Spire STL Pipeline Company, LLC; Notice of Intent To Prepare an Environmental Assessment for the Planned Spire STL Pipeline Project, Request for Comments on Environmental Issues, and Notice of Public Scoping Sessions, 76576-76578 [2016-26592]
Download as PDF
76576
Federal Register / Vol. 81, No. 213 / Thursday, November 3, 2016 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. PF16–9–000]
Spire STL Pipeline Company, LLC;
Notice of Intent To Prepare an
Environmental Assessment for the
Planned Spire STL Pipeline Project,
Request for Comments on
Environmental Issues, and Notice of
Public Scoping Sessions
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Spire STL Pipeline Project (Project)
involving construction and operation of
facilities by Spire STL Pipeline
Company, LLC (Spire) in Scott, Greene,
and Jersey Counties, Illinois and St.
Charles and St. Louis Counties,
Missouri. The Commission will use this
EA in its decision-making process to
determine whether the Project is in the
public convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the Project.
You can make a difference by providing
us with your specific comments or
concerns about the Project. Your
comments should focus on the potential
environmental effects, reasonable
alternatives, and measures to avoid or
lessen environmental impacts. Your
input will help the Commission staff
determine what issues they need to
evaluate in the EA. To ensure that your
comments are timely and properly
recorded, please send your comments so
that the Commission receives them in
Washington, DC on or before November
25, 2016.
If you sent comments on the Project
to the Commission before the opening of
this docket on July 22, 2016, you will
need to file those comments in Docket
No. PF16–9–000 to ensure they are
considered as part of this proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this Project. State and
local government representatives should
notify their constituents of this planned
project and encourage them to comment
on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
planned facilities. The company would
seek to negotiate a mutually acceptable
agreement. However, if the Commission
approves the Project, that approval
conveys with it the right of eminent
domain. Therefore, if easement
negotiations fail to produce an
agreement, the pipeline company could
initiate condemnation proceedings
where compensation would be
determined in accordance with state
law.
A fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ is available for viewing on
the FERC Web site (www.ferc.gov). This
fact sheet addresses a number of
typically asked questions, including the
use of eminent domain and how to
participate in the Commission’s
proceedings.
Public Participation
For your convenience, there are four
methods you can use to submit your
comments to the Commission. The
Commission will provide equal
consideration to all comments received,
whether filed in written form or
provided verbally. The Commission
encourages electronic filing of
comments and has expert staff available
to assist you at (202) 502–6652 or
ferconlinesupport@ferc.gov. Please
carefully follow these instructions so
that your comments are properly
recorded.
(1) You can file your comments
electronically using the eComment
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. This is an easy
method for submitting brief, text-only
comments on a project;
(2) You can file your comments
electronically by using the eFiling
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. With eFiling,
you can provide comments in a variety
of formats by attaching them as a file
with your submission. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ If you are filing
a comment on a particular project,
please select ‘‘Comment on a Filing’’ as
the filing type; or
(3) You can file a paper copy of your
comments by mailing them to the
following address. Be sure to reference
the Project docket number (PF16–9–000)
with your submission: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Room 1A, Washington, DC 20426.
(4) In lieu of sending written or
electronic comments, the Commission
invites you to attend one of the public
scoping sessions its staff will conduct in
the Project area, scheduled as follows.
Date and time
Location
Monday, November 14, 2016, 4:00–8:00 p.m. ...
Tuesday, November 15, 2016, 4:00–8:00 p.m. ..
North County Recreation Complex 2577 Redman Rd., St. Louis, MO 63136.
Elsah Township Community Building 14690 Fessler Rd., Dow, IL 62022. (at Fessler Rd. and
Highway 3).
Knights of Columbus Hall 1/2 mile south of Town of Carrollton on US 67 Highway, Carrollton,
IL 62016. (at U.S. 67 and Jack Pine Rd., behind the Dollar General).
mstockstill on DSK3G9T082PROD with NOTICES
Wednesday, November 16, 2016, 4:00–8:00
p.m.
