74818
Federal Register / Vol. 81, No. 208 / Thursday, October 27, 2016 / Notices
Register and will last for 30 days. The
public comment period will end on
November 25, 2016.
ADDRESSES: Interested parties should
provide comments at the following link:
https://policy.cio.gov/it-modernization/.
The Office of Management and Budget
is located at 725 17th Street NW.,
Washington, DC 20503.
FOR FURTHER INFORMATION CONTACT:
Sean Casey at Sean_C_Casey@
omb.eop.gov or OFCIO@omb.eop.gov.
SUPPLEMENTARY INFORMATION: The Office
of Management and Budget (OMB) is
proposing a new policy to modernize
the Federal government’s aging IT
systems. This memorandum would
require the CFO-Act agencies to identify
systems as candidates for modernization
and submit modernization proposals to
OMB. Research and agency-submitted
analysis indicates that aging legacy
systems pose operations risks for the
agencies and the government as a whole
when these systems cannot adapt to
current or expected mission
requirements, user needs, or operating
environments. This memorandum
strives to assist agencies with the costs
and risks of modernizing critical
systems, and it seeks to promote cost
reductions, risk reductions, and
improved delivery of services to the
American public through modernization
of these systems. Authority for this
notice is granted under the ClingerCohen Act, 40 U.S.C. Subtitle III.
Tony Scott,
U.S. Federal Chief Information Officer.
[FR Doc. 2016–25948 Filed 10–26–16; 8:45 am]
BILLING CODE P
NATIONAL SCIENCE FOUNDATION
Notice of Permits Issued Under the
Antarctic Conservation Act of 1978
National Science Foundation.
Notice of permits issued under
the Antarctic Conservation of 1978,
Public Law 95–541.
AGENCY:
ACTION:
The National Science
Foundation (NSF) is required to publish
notice of permits issued under the
Antarctic Conservation Act of 1978.
This is the required notice.
FOR FURTHER INFORMATION CONTACT:
Nature McGinn, ACA Permit Officer,
Division of Polar Programs, Rm. 755,
National Science Foundation, 4201
Wilson Boulevard, Arlington, VA 22230.
Or by email: ACApermits@nsf.gov.
SUPPLEMENTARY INFORMATION: On
September 9, 2016 the National Science
Foundation published a notice in the
sradovich on DSK3GMQ082PROD with NOTICES
SUMMARY:
VerDate Sep<11>2014
17:43 Oct 26, 2016
Jkt 241001
Federal Register of permit applications
received. The permits were issued on
October 21, 2016 to:
Dr. George Watters
Permit Nos. 2017–012; 2017–013
Nadene G. Kennedy,
Polar Coordination Specialist, Division of
Polar Programs.
[FR Doc. 2016–25932 Filed 10–26–16; 8:45 am]
BILLING CODE 7555–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket Nos. 50–0348 and 50–0364; NRC–
2015–0015]
Southern Nuclear Operating Company,
Inc.; Joseph M. Farley Nuclear Plant,
Units 1 and 2
Nuclear Regulatory
Commission.
ACTION: License amendment application;
withdrawal by applicant.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) has granted the
request of the Southern Nuclear
Operating Company, Inc. (SNC—the
licensee) to withdraw its license
amendment application dated
November 24, 2014, as supplemented on
September 28, 2015; March 3, 2016; and
July 25, 2016, for proposed amendments
to Renewed Facility Operating License
Nos. NPF 2 and NPF 8 for the Joseph M.
Farley Nuclear Plant, Units 1 and 2,
respectively, located in Houston
County, Alabama. The application
contained 24 requests. Twenty-three of
those requests were addressed in NRC
letter dated August 3, 2016. The
amendments adopted previously
approved Technical Specifications Task
Force Travelers and made two changes
not associated with Travelers. A request
to incorporate TSTF–312–A, Revision 1,
‘‘Administratively Control Containment
Penetrations,’’ has been withdrawn by
SNC in a letter dated October 17, 2016.
DATES: The license amendment was
withdrawn by the licensee on October
17, 2016.
ADDRESSES: Please refer to Docket ID
NRC–2015–0015 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly-available
information related to this document
using any of the following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2015–0015. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–415–3463;
email: Carol.Gallagher@nrc.gov. For
technical questions, contact the
SUMMARY:
PO 00000
Frm 00057
Fmt 4703
Sfmt 4703
individual listed in the FOR FURTHER
section of this
document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘ADAMS Public Documents’’ and then
select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The
ADAMS accession number for each
document referenced (if it is available in
ADAMS) is provided the first time that
it is mentioned in this document.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
INFORMATION CONTACT
FOR FURTHER INFORMATION CONTACT:
Shawn Williams, Office of Nuclear
Reactor Regulation, U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001; telephone: 301–415–
1009, email: Shawn.Williams@nrc.gov.
The NRC
has granted the request of the licensee
to withdraw its November 24, 2014,
license amendment application
(ADAMS Package Accession No.
