Federal Register / Vol. 81, No. 217 / Wednesday, November 9, 2016 / Notices
DEPARTMENT OF ENERGY
Background
Federal Energy Regulatory
Commission
On February 23, 2016, the
Commission issued a Notice of Intent to
Prepare an Environmental Assessment
for the Planned Cedar Station Upgrade
Project, Request for Comments on
Environmental Issues, and Notice of
Public Scoping Meeting (NOI). The NOI
was issued during the pre-filing review
of the Project in Docket No. PF15–32–
000 and was sent to affected
landowners; federal, state, and local
government agencies; elected officials;
environmental and public interest
groups; Native American tribes; other
interested parties; and local libraries
and newspapers. In response to the NOI,
the Commission received comments
from Dakota and Goodhue Counties,
Thomas Lake Country Homes
Homeowners Association, Winnebago
Tribe of Nebraska, Minnesota
Department of Natural Resources, and
over 350 concerned landowners/
stakeholders. The primary issues raised
by the commentors are: Impacts on
residential areas from construction;
alternatives that avoid residential areas;
and impacts on Lebanon Hills Regional
Park and alternatives that would avoid
this park.
[Docket No. CP16–487–000; PF15–32–000]
Northern Natural Gas Company; Notice
of Schedule for Environmental Review
of the Cedar Station Upgrade Project
On July 29, 2016, Northern Natural
Gas Company (Northern) filed an
application in Docket No. CP16–487–
000 requesting a Certificate of Public
Convenience and Necessity pursuant to
section 7(c) of the Natural Gas Act to
construct and operate certain natural gas
pipeline facilities. The project is known
as the Cedar Station Upgrade Project
(Project), and would involve the
construction of a new 20-inch-diameter
pipeline loop 1 to fulfill Northern’s
contractual obligation to provide an
increased gas pressure of 650 pounds
per square inch gauge to Northern States
Power Company.
On August 11, 2016, the Federal
Energy Regulatory Commission
(Commission or FERC) issued its Notice
of Application for the Project. Among
other things, that notice alerted agencies
issuing federal authorizations of the
requirement to complete all necessary
reviews and to reach a final decision on
a request for a federal authorization
within 90 days of the date of issuance
of the Commission staff’s Environmental
Assessment (EA) for the Project. This
instant notice identifies the FERC staff’s
planned schedule for the completion of
the EA for the Project.
Schedule for Environmental Review
Issuance of EA December 9, 2016
90-day Federal Authorization Decision
Deadline March 9, 2017
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the Project’s
progress.
sradovich on DSK3GMQ082PROD with NOTICES
Project Description
Northern proposes to construct the
following facilities:
• About 7.86 miles of 20-inchdiameter pipeline loop;
• a pig 2 launcher and takeoff valve at
milepost 0.0; and
• a pig receiver and tie-in valve, and
modifications to regulators and piping
within the existing Cedar Meter Station
boundaries.
1 A pipeline ‘‘loop’’ is a segment of pipe installed
parallel to an existing pipeline.
2 A pig is an internal pipeline tool used to clean
a pipeline and/or to inspect for damage or
corrosion.
VerDate Sep<11>2014
16:29 Nov 08, 2016
Jkt 241001
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC Web
site (www.ferc.gov). Using the
‘‘eLibrary’’ link, select ‘‘General Search’’
from the eLibrary menu, enter the
selected date range and ‘‘Docket
Number’’ excluding the last three digits
(i.e., CP16–487), and follow the
instructions. For assistance with access
to eLibrary, the helpline can be reached
at (866) 208–3676, TTY (202) 502–8659,
or at FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC Web site also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
PO 00000
Frm 00031
Fmt 4703
Sfmt 4703
Dated: November 3, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–27066 Filed 11–8–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2343–086]
PE Hydro Generation, LLC; Notice of
Application Accepted for Filing,
Soliciting Motions To Intervene and
Protests, Ready for Environmental
Analysis, and Soliciting Comments,
Recommendations, Preliminary Terms
and Conditions, and Preliminary
Fishway Prescriptions
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Major License.
b. Project No.: 2343–086.
c. Date filed: December 30, 2015.
d. Applicant: PE Hydro Generation,
LLC.
e. Name of Project: Millville
Hydroelectric Project.
f. Location: The existing project is
located on the Shenandoah River, near
the town of Harpers Ferry in Jefferson
County, West Virginia. No federal lands
are occupied by project works or located
within the project boundary.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: John Collins,
Executive Vice President, Cube Hydro
Partners, LLC, 2 Bethesda Metro Center,
Suite 1330, Bethesda, MD 20814;
Telephone—(240) 482–2703.
i. FERC Contact: Michael Spencer,
(202) 502–6093, or michael.spencer@
ferc.gov.
j. Deadline for filing motions to
intervene and protests, comments,
recommendations, preliminary terms
and conditions, and preliminary
prescriptions: 60 Days from the issuance
date of this notice; reply comments are
due 105 days from the issuance date of
this notice.