The primary goal of these scoping
sessions is to have you identify the
specific environmental issues and
concerns that should be considered in
the EA to be prepared for this Project.
Individual verbal comments will be
taken on a one-on-one basis with a court
reporter. This format is designed to
receive the maximum amount of verbal
comments, in a convenient way during
the timeframe allotted.
Each scoping session is scheduled
from 4:00 p.m. to 8:00 p.m. Central
VerDate Sep<11>2014
17:54 Nov 02, 2016
Jkt 241001
Standard Time. You may arrive at any
time after 4:00 p.m. There will not be a
formal presentation by Commission staff
when the session opens. If you wish to
speak, the Commission staff will hand
out numbers in the order of your arrival;
distribution of numbers will be
discontinued at 7:30 p.m.
Your verbal scoping comments will be
recorded by the court reporter (with
FERC staff or representative present)
and become part of the public record for
this proceeding. Transcripts will be
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
publicly available on FERC’s eLibrary
system (see below for instructions on
using eLibrary). If a significant number
of people are interested in providing
verbal comments in the one-on-one
settings, a time limit of 5 minutes may
be implemented for each commentor.
It is important to note that verbal
comments hold the same weight as
written or electronically submitted
comments. Although there will not be a
formal presentation, Commission staff
will be available throughout the scoping
E:\FR\FM\03NON1.SGM
03NON1
Federal Register / Vol. 81, No. 213 / Thursday, November 3, 2016 / Notices
session to answer your questions about
the environmental review process.
Representatives from Spire will also be
present to answer project-specific
questions.
Please note this is not your only
public input opportunity; please refer to
the review process flow chart in
appendix 1.1
Summary of the Planned Project
Spire plans to construct and operate
a pipeline to transport natural gas from
the Rockies Express Pipeline LLC
pipeline in Scott County, Illinois to an
interconnect with Laclede Gas
Company’s Line 880. The Project would
consist of the following facilities in
Illinois and Missouri:
• Approximately 57.4 miles of new
24-inch-diameter pipeline in Scott,
Greene, and Jersey Counties, Illinois and
St. Charles and St. Louis Counties,
Missouri;
• purchase of and modification of 7.6
miles of the existing 20-inch-diameter
Line 880 pipeline in St. Louis County,
Missouri;
• three new meter and regulating
stations in Scott County, Illinois and St.
Louis County, Missouri;
• modifications at the existing
Redman Delivery Station in St. Louis
County; Missouri; and
• appurtenant underground and
aboveground facilities.
According to Spire, the Project would
be designed to transport about 400,000
dekatherms per day of natural gas
service. The general location of the
Project facilities is shown in appendix
2.
Land Requirements for Construction
Construction of the planned facilities
would disturb about 920.3 acres of land
for the new pipeline, modifications to
the existing Line 880, and aboveground
facilities. Spire would maintain about
352.2 acres for permanent operation of
the Spire Project’s facilities following
construction; the remaining acreage
would be restored and revert to former
uses. Modifications at the existing
Redman Delivery Station would occur
within the boundary of the facility.
mstockstill on DSK3G9T082PROD with NOTICES
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
1 The appendices referenced in this notice will
not appear in the Federal Register. Copies of the
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’ or from the
Commission’s Public Reference Room, 888 First
Street NE., Washington, DC 20426, or call (202)
502–8371. For instructions on connecting to
eLibrary, refer to page 7 of this notice.
VerDate Sep<11>2014
17:54 Nov 02, 2016
Jkt 241001
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us 2 to
discover and address concerns the
public may have about proposals. This
process is referred to as scoping. The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
notice, the Commission requests public
comments on the scope of the issues to
be addressed in the EA. We will
consider all filed comments during the
preparation of the EA.
