Dairyland Power Cooperative: Notice of Intent To Prepare an Environmental Impact Statement and Hold Public Scoping Meetings, 71696-71697 [2016-25132]

Download as PDF 71696 Federal Register / Vol. 81, No. 201 / Tuesday, October 18, 2016 / Notices Washington, DC 20250. Telephone: (202) 401–0142. Email: maureen.hessel@wdc.usda.gov. VIII. Other Information A. Paperwork Reduction Act In accordance with the Paperwork Reduction Act of 1995, the information collection requirements associated with renewable energy system and energy efficiency improvements grants and guaranteed loans, as covered in this Notice, have been approved by the Office of Management and Budget (OMB) under OMB Control Number 0570–0050. The information collection requirements associated with energy audit and renewable energy development assistance grants have also been approved by OMB under OMB Control Number 0570–0059. B. Nondiscrimination Statement The U.S. Department of Agriculture (USDA) prohibits discrimination against its customers, employees, and applicants for employment on the basis of race, color, national origin, age, disability, sex, gender identity, reprisal and where applicable, political beliefs, marital status, familial or parental status, religion, sexual orientation, or all or part of an individual’s income is derived from any public assistance program, or protected genetic information in employment or in any program or activity conducted or funded by the Department. (Not all prohibited bases will apply to all programs and/or employment activities.) If you wish to file a Civil Rights program complaint of discrimination, complete the USDA Program Discrimination Complaint Form (PDF), found online at www.ascr.usda.gov/ complaint_filing_cust.html, or complete the form at any USDA office, or call (866) 632–9992 to request the form. You may also write a letter containing all of the information requested in the form. Send your completed complaint form or letter to us by mail at U.S. Department of Agriculture, Director, Office of Adjudication, 1400 Independence Avenue SW., Washington, DC 20250– 9410, by fax (202) 690–7442 or email at program.intake@usda.gov. Individuals who are deaf, hard of hearing or have speech disabilities and wish to file either an EEO or program complaint, please contact USDA through the Federal Relay Service at (800) 877–8339 or (800) 845–6136 (in Spanish). Persons with disabilities, who wish to file a program complaint, please see information above on how to contact us directly by mail or by email. If you require alternative means of communication for program information (e.g., Braille, large print, audiotape, etc.) please contact USDA’s TARGET Center at (202) 720–2600 (voice and TDD). Dated: October 12, 2016. Justin Hatmaker, Acting Administrator, Rural BusinessCooperative Service. [FR Doc. 2016–25163 Filed 10–17–16; 8:45 am] BILLING CODE 3410–XY–P DEPARTMENT OF AGRICULTURE Rural Utilities Service Dairyland Power Cooperative: Notice of Intent To Prepare an Environmental Impact Statement and Hold Public Scoping Meetings AGENCY: Rural Utilities Service, USDA. Notice of Intent to Prepare an Environmental Impact Statement and Hold Public Scoping Meetings. ACTION: The Rural Utilities Service (RUS) intends to prepare an Environmental Impact Statement (EIS) and hold public scoping meetings in connection with possible impacts related to the Cardinal-Hickory Creek Transmission Line Project proposed by Dairyland Power Cooperative (DPC). Other utilities participating in the Project are American Transmission Company LLC, by its corporate manager ATC Management Inc. and ITC Midwest LLC. The proposal consists of the construction of a 345-kilovolt (kV) transmission line and associated infrastructure connecting the Hickory Creek Substation in Dubuque County, Iowa, with the Cardinal Substation in the Town of Middleton, Wisconsin (near Madison, Wisconsin). The Project also includes a new intermediate 345/138-kV substation near the Village of Montfort in either Grant County or Iowa County, Wisconsin. The total length of the 345kV transmission lines associated with the proposed project will be approximately 125 miles. DPC and the other project participants have identified proposed and alternate segments and locations for transmission lines and associated facilities and for the intermediate substation. Dairyland Power Cooperative is requesting RUS to provide financing for its portion of the proposed project. SUMMARY: RUS will conduct four public scoping meetings in an open-house format at the following locations: DATES: Date Location Time Venue October 31, 2016 ................. Peosta, Iowa ...................... 