Vogtle Electric Generating Plant, Units 3 and 4, 69553-69554 [2016-24192]
Download as PDF
Federal Register / Vol. 81, No. 194 / Thursday, October 6, 2016 / Notices
Dated: October 3, 2016.
Crystal Robinson,
Committee Management Officer.
[FR Doc. 2016–24176 Filed 10–5–16; 8:45 am]
BILLING CODE 7555–01–P
NUCLEAR REGULATORY
COMMISSION
[NRC–2016–0001]
Sunshine Act Meeting Notice
Week of October 3, 2016.
Commissioners’ Conference
Room, 11555 Rockville Pike, Rockville,
Maryland.
STATUS: Public.
DATE:
PLACE:
Wednesday, October 5, 2016
8:55 a.m. Affirmation Session (Public
Meeting) (Tentative)
U.S. Department of Energy (Export of
93.20% Enriched Uranium)
(Petition Seeking Leave to Intervene
and Request for Hearing)
(Tentative).
This meeting will be webcast live at
the Web address—https://www.nrc.gov/.
*
*
*
*
*
The schedule for Commission
meetings is subject to change on short
notice. For more information or to verify
the status of meetings, contact Denise
McGovern at 301–415–0681 or via email
at Denise.McGovern@nrc.gov.
*
*
*
*
*
sradovich on DSK3GMQ082PROD with NOTICES
Additional Information
By a vote of 3–0 on October 3, 2016,
the Commission determined pursuant to
U.S.C. 552b(e) and ’9.107(a) of the
Commission’s rules that the above
referenced Affirmation Session be held
with less than one week notice to the
public. The meeting is scheduled on
October 5, 2016.
*
*
*
*
*
The NRC Commission Meeting
Schedule can be found on the Internet
at: https://www.nrc.gov/public-involve/
public-meetings/schedule.html.
*
*
*
*
*
The NRC provides reasonable
accommodation to individuals with
disabilities where appropriate. If you
need a reasonable accommodation to
participate in these public meetings, or
need this meeting notice or the
transcript or other information from the
public meetings in another format (e.g.
braille, large print), please notify
Kimberly Meyer, NRC Disability
Program Manager, at 301–287–0739, by
videophone at 240–428–3217, or by
18:46 Oct 05, 2016
Dated: October 3, 2016.
Denise L. McGovern,
Policy Coordinator, Office of the Secretary.
[FR Doc. 2016–24389 Filed 10–4–16; 4:15 pm]
BILLING CODE 7590–01–P
Week of October 3, 2016
VerDate Sep<11>2014
email at Kimberly.Meyer-Chambers@
nrc.gov. Determinations on requests for
reasonable accommodation will be
made on a case-by-case basis.
*
*
*
*
*
Members of the public may request to
receive this information electronically.
If you would like to be added to the
distribution, please contact the Nuclear
Regulatory Commission, Office of the
Secretary, Washington, DC 20555 (301–
415–1969), or email
Brenda.Akstulewicz@nrc.gov or
Patricia.Jimenez@nrc.gov.
Jkt 241001
NUCLEAR REGULATORY
COMMISSION
SUPPLEMENTARY INFORMATION:
Vogtle Electric Generating Plant, Units
3 and 4
Nuclear Regulatory
Commission.
ACTION: Determination of the successful
completion of inspections, tests, and
analyses.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) staff has determined
that the inspections, tests, and analyses
have been successfully completed, and
that the specified acceptance criteria are
met for multiple inspections, tests,
analyses, and acceptance criteria
(ITAAC) for the Vogtle Electric
Generating Plant (VEGP), Units 3 and 4.
ADDRESSES: Please refer to Docket ID
NRC–2008–0252 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly-available
information related to this document
using any of the following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2008–0252. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–415–3463;
email: Carol.Gallagher@nrc.gov. For
technical questions, contact the
individual listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘ADAMS Public Documents’’ and then
SUMMARY:
Frm 00045
Fmt 4703
select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The
ADAMS accession number for each
document referenced in this document
(if that document is available in
ADAMS) is provided the first time that
a document is referenced.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT:
Chandu Patel, Office of New Reactors,
U.S. Nuclear Regulatory Commission,
Washington, DC 20555–0001; telephone:
301–415–3025; email:
Chandu.Patel@nrc.gov.