In the EA we will discuss impacts that
could occur as a result of the
construction and operation of the
planned project under these general
headings: Geology and soils; land use;
water resources, fisheries, and wetlands;
cultural resources; socioeconomics;
vegetation and wildlife, including
migratory birds; air quality and noise;
endangered and threatened species;
public safety; and cumulative impacts.
We will also evaluate possible
alternatives to the planned Project or
portions of the Project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
Although no formal application has
been filed, we have already initiated our
NEPA review under the Commission’s
pre-filing process. The purpose of the
pre-filing process is to encourage early
involvement of interested stakeholders
and to identify and resolve issues before
the FERC receives an application. As
part of our pre-filing review, we have
begun to contact some federal and state
agencies to discuss their involvement in
the scoping process and the preparation
of the EA.
The EA will present our independent
analysis of the issues and will be
available in the public record through
eLibrary. Depending on the comments
received during the scoping process, we
may also publish and distribute the EA
to the public for an allotted comment
period. We will consider all comments
on the EA before we make our
recommendations to the Commission.
To ensure we have the opportunity to
consider and address your comments,
please carefully follow the instructions
in the Public Participation section,
beginning on page 2.
With this notice, we are asking
agencies with jurisdiction by law and/
or special expertise with respect to the
environmental issues related to this
Project to formally cooperate with us in
2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the
environmental staff of the Commission’s Office of
Energy Projects.
PO 00000
Frm 00025
Fmt 4703
Sfmt 4703
76577
the preparation of the EA.3 Agencies
that would like to request cooperating
agency status should follow the
instructions for filing comments
provided under the Public Participation
section of this notice. Currently, the
U.S. Army Corps of Engineers and
Illinois Department of Agriculture have
expressed their intention to participate
as cooperating agencies in the
preparation of the EA to satisfy their
NEPA responsibilities related to this
Project.
Consultations Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for Section
106 of the National Historic
Preservation Act, we are using this
notice to initiate consultation with the
applicable State Historic Preservation
Offices (SHPO), and to solicit their
views and those of other government
agencies, interested Indian tribes, and
the public on the Project’s potential
effects on historic properties.4 We will
define the project-specific Area of
Potential Effects (APE) in consultation
with the SHPOs as the Project develops.
On natural gas facility projects, the APE
at a minimum encompasses all areas
subject to ground disturbance (examples
include construction right-of-way,
contractor/pipe storage yards, meter and
regulating stations, and access roads).
Our EA for this Project will document
our findings on the impacts on historic
properties and summarize the status of
consultations under Section 106.
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the Project. We will
3 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
4 The Advisory Council on Historic Preservation
regulations are at Title 36, Code of Federal
Regulations, Part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
E:\FR\FM\03NON1.SGM
03NON1
76578
Federal Register / Vol. 81, No. 213 / Thursday, November 3, 2016 / Notices
update the environmental mailing list as
the analysis proceeds to ensure that we
send the information related to this
environmental review to all individuals,
organizations, and government entities
interested in and/or potentially affected
by the planned project.
Copies of the EA will be sent to the
environmental mailing list for public
review and comment. If you would
prefer to receive a paper copy of the
document instead of the CD version or
would like to remove your name from
the mailing list, please return the
attached Information Request (see
appendix 3).
mstockstill on DSK3G9T082PROD with NOTICES
Becoming an Intervenor
Once Spire files its application with
the Commission, you may want to
become an ‘‘intervenor’’ which is an
official party to the Commission’s
proceeding. Intervenors play a more
formal role in the process and are able
to file briefs, appear at hearings, and be
heard by the courts if they choose to
appeal the Commission’s final ruling.
An intervenor formally participates in
the proceeding by filing a request to
intervene. Motions to intervene are
more fully described at https://
www.ferc.gov/resources/guides/how-to/
intervene.asp. Instructions for becoming
an intervenor are in the ‘‘Document-less
Intervention Guide’’ under the ‘‘e-filing’’
link on the Commission’s Web site.
