Columbia Gas Transmission, LLC; Notice of Request Under Blanket Authorization, 87924-87925 [2016-29227]
Download as PDF
87924
Federal Register / Vol. 81, No. 234 / Tuesday, December 6, 2016 / Notices
portions of the project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
The EA will present our independent
analysis of the issues. The EA will be
available in the public record through
eLibrary. Depending on the comments
received during the scoping process, we
may also publish and distribute the EA
to the public for an allotted comment
period. We will consider all comments
on the EA before making our
recommendations to the Commission.
To ensure we have the opportunity to
consider and address your comments,
please carefully follow the instructions
in the Public Participation section,
beginning on page [2].
With this notice, we are asking
agencies with jurisdiction by law and/
or special expertise with respect to the
environmental issues of this project to
formally cooperate with us in the
preparation of the EA.3 Agencies that
would like to request cooperating
agency status should follow the
instructions for filing comments
provided under the Public Participation
section of this notice.
Consultations Under Section 106 of the
National Historic Preservation Act
mstockstill on DSK3G9T082PROD with NOTICES
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, we are using this
notice to initiate consultation with the
applicable State Historic Preservation
Office. (SHPO), and to solicit their
views and those of other government
agencies, interested Indian tribes, and
the public on the project’s potential
effects on historic properties.4 We will
define the project-specific Area of
Potential Effects (APE) in consultation
with the SHPO as the project develops.
On natural gas facility projects, the APE
at a minimum encompasses all areas
subject to ground disturbance (examples
include construction right-of-way,
contractor/pipe storage yards,
compressor stations, and access roads).
Our EA for this project will document
our findings on the impacts on historic
properties and summarize the status of
consultations under section 106.
3 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
4 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, Part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
VerDate Sep<11>2014
17:39 Dec 05, 2016
Jkt 241001
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the project. We will
update the environmental mailing list as
the analysis proceeds to ensure that we
send the information related to this
environmental review to all individuals,
organizations, and government entities
interested in and/or potentially affected
by the proposed project.
If we publish and distribute the EA,
copies of the EA will be sent to the
environmental mailing list for public
review and comment. If you would
prefer to receive a paper copy of the
document instead of the CD version or
would like to remove your name from
the mailing list, please return the
attached Information Request (appendix
2).
Online Support at FercOnlineSupport@
ferc.gov or toll free at (866) 208–3676, or
for TTY, contact (202) 502–8659. The
eLibrary link also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Dated: November 29, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016–29218 Filed 12–5–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Becoming an Intervenor
[Docket No. CP17–18–000]
In addition to involvement in the EA
scoping process, you may want to
become an ‘‘intervenor’’ which is an
official party to the Commission’s
proceeding. Intervenors play a more
formal role in the process and are able
to file briefs, appear at hearings, and be
heard by the courts if they choose to
appeal the Commission’s final ruling.
An intervenor formally participates in
the proceeding by filing a request to
intervene. Instructions for becoming an
intervenor are in the ‘‘Document-less
Intervention Guide’’ under the ‘‘e-filing’’
link on the Commission’s Web site.
Motions to intervene are more fully
described at https://www.ferc.gov/
resources/guides/how-to/intervene.asp.
Columbia Gas Transmission, LLC;
Notice of Request Under Blanket
Authorization
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC Web
site at www.ferc.gov using the
‘‘eLibrary’’ link. Click on the eLibrary
link, click on ‘‘General Search’’ and
enter the docket number, excluding the
last three digits in the Docket Number
field (i.e., CP17–9–000). Be sure you
have selected an appropriate date range.
