ANR Pipeline Company; Notice of Intent To Prepare an Environmental Assessment for the Proposed Wisconsin South Expansion Project, and Request for Comments on Environmental Issues, 87922-87924 [2016-29218]
Download as PDF
87922
Federal Register / Vol. 81, No. 234 / Tuesday, December 6, 2016 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 11834–065]
mstockstill on DSK3G9T082PROD with NOTICES
Brookfield White Pine Hydro, LLC;
Notice of Application Accepted for
Filing, Soliciting Comments, Motions
To Intervene, and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Application
for Temporary Variance of Minimum
Flow Requirements.
b. Project No.: 11834–065.
c. Date Filed: November 23, 2016.
d. Applicant: Brookfield White Pine
Hydro, LLC (licensee).
e. Name of Project: Upper and Middle
Dams Storage Hydroelectric Project.
f. Location: Rapid River in Oxford and
Franklin counties, Maine.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Kelly Maloney,
Manager, Licensing and Compliance,
Brookfield White Pine Hydro LLC, 150
Main Street, Lewiston, ME 04240,
Phone: (207) 755–5605.
i. FERC Contact: Robert Ballantine,
(202) 502–6289, or robert.ballantine@
ferc.gov.
j. Deadline for filing comments,
motions to intervene, protests, and
recommendations is 30 days from the
issuance date of this notice (by
December 29, 2016). The Commission
strongly encourages electronic filing.
Please file motions to intervene,
protests, comments, or
recommendations using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
Please include the project number (P–
11834–065) on any comments, motions
to intervene, protests, or
recommendations filed.
k. Description of Request: The
licensee requests a temporary variance
of the minimum flow requirements in
the Rapid River below the Middle Dam
VerDate Sep<11>2014
17:39 Dec 05, 2016
Jkt 241001
development due to drought conditions.
License Article 402, in part, requires the
licensee to release from September 16
through the start of the spring refill of
Richardson Lake, a minimum flow of
472 cubic feet per second (cfs). The
licensee explains that due to drought
conditions, Richardson Lake is below its
long term average. Considering a dry
long term precipitation forecast and the
impending winter freeze up, the
licensee is concerned that the reservoir
may not refill by spring as intended,
which could cause additional water
level and minimum flow issues in the
spring of 2017. Therefore in order to
conserve as much fall runoff as possible,
the licensee is requesting to reduce the
minimum flow to 200 cfs until April 23,
2017, at which time a minimum flow of
382 cfs would be released in accordance
with the requirements of Article 402.
l. Locations of the Application: A
copy of the application is available for
inspection and reproduction at the
Commission’s Public Reference Room,
located at 888 First Street NE., Room
2A, Washington, DC 20426, or by calling
(202) 502–8371. This filing may also be
viewed on the Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
excluding the last three digits in the
docket number field to access the
document. You may also register online
at https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208–3676 or
email FERCOnlineSupport@ferc.gov, for
TTY, call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item (h)
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
o. Filing and Service of Responsive
Documents: Any filing must (1) bear in
all capital letters the title
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
‘‘COMMENTS’’, ‘‘PROTEST’’, or
‘‘MOTION TO INTERVENE’’ as
applicable; (2) set forth in the heading
the name of the applicant and the
project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. All
comments, motions to intervene, or
protests must set forth their evidentiary
basis and otherwise comply with the
requirements of 18 CFR 4.34(b). All
comments, motions to intervene, or
protests should relate to project works
which are the subject of proposed
action. Agencies may obtain copies of
the application directly from the
applicant. A copy of any protest or
motion to intervene must be served
upon each representative of the
applicant specified in the particular
application. If an intervener files
comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency. A copy of all
other filings in reference to this
application must be accompanied by
proof of service on all persons listed in
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
Dated: November 29, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016–29226 Filed 12–5–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP17–9–000]
ANR Pipeline Company; Notice of
Intent To Prepare an Environmental
Assessment for the Proposed
Wisconsin South Expansion Project,
and Request for Comments on
Environmental Issues
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Wisconsin South Expansion Project
(Project) involving replacement and
expansion of existing aboveground
facilities by ANR Pipeline Company
(ANR) in the area west and southwest of
E:\FR\FM\06DEN1.SGM
06DEN1
mstockstill on DSK3G9T082PROD with NOTICES
Federal Register / Vol. 81, No. 234 / Tuesday, December 6, 2016 / Notices
Lake Michigan. The Commission will
use this EA in its decision-making
process to determine whether the
project is in the public convenience and
necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the project.