Please note that the Commission will
not accept requests for intervenor status
at this time. You must wait until the
Commission receives a formal
application for the Project.
Additional Information
Additional information about the
Project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC Web
site (www.ferc.gov) using the eLibrary
link. Click on the eLibrary link, click on
‘‘General Search’’ and enter the docket
number, excluding the last three digits
in the Docket Number field (i.e., PF16–
9). Be sure you have selected an
appropriate date range. For assistance,
please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free
at (866) 208–3676, or for TTY, contact
(202) 502–6652. The eLibrary link also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
VerDate Sep<11>2014
17:54 Nov 02, 2016
Jkt 241001
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Dated: October 26, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–26592 Filed 11–2–16; 8:45 am]
BILLING CODE 6717–01–P
ENVIRONMENTAL PROTECTION
AGENCY
[EPA–HQ–OPP–2015–0762; FRL–9953–06]
Registration Review; Conventional,
Biopesticide and Antimicrobial
Pesticides Dockets Opened for Review
and Comment
Environmental Protection
Agency (EPA).
ACTION: Notice.
AGENCY:
With this document, EPA is
opening the public comment period for
several registration reviews for the list
of chemicals identified in the table in
Unit III. Registration review is EPA’s
periodic review of pesticide
registrations to ensure that each
pesticide continues to satisfy the
statutory standard for registration, that
is, the pesticide can perform its
intended function without unreasonable
adverse effects on human health or the
environment. Registration review
dockets contain information that will
assist the public in understanding the
types of information and issues that the
Agency may consider during the course
of registration reviews. Through this
program, EPA is ensuring that each
pesticide’s registration is based on
current scientific and other knowledge,
including its effects on human health
and the environment. This document
also announces that the Agency has
closed the registration review case for
bromine chloride (case 5008) and that it
will not be opening registration review
dockets for the following cases: Xylene
(aromatic solvents, case 3020);
butafenacil (case 7261), naptalam (case
0183); spiroxamine (case 7040);
polyethoxylated alcohols &
polyethoxylated aliphatic alcohols (case
3119); and carbofuran (case 0101).
DATES: Comments must be received on
or before January 3, 2017.
ADDRESSES: Submit your comments
identified by the docket identification
SUMMARY:
PO 00000
Frm 00026
Fmt 4703
Sfmt 4703
(ID) number for the specific pesticide of
interest provided in the table in Unit
III.A., by one of the following methods:
• Federal eRulemaking Portal: https://
www.regulations.gov. Follow the online
instructions for submitting comments.
Do not submit electronically any
information you consider to be
Confidential Business Information (CBI)
or other information whose disclosure is
restricted by statute.
• Mail: OPP Docket, Environmental
Protection Agency Docket Center (EPA/
DC), (28221T), 1200 Pennsylvania Ave.
NW., Washington, DC 20460–0001.
• Hand Delivery: To make special
arrangements for hand delivery or
delivery of boxed information, please
follow the instructions at https://
www.epa.gov/dockets/contacts.html.
Additional instructions on
commenting or visiting the docket,
along with more information about
dockets generally, is available at https://
www.epa.gov/dockets.
FOR FURTHER INFORMATION CONTACT: For
pesticide specific information contact:
The person identified as a contact in the
table in Unit III.A. Also include the
docket ID number listed in the table in
Unit III.A. for the pesticide of interest.
For general information contact:
Richard Dumas, Pesticide Re-Evaluation
Division (7508P), Office of Pesticide
Programs, Environmental Protection
Agency, 1200 Pennsylvania Ave. NW.,
Washington, DC 20460–0001; telephone
number: (703) 308–8015; fax number:
(703) 308–8090; email address:
dumas.richard@epa.gov.
SUPPLEMENTARY INFORMATION:
I. General Information
A. Does this action apply to me?
This action is directed to the public
in general, and may be of interest to a
wide range of stakeholders including
environmental, human health,
farmworker, and agricultural advocates;
the chemical industry; pesticide users;
and members of the public interested in
the sale, distribution, or use of
pesticides. Since others also may be
interested, the Agency has not
attempted to describe all the specific
entities that may be affected by this
action.