3:00–6:00 p.m ................... November 1, 2016 ............... Cassville, Wisconsin .......... 4:00–7:00 p.m ................... November 2, 2016 ............... Dodgeville, Wisconsin ....... 4:00–7:00 p.m ................... November 3, 2016 ............... Middleton, Wisconsin ........ 4:00–7:00 p.m ................... Peosta Community Center, 7896 Burds Road, Peosta, IA 53068. Cassville Middle School Cafeteria, 715 E. Amelia Street, Cassville, WI 53806. Dodgeville Middle School Cafeteria, 951 Chapel St., Dodgeville, WI 53533. Madison Marriott West, 1313 John Q Hammons Dr., Middleton, WI 53562. To send comments or for further information, contact Dennis Rankin, Environmental Protection Specialist, U.S. Department of Agriculture, Rural Utilities Service, 1400 Independence Avenue SW., Room 2244, Stop 1571, Washington, DC 20250–1571 Email: dennis.rankin@ wdc.usda.gov Washington, DC 20250– 1571. Lhorne on DSK30JT082PROD with NOTICES ADDRESSES: VerDate Sep<11>2014 13:19 Oct 17, 2016 Jkt 241001 An Alternative Evaluation Study (AES) and Macro Corridor Study (MCS), prepared by Dairyland Power Cooperative, will be presented at the public scoping meetings. The reports are available for public review at the RUS address provided in this notice and at Dairyland Power Cooperative, 3251 East Avenue, South, La Crosse, WI 54602. In addition, the reports will be available at RUS’ Web site, https://www.rd.usda.gov/ PO 00000 Frm 00008 Fmt 4703 Sfmt 4703 publications/environmental-studies/ impact-statements and at local libraries in the project area. SUPPLEMENTARY INFORMATION: Preliminary proposed transmission line corridors, the siting area for the intermediate substation, and the two existing end-point substations have been identified. The EIS will address the construction, operation, and E:\FR\FM\18OCN1.SGM 18OCN1 Lhorne on DSK30JT082PROD with NOTICES Federal Register / Vol. 81, No. 201 / Tuesday, October 18, 2016 / Notices management of the proposed project, which includes the following: A new 345-kV terminal within the existing Hickory Creek Substation in Dubuque County, Iowa; a new intermediate 345/ 138-kV substation near the Village of Montfort in either Grant or Iowa County, Wisconsin; a new 345-kV terminal within the existing Cardinal Substation in the Town of Middleton in Dane County, Wisconsin; a new 45- to 65-mile (depending on the final route) 345-kV transmission line between the Hickory Creek Substation and the intermediate substation; a new 45- to 60-mile (depending on the final route) 345-kV transmission line between the intermediate substation and the existing Cardinal Substation; a short, less than one-mile, 69-kV line in Iowa; facility reinforcement needed in Iowa and Wisconsin; construction and maintenance of access roads for all proposed transmission lines and rebuild of the Turkey River Substation in Dubuque County, Iowa with two 161/69 kV transformers, four 161-kV circuit breakers, and three 69-kV circuit breakers. Total length of the transmission lines for the proposed project will be approximately 125 miles. The project study area includes part or all of the following counties in Iowa: Clayton and Dubuque. In Wisconsin, the project area includes parts of the following counties: Dane, Grant, Iowa, and Lafayette. Among the alternatives RUS will address in the EIS is the No Action alternative, under which the project would not be undertaken. In the EIS, the effects of the proposed project will be compared to the existing conditions in the area affected. Alternative transmission line corridors and the intermediate substation location will be refined as part of the EIS scoping process and will be addressed in the Draft EIS. RUS will carefully study public health and safety, environmental impacts, and engineering aspects of the proposed project and all related facilities. The U.S. Army Corps of Engineers (USACE) and the U.S. Fish and Wildlife Service (USFWS) are participating in the environmental review process as cooperating agencies, with RUS as the lead Federal agency. RUS will use input provided by government agencies, private organizations, and the public in the preparation of the Draft EIS. The Draft EIS will be available for review and comment for 45 days. A