You can make a difference by providing
us with your specific comments or
concerns about the project. Your
comments should focus on the potential
environmental effects, reasonable
alternatives, and measures to avoid or
lessen environmental impacts. Your
input will help the Commission staff
determine what issues they need to
evaluate in the EA. To ensure that your
comments are timely and properly
recorded, please send your comments so
that the Commission receives them in
Washington, DC, on or before December
29, 2016.
If you sent comments on this project
to the Commission before the opening of
this docket on November 3, 2016, you
will need to file those comments in
Docket No. CP17–9–000 to ensure they
are considered as part of this
proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives should
notify their constituents of this
proposed project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The company would
seek to negotiate a mutually acceptable
agreement. However, if the Commission
approves the project, that approval
conveys with it the right of eminent
domain. Therefore, if easement
negotiations fail to produce an
agreement, the pipeline company could
initiate condemnation proceedings
where compensation would be
determined in accordance with state
law.
ANR provided landowners within 0.5
mile of proposed expansion facilities
with a fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ This fact sheet addresses a
number of typically asked questions,
including the use of eminent domain
and how to participate in the
Commission’s proceedings. It is also
available for viewing on the FERC Web
site (www.ferc.gov).
VerDate Sep<11>2014
17:39 Dec 05, 2016
Jkt 241001
Public Participation
For your convenience, there are three
methods you can use to submit your
comments to the Commission. The
Commission encourages electronic filing
of comments and has expert staff
available to assist you at (202) 502–8258
or efiling@ferc.gov. Please carefully
follow these instructions so that your
comments are properly recorded.
(1) You can file your comments
electronically using the eComment
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. This is an easy
method for submitting brief, text-only
comments on a project;
(2) You can file your comments
electronically by using the eFiling
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. With eFiling,
you can provide comments in a variety
of formats by attaching them as a file
with your submission. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ If you are filing
a comment on a particular project,
please select ‘‘Comment on a Filing’’ as
the filing type; or
(3) You can file a paper copy of your
comments by mailing them to the
following address. Be sure to reference
the project docket number (CP17–9–
000) with your submission: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Room 1A, Washington, DC 20426.
Summary of the Proposed Project
ANR is proposing to expand ANR’s
delivery by 230,950 dekatherms per day
(Dth/d), into the Northern Illinois and
Wisconsin market areas by modifying
five existing ANR facilities, to meet
growing natural gas demand and
enhance ANR’s system reliability in
Northern Illinois and Wisconsin.
The Project would consist of the
following facilities:
1. Install one new 6,130-horsepower
(HP) Solar Centaur 50 compressor unit
and appurtenant facilities at ANR’s
existing Sandwich Compressor Station
in Kendall County, Illinois;
2. increase capacity of the existing
Hampshire Meter Station in Kane
County, Illinois from the current 300
million cubic feet per day (MMCFD) to
500 MMCFD;
3. replace the existing 0.54-mile Line
332 Lateral located in Kane County,
Illinois, which originates at the
Hampshire Meter Station;
4. increase capacity of ANR’s existing
Tiffany East Meter Station in Rock
County, Wisconsin from the current 118
MMCFD to 237 MMCFD; and
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
87923
5. Re-stage an existing Saturn 10
turbine compressor unit at ANR’s
Kewaskum Compressor Station in
Sheboygan County, Wisconsin.
The general location of the project
facilities is shown in appendix 1.1
Land Requirements for Construction
Most of the Project impacts would
occur within existing facilities in areas
that have been previously disturbed or
are currently in agricultural use. A total
of 56.23 acres would be used as
construction workspace, of which 46.30
acres are existing permanent easement
and 9.45 acres would be restored to preexisting conditions after construction is
completed. Approximately 0.16 acres
would be converted to new permanent
easement at the Hampshire Meter
Station and 0.32 acres would be
converted to new permanent easement
for the Line 332 Lateral Replacement.
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us 2 to
discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping.’’ The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
notice, the Commission requests public
comments on the scope of the issues to
address in the EA. We will consider all
filed comments during the preparation
of the EA.