B. What should I consider as I prepare
my comments for EPA?
1. Submitting CBI. Do not submit this
information to EPA through
regulations.gov or email. Clearly mark
the part or all of the information that
you claim to be CBI. For CBI
information in a disk or CD–ROM that
you mail to EPA, mark the outside of the
disk or CD–ROM as CBI and then
E:\FR\FM\03NON1.SGM
03NON1
Agencies
[Federal Register Volume 81, Number 213 (Thursday, November 3, 2016)]
[Notices]
[Pages 76576-76578]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-26592]
[[Page 76576]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. PF16-9-000]
Spire STL Pipeline Company, LLC; Notice of Intent To Prepare an
Environmental Assessment for the Planned Spire STL Pipeline Project,
Request for Comments on Environmental Issues, and Notice of Public
Scoping Sessions
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Spire STL Pipeline Project
(Project) involving construction and operation of facilities by Spire
STL Pipeline Company, LLC (Spire) in Scott, Greene, and Jersey
Counties, Illinois and St. Charles and St. Louis Counties, Missouri.
The Commission will use this EA in its decision-making process to
determine whether the Project is in the public convenience and
necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the Project. You can make a difference by providing us with
your specific comments or concerns about the Project. Your comments
should focus on the potential environmental effects, reasonable
alternatives, and measures to avoid or lessen environmental impacts.
Your input will help the Commission staff determine what issues they
need to evaluate in the EA. To ensure that your comments are timely and
properly recorded, please send your comments so that the Commission
receives them in Washington, DC on or before November 25, 2016.
If you sent comments on the Project to the Commission before the
opening of this docket on July 22, 2016, you will need to file those
comments in Docket No. PF16-9-000 to ensure they are considered as part
of this proceeding.
This notice is being sent to the Commission's current environmental
mailing list for this Project. State and local government
representatives should notify their constituents of this planned
project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the planned facilities. The company
would seek to negotiate a mutually acceptable agreement. However, if
the Commission approves the Project, that approval conveys with it the
right of eminent domain. Therefore, if easement negotiations fail to
produce an agreement, the pipeline company could initiate condemnation
proceedings where compensation would be determined in accordance with
state law.
A fact sheet prepared by the FERC entitled ``An Interstate Natural
Gas Facility On My Land? What Do I Need To Know?'' is available for
viewing on the FERC Web site (www.ferc.gov). This fact sheet addresses
a number of typically asked questions, including the use of eminent
domain and how to participate in the Commission's proceedings.
Public Participation
For your convenience, there are four methods you can use to submit
your comments to the Commission. The Commission will provide equal
consideration to all comments received, whether filed in written form
or provided verbally. The Commission encourages electronic filing of
comments and has expert staff available to assist you at (202) 502-6652
or ferconlinesupport@ferc.gov. Please carefully follow these
instructions so that your comments are properly recorded.
(1) You can file your comments electronically using the eComment
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. This is an easy method for submitting brief,
text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. With eFiling, you can provide comments in a
variety of formats by attaching them as a file with your submission.
New eFiling users must first create an account by clicking on
``eRegister.'' If you are filing a comment on a particular project,
please select ``Comment on a Filing'' as the filing type; or
(3) You can file a paper copy of your comments by mailing them to
the following address. Be sure to reference the Project docket number
(PF16-9-000) with your submission: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888 First Street NE., Room 1A,
Washington, DC 20426.
(4) In lieu of sending written or electronic comments, the
Commission invites you to attend one of the public scoping sessions its
staff will conduct in the Project area, scheduled as follows.
------------------------------------------------------------------------
Date and time Location
------------------------------------------------------------------------
Monday, November 14, 2016, 4:00- North County Recreation Complex 2577
8:00 p.m.. Redman Rd., St. Louis, MO 63136.
