
to the proceeding must file a motion to
intervene pursuant to Rule 214 of the
Commission’s Rules of Practice and
Procedures (18 CFR part 385.214).1 Only
intervenors have the right to seek
rehearing of the Commission’s decision.
The Commission grants affected
landowners and others with
environmental concerns intervenor
status upon showing good cause by
stating that they have a clear and direct
interest in this proceeding which no
other party can adequately represent.
Simply filing environmental comments
will not give you intervenor status, but
you do not need intervenor status to
have your comments considered.
Questions?
Additional information about the
projects is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC Web
site (www.ferc.gov) using the eLibrary
link. Click on the eLibrary link, click on
‘‘General Search,’’ and enter the docket
number excluding the last three digits in
the Docket Number field (i.e., CP15–
554, CP15–555, or CP15–556). Be sure
you have selected an appropriate date
range. For assistance, please contact
FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at (866) 208–3676; for TTY, contact
(202) 502–8659. The eLibrary link also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
In addition, the Commission offers a
free service called eSubscription that
1 See the previous discussion on the methods for
filing comments.
PO 00000
Frm 00042
Fmt 4703
Sfmt 4703
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp to subscribe.
Dated: December 30, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017–00068 Filed 1–6–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER17–737–000]
Viridity Energy Solutions Inc.;
Supplemental Notice That Initial
Market-Based Rate Filing Includes
Request For Blanket Section 204
Authorization
This is a supplemental notice in the
above-referenced proceeding of Viridity
Energy Solutions Inc.’s application for
market-based rate authority, with an
accompanying rate tariff, noting that
such application includes a request for
blanket authorization, under 18 CFR
part 34, of future issuances of securities
and assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR part 34, of
E:\FR\FM\09JAN1.SGM
09JAN1
Agencies
[Federal Register Volume 82, Number 5 (Monday, January 9, 2017)]
[Notices]
[Pages 2348-2350]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-00068]
[[Page 2348]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice of Availability of the Draft Environmental Impact
Statement for the Proposed Atlantic Coast Pipeline, Supply Header
Project, and Capacity Lease Proposal
------------------------------------------------------------------------
Docket Nos.
------------------------------------------------------------------------
Atlantic Coast Pipeline, LLC........... CP15-554-000, CP15-554-001
Dominion Transmission, Inc............. CP15-555-000
Piedmont Natural Gas Company, Inc...... CP15-556-000
------------------------------------------------------------------------
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) has prepared a draft environmental impact statement (EIS)
for the Atlantic Coast Pipeline (ACP) and Supply Header Project (SHP)
as proposed by Atlantic Coast Pipeline, LLC (Atlantic) and Dominion
Transmission, Inc. (DTI), respectively, in the above-referenced
dockets. Atlantic and DTI request authorization to construct and
operate a total of 641.3 miles of natural gas transmission pipeline and
associated facilities, and three new natural gas-fired compressor
stations, and to modify four existing compressor stations. The projects
would provide about 1.44 billion cubic feet per day of natural gas to
electric generation, distribution, and end use markets in Virginia and
North Carolina. In addition, Atlantic and Piedmont Natural Gas Co.,
Inc. (Piedmont) request authorization to allow Atlantic to lease
capacity on Piedmont's existing pipeline distribution system in North
Carolina for use by Atlantic (Capacity Lease Proposal). No construction
or facility modifications are proposed with the Capacity Lease
Proposal.
The draft EIS assesses the potential environmental effects of the
construction and operation of the projects in accordance with the
requirements of the National Environmental Policy Act (NEPA). The FERC
staff concludes that approval of the projects would have some adverse
and significant environmental impacts; however, the majority of impacts
would be reduced to less-than-significant levels with the
implementation of the Atlantic's and DTI's proposed mitigation and the
additional measures recommended in the draft EIS.
The U.S. Department of Agriculture--Forest Service (FS); U.S. Army
Corps of Engineers; U.S. Environmental Protection Agency; U.S. Fish and
Wildlife Service--Great Dismal Swamp National Wildlife Refuge; West
Virginia Department of Environmental Protection; and West Virginia
Division of Natural Resources participated as cooperating agencies in
the preparation of the draft EIS. Cooperating agencies have
jurisdiction by law or special expertise with respect to resources
potentially affected by the proposals and participate in the NEPA
analysis. Further, the FS may use the EIS when it considers amendments
to Land and Resource Management Plans (LRMPs) for the proposed
crossings of the Monongahela National Forest (MNF) and George
Washington National Forest (GWNF). Although the cooperating agencies
provide input to the conclusions and recommendations presented in the
draft EIS, each agency will present its own conclusions and
recommendations in its respective record of decision or determination
for the projects.