In the EA we will discuss impacts that
could occur as a result of the
construction and operation of the
proposed project under these general
headings:
• Water resources, fisheries, and
wetlands;
• cultural resources;
• vegetation and wildlife;
• air quality and noise;
• endangered and threatened species;
• public safety; and
• cumulative impacts
We will also evaluate reasonable
alternatives to the proposed project or
1 The appendices referenced in this notice will
not appear in the Federal Register. Copies of
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’ or from the
Commission’s Public Reference Room, 888 First
Street NE., Washington, DC 20426, or call (202)
502–8371. For instructions on connecting to
eLibrary, refer to the last page of this notice.
2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the
environmental staff of the Commission’s Office of
Energy Projects.
E:\FR\FM\06DEN1.SGM
06DEN1
87924
Federal Register / Vol. 81, No. 234 / Tuesday, December 6, 2016 / Notices
portions of the project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
The EA will present our independent
analysis of the issues. The EA will be
available in the public record through
eLibrary. Depending on the comments
received during the scoping process, we
may also publish and distribute the EA
to the public for an allotted comment
period. We will consider all comments
on the EA before making our
recommendations to the Commission.
To ensure we have the opportunity to
consider and address your comments,
please carefully follow the instructions
in the Public Participation section,
beginning on page [2].
With this notice, we are asking
agencies with jurisdiction by law and/
or special expertise with respect to the
environmental issues of this project to
formally cooperate with us in the
preparation of the EA.3 Agencies that
would like to request cooperating
agency status should follow the
instructions for filing comments
provided under the Public Participation
section of this notice.
Consultations Under Section 106 of the
National Historic Preservation Act
mstockstill on DSK3G9T082PROD with NOTICES
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, we are using this
notice to initiate consultation with the
applicable State Historic Preservation
Office. (SHPO), and to solicit their
views and those of other government
agencies, interested Indian tribes, and
the public on the project’s potential
effects on historic properties.4 We will
define the project-specific Area of
Potential Effects (APE) in consultation
with the SHPO as the project develops.
On natural gas facility projects, the APE
at a minimum encompasses all areas
subject to ground disturbance (examples
include construction right-of-way,
contractor/pipe storage yards,
compressor stations, and access roads).
Our EA for this project will document
our findings on the impacts on historic
properties and summarize the status of
consultations under section 106.
3 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
4 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, Part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
VerDate Sep<11>2014
17:39 Dec 05, 2016
Jkt 241001
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the project. We will
update the environmental mailing list as
the analysis proceeds to ensure that we
send the information related to this
environmental review to all individuals,
organizations, and government entities
interested in and/or potentially affected
by the proposed project.
If we publish and distribute the EA,
copies of the EA will be sent to the
environmental mailing list for public
review and comment. If you would
prefer to receive a paper copy of the
document instead of the CD version or
would like to remove your name from
the mailing list, please return the
attached Information Request (appendix
2).
Online Support at FercOnlineSupport@
ferc.gov or toll free at (866) 208–3676, or
for TTY, contact (202) 502–8659. The
eLibrary link also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Dated: November 29, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016–29218 Filed 12–5–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Becoming an Intervenor
[Docket No. CP17–18–000]
In addition to involvement in the EA
scoping process, you may want to
become an ‘‘intervenor’’ which is an
official party to the Commission’s
proceeding. Intervenors play a more
formal role in the process and are able
to file briefs, appear at hearings, and be
heard by the courts if they choose to
appeal the Commission’s final ruling.
An intervenor formally participates in
the proceeding by filing a request to
intervene. Instructions for becoming an
intervenor are in the ‘‘Document-less
Intervention Guide’’ under the ‘‘e-filing’’
link on the Commission’s Web site.
Motions to intervene are more fully
described at https://www.ferc.gov/
resources/guides/how-to/intervene.asp.
Columbia Gas Transmission, LLC;
Notice of Request Under Blanket
Authorization
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC Web
site at www.ferc.gov using the
‘‘eLibrary’’ link. Click on the eLibrary
link, click on ‘‘General Search’’ and
enter the docket number, excluding the
last three digits in the Docket Number
field (i.e., CP17–9–000). Be sure you
have selected an appropriate date range.