Final EIS that considers all comments received will subsequently be prepared. The Final EIS will be available for review and comment for 30 days. Following the 30- VerDate Sep<11>2014 13:19 Oct 17, 2016 Jkt 241001 day comment period, RUS will prepare a Record of Decision (ROD). Notices announcing the availability of the Draft EIS, the Final EIS, and the ROD will be published in the Federal Register and in local newspapers. Any final action by RUS related to the proposed project will be subject to, and contingent upon, compliance with all relevant federal, state, and local environmental laws and regulations and completion of the environmental review requirements as prescribed in the RUS Environmental Policies and Procedures (7 CFR part 1970). Dated: October 12, 2016. Kellie Kubena, Director, Engineering and Environmental Staff, Rural Utilities Service. [FR Doc. 2016–25132 Filed 10–17–16; 8:45 am] BILLING CODE P DEPARTMENT OF COMMERCE Bureau of Industry and Security Discontinuance of Information Collection 0694–0009: Triangular Transactions ‘‘Stamp’’ Covered by a U.S. Import Certificate Bureau of Industry and Security, Commere. AGENCY: ACTION: Notice. The Department of Commerce, as part of its continuing effort to reduce paperwork and respondent burden, has discontinued Information Collection 0694–0009, ‘‘Triangular Transactions Covered by a U.S. Import Certificate.’’ Although this collection has been discontinued, the Triangular Transactions ‘‘Stamp’’ is still valid and has been added to collection 0694–0017 as a supplemental document. SUMMARY: FOR FURTHER INFORMATION CONTACT: Requests for additional information should be directed to Mark Crace, BIS ICB Liaison, (202)482–8093 or Mark.Crace@bis.doc.gov. Sheleen Dumas, Departmental PRA Lead, Office of the Chief Information Officer. [FR Doc. 2016–25125 Filed 10–17–16; 8:45 am] BILLING CODE 3510–33–P PO 00000 71697 DEPARTMENT OF COMMERCE International Trade Administration [A–588–876, A–583–859, A–489–829] Steel Concrete Reinforcing Bar From Japan, Taiwan and the Republic of Turkey: Initiation of Less-Than-FairValue Investigations Enforcement and Compliance, International Trade Administration, Department of Commerce. DATES: Effective October 11, 2016. FOR FURTHER INFORMATION CONTACT: Emily Halle at (202) 482–0176 (Japan); Jun Jack Zhao at (202) 482–1396 (Taiwan); and Myrna Lobo at (202) 482– 2371 (Republic of Turkey), AD/CVD Operations, Enforcement and Compliance, U.S. Department of Commerce, 14th Street and Constitution Avenue NW., Washington, DC 20230. SUPPLEMENTARY INFORMATION: AGENCY: The Petitions On September 20, 2016, the Department of Commerce (the Department) received antidumping duty (AD) petitions concerning imports of steel concrete reinforcing bar (rebar) from Japan, Taiwan, and the Republic of Turkey (Turkey), filed in proper form on behalf of the Rebar Trade Action Coalition and its individual members (Petitioners).1 The Petitions were accompanied by a countervailing duty (CVD) petition on rebar from Turkey.2 Petitioners are domestic producers of rebar.3 On September 23 and 30, 2016, the Department requested additional information and clarification of certain areas of the Petitions.4 Petitioners filed 1 See Petition for the Imposition of Antidumping and Countervailing Duties: Steel Concrete Reinforcing Bar from Japan, Taiwan, and the Republic of Turkey, dated September 20, 2016 (the Petitions). The individual members of the Rebar Trade Action Coalition are Bayou Steel Group, Byer Steel Group, Inc., Commercial Metals Company, Gerdau Ameristeel U.S. Inc., Nucor Corporation, and Steel Dynamics, Inc. 2 Id. 3 See Volume I of the Petitions, at 2 and Exhibits I–1. 4 See Letter from the Department to Petitioners entitled ‘‘Petitions for the Imposition of Antidumping Duties on Imports of Steel Concrete Reinforcing Bar from Japan, Taiwan, and the Republic of Turkey and Countervailing Duties on Imports of Steel Concrete Reinforcing Bar from the Republic of Turkey: Supplemental Questions,’’ dated September 23, 2016 (General Issues Supplemental Questionnaire); see also Letter from the Department to Petitioners entitled ‘‘Petition for the Imposition of Antidumping Duties on Imports of Steel Concrete Reinforcing Bar from Japan: Supplemental Questions,’’ dated September 23, 2016 (Japan Supplemental Questionnaire); see also Letter from the Department to Petitioners entitled Continued Frm 00009 Fmt 4703 Sfmt 4703 E:\FR\FM\18OCN1.SGM 18OCN1