For assistance, please contact FERC
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
Take notice that on November 18,
2016, Columbia Gas Transmission, LLC
(Columbia), 5151 San Felipe, Suite
2500, Houston, Texas 77056, filed in
Docket No. CP17–18–000 a prior notice
request pursuant to sections 157.205
and 157.208 of the Commission’s
regulations under the Natural Gas Act
(NGA), and Columbia’s blanket
certificate issued in Docket No. CP83–
76–000, to construct and modify certain
facilities on its existing Line V located
in Holmes, Wayne, Stark, Carroll, and
Columbiana Counties, Ohio (Line V
Project). Columbia states that its Line V
Project involves the installation of bidirectional launcher/receivers allowing
Line V to be pigged for integrity
assessment of multiple high
consequence areas. The existing Line V
extends approximately 70.0 miles from
Holmes Compressor Station located in
Holmes County, Ohio to Dungannon
Measuring Station located in
Columbiana County, Ohio. Columbia
states that the proposed Line V Project
includes 45 modifications and estimates
the cost of the project to be $14.3
E:\FR\FM\06DEN1.SGM
06DEN1
mstockstill on DSK3G9T082PROD with NOTICES
Federal Register / Vol. 81, No. 234 / Tuesday, December 6, 2016 / Notices
million, all as more fully set forth in the
application which is on file with the
Commission and open to public
inspection. The filing may also be
viewed on the web at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov or toll free at (866) 208–3676, or
TTY, contact (202) 502–8659.
Any questions concerning this
application may be directed to Robert D.
Jackson, Manager, Certificates &
Regulatory Administration, Columbia
Gas Transmission, LLC, 700 Louisiana
Street, Suite 700, Houston, TX 77002–
2700, by telephone at (832) 320–5487, or
by email at robert_jackson@
transcanada.com.
Any person or the Commission’s staff
may, within 60 days after issuance of
the instant notice by the Commission,
file pursuant to Rule 214 of the
Commission’s Procedural Rules (18 CFR
385.214) a motion to intervene or notice
of intervention and pursuant to section
157.205 of the regulations under the
NGA (18 CFR 157.205), a protest to the
request. If no protest is filed within the
time allowed therefore, the proposed
activity shall be deemed to be
authorized effective the day after the
time allowed for filing a protest. If a
protest is filed and not withdrawn
within 30 days after the allowed time
for filing a protest, the instant request
shall be treated as an application for
authorization pursuant to section 7 of
the NGA.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: Complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding, or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
Persons who wish to comment only
on the environmental review of this
VerDate Sep<11>2014
17:39 Dec 05, 2016
Jkt 241001
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenters will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commenters,
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically should submit an original
and seven copies of the protest or
intervention to the Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
Dated: November 28, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016–29227 Filed 12–5–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[P–6764–038]
BMB Enterprises, Inc.; Notice of
Application Accepted for Filing and
Soliciting Comments, Motions To
Intervene, and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Amendment
of License.
b. Project No.: 6764–038.
c. Date Filed: July 18, 2016.
d. Applicant: BMB Enterprises, Inc.
e. Name of Project: Sixmile Creek
Hydroelectric Project.
f. Location: The project is located on
the Sixmile Creek in Sanpete County,
Utah.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Mr. Brad F.
Hutchings, BMB Enterprises, Inc., 282
North 1350 East, Bountiful, Utah 84010,
(801) 298–7383.
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
87925
i. FERC Contact: Anumzziatta
Purchiaroni, (202) 502–6191,
anumzziatta.purchiaroni@ferc.gov.
j. Deadline for filing comments,
motions to intervene, and protests is 30
days from the issuance of this notice by
the Commission. The Commission
strongly encourages electronic filing.
Please file comments, motions to
intervene, and protests using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–6764–038.
k. Description of Request: The
licensee is proposing to delete a portion
of the project transmission line that is
no longer needed for interconnection of
the project and change the point of
interconnection with Manti City. The
proposed changes are within the project
boundary and will have no impact on
federal lands.