Tuesday, November 15, 2016, 4:00- Elsah Township Community Building
8:00 p.m.. 14690 Fessler Rd., Dow, IL 62022.
(at Fessler Rd. and Highway 3).
Wednesday, November 16, 2016, 4:00- Knights of Columbus Hall 1/2 mile
8:00 p.m. south of Town of Carrollton on US
67 Highway, Carrollton, IL 62016.
(at U.S. 67 and Jack Pine Rd.,
behind the Dollar General).
------------------------------------------------------------------------
The primary goal of these scoping sessions is to have you identify
the specific environmental issues and concerns that should be
considered in the EA to be prepared for this Project. Individual verbal
comments will be taken on a one-on-one basis with a court reporter.
This format is designed to receive the maximum amount of verbal
comments, in a convenient way during the timeframe allotted.
Each scoping session is scheduled from 4:00 p.m. to 8:00 p.m.
Central Standard Time. You may arrive at any time after 4:00 p.m. There
will not be a formal presentation by Commission staff when the session
opens. If you wish to speak, the Commission staff will hand out numbers
in the order of your arrival; distribution of numbers will be
discontinued at 7:30 p.m.
Your verbal scoping comments will be recorded by the court reporter
(with FERC staff or representative present) and become part of the
public record for this proceeding. Transcripts will be publicly
available on FERC's eLibrary system (see below for instructions on
using eLibrary). If a significant number of people are interested in
providing verbal comments in the one-on-one settings, a time limit of 5
minutes may be implemented for each commentor.
It is important to note that verbal comments hold the same weight
as written or electronically submitted comments. Although there will
not be a formal presentation, Commission staff will be available
throughout the scoping
[[Page 76577]]
session to answer your questions about the environmental review
process. Representatives from Spire will also be present to answer
project-specific questions.
Please note this is not your only public input opportunity; please
refer to the review process flow chart in appendix 1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of the appendices were sent to all
those receiving this notice in the mail and are available at
www.ferc.gov using the link called ``eLibrary'' or from the
Commission's Public Reference Room, 888 First Street NE.,
Washington, DC 20426, or call (202) 502-8371. For instructions on
connecting to eLibrary, refer to page 7 of this notice.
---------------------------------------------------------------------------
Summary of the Planned Project
Spire plans to construct and operate a pipeline to transport
natural gas from the Rockies Express Pipeline LLC pipeline in Scott
County, Illinois to an interconnect with Laclede Gas Company's Line
880. The Project would consist of the following facilities in Illinois
and Missouri:
Approximately 57.4 miles of new 24-inch-diameter pipeline
in Scott, Greene, and Jersey Counties, Illinois and St. Charles and St.
Louis Counties, Missouri;
purchase of and modification of 7.6 miles of the existing
20-inch-diameter Line 880 pipeline in St. Louis County, Missouri;
three new meter and regulating stations in Scott County,
Illinois and St. Louis County, Missouri;
modifications at the existing Redman Delivery Station in
St. Louis County; Missouri; and
appurtenant underground and aboveground facilities.
According to Spire, the Project would be designed to transport
about 400,000 dekatherms per day of natural gas service. The general
location of the Project facilities is shown in appendix 2.
Land Requirements for Construction
Construction of the planned facilities would disturb about 920.3
acres of land for the new pipeline, modifications to the existing Line
880, and aboveground facilities. Spire would maintain about 352.2 acres
for permanent operation of the Spire Project's facilities following
construction; the remaining acreage would be restored and revert to
former uses. Modifications at the existing Redman Delivery Station
would occur within the boundary of the facility.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
\2\ to discover and address concerns the public may have about
proposals. This process is referred to as scoping. The main goal of the
scoping process is to focus the analysis in the EA on the important
environmental issues. By this notice, the Commission requests public
comments on the scope of the issues to be addressed in the EA. We will
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------
\2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EA we will discuss impacts that could occur as a result of
the construction and operation of the planned project under these
general headings: Geology and soils; land use; water resources,
fisheries, and wetlands; cultural resources; socioeconomics; vegetation
and wildlife, including migratory birds; air quality and noise;
endangered and threatened species; public safety; and cumulative
impacts.
