Drawbridge Operation Regulation; Great Channel, New Jersey Intracoastal Waterway, Stone Harbor, NJ, 79393 [2016-27281]

Download as PDF Federal Register / Vol. 81, No. 219 / Monday, November 14, 2016 / Rules and Regulations reviewed by the Office of Management and Budget (OMB). This action will not have substantial direct effects on the States, on the relationship between the national government and the States, or on the distribution of power and responsibilities among the various levels of government. Therefore, in accordance with Executive Order 13132 (Federalism) it is determined that this action does not have sufficient federalism implications to warrant the preparation of a Federalism Assessment. As noted above, this action is an order, not a rule. Accordingly, the Congressional Review Act (CRA) is inapplicable, as it applies only to rules. However, if this were a rule, pursuant to the Congressional Review Act, ‘‘any rule for which an agency for good cause finds that notice and public procedure thereon are impracticable, unnecessary, or contrary to the public interest, shall take effect at such time as the federal agency promulgating the rule determines.’’ 5 U.S.C. 808(2). It is in the public interest to schedule this substance immediately because it poses a public health risk. This temporary scheduling action is taken pursuant to 21 U.S.C. 811(h), which is specifically designed to enable the DEA to act in an expeditious manner to avoid an imminent hazard to the public safety. 21 U.S.C. 811(h) exempts the temporary scheduling order from standard notice and comment rulemaking procedures to ensure that the process moves swiftly. For the same reasons that underlie 21 U.S.C. 811(h), that is, the DEA’s need to move quickly to place this substance into schedule I because it poses an imminent hazard to the public safety and it would be contrary to the public interest to delay implementation of the temporary scheduling order. Therefore, this order shall take effect immediately upon its publication. The DEA has submitted a copy of this final order to both Houses of Congress and to the Comptroller General, although such filing is not required under the Small Business Regulatory Enforcement Fairness Act of 1996 (Congressional Review Act), 5 U.S.C. 801–808, because, as noted above, this action is an order, not a rule. Lhorne on DSK30JT082PROD with RULES List of Subjects in 21 CFR Part 1308 Administrative practice and procedure, Drug traffic control, Reporting and recordkeeping requirements. For the reasons set out above, the DEA amends 21 CFR part 1308 as follows: VerDate Sep<11>2014 15:02 Nov 10, 2016 Jkt 241001 79393 Click on Open Docket Folder on the line associated with this deviation. FOR FURTHER INFORMATION CONTACT: If ■ 1. The authority citation for part 1308 you have questions on this temporary continues to read as follows: deviation, call or email Mr. Hal R. Pitts, Authority: 21 U.S.C. 811, 812, 871(b), Bridge Administration Branch Fifth unless otherwise noted. District, Coast Guard, telephone 757– 398–6222, email Hal.R.Pitts@uscg.mil. ■ 2. Amend § 1308.11 by adding SUPPLEMENTARY INFORMATION: The paragraph (h)(18) to read as follows: County of Cape May, NJ, that owns and § 1308.11 Schedule I. operates the Stone Harbor Boulevard * * * * * (CR657) Bridge across the Great (h) * * * Channel, mile 102.0, New Jersey (18) 3,4-Dichloro-N-[2Intracoastal Waterway, at Stone Harbor, (dimethylamino)cyclohexyl]-NNJ, has requested a temporary deviation methylbenzamide, its isomers, from the current operating regulations to esters, ethers, salts and salts of avoid bridge failure and perform isomers, esters and ethers emergency repairs to the bridge, due to (Other name: U–47700) ............. (9547) a serious crack in one of two main * * * * * bridge girders, causing the bridge to be unsafe for vehicular traffic and Dated: November 7, 2016. movement of the bascule spans. The Chuck Rosenberg, bridge is a bascule drawbridge and has Acting Administrator. a vertical clearance in the closed [FR Doc. 2016–27357 Filed 11–10–16; 8:45 am] position of 10 feet above mean high BILLING CODE 4410–09–P water. The current operating schedule is set out in 33 CFR 117.733(h). Under this DEPARTMENT OF HOMELAND temporary deviation, the bridge will SECURITY remain in the closed-to-navigation position until 4 p.m. on December 2, Coast Guard 2016. The Great Channel, New Jersey 33 CFR Part 117 Intracoastal Waterway is used by a [Docket No. USCG–2016–1008] variety of vessels including small public vessels, small commercial vessels, tug Drawbridge Operation Regulation; and barge traffic, and recreational Great Channel, New Jersey vessels. The Coast Guard has carefully Intracoastal Waterway, Stone Harbor, considered the nature and volume of NJ vessel traffic on the waterway in publishing this temporary deviation. AGENCY: Coast Guard, DHS. Vessels able to safely pass through the ACTION: Notice of deviation from bridge in the closed position may do so drawbridge regulation. at any time. The bridge will not be able to open for emergencies and there is no SUMMARY: The Coast Guard has issued a immediate alternate route for vessels to temporary deviation from the operating pass. The Coast Guard will also inform schedule that governs the Stone Harbor the users of the waterways through our Boulevard (CR657) Bridge across the Local and Broadcast Notices to Mariners Great Channel, mile 102.0, New Jersey Intracoastal Waterway, at Stone Harbor, of the change in operating schedule for the bridge so that vessel operators can NJ. This deviation is necessary to avoid arrange their transit to minimize any bridge failure and perform emergency bridge repairs. This deviation allows the impact caused by the temporary deviation. bridge to remain in the closed-toIn accordance with 33 CFR 117.35(e), navigation position. the drawbridge must return to its regular DATES: This deviation is effective operating schedule immediately at the without actual notice from November 14, 2016 through 4 p.m. on December 2, end of the effective period of this temporary deviation. This deviation 2016. For the purposes of enforcement, from the operating regulations is actual notice will be used from authorized under 33 CFR 117.35. November 8, 2016, until November 14, Dated: November 8, 2016. 2016. Hal R. Pitts, ADDRESSES: The docket for this Bridge Program Manager, Fifth Coast Guard deviation, [USCG–2016–1008] is available at https://www.regulations.gov. District. [FR Doc. 2016–27281 Filed 11–10–16; 8:45 am] Type the docket number in the ‘‘SEARCH’’ box and click ‘‘SEARCH’’. BILLING CODE 9110–04–P PART 1308—SCHEDULES OF CONTROLLED SUBSTANCES PO 00000 Frm 00013 Fmt 4700 Sfmt 9990 E:\FR\FM\14NOR1.SGM 14NOR1

