ANR Pipeline Company; Notice of Intent To Prepare an Environmental Assessment for the Proposed Wisconsin South Expansion Project, and Request for Comments on Environmental Issues, 87922-87924 [2016-29218]

Download as PDF 87922 Federal Register / Vol. 81, No. 234 / Tuesday, December 6, 2016 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 11834–065] mstockstill on DSK3G9T082PROD with NOTICES Brookfield White Pine Hydro, LLC; Notice of Application Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Type of Application: Application for Temporary Variance of Minimum Flow Requirements. b. Project No.: 11834–065. c. Date Filed: November 23, 2016. d. Applicant: Brookfield White Pine Hydro, LLC (licensee). e. Name of Project: Upper and Middle Dams Storage Hydroelectric Project. f. Location: Rapid River in Oxford and Franklin counties, Maine. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Kelly Maloney, Manager, Licensing and Compliance, Brookfield White Pine Hydro LLC, 150 Main Street, Lewiston, ME 04240, Phone: (207) 755–5605. i. FERC Contact: Robert Ballantine, (202) 502–6289, or robert.ballantine@ ferc.gov. j. Deadline for filing comments, motions to intervene, protests, and recommendations is 30 days from the issuance date of this notice (by December 29, 2016). The Commission strongly encourages electronic filing. Please file motions to intervene, protests, comments, or recommendations using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. Please include the project number (P– 11834–065) on any comments, motions to intervene, protests, or recommendations filed. k. Description of Request: The licensee requests a temporary variance of the minimum flow requirements in the Rapid River below the Middle Dam VerDate Sep<11>2014 17:39 Dec 05, 2016 Jkt 241001 development due to drought conditions. License Article 402, in part, requires the licensee to release from September 16 through the start of the spring refill of Richardson Lake, a minimum flow of 472 cubic feet per second (cfs). The licensee explains that due to drought conditions, Richardson Lake is below its long term average. Considering a dry long term precipitation forecast and the impending winter freeze up, the licensee is concerned that the reservoir may not refill by spring as intended, which could cause additional water level and minimum flow issues in the spring of 2017. Therefore in order to conserve as much fall runoff as possible, the licensee is requesting to reduce the minimum flow to 200 cfs until April 23, 2017, at which time a minimum flow of 382 cfs would be released in accordance with the requirements of Article 402. l. Locations of the Application: A copy of the application is available for inspection and reproduction at the Commission’s Public Reference Room, located at 888 First Street NE., Room 2A, Washington, DC 20426, or by calling (202) 502–8371. This filing may also be viewed on the Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1–866–208–3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item (h) above. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Responsive Documents: Any filing must (1) bear in all capital letters the title PO 00000 Frm 00021 Fmt 4703 Sfmt 4703 ‘‘COMMENTS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’ as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). All comments, motions to intervene, or protests should relate to project works which are the subject of proposed action. Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application. If an intervener files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010. Dated: November 29, 2016. Kimberly D. Bose, Secretary. [FR Doc. 2016–29226 Filed 12–5–16; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP17–9–000] ANR Pipeline Company; Notice of Intent To Prepare an Environmental Assessment for the Proposed Wisconsin South Expansion Project, and Request for Comments on Environmental Issues The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the Wisconsin South Expansion Project (Project) involving replacement and expansion of existing aboveground facilities by ANR Pipeline Company (ANR) in the area west and southwest of E:\FR\FM\06DEN1.SGM 06DEN1 mstockstill on DSK3G9T082PROD with NOTICES Federal Register / Vol. 81, No. 234 / Tuesday, December 6, 2016 / Notices Lake Michigan. The Commission will use this EA in its decision-making process to determine whether the project is in the public convenience and necessity. This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies on the project. You can make a difference by providing us with your specific comments or concerns about the project. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. Your input will help the Commission staff determine what issues they need to evaluate in the EA. To ensure that your comments are timely and properly recorded, please send your comments so that the Commission receives them in Washington, DC, on or before December 29, 2016. If you sent comments on this project to the Commission before the opening of this docket on November 3, 2016, you will need to file those comments in Docket No. CP17–9–000 to ensure they are considered as part of this proceeding. This notice is being sent to the Commission’s current environmental mailing list for this project. State and local government representatives should notify their constituents of this proposed project and encourage them to comment on their areas of concern. If you are a landowner receiving this notice, a pipeline company representative may contact you about the acquisition of an easement to construct, operate, and maintain the proposed facilities. The company would seek to negotiate a mutually acceptable agreement. However, if the Commission approves the project, that approval conveys with it the right of eminent domain. Therefore, if easement negotiations fail to produce an agreement, the pipeline company could initiate condemnation proceedings where compensation would be determined in accordance with state law. ANR provided landowners within 0.5 mile of proposed expansion facilities with a fact sheet prepared by the FERC entitled ‘‘An Interstate Natural Gas Facility On My Land? What Do I Need To Know?’’ This fact sheet addresses a number of typically asked questions, including the use of eminent domain and how to participate in the Commission’s proceedings. It is also available for viewing on the FERC Web site (www.ferc.gov). VerDate Sep<11>2014 17:39 Dec 05, 2016 Jkt 241001 Public Participation For your convenience, there are three methods you can use to submit your comments to the Commission. The Commission encourages electronic filing of comments and has expert staff available to assist you at (202) 502–8258 or efiling@ferc.gov. Please carefully follow these instructions so that your comments are properly recorded. (1) You can file your comments electronically using the eComment feature on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. This is an easy method for submitting brief, text-only comments on a project; (2) You can file your comments electronically by using the eFiling feature on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ If you are filing a comment on a particular project, please select ‘‘Comment on a Filing’’ as the filing type; or (3) You can file a paper copy of your comments by mailing them to the following address. Be sure to reference the project docket number (CP17–9– 000) with your submission: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 20426. Summary of the Proposed Project ANR is proposing to expand ANR’s delivery by 230,950 dekatherms per day (Dth/d), into the Northern Illinois and Wisconsin market areas by modifying five existing ANR facilities, to meet growing natural gas demand and enhance ANR’s system reliability in Northern Illinois and Wisconsin. The Project would consist of the following facilities: 1. Install one new 6,130-horsepower (HP) Solar Centaur 50 compressor unit and appurtenant facilities at ANR’s existing Sandwich Compressor Station in Kendall County, Illinois; 2. increase capacity of the existing Hampshire Meter Station in Kane County, Illinois from the current 300 million cubic feet per day (MMCFD) to 500 MMCFD; 3. replace the existing 0.54-mile Line 332 Lateral located in Kane County, Illinois, which originates at the Hampshire Meter Station; 4. increase capacity of ANR’s existing Tiffany East Meter Station in Rock County, Wisconsin from the current 118 MMCFD to 237 MMCFD; and PO 00000 Frm 00022 Fmt 4703 Sfmt 4703 87923 5. Re-stage an existing Saturn 10 turbine compressor unit at ANR’s Kewaskum Compressor Station in Sheboygan County, Wisconsin. The general location of the project facilities is shown in appendix 1.1 Land Requirements for Construction Most of the Project impacts would occur within existing facilities in areas that have been previously disturbed or are currently in agricultural use. A total of 56.23 acres would be used as construction workspace, of which 46.30 acres are existing permanent easement and 9.45 acres would be restored to preexisting conditions after construction is completed. Approximately 0.16 acres would be converted to new permanent easement at the Hampshire Meter Station and 0.32 acres would be converted to new permanent easement for the Line 332 Lateral Replacement. The EA Process The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental impacts that could result from an action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. NEPA also requires us 2 to discover and address concerns the public may have about proposals. This process is referred to as ‘‘scoping.’’ The main goal of the scoping process is to focus the analysis in the EA on the important environmental issues. By this notice, the Commission requests public comments on the scope of the issues to address in the EA. We will consider all filed comments during the preparation of the EA. In the EA we will discuss impacts that could occur as a result of the construction and operation of the proposed project under these general headings: • Water resources, fisheries, and wetlands; • cultural resources; • vegetation and wildlife; • air quality and noise; • endangered and threatened species; • public safety; and • cumulative impacts We will also evaluate reasonable alternatives to the proposed project or 1 The appendices referenced in this notice will not appear in the Federal Register. Copies of appendices were sent to all those receiving this notice in the mail and are available at www.ferc.gov using the link called ‘‘eLibrary’’ or from the Commission’s Public Reference Room, 888 First Street NE., Washington, DC 20426, or call (202) 502–8371. For instructions on connecting to eLibrary, refer to the last page of this notice. 