We will also evaluate possible alternatives to the planned Project
or portions of the Project, and make recommendations on how to lessen
or avoid impacts on the various resource areas.
Although no formal application has been filed, we have already
initiated our NEPA review under the Commission's pre-filing process.
The purpose of the pre-filing process is to encourage early involvement
of interested stakeholders and to identify and resolve issues before
the FERC receives an application. As part of our pre-filing review, we
have begun to contact some federal and state agencies to discuss their
involvement in the scoping process and the preparation of the EA.
The EA will present our independent analysis of the issues and will
be available in the public record through eLibrary. Depending on the
comments received during the scoping process, we may also publish and
distribute the EA to the public for an allotted comment period. We will
consider all comments on the EA before we make our recommendations to
the Commission. To ensure we have the opportunity to consider and
address your comments, please carefully follow the instructions in the
Public Participation section, beginning on page 2.
With this notice, we are asking agencies with jurisdiction by law
and/or special expertise with respect to the environmental issues
related to this Project to formally cooperate with us in the
preparation of the EA.\3\ Agencies that would like to request
cooperating agency status should follow the instructions for filing
comments provided under the Public Participation section of this
notice. Currently, the U.S. Army Corps of Engineers and Illinois
Department of Agriculture have expressed their intention to participate
as cooperating agencies in the preparation of the EA to satisfy their
NEPA responsibilities related to this Project.
---------------------------------------------------------------------------
\3\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
---------------------------------------------------------------------------
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for Section 106 of the National Historic
Preservation Act, we are using this notice to initiate consultation
with the applicable State Historic Preservation Offices (SHPO), and to
solicit their views and those of other government agencies, interested
Indian tribes, and the public on the Project's potential effects on
historic properties.\4\ We will define the project-specific Area of
Potential Effects (APE) in consultation with the SHPOs as the Project
develops. On natural gas facility projects, the APE at a minimum
encompasses all areas subject to ground disturbance (examples include
construction right-of-way, contractor/pipe storage yards, meter and
regulating stations, and access roads). Our EA for this Project will
document our findings on the impacts on historic properties and
summarize the status of consultations under Section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the Project. We will
[[Page 76578]]
update the environmental mailing list as the analysis proceeds to
ensure that we send the information related to this environmental
review to all individuals, organizations, and government entities
interested in and/or potentially affected by the planned project.
Copies of the EA will be sent to the environmental mailing list for
public review and comment. If you would prefer to receive a paper copy
of the document instead of the CD version or would like to remove your
name from the mailing list, please return the attached Information
Request (see appendix 3).
Becoming an Intervenor
Once Spire files its application with the Commission, you may want
to become an ``intervenor'' which is an official party to the
Commission's proceeding. Intervenors play a more formal role in the
process and are able to file briefs, appear at hearings, and be heard
by the courts if they choose to appeal the Commission's final ruling.
An intervenor formally participates in the proceeding by filing a
request to intervene. Motions to intervene are more fully described at
https://www.ferc.gov/resources/guides/how-to/intervene.asp. Instructions
for becoming an intervenor are in the ``Document-less Intervention
Guide'' under the ``e-filing'' link on the Commission's Web site.
Please note that the Commission will not accept requests for intervenor
status at this time. You must wait until the Commission receives a
formal application for the Project.
Additional Information
Additional information about the Project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC Web site (www.ferc.gov) using the eLibrary link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number,
excluding the last three digits in the Docket Number field (i.e., PF16-
9). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY,
contact (202) 502-6652. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Dated: October 26, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-26592 Filed 11-2-16; 8:45 am]
BILLING CODE 6717-01-P