Natural Gas Pipeline Company of America; Notice of Intent To Prepare an Environmental Assessment for the Proposed Gulf Coast Expansion Project, and Request for Comments on Environmental Issues, 64453-64455 [2016-22600]
Download as PDF
Federal Register / Vol. 81, No. 182 / Tuesday, September 20, 2016 / Notices
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–2376–049.
Dated: September 12, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016–22597 Filed 9–19–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. EL16–115–000]
Windham Solar, LLC, Allco Finance
Limited; Notice of Petition for
Enforcement
sradovich on DSK3GMQ082PROD with NOTICES
Windham Solar, LLC: QF16–362–002,
QF16–363–002, QF16–364–002, QF16–365–
002, QF16–366–002, QF16–367–002, QF16–
368–002, QF16–369–002, QF16–370–002,
QF16–371–002, QF16–372–002, QF16–373–
002, QF16–374–002, QF16–375–002, QF16–
376–002, QF16–377–002, QF16–378–002,
QF16–379–002, QF16–380–002, QF16–381–
002, QF16–382–002, QF16–383–002, QF16–
384–002, QF16–385–002, QF16–386–002,
QF16–387–002
Take notice that on September 12,
2016, pursuant to section 210(h)(2)(B) of
the Public Utility Regulatory Policies
Act of 1978 (PURPA), 16 U.S.C. 824a–
3(h), Windham Solar LLC and Allco
Finance Limited filed a Petition for
Enforcement requesting the Federal
Energy Regulatory Commission
(Commission) exercise its authority and
initiate enforcement action against the
Connecticut Public Utilities Regulatory
Authority to remedy its implementation
of PURPA, all as more fully explained
in the petition.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. On or before the
comment date, it is not necessary to
VerDate Sep<11>2014
17:13 Sep 19, 2016
Jkt 238001
serve motions to intervene or protests
on persons other than the Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 5 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5:00 p.m. Eastern
Time on October 3, 2016.
Dated: September 13, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016–22601 Filed 9–19–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No.CP16–488–000]
Natural Gas Pipeline Company of
America; Notice of Intent To Prepare
an Environmental Assessment for the
Proposed Gulf Coast Expansion
Project, and Request for Comments on
Environmental Issues
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Gulf Coast Expansion Project
involving construction and operation of
facilities by Natural Gas Pipeline
Company of America, LLC (Natural) in
Cass and Wharton Counties, Texas. The
Commission will use this EA in its
decision-making process to determine
whether the Project is in the public
convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the project.
You can make a difference by providing
us with your specific comments or
PO 00000
Frm 00026
Fmt 4703
Sfmt 4703
64453
concerns about the project. Your
comments should focus on the potential
environmental effects, reasonable
alternatives, and measures to avoid or
lessen environmental impacts. Your
input will help the Commission staff
determine what issues they need to
evaluate in the EA. To ensure that your
comments are timely and properly
recorded, please send your comments so
that the Commission receives them in
Washington, DC on or before October
14, 2016.
If you sent comments on this project
to the Commission before the opening of
this docket on August 1, 2016, you will
need to file those comments in Docket
No. CP16–488–000 to ensure they are
considered as part of this proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives should
notify their constituents of this
proposed project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The company would
seek to negotiate a mutually acceptable
agreement. However, if the Commission
approves the project, that approval
conveys with it the right of eminent
domain. Therefore, if easement
negotiations fail to produce an
agreement, the pipeline company could
initiate condemnation proceedings
where compensation would be
determined in accordance with state
law.
Natural provided landowners with a
fact sheet prepared by the FERC entitled
‘‘An Interstate Natural Gas Facility On
My Land? What Do I Need To Know?’’
This fact sheet addresses a number of
typically asked questions, including the
use of eminent domain and how to
participate in the Commission’s
proceedings. It is also available for
viewing on the FERC Web site
(www.ferc.gov).
Public Participation
For your convenience, there are three
methods you can use to submit your
comments to the Commission. The
Commission encourages electronic filing
of comments and has expert staff
available to assist you at (202) 502–8258
or efiling@ferc.gov. Please carefully
follow these instructions so that your
comments are properly recorded.