2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the environmental staff of the Commission’s Office of Energy Projects. E:\FR\FM\06DEN1.SGM 06DEN1 87924 Federal Register / Vol. 81, No. 234 / Tuesday, December 6, 2016 / Notices portions of the project, and make recommendations on how to lessen or avoid impacts on the various resource areas. The EA will present our independent analysis of the issues. The EA will be available in the public record through eLibrary. Depending on the comments received during the scoping process, we may also publish and distribute the EA to the public for an allotted comment period. We will consider all comments on the EA before making our recommendations to the Commission. To ensure we have the opportunity to consider and address your comments, please carefully follow the instructions in the Public Participation section, beginning on page [2]. With this notice, we are asking agencies with jurisdiction by law and/ or special expertise with respect to the environmental issues of this project to formally cooperate with us in the preparation of the EA.3 Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice. Consultations Under Section 106 of the National Historic Preservation Act mstockstill on DSK3G9T082PROD with NOTICES In accordance with the Advisory Council on Historic Preservation’s implementing regulations for section 106 of the National Historic Preservation Act, we are using this notice to initiate consultation with the applicable State Historic Preservation Office. (SHPO), and to solicit their views and those of other government agencies, interested Indian tribes, and the public on the project’s potential effects on historic properties.4 We will define the project-specific Area of Potential Effects (APE) in consultation with the SHPO as the project develops. On natural gas facility projects, the APE at a minimum encompasses all areas subject to ground disturbance (examples include construction right-of-way, contractor/pipe storage yards, compressor stations, and access roads). Our EA for this project will document our findings on the impacts on historic properties and summarize the status of consultations under section 106. 3 The Council on Environmental Quality regulations addressing cooperating agency responsibilities are at Title 40, Code of Federal Regulations, Part 1501.6. 4 The Advisory Council on Historic Preservation’s regulations are at Title 36, Code of Federal Regulations, Part 800. Those regulations define historic properties as any prehistoric or historic district, site, building, structure, or object included in or eligible for inclusion in the National Register of Historic Places. VerDate Sep<11>2014 17:39 Dec 05, 2016 Jkt 241001 Environmental Mailing List The environmental mailing list includes federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission’s regulations) who are potential right-of-way grantors, whose property may be used temporarily for project purposes, or who own homes within certain distances of aboveground facilities, and anyone who submits comments on the project. We will update the environmental mailing list as the analysis proceeds to ensure that we send the information related to this environmental review to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed project. If we publish and distribute the EA, copies of the EA will be sent to the environmental mailing list for public review and comment. If you would prefer to receive a paper copy of the document instead of the CD version or would like to remove your name from the mailing list, please return the attached Information Request (appendix 2). Online Support at FercOnlineSupport@ ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/docsfiling/esubscription.asp. Finally, public meetings or site visits will be posted on the Commission’s calendar located at www.ferc.gov/ EventCalendar/EventsList.aspx along with other related information. Dated: November 29, 2016. Kimberly D. Bose, Secretary. [FR Doc. 2016–29218 Filed 12–5–16; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Becoming an Intervenor [Docket No. CP17–18–000] In addition to involvement in the EA scoping process, you may want to become an ‘‘intervenor’’ which is an official party to the Commission’s proceeding. Intervenors play a more formal role in the process and are able to file briefs, appear at hearings, and be heard by the courts if they choose to appeal the Commission’s final ruling. An intervenor formally participates in the proceeding by filing a request to intervene. Instructions for becoming an intervenor are in the ‘‘Document-less Intervention Guide’’ under the ‘‘e-filing’’ link on the Commission’s Web site. Motions to intervene are more fully described at https://www.ferc.gov/ resources/guides/how-to/intervene.asp. Columbia Gas Transmission, LLC; Notice of Request Under Blanket Authorization Additional Information Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC Web site at www.ferc.gov using the ‘‘eLibrary’’ link. Click on the eLibrary link, click on ‘‘General Search’’ and enter the docket number, excluding the last three digits in the Docket Number field (i.e., CP17–9–000). Be sure you have selected an appropriate date range. For assistance, please contact FERC PO 00000 Frm 00023 Fmt 4703 Sfmt 4703 Take notice that on November 18, 2016, Columbia Gas Transmission, LLC (Columbia), 5151 San Felipe, Suite 2500, Houston, Texas 77056, filed in Docket No. CP17–18–000 a prior notice request pursuant to sections 157.205 and 157.208 of the Commission’s regulations under the Natural Gas Act (NGA), and Columbia’s blanket certificate issued in Docket No. CP83– 76–000, to construct and modify certain facilities on its existing Line V located in Holmes, Wayne, Stark, Carroll, and Columbiana Counties, Ohio (Line V Project). Columbia states that its Line V Project involves the installation of bidirectional launcher/receivers allowing Line V to be pigged for integrity assessment of multiple high consequence areas. The existing Line V extends approximately 70.0 miles from Holmes Compressor Station located in Holmes County, Ohio to Dungannon Measuring Station located in Columbiana County, Ohio. Columbia states that the proposed Line V Project includes 45 modifications and estimates the cost of the project to be $14.3 E:\FR\FM\06DEN1.SGM 06DEN1