The Commission strongly encourages
electronic filing. Please file motions to
intervene, protests, comments,
recommendations, preliminary terms
and conditions, and preliminary
fishway prescriptions using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
E:\FR\FM\09NON1.SGM
09NON1
Federal Register / Vol. 81, No. 217 / Wednesday, November 9, 2016 / Notices
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–2343–086.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. This application has been accepted
for filing and is now ready for
environmental analysis.
l. The Millville project consists of: (1)
A 14.0-foot-high concrete and stone dam
consisting of three sections: a 36-footlong non-overflow abutment on the east
bank; an 813-foot long, non-gated
spillway section; and a 122-foot-long
intake structure, equipped with four
vertical lift gates and one canal gate, and
extending to the west riverbank; (2) a
100 acre reservoir with gross storage
capacity of 900 acre-feet at elevation
324.0 mean sea level; (3) a 1,600-footlong, 30-foot-wide, 12-foot-high
masonry and concrete sided headrace
canal; (4) a 125-foot-long, 40-foot-wide
brick powerhouse containing 3 turbinegenerating units with a combined
capacity of 2.84 megawatts; (5) a 550foot-long tailrace, excavated in bedrock
and returning flow to the river channel;
and (6) a 1,006-foot-long, 2.4 kilovolt
(kV) transmission line to a transformer,
with a 794-foot-long, 34.5 kV
transmission line to the interconnection
with the local grid.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h above.
Register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Anyone may submit comments, a
protest, or a motion to intervene in
accordance with the requirements of
Rules of Practice and Procedure, 18 CFR
385.210, .211, and .214. In determining
the appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
for the particular application.
All filings must (1) bear in all capital
letters the title ‘‘PROTEST’’, ‘‘MOTION
TO INTERVENE’’, ‘‘COMMENTS,’’
‘‘REPLY COMMENTS,’’
‘‘RECOMMENDATIONS,’’
‘‘PRELIMINARY TERMS AND
CONDITIONS,’’ or ‘‘PRELIMINARY
FISHWAY PRESCRIPTIONS;’’ (2) set
forth in the heading the name of the
applicant and the project number of the
application to which the filing
responds; (3) furnish the name, address,
and telephone number of the person
protesting or intervening; and (4)
otherwise comply with the requirements
of 18 CFR 385.2001 through 385.2005.
All comments, recommendations, terms
and conditions or prescriptions must set
forth their evidentiary basis and
otherwise comply with the requirements
of 18 CFR 4.34(b). Agencies may obtain
copies of the application directly from
the applicant. A copy of any protest or
motion to intervene must be served
upon each representative of the
applicant specified in the particular
application. A copy of all other filings
in reference to this application must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
4.34(b) and 385.2010.
o. Procedural Schedule:
The application will be processed
according to the following revised
Hydro Licensing Schedule. Revisions to
the schedule may be made as
appropriate.
Milestone
Target date
sradovich on DSK3GMQ082PROD with NOTICES
Filing of recommendations, preliminary terms and conditions, and preliminary fishway prescriptions ....................................
Commission issues EA ..............................................................................................................................................................
Comments on EA or EIS ...........................................................................................................................................................
Modified terms and conditions ...................................................................................................................................................
p. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of this notice.
q. A license applicant must file no
later than 60 days following the date of
issuance of the notice of acceptance and
ready for environmental analysis
provided for in 5.22: (1) A copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification.
Dated: November 2, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–26992 Filed 11–8–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG17–23–000.
VerDate Sep<11>2014
16:29 Nov 08, 2016
Jkt 241001
PO 00000
Frm 00032
Fmt 4703
78803
Sfmt 4703
January, 2016.
May, 2017.
June, 2017.
August, 2017.
Applicants: Pima Energy Storage
System, LLC.
Description: Notice of SelfCertification of Exempt Wholesale
Generator Status of Pima Energy Storage
System, LLC.
Filed Date: 11/2/16.
Accession Number: 20161102–5166.
Comments Due: 5 p.m. ET 11/23/16.
Docket Numbers: EG17–24–000.
Applicants: Portal Ridge Solar A, LLC.
Description: Portal Ridge Solar A, LLC
submits Notice of Self-Certification of
Exempt Wholesale Generator Status.
Filed Date: 11/3/16.
Accession Number: 20161103–5077.
Comments Due: 5 p.m. ET 11/25/16.