ML14335A689), as supplemented on
September 28, 2015 (ADAMS Accession
No. ML15271A223); March 3, 2016
(ADAMS Accession No. ML16063A516);
and July 25, 2016 (ADAMS Accession
Package No. ML16214A040), for
proposed amendments to Renewed
Facility Operating License Nos. NPF 2
and NPF 8 for the Joseph M. Farley
Nuclear Plant, Units 1 and 2,
respectively, located in Houston
County, Alabama.
The licensee requested to change the
Technical Specifications related to
TSTF–312–A, Revision 1,
‘‘Administratively Control Containment
Penetrations.’’
The proposed amendment was
noticed in the Federal Register on
February 3, 2015 (80 FR 5804). By letter
dated October 17, 2016 (ADAMS
Accession No. ML16291A520), the
licensee withdrew its license
amendment application.
SUPPLEMENTARY INFORMATION:
Dated at Rockville, Maryland, this 20th day
of October 2016.
E:\FR\FM\27OCN1.SGM
27OCN1
Federal Register / Vol. 81, No. 208 / Thursday, October 27, 2016 / Notices
For the Nuclear Regulatory Commission.
Michael T. Markley,
Chief, Plant Licensing Branch II–1, Division
of Operating Reactor Licensing, Office of
Nuclear Reactor Regulation.
[FR Doc. 2016–25987 Filed 10–26–16; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket Nos. 52–025 and 52–026; NRC–
2008–0252]
Southern Nuclear Operating Company,
Vogtle Electric Generating Plant, Units
3 and 4; Passive Core Cooling System
(PXS) Design Changes To Address
Potential Gas Intrusion
Nuclear Regulatory
Commission.
ACTION: Exemption and combined
license amendment; issuance.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is granting an
exemption to allow a departure from the
certification information of Tier 1 of the
generic design control document (DCD)
and is issuing License Amendment No.
55 to Combined Licenses (COL), NPF–
91 and NPF–92. The COLs were issued
to Southern Nuclear Operating
Company, Inc., and Georgia Power
Company, Oglethorpe Power
Corporation, MEAG Power SPVM, LLC,
MEAG Power SPVJ, LLC, MEAG Power
SPVP, LLC, Authority of Georgia, and
the City of Dalton, Georgia (the
licensee); for construction and operation
of the Vogtle Electric Generating Plant
(VEGP) Units 3 and 4, located in Burke
County, Georgia.
The granting of the exemption allows
the changes to Tier 1 information asked
for in the amendment. Because the
acceptability of the exemption was
determined in part by the acceptability
of the amendment, the exemption and
amendment are being issued
concurrently.
ADDRESSES: Please refer to Docket ID
NRC–2008–0252 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly-available
information related to this document
using any of the following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2008–0252. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–415–3463;
email: Carol.Gallagher@nrc.gov. For
technical questions, contact the
individual listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
sradovich on DSK3GMQ082PROD with NOTICES
SUMMARY:
VerDate Sep<11>2014
17:43 Oct 26, 2016
Jkt 241001
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘ADAMS Public Documents’’ and then
select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The
ADAMS accession number for each
document referenced (if it is available in
ADAMS) is provided the first time that
it is mentioned in this document. The
request for the amendment and
exemption was submitted by letter
dated May 5, 2016 (ADAMS Accession
No. ML16126A276).
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: Paul
Kallan, Office of New Reactors, U.S.
Nuclear Regulatory Commission,
Washington, DC 20555–0001; telephone:
301–415–2809; email: Paul.Kallan@
nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Introduction
The NRC is granting an exemption
from paragraph B of section III, ‘‘Scope
and Contents,’’ of Appendix D, ‘‘Design
Certification Rule for the AP1000,’’ to
part 52 of Title 10 of the Code of Federal
Regulations (10 CFR), and issuing
License Amendment No. 55 to COLs,
NPF–91 and NPF–92, to the licensee.
The exemption is required by paragraph
A.4 of section VIII, ‘‘Processes for
Changes and Departures,’’ Appendix d,
to 10 CFR part 52 to allow the licensee
to depart from Tier 1 information. With
the requested amendment, the licensee
sought proposed changes that would
revise the Updated Final Safety
Analysis Report in the form of
departures from the incorporated plantspecific DCD Tier 2 information. The
proposed amendment also involves
related changes to plant-specific Tier 1
information, with corresponding
changes to the associated COL
Appendix C information.
Part of the justification for granting
the exemption was provided by the
review of the amendment. Because the
exemption is necessary in order to issue
the requested license amendment, the
NRC granted the exemption and issued
the amendment concurrently, rather
than in sequence. This included issuing
PO 00000
Frm 00058
Fmt 4703
Sfmt 4703
74819
a combined safety evaluation containing
the NRC staff’s review of both the
exemption request and the license
amendment. The exemption met all
applicable regulatory criteria set forth in
10 CFR 50.12, 10 CFR 52.7, and Section
VIII.A.4 of Appendix d to 10 CFR part
52. The license amendment was found
to be acceptable as well. The combined
safety evaluation is available in ADAMS
under Accession No. ML16237A393.