Agencies

[Federal Register Volume 81, Number 234 (Tuesday, December 6, 2016)]
[Notices]
[Pages 87922-87924]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-29218]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP17-9-000]


ANR Pipeline Company; Notice of Intent To Prepare an 
Environmental Assessment for the Proposed Wisconsin South Expansion 
Project, and Request for Comments on Environmental Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Wisconsin South Expansion 
Project (Project) involving replacement and expansion of existing 
aboveground facilities by ANR Pipeline Company (ANR) in the area west 
and southwest of

[[Page 87923]]

Lake Michigan. The Commission will use this EA in its decision-making 
process to determine whether the project is in the public convenience 
and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the project. You can make a difference by providing us with 
your specific comments or concerns about the project. Your comments 
should focus on the potential environmental effects, reasonable 
alternatives, and measures to avoid or lessen environmental impacts. 
Your input will help the Commission staff determine what issues they 
need to evaluate in the EA. To ensure that your comments are timely and 
properly recorded, please send your comments so that the Commission 
receives them in Washington, DC, on or before December 29, 2016.
    If you sent comments on this project to the Commission before the 
opening of this docket on November 3, 2016, you will need to file those 
comments in Docket No. CP17-9-000 to ensure they are considered as part 
of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this proposed 
project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the proposed facilities. The company 
would seek to negotiate a mutually acceptable agreement. However, if 
the Commission approves the project, that approval conveys with it the 
right of eminent domain. Therefore, if easement negotiations fail to 
produce an agreement, the pipeline company could initiate condemnation 
proceedings where compensation would be determined in accordance with 
state law.
    ANR provided landowners within 0.5 mile of proposed expansion 
facilities with a fact sheet prepared by the FERC entitled ``An 
Interstate Natural Gas Facility On My Land? What Do I Need To Know?'' 
This fact sheet addresses a number of typically asked questions, 
including the use of eminent domain and how to participate in the 
Commission's proceedings. It is also available for viewing on the FERC 
Web site (www.ferc.gov).

Public Participation

    For your convenience, there are three methods you can use to submit 
your comments to the Commission. The Commission encourages electronic 
filing of comments and has expert staff available to assist you at 
(202) 502-8258 or efiling@ferc.gov. Please carefully follow these 
instructions so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
``eRegister.'' If you are filing a comment on a particular project, 
please select ``Comment on a Filing'' as the filing type; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address. Be sure to reference the project docket number 
(CP17-9-000) with your submission: Kimberly D. Bose, Secretary, Federal 
Energy Regulatory Commission, 888 First Street NE., Room 1A, 
Washington, DC 20426.