I. Licensee Notification of Completion
of ITAAC
[NRC–2008–0252]
PO 00000
69553
Sfmt 4703
Southern Nuclear Operating
Company, Inc. (SNC), Georgia Power
Company, Oglethorpe Power
Corporation, MEAG Power SPVM, LLC.,
MEAG Power SPVJ, LLC., MEAG Power
SPVP, LLC., and the City of Dalton,
Georgia, (hereafter called the licensee)
has submitted ITAAC closure
notifications (ICNs) under § 52.99(c)(1)
of title 10 of the Code of Federal
Regulations (10 CFR), informing the
NRC that the licensee has successfully
performed the required inspections,
tests, and analyses, and that the
acceptance criteria are met for:
VEGP Unit 3 ITAAC
2.1.02.08a.ii (29), 2.2.03.08c.vi.01 (189),
2.2.03.08c.vi.02 (190), 2.5.01.03c
(513), 2.5.02.13 (552), and
E.3.9.05.01.05 (853)
VEGP Unit 4 ITAAC
2.1.02.08a.ii (29), 2.2.03.08c.vi.01 (189),
2.2.03.08c.vi.02 (190), 2.5.01.03c
(513), and 2.5.02.13 (552)
The ITAAC for VEGP Unit 3 are in
Appendix C of the VEGP Unit 3
combined license (ADAMS Accession
No. ML14100A106). The ITAAC for
VEGP Unit 4 are in Appendix C of VEGP
Unit 4 combined license (ADAMS
Accession No. ML14100A135).
II. NRC Staff Determination of
Completion of ITAAC
The NRC staff has determined that the
specified inspections, tests, and
analyses have been successfully
completed, and that the specified
acceptance criteria are met. The
documentation of the NRC staff’s
E:\FR\FM\06OCN1.SGM
06OCN1
69554
Federal Register / Vol. 81, No. 194 / Thursday, October 6, 2016 / Notices
determination is in the ITAAC Closure
Verification Evaluation Form (VEF) for
each ITAAC. The VEF is a form that
represents the NRC staff’s structured
process for reviewing ICNs. Each ICN
presents a narrative description of how
the ITAAC was completed. The NRC’s
ICN review process involves a
determination on whether, among other
things: (1) Each ICN provides sufficient
information, including a summary of the
methodology used to perform the
ITAAC, to demonstrate that the
inspections, tests, and analyses have
been successfully completed; (2) each
ICN provides sufficient information to
demonstrate that the acceptance criteria
of the ITAAC are met; and (3) any NRC
inspections for the ITAAC have been
completed and any ITAAC findings
associated with that ITAAC have been
closed.
The NRC staff’s determination of the
successful completion of these ITAAC is
based on information available at this
time and is subject to the licensee’s
ability to maintain the condition that
the acceptance criteria are met. If the
staff receives new information that
suggests the staff’s determination on any
of these ITAAC is incorrect, then the
staff will determine whether to reopen
that ITAAC (including withdrawing the
staff’s determination on that ITAAC).
The NRC staff’s determination will be
used to support a subsequent finding,
pursuant to 10 CFR 52.103(g), at the end
of construction that all acceptance
criteria in the combined license are met.
The ITAAC closure process is not
finalized for these ITAAC until the NRC
makes an affirmative finding under 10
CFR 52.103(g). Any future updates to
the status of these ITAAC will be
reflected on the NRC’s Web site at
https://www.nrc.gov/reactors/newreactors/oversight/itaac.html.
This notice fulfills the staff’s
obligations under 10 CFR 52.99(e)(1) to
publish a notice in the Federal Register
of the NRC staff’s determination of the
successful completion of inspections,
tests and analyses.
sradovich on DSK3GMQ082PROD with NOTICES
Vogtle Electric Generating Plant Unit 3,
Docket No. 5200025
A complete list of the review status
for VEGP Unit 3 ITAAC, including the
submission date and ADAMS Accession
Number for each ICN received, the
ADAMS Accession Number for each
VEF, and the ADAMS Accession
Numbers for the inspection reports
associated with these specific ITAAC,
can be found on the NRC’s Web site at
https://www.nrc.gov/reactors/newreactors/new-licensing-files/vog3icnsr.pdf.
VerDate Sep<11>2014
18:46 Oct 05, 2016
Jkt 241001
Vogtle Electric Generating Plant Unit 4,
Docket No. 5200026
A complete list of the review status
for VEGP Unit 4 ITAAC, including the
submission date and ADAMS Accession
Number for each ICN received, the
ADAMS Accession Number for each
VEF, and the ADAMS Accession
Numbers for the inspection reports
associated with these specific ITAAC,
can be found on the NRC’s Web site at
https://www.nrc.gov/reactors/newreactors/new-licensing-files/vog4icnsr.pdf.
Dated at Rockville, Maryland, this 29th day
of September 2016.
For the Nuclear Regulatory Commission.