Identical exemption documents
(except for referenced unit numbers and
license numbers) were issued to the
licensee for VEGP Units 3 and 4 (COLs
NPF–91 and NPF–92). The exemption
documents for VEGP Units 3 and 4 can
be found in ADAMS under Accession
Nos. ML16237A325 and ML16237A344,
respectively. The exemption is
reproduced (with the exception of
abbreviated titles and additional
citations) in Section II of this document.
The amendment documents for COLs
NPF–91 and NPF–92 are available in
ADAMS under Accession Nos.
ML16237A315 and ML16237A319,
respectively. A summary of the
amendment documents is provided in
Section III of this document.
II. Exemption
Reproduced below is the exemption
document issued to Vogtle Units 3 and
Unit 4. It makes reference to the
combined safety evaluation that
provides the reasoning for the findings
made by the NRC (and listed under Item
1) in order to grant the exemption:
1. In a letter dated May 5, 2016, the
licensee requested from the Commission
an exemption from the provisions of 10
CFR part 52, Appendix d, Section III.B,
as part of License Amendment Request
16–004, ‘‘Passive Core Cooling System
(PXS) Design Changes to Address
Potential Gas Intrusion (LAR–16–004).’’
For the reasons set forth in Section
3.1, ‘‘Evaluation of Exemption,’’ of the
NRC staff’s Safety Evaluation, which
can be found in ADAMS under
Accession No. ML16237A393, the
Commission finds that:
A. The exemption is authorized by
law;
B. the exemption presents no undue
risk to public health and safety;
C. the exemption is consistent with
the common defense and security;
D. special circumstances are present
in that the application of the rule in this
circumstance is not necessary to serve
the underlying purpose of the rule;
E. the special circumstances outweigh
any decrease in safety that may result
from the reduction in standardization
caused by the exemption; and
E:\FR\FM\27OCN1.SGM
27OCN1
Agencies
[Federal Register Volume 81, Number 208 (Thursday, October 27, 2016)]
[Notices]
[Pages 74818-74819]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-25987]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-0348 and 50-0364; NRC-2015-0015]
Southern Nuclear Operating Company, Inc.; Joseph M. Farley
Nuclear Plant, Units 1 and 2
AGENCY: Nuclear Regulatory Commission.
ACTION: License amendment application; withdrawal by applicant.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) has granted the
request of the Southern Nuclear Operating Company, Inc. (SNC--the
licensee) to withdraw its license amendment application dated November
24, 2014, as supplemented on September 28, 2015; March 3, 2016; and
July 25, 2016, for proposed amendments to Renewed Facility Operating
License Nos. NPF 2 and NPF 8 for the Joseph M. Farley Nuclear Plant,
Units 1 and 2, respectively, located in Houston County, Alabama. The
application contained 24 requests. Twenty-three of those requests were
addressed in NRC letter dated August 3, 2016. The amendments adopted
previously approved Technical Specifications Task Force Travelers and
made two changes not associated with Travelers. A request to
incorporate TSTF-312-A, Revision 1, ``Administratively Control
Containment Penetrations,'' has been withdrawn by SNC in a letter dated
October 17, 2016.
DATES: The license amendment was withdrawn by the licensee on October
17, 2016.
ADDRESSES: Please refer to Docket ID NRC-2015-0015 when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly-available information related to this document
using any of the following methods:
Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2015-0015. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: Carol.Gallagher@nrc.gov. For technical questions, contact
the individual listed in the FOR FURTHER INFORMATION CONTACT section of
this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly-available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS,
please contact the NRC's Public Document Room (PDR) reference staff at
1-800-397-4209, 301-415-4737, or by email to pdr.resource@nrc.gov. The
ADAMS accession number for each document referenced (if it is available
in ADAMS) is provided the first time that it is mentioned in this
document.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: Shawn Williams, Office of Nuclear
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC
20555-0001; telephone: 301-415-1009, email: Shawn.Williams@nrc.gov.
SUPPLEMENTARY INFORMATION: The NRC has granted the request of the
licensee to withdraw its November 24, 2014, license amendment
application (ADAMS Package Accession No. ML14335A689), as supplemented
on September 28, 2015 (ADAMS Accession No. ML15271A223); March 3, 2016
(ADAMS Accession No. ML16063A516); and July 25, 2016 (ADAMS Accession
Package No. ML16214A040), for proposed amendments to Renewed Facility
Operating License Nos. NPF 2 and NPF 8 for the Joseph M. Farley Nuclear
Plant, Units 1 and 2, respectively, located in Houston County, Alabama.
The licensee requested to change the Technical Specifications
related to TSTF-312-A, Revision 1, ``Administratively Control
Containment Penetrations.''
The proposed amendment was noticed in the Federal Register on
February 3, 2015 (80 FR 5804). By letter dated October 17, 2016 (ADAMS
Accession No. ML16291A520), the licensee withdrew its license amendment
application.
Dated at Rockville, Maryland, this 20th day of October 2016.
[[Page 74819]]
For the Nuclear Regulatory Commission.
Michael T. Markley,
Chief, Plant Licensing Branch II-1, Division of Operating Reactor
Licensing, Office of Nuclear Reactor Regulation.
[FR Doc. 2016-25987 Filed 10-26-16; 8:45 am]