l. Locations of the Applications: A
copy of the application is available for
inspection and reproduction at the
Commission’s Public Reference Room,
located at 888 First Street NE., Room
2A, Washington, DC 20426, or by calling
(202) 502–8371. The filing may also be
viewed on the Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
excluding the last three digits in the
docket number field to access the
document (i.e., P–6764). You may also
register online at https://www.ferc.gov/
docs-filing/esubscription.asp to be
notified via email of new filings and
issuances related to this or other
pending projects. For assistance, call
1–866–208–3676 or email
FERCOnlineSupport@ferc.gov, for TTY,
call (202) 502–8659.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Motions to Intervene or
Protests: Anyone may submit
comments, a motion to intervene, or a
protest in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
E:\FR\FM\06DEN1.SGM
06DEN1
Agencies
[Federal Register Volume 81, Number 234 (Tuesday, December 6, 2016)]
[Notices]
[Pages 87924-87925]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-29227]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP17-18-000]
Columbia Gas Transmission, LLC; Notice of Request Under Blanket
Authorization
Take notice that on November 18, 2016, Columbia Gas Transmission,
LLC (Columbia), 5151 San Felipe, Suite 2500, Houston, Texas 77056,
filed in Docket No. CP17-18-000 a prior notice request pursuant to
sections 157.205 and 157.208 of the Commission's regulations under the
Natural Gas Act (NGA), and Columbia's blanket certificate issued in
Docket No. CP83-76-000, to construct and modify certain facilities on
its existing Line V located in Holmes, Wayne, Stark, Carroll, and
Columbiana Counties, Ohio (Line V Project). Columbia states that its
Line V Project involves the installation of bi-directional launcher/
receivers allowing Line V to be pigged for integrity assessment of
multiple high consequence areas. The existing Line V extends
approximately 70.0 miles from Holmes Compressor Station located in
Holmes County, Ohio to Dungannon Measuring Station located in
Columbiana County, Ohio. Columbia states that the proposed Line V
Project includes 45 modifications and estimates the cost of the project
to be $14.3
[[Page 87925]]
million, all as more fully set forth in the application which is on
file with the Commission and open to public inspection. The filing may
also be viewed on the web at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, please
contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free
at (866) 208-3676, or TTY, contact (202) 502-8659.
Any questions concerning this application may be directed to Robert
D. Jackson, Manager, Certificates & Regulatory Administration, Columbia
Gas Transmission, LLC, 700 Louisiana Street, Suite 700, Houston, TX
77002-2700, by telephone at (832) 320-5487, or by email at
robert_jackson@transcanada.com.
Any person or the Commission's staff may, within 60 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice of intervention and pursuant to section 157.205 of
the regulations under the NGA (18 CFR 157.205), a protest to the
request. If no protest is filed within the time allowed therefore, the
proposed activity shall be deemed to be authorized effective the day
after the time allowed for filing a protest. If a protest is filed and
not withdrawn within 30 days after the allowed time for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to section 7 of the NGA.
Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9,
within 90 days of this Notice the Commission staff will either:
Complete its environmental assessment (EA) and place it into the
Commission's public record (eLibrary) for this proceeding, or issue a
Notice of Schedule for Environmental Review. If a Notice of Schedule
for Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the final environmental impact statement (FEIS) or EA for this
proposal. The filing of the EA in the Commission's public record for
this proceeding or the issuance of a Notice of Schedule for
Environmental Review will serve to notify federal and state agencies of
the timing for the completion of all necessary reviews, and the
subsequent need to complete all federal authorizations within 90 days
of the date of issuance of the Commission staff's FEIS or EA.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commenters will be
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with the Commission's environmental review process.
Environmental commenters will not be required to serve copies of filed
documents on all other parties. However, the non-party commenters, will
not receive copies of all documents filed by other parties or issued by
the Commission (except for the mailing of environmental documents
issued by the Commission) and will not have the right to seek court
review of the Commission's final order.
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the ``eFiling'' link
at https://www.ferc.gov. Persons unable to file electronically should
submit an original and seven copies of the protest or intervention to
the Federal Energy Regulatory Commission, 888 First Street NE.,
Washington, DC 20426.
Dated: November 28, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016-29227 Filed 12-5-16; 8:45 am]