Transcontinental Gas Pipe Line Company, LLC; Notice of Revised Schedule for Environmental Review of the Atlantic Sunrise Project, 74420 [2016-25834]
Download as PDF
74420
Federal Register / Vol. 81, No. 207 / Wednesday, October 26, 2016 / Notices
Number of
respondents
Annual
number of
responses per
respondent
Total
number of
responses
Average
burden hours
Total annual
burden hours
(1)
Information collection requirements
(2)
(1) * (2) = (3)
(4)
(3) * (4) = (5)
R13: GO 4 and TO to have evidence it acquired and installed dynamic disturbance recorders and a mutually
agreed upon implementation schedule with the RC
(record retention) ..............................................................
R14.5: GO and TO to have evidence of a maintenance
and testing program for stand-alone disturbance monitoring equipment including monthly verification of active
analog quantities ..............................................................
R14.7: GO and TO to record efforts to return failed units
to service if it takes longer than 90 days 5 .......................
R14.7: GO and TO record retention ....................................
R17: RC provide certain disturbance monitoring equipment
data to the Regional Entity upon request ........................
R17: RC record retention .....................................................
TOTAL REDUCTIONS .................................................
Comments: Comments are invited on:
(1) Whether the collection of
information is necessary for the proper
performance of the functions of the
Commission, including whether the
information will have practical utility;
(2) the accuracy of the agency’s estimate
of the burden and cost of the collection
of information, including the validity of
the methodology and assumptions used;
(3) ways to enhance the quality, utility
and clarity of the information collection;
and (4) ways to minimize the burden of
the collection of information on those
who are to respond, including the use
of automated collection techniques or
other forms of information technology.
Dated: October 20, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016–25841 Filed 10–25–16; 8:45 am]
BILLING CODE 6717–01–P
1
1
1
10
10
169
12
2,028
5
10,140
33
33
1
1
33
33
10
10
330
330
5
5
1
1
5
5
5
10
25
50
........................
........................
2,105
........................
10,885
a free service called eSubscription
(https://www.ferc.gov/docs-filing/
esubscription.asp).
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP15–138–000]
Transcontinental Gas Pipe Line
Company, LLC; Notice of Revised
Schedule for Environmental Review of
the Atlantic Sunrise Project
This notice identifies the Federal
Energy Regulatory Commission (FERC
or Commission) staff’s revised schedule
for the completion of the environmental
impact statement (EIS) for
Transcontinental Gas Pipe Line
Company, LLC’s (Transco) Atlantic
Sunrise Project. The first notice of
schedule, issued on March 9, 2016,
identified October 21, 2016 as the EIS
issuance date. Based on additional
information filed by Transco, however,
we intend to issue a draft General
Conformity Determination for the
Atlantic Sunrise Project with a 30-day
comment period. Commission staff has
therefore revised the schedule for
issuance of the final EIS.
asabaliauskas on DSK3SPTVN1PROD with NOTICES
Schedule for Environmental Review
4 For purposes of these charts, generation owner
is abbreviated to GO, transmission owner is
abbreviated to TO, reliability coordinator is
abbreviated to RC, and planning coordinator is
abbreviated to PC.
5 We estimate that an entity will experience a unit
failure greater than 90 days once every five years.
Therefore, 20 percent of NPCC’s 169 generator
owners and transmission owners will experience a
unit failure of this duration each year.
VerDate Sep<11>2014
18:25 Oct 25, 2016
Jkt 241001
Issuance of Notice of Availability of
the final EIS—December 30, 2016.
90-day Federal Authorization
Decision Deadline—March 30, 2017.
If a schedule change becomes
necessary, an additional notice will be
provided so that the relevant agencies
are kept informed of the project’s
progress.
Additional Information
In order to receive notification of the
issuance of the EIS and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
PO 00000
Frm 00030
Fmt 4703
Sfmt 4703
Dated: October 20, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016–25834 Filed 10–25–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2485–073]
FirstLight Hydro Generating Company;
Notice of Application Accepted for
Filing, Soliciting Comments, Motions
To Intervene, and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Application
for Temporary Amendment of Minimum
and Maximum Reservoir Elevation
Requirement.
b. Project No.: 2485–073.
c. Date Filed: September 16, 2016.
d. Applicant: FirstLight Hydro
Generating Company (FirstLight).
e. Name of Project: Northfield
Mountain Pumped Storage Project.
f. Location: The project is located on
the east side of the Connecticut River,
in the towns of Northfield and Erving,
in Franklin County, Massachusetts.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Mr. Gus Bakas,
Director—Massachusetts Hydro,
FirstLight Hydro Generating Company,
Northfield Mountain Station, 99 Millers
E:\FR\FM\26OCN1.SGM
26OCN1
Agencies
[Federal Register Volume 81, Number 207 (Wednesday, October 26, 2016)]
[Notices]
[Page 74420]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-25834]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP15-138-000]
Transcontinental Gas Pipe Line Company, LLC; Notice of Revised
Schedule for Environmental Review of the Atlantic Sunrise Project
This notice identifies the Federal Energy Regulatory Commission
(FERC or Commission) staff's revised schedule for the completion of the
environmental impact statement (EIS) for Transcontinental Gas Pipe Line
Company, LLC's (Transco) Atlantic Sunrise Project. The first notice of
schedule, issued on March 9, 2016, identified October 21, 2016 as the
EIS issuance date. Based on additional information filed by Transco,
however, we intend to issue a draft General Conformity Determination
for the Atlantic Sunrise Project with a 30-day comment period.
Commission staff has therefore revised the schedule for issuance of the
final EIS.
Schedule for Environmental Review
Issuance of Notice of Availability of the final EIS--December 30,
2016.
90-day Federal Authorization Decision Deadline--March 30, 2017.
If a schedule change becomes necessary, an additional notice will
be provided so that the relevant agencies are kept informed of the
project's progress.
Additional Information
In order to receive notification of the issuance of the EIS and to
keep track of all formal issuances and submittals in specific dockets,
the Commission offers a free service called eSubscription (https://www.ferc.gov/docs-filing/esubscription.asp).
Dated: October 20, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016-25834 Filed 10-25-16; 8:45 am]