Jennifer Dixon-Herrity,
Acting Chief, Licensing Branch 4, Division
of New Reactor Licensing, Office of New
Reactors.
[FR Doc. 2016–24192 Filed 10–5–16; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket No. 40–09091; NRC–2011–0148]
Strata Energy, Inc.; Ross Uranium InSitu Recovery Facility; Source and
Byproduct Materials License
Nuclear Regulatory
Commission.
ACTION: Record of decision; update.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) has issued an
updated Record of Decision (ROD)
related to the license for Strata Energy,
Inc. (Strata), Ross Uranium In-Situ
Recovery (ISR) Facility in Crook County,
Wyoming. Strata’s request for a source
and byproduct materials license for the
Ross ISR facility was contested through
the NRC’s adjudicatory process. On June
29, 2016, the Commission denied a
petition for review of the Atomic Safety
and Licensing Board’s (ASLB) decision.
The ROD has been updated to account
for the ASLB’s decision and the
Commission’s ruling.
DATES: The ROD was updated as of
September 28, 2016.
ADDRESSES: Please refer to Docket ID
NRC–2011–0148 when contacting the
NRC about the availability of
information regarding this document.
You may access publicly-available
information related to this document
using any of the following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2011–0148. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–415–3463;
SUMMARY:
PO 00000
Frm 00046
Fmt 4703
Sfmt 4703
email: Carol.Gallagher@nrc.gov. For
technical questions, contact the
individual listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘ADAMS Public Documents’’ and then
select ‘‘Begin WBA Search.’’ For
problems with ADAMS, please contact
the NRC’s Public Document Room (PDR)
reference staff at 1–800–397–4209, 301–
415–4737, or by email to pdr.resource@
nrc.gov. For the convenience of the
reader, the ADAMS accession numbers
are provided in a table in the
‘‘Availability of Documents’’ section of
this document.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT:
Jessie Muir-Quintero, Office of Nuclear
Material Safety and Safeguards, U.S.
Nuclear Regulatory Commission,
Washington DC 20555–0001; telephone:
301–415–7476; email: Jessie.MuirQuintero@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Discussion
The NRC issued a license to Strata for
its Ross ISR Facility in Crook County,
Wyoming in April 2014. Along with the
issuance of the license, the NRC
published a ROD that supported its
decision to approve Strata’s license
application for the Ross ISR Facility.
After the license was issued, the
NRC’s ASLB, an independent, trial-level
adjudicatory body, granted a hearing
request from joint intervenors, the
Natural Resources Defense Council and
the Powder River Basin Resource
Council. The ASLB held an evidentiary
hearing from September 30, 2014,
through October 1, 2014, for three
admitted contentions on environmental
matters related to the licensing of the
Ross ISR Facility. In its initial decision
following the hearing, the ASLB ruled
in favor of Strata and the NRC on all
three contentions. In doing so, the ASLB
supplemented the ROD to include a
revised license condition (10.12) and
additional analyses that were placed on
the record by various parties. In June
2016, the Commission denied a petition
for review of the ASLB’s decision. The
NRC’s initial ROD was published on
April 24, 2014. The updated ROD
E:\FR\FM\06OCN1.SGM
06OCN1
Agencies
[Federal Register Volume 81, Number 194 (Thursday, October 6, 2016)]
[Notices]
[Pages 69553-69554]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-24192]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[NRC-2008-0252]
Vogtle Electric Generating Plant, Units 3 and 4
AGENCY: Nuclear Regulatory Commission.
ACTION: Determination of the successful completion of inspections,
tests, and analyses.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) staff has
determined that the inspections, tests, and analyses have been
successfully completed, and that the specified acceptance criteria are
met for multiple inspections, tests, analyses, and acceptance criteria
(ITAAC) for the Vogtle Electric Generating Plant (VEGP), Units 3 and 4.