The draft EIS addresses the potential environmental effects of the
construction and operation of the following proposed project
facilities:
The ACP includes:
519.1 miles of new 42- and 36-inch-diameter natural gas
pipeline in West Virginia, Virginia, and North Carolina;
84.6 miles of 20- and 16-inch-diameter natural gas
pipeline in Virginia and North Carolina;
three new compressor station in Lewis County, West
Virginia; Buckingham County, Virginia; and Northampton County, North
Carolina; and
nine meter stations, along with pig launchers/receivers
and mainline valves.
The SHP includes:
37.5 miles of new 36-inch-diameter natural gas pipeline in
Pennsylvania and West Virginia;
modifications at four existing compressor stations in
Westmoreland and Green Counties Pennsylvania and Marshall and Wetzel
Counties West Virginia;
abandonment of existing compressor units and associated
facilities in Wetzel County, West Virginia; and
one meter station, along with pig launchers/receivers and
mainline valves.
Actions of the Forest Service
The FS's purpose and need for the proposed action is to respond to
a special use application submitted by Atlantic on November 12, 2015,
to allow the construction and operation of the ACP on national forest
system (NFS) lands managed by the MNF and the GWNF. If the FS decides
to authorize the pipeline crossing of NFS lands and issue a special use
permit, the FS has determined that amendments to each national forest
LRMP would be needed.
Project-specific plan amendments would be needed to deviate from
the precise wording of forest plan standards for the construction and
operation of the ACP. These amendments are considered ``project-
specific'' amendments because they would not change FS requirements for
other projects or authorize any other actions. Additionally, if the
proposed route is authorized and a special use permit issued, the GWNF
LRMP would need to be amended to change the current management
prescriptions in the pipeline's operational corridor to Management
Prescription Area (Rx) 5C-Designated Utility Corridors. The MNF does
not have LRMP direction that would require a similar plan amendment to
reallocate management prescriptions. Therefore, this amendment is
considered a ``plan-level'' amendment and would change future
management direction for the lands reallocated to the new management
prescription. The FS has also identified other potential amendments
that may be required, pending survey information and analyses that are
not currently available.
Pursuant to Title 40 of the Code of Federal Regulations, Part
1506.3(c) (40 CFR 1506.3(c)), the FS may adopt and use the EIS
developed by FERC to consider authorization for the construction and
operation of the ACP crossing NFS lands. Further, the FS may use this
EIS when it considers amendments to the LRMPs that would be required
for the proposed crossings of the MNF and GWNF. The FS will prepare
separate Records of Decision for the authorization decision and for the
plan amendments decisions, after issuance of the FERC final EIS.
The following amendments have been proposed by the FS as part of
the proposed action in the FERC draft EIS:
Monongahela National Forest
The type of amendment applicable to the MNF would be a project-
specific amendment. This amendment would not change FS requirements for
other projects or authorize any other actions.
Potential Amendment 1: The MNF LRMP may need to be amended to allow
construction of the ACP to temporarily exceed standards identified
under management direction for soils and water, specifically forest-
wide standards SW06 and SW07, provided that design criteria, mitigation
measures, project requirements, and/or monitoring activities agreed
upon by the FS are
[[Page 2349]]
implemented as needed to achieve adequate slope and soil stability.
Other potential amendments may be needed pending the outcome of
ongoing analyses and development of project design and mitigation.
George Washington National Forest
The first type of LRMP amendment applicable to the GWNF would be a
plan-level amendment that would change land allocations. This would
change future management direction for the lands reallocated to the new
Rx and is required by LRMP Standards FW-243 and FW-244.
Proposed Amendment 1: The LRMP would be amended to reallocate 102.3
acres to the Rx 5C-Designated Utility Corridors from these Rxs: 7E1-
Dispersed Recreation Areas (7 acres), and 13-Mosaics of Habitat (95
acres). Rx 11-Riparian Corridors would remain embedded within the new
Rx 5C area.
Rx 5C-Designated Utility Corridors contains special uses which
serve a public benefit by providing a reliable supply of electricity,
natural gas, or water essential to local, regional, and national
economies. The new Rx 5C land allocation would be 53.5 feet wide, the
width of the final operational right-of-way of the ACP. The area would
not cross into the Rx 4A-Appalachian National Scenic Area but would
stop and start at the existing Rx 4A boundary. The Rx4A would continue
to be managed for the Appalachian National Scenic Trail.
The second type of amendment applicable to the GWNF would be a
project-specific amendment that would apply only to the construction
and operation of the ACP. The following standards would require a
temporary waiver to allow the project to proceed. These amendments
would not change LRMP requirements for other projects or authorize any
other actions.