Agencies

[Federal Register Volume 81, Number 201 (Tuesday, October 18, 2016)]
[Notices]
[Pages 71696-71697]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-25132]


-----------------------------------------------------------------------

DEPARTMENT OF AGRICULTURE

Rural Utilities Service


Dairyland Power Cooperative: Notice of Intent To Prepare an 
Environmental Impact Statement and Hold Public Scoping Meetings

AGENCY: Rural Utilities Service, USDA.

ACTION: Notice of Intent to Prepare an Environmental Impact Statement 
and Hold Public Scoping Meetings.

-----------------------------------------------------------------------

SUMMARY: The Rural Utilities Service (RUS) intends to prepare an 
Environmental Impact Statement (EIS) and hold public scoping meetings 
in connection with possible impacts related to the Cardinal-Hickory 
Creek Transmission Line Project proposed by Dairyland Power Cooperative 
(DPC). Other utilities participating in the Project are American 
Transmission Company LLC, by its corporate manager ATC Management Inc. 
and ITC Midwest LLC.
    The proposal consists of the construction of a 345-kilovolt (kV) 
transmission line and associated infrastructure connecting the Hickory 
Creek Substation in Dubuque County, Iowa, with the Cardinal Substation 
in the Town of Middleton, Wisconsin (near Madison, Wisconsin). The 
Project also includes a new intermediate 345/138-kV substation near the 
Village of Montfort in either Grant County or Iowa County, Wisconsin. 
The total length of the 345-kV transmission lines associated with the 
proposed project will be approximately 125 miles. DPC and the other 
project participants have identified proposed and alternate segments 
and locations for transmission lines and associated facilities and for 
the intermediate substation. Dairyland Power Cooperative is requesting 
RUS to provide financing for its portion of the proposed project.

DATES: RUS will conduct four public scoping meetings in an open-house 
format at the following locations:

----------------------------------------------------------------------------------------------------------------
                Date                        Location                  Time                      Venue
----------------------------------------------------------------------------------------------------------------
October 31, 2016...................  Peosta, Iowa..........  3:00-6:00 p.m.........  Peosta Community Center,
                                                                                      7896 Burds Road, Peosta,
                                                                                      IA 53068.
November 1, 2016...................  Cassville, Wisconsin..  4:00-7:00 p.m.........  Cassville Middle School
                                                                                      Cafeteria, 715 E. Amelia
                                                                                      Street, Cassville, WI
                                                                                      53806.
November 2, 2016...................  Dodgeville, Wisconsin.  4:00-7:00 p.m.........  Dodgeville Middle School
                                                                                      Cafeteria, 951 Chapel St.,
                                                                                      Dodgeville, WI 53533.
November 3, 2016...................  Middleton, Wisconsin..  4:00-7:00 p.m.........  Madison Marriott West, 1313
                                                                                      John Q Hammons Dr.,
                                                                                      Middleton, WI 53562.
----------------------------------------------------------------------------------------------------------------