Summary of the Proposed Project

    ANR is proposing to expand ANR's delivery by 230,950 dekatherms per 
day (Dth/d), into the Northern Illinois and Wisconsin market areas by 
modifying five existing ANR facilities, to meet growing natural gas 
demand and enhance ANR's system reliability in Northern Illinois and 
Wisconsin.
    The Project would consist of the following facilities:
    1. Install one new 6,130-horsepower (HP) Solar Centaur 50 
compressor unit and appurtenant facilities at ANR's existing Sandwich 
Compressor Station in Kendall County, Illinois;
    2. increase capacity of the existing Hampshire Meter Station in 
Kane County, Illinois from the current 300 million cubic feet per day 
(MMCFD) to 500 MMCFD;
    3. replace the existing 0.54-mile Line 332 Lateral located in Kane 
County, Illinois, which originates at the Hampshire Meter Station;
    4. increase capacity of ANR's existing Tiffany East Meter Station 
in Rock County, Wisconsin from the current 118 MMCFD to 237 MMCFD; and
    5. Re-stage an existing Saturn 10 turbine compressor unit at ANR's 
Kewaskum Compressor Station in Sheboygan County, Wisconsin.
    The general location of the project facilities is shown in appendix 
1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of appendices were sent to all those 
receiving this notice in the mail and are available at www.ferc.gov 
using the link called ``eLibrary'' or from the Commission's Public 
Reference Room, 888 First Street NE., Washington, DC 20426, or call 
(202) 502-8371. For instructions on connecting to eLibrary, refer to 
the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    Most of the Project impacts would occur within existing facilities 
in areas that have been previously disturbed or are currently in 
agricultural use. A total of 56.23 acres would be used as construction 
workspace, of which 46.30 acres are existing permanent easement and 
9.45 acres would be restored to pre-existing conditions after 
construction is completed. Approximately 0.16 acres would be converted 
to new permanent easement at the Hampshire Meter Station and 0.32 acres 
would be converted to new permanent easement for the Line 332 Lateral 
Replacement.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. NEPA also requires us 
\2\ to discover and address concerns the public may have about 
proposals. This process is referred to as ``scoping.'' The main goal of 
the scoping process is to focus the analysis in the EA on the important 
environmental issues. By this notice, the Commission requests public 
comments on the scope of the issues to address in the EA. We will 
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------

    \2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EA we will discuss impacts that could occur as a result of 
the construction and operation of the proposed project under these 
general headings:
     Water resources, fisheries, and wetlands;
     cultural resources;
     vegetation and wildlife;
     air quality and noise;
     endangered and threatened species;
     public safety; and
     cumulative impacts
    We will also evaluate reasonable alternatives to the proposed 
project or

[[Page 87924]]

portions of the project, and make recommendations on how to lessen or 
avoid impacts on the various resource areas.
    The EA will present our independent analysis of the issues. The EA 
will be available in the public record through eLibrary. Depending on 
the comments received during the scoping process, we may also publish 
and distribute the EA to the public for an allotted comment period. We 
will consider all comments on the EA before making our recommendations 
to the Commission. To ensure we have the opportunity to consider and 
address your comments, please carefully follow the instructions in the 
Public Participation section, beginning on page [2].
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the environmental issues of 
this project to formally cooperate with us in the preparation of the 
EA.\3\ Agencies that would like to request cooperating agency status 
should follow the instructions for filing comments provided under the 
Public Participation section of this notice.
---------------------------------------------------------------------------

    \3\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with the applicable State Historic Preservation Office. (SHPO), and to 
solicit their views and those of other government agencies, interested 
Indian tribes, and the public on the project's potential effects on 
historic properties.\4\ We will define the project-specific Area of 
Potential Effects (APE) in consultation with the SHPO as the project 
develops. On natural gas facility projects, the APE at a minimum 
encompasses all areas subject to ground disturbance (examples include 
construction right-of-way, contractor/pipe storage yards, compressor 
stations, and access roads). Our EA for this project will document our 
findings on the impacts on historic properties and summarize the status 
of consultations under section 106.
---------------------------------------------------------------------------

    \4\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the project. We will update the environmental mailing list 
as the analysis proceeds to ensure that we send the information related 
to this environmental review to all individuals, organizations, and 
government entities interested in and/or potentially affected by the 
proposed project.
    If we publish and distribute the EA, copies of the EA will be sent 
to the environmental mailing list for public review and comment. If you 
would prefer to receive a paper copy of the document instead of the CD 
version or would like to remove your name from the mailing list, please 
return the attached Information Request (appendix 2).

Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want 
to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are in 
the ``Document-less Intervention Guide'' under the ``e-filing'' link on 
the Commission's Web site. Motions to intervene are more fully 
described at https://www.ferc.gov/resources/guides/how-to/intervene.asp.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number, 
excluding the last three digits in the Docket Number field (i.e., CP17-
9-000). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

    Dated: November 29, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016-29218 Filed 12-5-16; 8:45 am]
 BILLING CODE 6717-01-P