Proposed Amendment 2: The LRMP would be amended to allow
construction of the ACP to exceed restrictions on soil conditions and
riparian corridor conditions as described in LRMP Standards FW-5, FW-
15, FW-16, FW-17, and 11-019, provided that mitigation measures or
project requirements agreed upon by the FS are implemented as needed.
Proposed Amendment 3: The LRMP would be amended to allow the ACP to
cross the Appalachian National Scenic Trail in Augusta County, Virginia
(reference LRMP Standard 4A-025).
Potential Amendment 4: The LRMP may need to be amended to allow the
removal of old growth trees within the construction corridor of ACP
(reference LRMP Standard FW-85).
Potential Amendment 5: The LRMP may need to be amended to allow
major reconstruction of a NFS road within the Rx 2C3 area to provide
access for pipeline construction. This is contingent on the final
location of access roads (reference LRMP Standard 2C3-015).
Potential Amendment 6: The LRMP may need to be amended to allow the
ACP to not immediately meet Scenic Integrity Objectives; however,
mitigation measures, including vegetation management and restoration
actions, are expected to improve visual quality over an extended
timeframe (reference LRMP Standard FW-182).
The FS is requesting public comments on the authorization of the
ACP on NFS lands and the draft proposed and potential amendments of the
LRMPs that would allow the ACP to cross the MNF and GWNF. All comments
must be submitted to the FERC as directed in this notice. The FS
decision to authorize the ACP will be subject to FS predecisional
administrative review procedures established in 36 CFR 218. The MNF
Potential Amendment 1, GWNF Proposed Amendments 2 and 3, and Potential
Amendments 4, 5, and 6 were developed in accordance with 36 CFR 219
(2012 version) regulations but will be subject to the administrative
review procedures under 36 CFR 218 regulations Subparts A and B, per 36
CFR 219.59(b). GWNF Proposed Amendment 1 was developed in accordance to
36 CFR 219 (2012) regulations and will be subject to the administrative
review procedures under 36 CFR 219 Subpart B. Refer to the applicable
administrative review regulations for eligibility requirements.
All comments must be submitted to the FERC, the lead federal
agency, within the timeframe stated in this Notice of Availability.
Refer to Docket No. CP15-554-000 (ACP) in all correspondence to ensure
that your comments are correctly filed in the record. You may submit
your comments to the FERC using one of the four methods listed below.
Distribution and Comments on the Draft Environmental Impact Statement
The FERC staff mailed copies of the draft EIS to federal, state,
and local government representatives and agencies; elected officials;
environmental and public interest groups; Native American tribes;
potentially affected landowners and other interested individuals and
groups; newspapers and libraries in the project areas; and parties to
this proceeding. Paper copy versions of this draft EIS were mailed to
those specifically requesting them; all others received a CD version.
In addition, the draft EIS is available for public viewing on the
FERC's Web site (www.ferc.gov) using the eLibrary link. A limited
number of copies of the draft EIS are available for distribution and
public inspection at:
Federal Energy Regulatory Commission, Public Reference Room, 888 First
Street NE., Room 2A, Washington, DC 20426, (202) 502-8371.
Any person wishing to comment on the draft EIS may do so. To ensure
consideration of your comments on the proposals in the final EIS, it is
important that the Commission receive your comments by April 6, 2017.
For your convenience, there are four methods you can use to submit
your comments to the Commission. In all instances, please reference the
appropriate docket numbers (CP15-554-000 and CP15-554-001 for ACP;
CP15-555-000 for SHP; or CP15-556-000 for Capacity Lease) with your
submission. The Commission encourages electronic filing of comments and
has expert staff available to assist you at (202) 502-8258 or
efiling@ferc.gov. Please carefully follow these instructions so that
your comments are properly recorded.
(1) You can file your comments electronically using the eComment
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. This is an easy method for submitting brief,
text-only comments on a project.
(2) You can file your comments electronically by using the eFiling
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. With eFiling, you can provide comments in a
variety of formats by attaching them as a file with your submission.
New eFiling users must first create an account by clicking on
``eRegister.'' If you are filing a comment on a particular project,
please select ``Comment on a Filing'' as the filing type.
(3) You can file a paper copy of your comments by mailing them to
the following address:
Nathaniel J. Davis, Sr., Deputy Secretary, Federal Energy Regulatory
Commission, 888 First Street NE., Room 1A, Washington, DC 20426.
(4) In lieu of sending written or electronic comments, the
Commission invites you to attend one of the public comment sessions its
staff will conduct in the project area to receive comments on the draft
EIS. We encourage interested groups and individuals to attend and
present oral comments on
[[Page 2350]]
the draft EIS. The sessions are scheduled as follows:
------------------------------------------------------------------------
Date and time Location
------------------------------------------------------------------------
Monday, February 13, 2017, Doubletree Hotel, 1965 Cedar Creek Road,
5:00-9:00 p.m. Fayetteville, NC 28312.