ADDRESSES: To send comments or for further information, contact Dennis 
Rankin, Environmental Protection Specialist, U.S. Department of 
Agriculture, Rural Utilities Service, 1400 Independence Avenue SW., 
Room 2244, Stop 1571, Washington, DC 20250-1571 Email: 
dennis.rankin@wdc.usda.gov Washington, DC 20250-1571.
    An Alternative Evaluation Study (AES) and Macro Corridor Study 
(MCS), prepared by Dairyland Power Cooperative, will be presented at 
the public scoping meetings. The reports are available for public 
review at the RUS address provided in this notice and at Dairyland 
Power Cooperative, 3251 East Avenue, South, La Crosse, WI 54602. In 
addition, the reports will be available at RUS' Web site, https://www.rd.usda.gov/publications/environmental-studies/impact-statements 
and at local libraries in the project area.

SUPPLEMENTARY INFORMATION: Preliminary proposed transmission line 
corridors, the siting area for the intermediate substation, and the two 
existing end-point substations have been identified. The EIS will 
address the construction, operation, and

[[Page 71697]]

management of the proposed project, which includes the following: A new 
345-kV terminal within the existing Hickory Creek Substation in Dubuque 
County, Iowa; a new intermediate 345/138-kV substation near the Village 
of Montfort in either Grant or Iowa County, Wisconsin; a new 345-kV 
terminal within the existing Cardinal Substation in the Town of 
Middleton in Dane County, Wisconsin; a new 45- to 65-mile (depending on 
the final route) 345-kV transmission line between the Hickory Creek 
Substation and the intermediate substation; a new 45- to 60-mile 
(depending on the final route) 345-kV transmission line between the 
intermediate substation and the existing Cardinal Substation; a short, 
less than one-mile, 69-kV line in Iowa; facility reinforcement needed 
in Iowa and Wisconsin; construction and maintenance of access roads for 
all proposed transmission lines and rebuild of the Turkey River 
Substation in Dubuque County, Iowa with two 161/69 kV transformers, 
four 161-kV circuit breakers, and three 69-kV circuit breakers.
    Total length of the transmission lines for the proposed project 
will be approximately 125 miles. The project study area includes part 
or all of the following counties in Iowa: Clayton and Dubuque. In 
Wisconsin, the project area includes parts of the following counties: 
Dane, Grant, Iowa, and Lafayette.
    Among the alternatives RUS will address in the EIS is the No Action 
alternative, under which the project would not be undertaken. In the 
EIS, the effects of the proposed project will be compared to the 
existing conditions in the area affected. Alternative transmission line 
corridors and the intermediate substation location will be refined as 
part of the EIS scoping process and will be addressed in the Draft EIS. 
RUS will carefully study public health and safety, environmental 
impacts, and engineering aspects of the proposed project and all 
related facilities.
    The U.S. Army Corps of Engineers (USACE) and the U.S. Fish and 
Wildlife Service (USFWS) are participating in the environmental review 
process as cooperating agencies, with RUS as the lead Federal agency.
    RUS will use input provided by government agencies, private 
organizations, and the public in the preparation of the Draft EIS. The 
Draft EIS will be available for review and comment for 45 days. A Final 
EIS that considers all comments received will subsequently be prepared. 
The Final EIS will be available for review and comment for 30 days. 
Following the 30- day comment period, RUS will prepare a Record of 
Decision (ROD). Notices announcing the availability of the Draft EIS, 
the Final EIS, and the ROD will be published in the Federal Register 
and in local newspapers.
    Any final action by RUS related to the proposed project will be 
subject to, and contingent upon, compliance with all relevant federal, 
state, and local environmental laws and regulations and completion of 
the environmental review requirements as prescribed in the RUS 
Environmental Policies and Procedures (7 CFR part 1970).

    Dated: October 12, 2016.
Kellie Kubena,
Director, Engineering and Environmental Staff, Rural Utilities Service.
[FR Doc. 2016-25132 Filed 10-17-16; 8:45 am]