E:\FR\FM\09NON1.SGM
09NON1
Agencies
[Federal Register Volume 81, Number 217 (Wednesday, November 9, 2016)]
[Notices]
[Pages 78802-78803]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-26992]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2343-086]
PE Hydro Generation, LLC; Notice of Application Accepted for
Filing, Soliciting Motions To Intervene and Protests, Ready for
Environmental Analysis, and Soliciting Comments, Recommendations,
Preliminary Terms and Conditions, and Preliminary Fishway Prescriptions
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Major License.
b. Project No.: 2343-086.
c. Date filed: December 30, 2015.
d. Applicant: PE Hydro Generation, LLC.
e. Name of Project: Millville Hydroelectric Project.
f. Location: The existing project is located on the Shenandoah
River, near the town of Harpers Ferry in Jefferson County, West
Virginia. No federal lands are occupied by project works or located
within the project boundary.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
h. Applicant Contact: John Collins, Executive Vice President, Cube
Hydro Partners, LLC, 2 Bethesda Metro Center, Suite 1330, Bethesda, MD
20814; Telephone--(240) 482-2703.
i. FERC Contact: Michael Spencer, (202) 502-6093, or
michael.spencer@ferc.gov.
j. Deadline for filing motions to intervene and protests, comments,
recommendations, preliminary terms and conditions, and preliminary
prescriptions: 60 Days from the issuance date of this notice; reply
comments are due 105 days from the issuance date of this notice.
The Commission strongly encourages electronic filing. Please file
motions to intervene, protests, comments, recommendations, preliminary
terms and conditions, and preliminary fishway prescriptions using the
Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000
characters, without prior registration, using the eComment system at
https://www.ferc.gov/docs-filing/
[[Page 78803]]
ecomment.asp. You must include your name and contact information at the
end of your comments. For assistance, please contact FERC Online
Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper
copy to: Secretary, Federal Energy Regulatory Commission, 888 First
Street NE., Washington, DC 20426. The first page of any filing should
include docket number P-2343-086.
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
k. This application has been accepted for filing and is now ready
for environmental analysis.
l. The Millville project consists of: (1) A 14.0-foot-high concrete
and stone dam consisting of three sections: a 36-foot-long non-overflow
abutment on the east bank; an 813-foot long, non-gated spillway
section; and a 122-foot-long intake structure, equipped with four
vertical lift gates and one canal gate, and extending to the west
riverbank; (2) a 100 acre reservoir with gross storage capacity of 900
acre-feet at elevation 324.0 mean sea level; (3) a 1,600-foot-long, 30-
foot-wide, 12-foot-high masonry and concrete sided headrace canal; (4)
a 125-foot-long, 40-foot-wide brick powerhouse containing 3 turbine-
generating units with a combined capacity of 2.84 megawatts; (5) a 550-
foot-long tailrace, excavated in bedrock and returning flow to the
river channel; and (6) a 1,006-foot-long, 2.4 kilovolt (kV)
transmission line to a transformer, with a 794-foot-long, 34.5 kV
transmission line to the interconnection with the local grid.
m. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support. A copy is also available for inspection and
reproduction at the address in item h above.
Register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
n. Anyone may submit comments, a protest, or a motion to intervene
in accordance with the requirements of Rules of Practice and Procedure,
18 CFR 385.210, .211, and .214. In determining the appropriate action
to take, the Commission will consider all protests or other comments
filed, but only those who file a motion to intervene in accordance with
the Commission's Rules may become a party to the proceeding. Any
comments, protests, or motions to intervene must be received on or
before the specified comment date for the particular application.
All filings must (1) bear in all capital letters the title
``PROTEST'', ``MOTION TO INTERVENE'', ``COMMENTS,'' ``REPLY COMMENTS,''
``RECOMMENDATIONS,'' ``PRELIMINARY TERMS AND CONDITIONS,'' or
``PRELIMINARY FISHWAY PRESCRIPTIONS;'' (2) set forth in the heading the
name of the applicant and the project number of the application to
which the filing responds; (3) furnish the name, address, and telephone
number of the person protesting or intervening; and (4) otherwise
comply with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, recommendations, terms and conditions or prescriptions must
set forth their evidentiary basis and otherwise comply with the
requirements of 18 CFR 4.34(b). Agencies may obtain copies of the
application directly from the applicant. A copy of any protest or
motion to intervene must be served upon each representative of the
applicant specified in the particular application. A copy of all other
filings in reference to this application must be accompanied by proof
of service on all persons listed in the service list prepared by the
Commission in this proceeding, in accordance with 18 CFR 4.34(b) and
385.2010.
o. Procedural Schedule:
The application will be processed according to the following
revised Hydro Licensing Schedule. Revisions to the schedule may be made
as appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Filing of recommendations, January, 2016.
preliminary terms and conditions,
and preliminary fishway
prescriptions.
Commission issues EA................. May, 2017.
Comments on EA or EIS................ June, 2017.
Modified terms and conditions........ August, 2017.
------------------------------------------------------------------------
p. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of this notice.
q. A license applicant must file no later than 60 days following
the date of issuance of the notice of acceptance and ready for
environmental analysis provided for in 5.22: (1) A copy of the water
quality certification; (2) a copy of the request for certification,
including proof of the date on which the certifying agency received the
request; or (3) evidence of waiver of water quality certification.
Dated: November 2, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-26992 Filed 11-8-16; 8:45 am]
BILLING CODE 6717-01-P