For assistance, please contact FERC
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
Take notice that on November 18,
2016, Columbia Gas Transmission, LLC
(Columbia), 5151 San Felipe, Suite
2500, Houston, Texas 77056, filed in
Docket No. CP17–18–000 a prior notice
request pursuant to sections 157.205
and 157.208 of the Commission’s
regulations under the Natural Gas Act
(NGA), and Columbia’s blanket
certificate issued in Docket No. CP83–
76–000, to construct and modify certain
facilities on its existing Line V located
in Holmes, Wayne, Stark, Carroll, and
Columbiana Counties, Ohio (Line V
Project). Columbia states that its Line V
Project involves the installation of bidirectional launcher/receivers allowing
Line V to be pigged for integrity
assessment of multiple high
consequence areas. The existing Line V
extends approximately 70.0 miles from
Holmes Compressor Station located in
Holmes County, Ohio to Dungannon
Measuring Station located in
Columbiana County, Ohio. Columbia
states that the proposed Line V Project
includes 45 modifications and estimates
the cost of the project to be $14.3
E:\FR\FM\06DEN1.SGM
06DEN1
Agencies
[Federal Register Volume 81, Number 234 (Tuesday, December 6, 2016)]
[Notices]
[Pages 87922-87924]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-29218]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP17-9-000]
ANR Pipeline Company; Notice of Intent To Prepare an
Environmental Assessment for the Proposed Wisconsin South Expansion
Project, and Request for Comments on Environmental Issues
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Wisconsin South Expansion
Project (Project) involving replacement and expansion of existing
aboveground facilities by ANR Pipeline Company (ANR) in the area west
and southwest of
[[Page 87923]]
Lake Michigan. The Commission will use this EA in its decision-making
process to determine whether the project is in the public convenience
and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the project. You can make a difference by providing us with
your specific comments or concerns about the project. Your comments
should focus on the potential environmental effects, reasonable
alternatives, and measures to avoid or lessen environmental impacts.
Your input will help the Commission staff determine what issues they
need to evaluate in the EA. To ensure that your comments are timely and
properly recorded, please send your comments so that the Commission
receives them in Washington, DC, on or before December 29, 2016.
If you sent comments on this project to the Commission before the
opening of this docket on November 3, 2016, you will need to file those
comments in Docket No. CP17-9-000 to ensure they are considered as part
of this proceeding.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this proposed
project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the proposed facilities. The company
would seek to negotiate a mutually acceptable agreement. However, if
the Commission approves the project, that approval conveys with it the
right of eminent domain. Therefore, if easement negotiations fail to
produce an agreement, the pipeline company could initiate condemnation
proceedings where compensation would be determined in accordance with
state law.
ANR provided landowners within 0.5 mile of proposed expansion
facilities with a fact sheet prepared by the FERC entitled ``An
Interstate Natural Gas Facility On My Land? What Do I Need To Know?''
This fact sheet addresses a number of typically asked questions,
including the use of eminent domain and how to participate in the
Commission's proceedings. It is also available for viewing on the FERC
Web site (www.ferc.gov).
Public Participation
For your convenience, there are three methods you can use to submit
your comments to the Commission. The Commission encourages electronic
filing of comments and has expert staff available to assist you at
(202) 502-8258 or efiling@ferc.gov. Please carefully follow these
instructions so that your comments are properly recorded.
(1) You can file your comments electronically using the eComment
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. This is an easy method for submitting brief,
text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. With eFiling, you can provide comments in a
variety of formats by attaching them as a file with your submission.
New eFiling users must first create an account by clicking on
``eRegister.'' If you are filing a comment on a particular project,
please select ``Comment on a Filing'' as the filing type; or
(3) You can file a paper copy of your comments by mailing them to
the following address. Be sure to reference the project docket number
(CP17-9-000) with your submission: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888 First Street NE., Room 1A,
Washington, DC 20426.
Summary of the Proposed Project
ANR is proposing to expand ANR's delivery by 230,950 dekatherms per
day (Dth/d), into the Northern Illinois and Wisconsin market areas by
modifying five existing ANR facilities, to meet growing natural gas
demand and enhance ANR's system reliability in Northern Illinois and
Wisconsin.
The Project would consist of the following facilities:
1. Install one new 6,130-horsepower (HP) Solar Centaur 50
compressor unit and appurtenant facilities at ANR's existing Sandwich
Compressor Station in Kendall County, Illinois;
2. increase capacity of the existing Hampshire Meter Station in
Kane County, Illinois from the current 300 million cubic feet per day
(MMCFD) to 500 MMCFD;
3. replace the existing 0.54-mile Line 332 Lateral located in Kane
County, Illinois, which originates at the Hampshire Meter Station;
4. increase capacity of ANR's existing Tiffany East Meter Station
in Rock County, Wisconsin from the current 118 MMCFD to 237 MMCFD; and
5. Re-stage an existing Saturn 10 turbine compressor unit at ANR's
Kewaskum Compressor Station in Sheboygan County, Wisconsin.
