Download as PDF 74420 Federal Register / Vol. 81, No. 207 / Wednesday, October 26, 2016 / Notices Number of respondents Annual number of responses per respondent Total number of responses Average burden hours Total annual burden hours (1) Information collection requirements (2) (1) * (2) = (3) (4) (3) * (4) = (5) R13: GO 4 and TO to have evidence it acquired and installed dynamic disturbance recorders and a mutually agreed upon implementation schedule with the RC (record retention) .............................................................. R14.5: GO and TO to have evidence of a maintenance and testing program for stand-alone disturbance monitoring equipment including monthly verification of active analog quantities .............................................................. R14.7: GO and TO to record efforts to return failed units to service if it takes longer than 90 days 5 ....................... R14.7: GO and TO record retention .................................... R17: RC provide certain disturbance monitoring equipment data to the Regional Entity upon request ........................ R17: RC record retention ..................................................... TOTAL REDUCTIONS ................................................. Comments: Comments are invited on: (1) Whether the collection of information is necessary for the proper performance of the functions of the Commission, including whether the information will have practical utility; (2) the accuracy of the agency’s estimate of the burden and cost of the collection of information, including the validity of the methodology and assumptions used; (3) ways to enhance the quality, utility and clarity of the information collection; and (4) ways to minimize the burden of the collection of information on those who are to respond, including the use of automated collection techniques or other forms of information technology. Dated: October 20, 2016. Kimberly D. Bose, Secretary. [FR Doc. 2016–25841 Filed 10–25–16; 8:45 am] BILLING CODE 6717–01–P 1 1 1 10 10 169 12 2,028 5 10,140 33 33 1 1 33 33 10 10 330 330 5 5 1 1 5 5 5 10 25 50 ........................ ........................ 2,105 ........................ 10,885 a free service called eSubscription (https://www.ferc.gov/docs-filing/ esubscription.asp). DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP15–138–000] Transcontinental Gas Pipe Line Company, LLC; Notice of Revised Schedule for Environmental Review of the Atlantic Sunrise Project This notice identifies the Federal Energy Regulatory Commission (FERC or Commission) staff’s revised schedule for the completion of the environmental impact statement (EIS) for Transcontinental Gas Pipe Line Company, LLC’s (Transco) Atlantic Sunrise Project. The first notice of schedule, issued on March 9, 2016, identified October 21, 2016 as the EIS issuance date. Based on additional information filed by Transco, however, we intend to issue a draft General Conformity Determination for the Atlantic Sunrise Project with a 30-day comment period. Commission staff has therefore revised the schedule for issuance of the final EIS. asabaliauskas on DSK3SPTVN1PROD with NOTICES Schedule for Environmental Review 4 For purposes of these charts, generation owner is abbreviated to GO, transmission owner is abbreviated to TO, reliability coordinator is abbreviated to RC, and planning coordinator is abbreviated to PC. 5 We estimate that an entity will experience a unit failure greater than 90 days once every five years. Therefore, 20 percent of NPCC’s 169 generator owners and transmission owners will experience a unit failure of this duration each year. VerDate Sep<11>2014 18:25 Oct 25, 2016 Jkt 241001 Issuance of Notice of Availability of the final EIS—December 30, 2016. 90-day Federal Authorization Decision Deadline—March 30, 2017. If a schedule change becomes necessary, an additional notice will be provided so that the relevant agencies are kept informed of the project’s progress. Additional Information In order to receive notification of the issuance of the EIS and to keep track of all formal issuances and submittals in specific dockets, the Commission offers PO 00000 Frm 00030 Fmt 4703 Sfmt 4703 Dated: October 20, 2016. Kimberly D. Bose, Secretary. [FR Doc. 2016–25834 Filed 10–25–16; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2485–073] FirstLight Hydro Generating Company; Notice of Application Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Type of Application: Application for Temporary Amendment of Minimum and Maximum Reservoir Elevation Requirement. b. Project No.: 2485–073. c. Date Filed: September 16, 2016. d. Applicant: FirstLight Hydro Generating Company (FirstLight). e. Name of Project: Northfield Mountain Pumped Storage Project. f. Location: The project is located on the east side of the Connecticut River, in the towns of Northfield and Erving, in Franklin County, Massachusetts. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Mr. Gus Bakas, Director—Massachusetts Hydro, FirstLight Hydro Generating Company, Northfield Mountain Station, 99 Millers E:\FR\FM\26OCN1.SGM 26OCN1

Agencies

[Federal Register Volume 81, Number 207 (Wednesday, October 26, 2016)]
[Notices]
[Page 74420]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-25834]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP15-138-000]


Transcontinental Gas Pipe Line Company, LLC; Notice of Revised 
Schedule for Environmental Review of the Atlantic Sunrise Project

    This notice identifies the Federal Energy Regulatory Commission 
(FERC or Commission) staff's revised schedule for the completion of the 
environmental impact statement (EIS) for Transcontinental Gas Pipe Line 
Company, LLC's (Transco) Atlantic Sunrise Project. The first notice of 
schedule, issued on March 9, 2016, identified October 21, 2016 as the 
EIS issuance date. Based on additional information filed by Transco, 
however, we intend to issue a draft General Conformity Determination 
for the Atlantic Sunrise Project with a 30-day comment period. 
Commission staff has therefore revised the schedule for issuance of the 
final EIS.

Schedule for Environmental Review

    Issuance of Notice of Availability of the final EIS--December 30, 
2016.
    90-day Federal Authorization Decision Deadline--March 30, 2017.
    If a schedule change becomes necessary, an additional notice will 
be provided so that the relevant agencies are kept informed of the 
project's progress.

Additional Information

    In order to receive notification of the issuance of the EIS and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription (https://www.ferc.gov/docs-filing/esubscription.asp).

    Dated: October 20, 2016.
Kimberly D. Bose,
 Secretary.
[FR Doc. 2016-25834 Filed 10-25-16; 8:45 am]