Tuesday, February 14, 2017, Forest Hills Middle School, 1210 Forest
5:00-9:00 p.m. Hills Road, Wilson, NC 27893.
Wednesday, February 15, 2017, Hilton Garden Inn Roanoke Rapids, 111
5:00-9:00 p.m. Carolina Crossroads Parkway, Roanoke
Rapids, NC 27870.
Thursday, February 16, 2017, Hilton Garden Inn Conference Center, 100
5:30-9:30 p.m. East Constance Road, Suffolk, VA 23434.
Tuesday, February 21, 2017, Moton Museum, 900 Griffin Boulevard,
5:00-9:00 p.m. Farmville, VA 23901.
Wednesday, February 22, 2017, Nelson County High School, 6919 Thomas
5:00-9:00 p.m. Nelson Highway, Route 29, Lovingston, VA
22949.
Thursday, February 23, 2017, Holiday Inn Hotel and Conference, 152
5:00-9:00 p.m. Fairway Lane, Staunton, VA 24401.
Tuesday, February 28, 2017, Highland Center, 61 Highland Center
5:00-9:00 p.m. Drive, Monterey, VA 24465.
Wednesday, March 1, 2017, Gandy Dance Theater, 359 Beverly Pike,
5:00-9:00 p.m. Elkins, WV 26241.
Thursday, March 2, 2017, 5:00- Marlinton Community Wellness Center, 320
9:00 p.m. 9th Street, Marlinton, WV 24954.
------------------------------------------------------------------------
There will not be a formal presentation by Commission staff at any
of the ten public comment sessions, although a format outline handout
will be made available. All sessions will begin at 5:00 p.m., with the
exception of the session on Thursday, February 16, 2017, which will
begin at 5:30 p.m. If you wish to provide verbal comments, the
Commission staff will hand out numbers in the order of your arrival.
Number distribution will be discontinued at 8:00 p.m. in order to
ensure all comments are received by the session closing time. Comments
will be taken until 9:00 p.m. (or 9:30 p.m. at the February 16
session). However, if no additional numbers have been handed out and
all individuals who wish to provide comments have had an opportunity to
do so, staff may conclude the session at 8:00 p.m., or after the last
comment is taken.
The primary goal of the public sessions is to allow individuals to
provide verbal comments on the draft EIS. Individual verbal comments
will be taken on a one-on-one basis with a Court Reporter (with FERC
staff or representative present), called up in the order of the numbers
received. Because we anticipate considerable interest from concerned
citizens, this format is designed to receive the maximum amount of
verbal comments, in a convenient way during the timeframe allotted. If
many people are interested in providing verbal comments in the one-on-
one setting at any particular session, a time limit of 3 minutes may be
implemented for each commenter.
Your verbal comments will be recorded by the Court Reporter.
Transcripts of all comments from the sessions will be placed into the
dockets for the projects, which are accessible for public viewing on
the FERC's Web site (at www.ferc.gov) through our eLibrary system.
Commission staff will be available at each venue of the public
sessions to answer questions about our environmental review process. It
is important to note that written comments mailed to the Commission and
those submitted electronically are reviewed by staff with the same
scrutiny and consideration as the verbal comments given at the public
sessions.
Any person seeking to become a party to the proceeding must file a
motion to intervene pursuant to Rule 214 of the Commission's Rules of
Practice and Procedures (18 CFR part 385.214).\1\ Only intervenors have
the right to seek rehearing of the Commission's decision. The
Commission grants affected landowners and others with environmental
concerns intervenor status upon showing good cause by stating that they
have a clear and direct interest in this proceeding which no other
party can adequately represent. Simply filing environmental comments
will not give you intervenor status, but you do not need intervenor
status to have your comments considered.
---------------------------------------------------------------------------
\1\ See the previous discussion on the methods for filing
comments.
---------------------------------------------------------------------------
Questions?
Additional information about the projects is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC Web site (www.ferc.gov) using the eLibrary link. Click on the
eLibrary link, click on ``General Search,'' and enter the docket number
excluding the last three digits in the Docket Number field (i.e., CP15-
554, CP15-555, or CP15-556). Be sure you have selected an appropriate
date range. For assistance, please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll free at (866) 208-3676; for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription that allows you to keep track of all formal issuances and
submittals in specific dockets. This can reduce the amount of time you
spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp to
subscribe.
Dated: December 30, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-00068 Filed 1-6-17; 8:45 am]
BILLING CODE 6717-01-P