The general location of the project facilities is shown in appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of appendices were sent to all those
receiving this notice in the mail and are available at www.ferc.gov
using the link called ``eLibrary'' or from the Commission's Public
Reference Room, 888 First Street NE., Washington, DC 20426, or call
(202) 502-8371. For instructions on connecting to eLibrary, refer to
the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Construction
Most of the Project impacts would occur within existing facilities
in areas that have been previously disturbed or are currently in
agricultural use. A total of 56.23 acres would be used as construction
workspace, of which 46.30 acres are existing permanent easement and
9.45 acres would be restored to pre-existing conditions after
construction is completed. Approximately 0.16 acres would be converted
to new permanent easement at the Hampshire Meter Station and 0.32 acres
would be converted to new permanent easement for the Line 332 Lateral
Replacement.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
\2\ to discover and address concerns the public may have about
proposals. This process is referred to as ``scoping.'' The main goal of
the scoping process is to focus the analysis in the EA on the important
environmental issues. By this notice, the Commission requests public
comments on the scope of the issues to address in the EA. We will
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------
\2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EA we will discuss impacts that could occur as a result of
the construction and operation of the proposed project under these
general headings:
Water resources, fisheries, and wetlands;
cultural resources;
vegetation and wildlife;
air quality and noise;
endangered and threatened species;
public safety; and
cumulative impacts
We will also evaluate reasonable alternatives to the proposed
project or
[[Page 87924]]
portions of the project, and make recommendations on how to lessen or
avoid impacts on the various resource areas.
The EA will present our independent analysis of the issues. The EA
will be available in the public record through eLibrary. Depending on
the comments received during the scoping process, we may also publish
and distribute the EA to the public for an allotted comment period. We
will consider all comments on the EA before making our recommendations
to the Commission. To ensure we have the opportunity to consider and
address your comments, please carefully follow the instructions in the
Public Participation section, beginning on page [2].
With this notice, we are asking agencies with jurisdiction by law
and/or special expertise with respect to the environmental issues of
this project to formally cooperate with us in the preparation of the
EA.\3\ Agencies that would like to request cooperating agency status
should follow the instructions for filing comments provided under the
Public Participation section of this notice.
---------------------------------------------------------------------------
\3\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
---------------------------------------------------------------------------
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, we are using this notice to initiate consultation
with the applicable State Historic Preservation Office. (SHPO), and to
solicit their views and those of other government agencies, interested
Indian tribes, and the public on the project's potential effects on
historic properties.\4\ We will define the project-specific Area of
Potential Effects (APE) in consultation with the SHPO as the project
develops. On natural gas facility projects, the APE at a minimum
encompasses all areas subject to ground disturbance (examples include
construction right-of-way, contractor/pipe storage yards, compressor
stations, and access roads). Our EA for this project will document our
findings on the impacts on historic properties and summarize the status
of consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project. We will update the environmental mailing list
as the analysis proceeds to ensure that we send the information related
to this environmental review to all individuals, organizations, and
government entities interested in and/or potentially affected by the
proposed project.
If we publish and distribute the EA, copies of the EA will be sent
to the environmental mailing list for public review and comment. If you
would prefer to receive a paper copy of the document instead of the CD
version or would like to remove your name from the mailing list, please
return the attached Information Request (appendix 2).
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an ``intervenor'' which is an official party to the
Commission's proceeding. Intervenors play a more formal role in the
process and are able to file briefs, appear at hearings, and be heard
by the courts if they choose to appeal the Commission's final ruling.
An intervenor formally participates in the proceeding by filing a
request to intervene. Instructions for becoming an intervenor are in
the ``Document-less Intervention Guide'' under the ``e-filing'' link on
the Commission's Web site. Motions to intervene are more fully
described at https://www.ferc.gov/resources/guides/how-to/intervene.asp.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number,
excluding the last three digits in the Docket Number field (i.e., CP17-
9-000). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Dated: November 29, 2016.
Kimberly D. Bose,
Secretary.