Agencies

[Federal Register Volume 81, Number 219 (Monday, November 14, 2016)]
[Rules and Regulations]
[Page 79393]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-27281]


=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF HOMELAND SECURITY

Coast Guard

33 CFR Part 117

[Docket No. USCG-2016-1008]


Drawbridge Operation Regulation; Great Channel, New Jersey 
Intracoastal Waterway, Stone Harbor, NJ

AGENCY: Coast Guard, DHS.

ACTION: Notice of deviation from drawbridge regulation.

-----------------------------------------------------------------------

SUMMARY: The Coast Guard has issued a temporary deviation from the 
operating schedule that governs the Stone Harbor Boulevard (CR657) 
Bridge across the Great Channel, mile 102.0, New Jersey Intracoastal 
Waterway, at Stone Harbor, NJ. This deviation is necessary to avoid 
bridge failure and perform emergency bridge repairs. This deviation 
allows the bridge to remain in the closed-to-navigation position.

DATES: This deviation is effective without actual notice from November 
14, 2016 through 4 p.m. on December 2, 2016. For the purposes of 
enforcement, actual notice will be used from November 8, 2016, until 
November 14, 2016.

ADDRESSES: The docket for this deviation, [USCG-2016-1008] is available 
at https://www.regulations.gov. Type the docket number in the ``SEARCH'' 
box and click ``SEARCH''. Click on Open Docket Folder on the line 
associated with this deviation.

FOR FURTHER INFORMATION CONTACT: If you have questions on this 
temporary deviation, call or email Mr. Hal R. Pitts, Bridge 
Administration Branch Fifth District, Coast Guard, telephone 757-398-
6222, email Hal.R.Pitts@uscg.mil.

SUPPLEMENTARY INFORMATION: The County of Cape May, NJ, that owns and 
operates the Stone Harbor Boulevard (CR657) Bridge across the Great 
Channel, mile 102.0, New Jersey Intracoastal Waterway, at Stone Harbor, 
NJ, has requested a temporary deviation from the current operating 
regulations to avoid bridge failure and perform emergency repairs to 
the bridge, due to a serious crack in one of two main bridge girders, 
causing the bridge to be unsafe for vehicular traffic and movement of 
the bascule spans. The bridge is a bascule drawbridge and has a 
vertical clearance in the closed position of 10 feet above mean high 
water.
    The current operating schedule is set out in 33 CFR 117.733(h). 
Under this temporary deviation, the bridge will remain in the closed-
to-navigation position until 4 p.m. on December 2, 2016.
    The Great Channel, New Jersey Intracoastal Waterway is used by a 
variety of vessels including small public vessels, small commercial 
vessels, tug and barge traffic, and recreational vessels. The Coast 
Guard has carefully considered the nature and volume of vessel traffic 
on the waterway in publishing this temporary deviation.
    Vessels able to safely pass through the bridge in the closed 
position may do so at any time. The bridge will not be able to open for 
emergencies and there is no immediate alternate route for vessels to 
pass. The Coast Guard will also inform the users of the waterways 
through our Local and Broadcast Notices to Mariners of the change in 
operating schedule for the bridge so that vessel operators can arrange 
their transit to minimize any impact caused by the temporary deviation.
    In accordance with 33 CFR 117.35(e), the drawbridge must return to 
its regular operating schedule immediately at the end of the effective 
period of this temporary deviation. This deviation from the operating 
regulations is authorized under 33 CFR 117.35.

    Dated: November 8, 2016.
Hal R. Pitts,
Bridge Program Manager, Fifth Coast Guard District.
[FR Doc. 2016-27281 Filed 11-10-16; 8:45 am]
 BILLING CODE 9110-04-P