ADDRESSES: Please refer to Docket ID NRC-2008-0252 when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly-available information related to this document
using any of the following methods:
Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2008-0252. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: Carol.Gallagher@nrc.gov. For technical questions, contact
the individual listed in the FOR FURTHER INFORMATION CONTACT section of
this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly-available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS,
please contact the NRC's Public Document Room (PDR) reference staff at
1-800-397-4209, 301-415-4737, or by email to pdr.resource@nrc.gov. The
ADAMS accession number for each document referenced in this document
(if that document is available in ADAMS) is provided the first time
that a document is referenced.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: Chandu Patel, Office of New Reactors,
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001;
telephone: 301-415-3025; email: Chandu.Patel@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Licensee Notification of Completion of ITAAC
Southern Nuclear Operating Company, Inc. (SNC), Georgia Power
Company, Oglethorpe Power Corporation, MEAG Power SPVM, LLC., MEAG
Power SPVJ, LLC., MEAG Power SPVP, LLC., and the City of Dalton,
Georgia, (hereafter called the licensee) has submitted ITAAC closure
notifications (ICNs) under Sec. 52.99(c)(1) of title 10 of the Code of
Federal Regulations (10 CFR), informing the NRC that the licensee has
successfully performed the required inspections, tests, and analyses,
and that the acceptance criteria are met for:
VEGP Unit 3 ITAAC
2.1.02.08a.ii (29), 2.2.03.08c.vi.01 (189), 2.2.03.08c.vi.02 (190),
2.5.01.03c (513), 2.5.02.13 (552), and E.3.9.05.01.05 (853)
VEGP Unit 4 ITAAC
2.1.02.08a.ii (29), 2.2.03.08c.vi.01 (189), 2.2.03.08c.vi.02 (190),
2.5.01.03c (513), and 2.5.02.13 (552)
The ITAAC for VEGP Unit 3 are in Appendix C of the VEGP Unit 3
combined license (ADAMS Accession No. ML14100A106). The ITAAC for VEGP
Unit 4 are in Appendix C of VEGP Unit 4 combined license (ADAMS
Accession No. ML14100A135).
II. NRC Staff Determination of Completion of ITAAC
The NRC staff has determined that the specified inspections, tests,
and analyses have been successfully completed, and that the specified
acceptance criteria are met. The documentation of the NRC staff's
[[Page 69554]]
determination is in the ITAAC Closure Verification Evaluation Form
(VEF) for each ITAAC. The VEF is a form that represents the NRC staff's
structured process for reviewing ICNs. Each ICN presents a narrative
description of how the ITAAC was completed. The NRC's ICN review
process involves a determination on whether, among other things: (1)
Each ICN provides sufficient information, including a summary of the
methodology used to perform the ITAAC, to demonstrate that the
inspections, tests, and analyses have been successfully completed; (2)
each ICN provides sufficient information to demonstrate that the
acceptance criteria of the ITAAC are met; and (3) any NRC inspections
for the ITAAC have been completed and any ITAAC findings associated
with that ITAAC have been closed.
The NRC staff's determination of the successful completion of these
ITAAC is based on information available at this time and is subject to
the licensee's ability to maintain the condition that the acceptance
criteria are met. If the staff receives new information that suggests
the staff's determination on any of these ITAAC is incorrect, then the
staff will determine whether to reopen that ITAAC (including
withdrawing the staff's determination on that ITAAC). The NRC staff's
determination will be used to support a subsequent finding, pursuant to
10 CFR 52.103(g), at the end of construction that all acceptance
criteria in the combined license are met. The ITAAC closure process is
not finalized for these ITAAC until the NRC makes an affirmative
finding under 10 CFR 52.103(g). Any future updates to the status of
these ITAAC will be reflected on the NRC's Web site at https://www.nrc.gov/reactors/new-reactors/oversight/itaac.html.
This notice fulfills the staff's obligations under 10 CFR
52.99(e)(1) to publish a notice in the Federal Register of the NRC
staff's determination of the successful completion of inspections,
tests and analyses.
Vogtle Electric Generating Plant Unit 3, Docket No. 5200025
A complete list of the review status for VEGP Unit 3 ITAAC,
including the submission date and ADAMS Accession Number for each ICN
received, the ADAMS Accession Number for each VEF, and the ADAMS
Accession Numbers for the inspection reports associated with these
specific ITAAC, can be found on the NRC's Web site at https://www.nrc.gov/reactors/new-reactors/new-licensing-files/vog3-icnsr.pdf.
Vogtle Electric Generating Plant Unit 4, Docket No. 5200026
A complete list of the review status for VEGP Unit 4 ITAAC,
including the submission date and ADAMS Accession Number for each ICN
received, the ADAMS Accession Number for each VEF, and the ADAMS
Accession Numbers for the inspection reports associated with these
specific ITAAC, can be found on the NRC's Web site at https://www.nrc.gov/reactors/new-reactors/new-licensing-files/vog4-icnsr.pdf.
Dated at Rockville, Maryland, this 29th day of September 2016.
For the Nuclear Regulatory Commission.
Jennifer Dixon-Herrity,
Acting Chief, Licensing Branch 4, Division of New Reactor Licensing,
Office of New Reactors.
[FR Doc. 2016-24192 Filed 10-5-16; 8:45 am]
BILLING CODE 7590-01-P