(1) You can file your comments
electronically using the eComment
feature on the Commission’s Web site
(www.ferc.gov) under the link to
E:\FR\FM\20SEN1.SGM
20SEN1
64454
Federal Register / Vol. 81, No. 182 / Tuesday, September 20, 2016 / Notices
Documents and Filings. This is an easy
method for submitting brief, text-only
comments on a project;
(2) You can file your comments
electronically by using the eFiling
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. With eFiling,
you can provide comments in a variety
of formats by attaching them as a file
with your submission. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ If you are filing
a comment on a particular project,
please select ‘‘Comment on a Filing’’ as
the filing type; or
(3) You can file a paper copy of your
comments by mailing them to the
following address. Be sure to reference
the project docket number (CP16–488–
000) with your submission: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Room 1A, Washington, DC 20426.
Summary of the Proposed Project
Natural proposes to construct and
operate a new compressor station,
identified as Compressor Station 394
(CS 394), and a new approximately
4,000-foot-long, 30-inch-diameter
lateral, with connections to Natural’s
existing Gulf Coast Line and A/G Line
in Cass County, Texas. Natural is also
requesting authorization to abandon two
compressor units at its Compressor
Station 301 (CS 301) located in Wharton
County, Texas. The Project would
provide about 460,000 dekatherms of
incremental southbound transportation
capacity from existing receipt points on
Natural’s Gulf Coast System to delivery
points in Natural’s South Texas Zone.
The general location of the project
facilities is shown in appendix 1.1
Land Requirements for Construction
Construction of the proposed facilities
would disturb about 39.9 acres of land
for the aboveground facilities and the
pipeline. Following construction,
Natural would maintain about 27.3
acres for permanent operation of the
project’s facilities. The remaining 12.6
acres would only be used for
construction and be allowed to
revegetate.
sradovich on DSK3GMQ082PROD with NOTICES
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
1 The appendices referenced in this notice will
not appear in the Federal Register. Copies of
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’ or from the
Commission’s Public Reference Room, 888 First
Street NE., Washington, DC 20426, or call (202)
502–8371. For instructions on connecting to
eLibrary, refer to the last page of this notice.
VerDate Sep<11>2014
17:13 Sep 19, 2016
Jkt 238001
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us 2 to
discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping.’’ The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
notice, the Commission requests public
comments on the scope of the issues to
address in the EA. We will consider all
filed comments during the preparation
of the EA.
In the EA we will discuss impacts that
could occur as a result of the
construction and operation of the
proposed project under these general
headings:
•
•
•
•
•
•
•
•
•
geology and soils;
land use;
water resources, fisheries, and wetlands;
cultural resources;
vegetation and wildlife;
air quality and noise;
endangered and threatened species;
public safety; and
cumulative impacts.
We will also evaluate reasonable
alternatives to the proposed project or
portions of the project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
The EA will present our independent
analysis of the issues. The EA will be
available in the public record through
eLibrary (for directions on the use of
eLibrary, please see the additional page
6). Depending on the comments
received during the scoping process, we
may also publish and distribute the EA
to the public for an allotted comment
period. We will consider all comments
on the EA before making our
recommendations to the Commission.
To ensure we have the opportunity to
consider and address your comments,
please carefully follow the instructions
in the Public Participation section,
beginning on page 2.
With this notice, we are asking
agencies with jurisdiction by law and/
or special expertise with respect to the
environmental issues of this project to
formally cooperate with us in the
preparation of the EA.3 Agencies that
would like to request cooperating
agency status should follow the
instructions for filing comments
2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the
environmental staff of the Commission’s Office of
Energy Projects.
3 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
PO 00000
Frm 00027
Fmt 4703
Sfmt 4703
provided under the Public Participation
section of this notice.
Consultations Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, we are using this
notice to initiate consultation with the
applicable Texas State Historic
Preservation Office (SHPO), and to
solicit their views and those of other
government agencies, interested
agencies, interested Indian tribes, and
the public on the project’s potential
effects on historic properties.4 We will
define the project-specific Area of
Potential Effects (APE) in consultation
with the SHPO as the project develops.
On natural gas facility projects, the APE
at a minimum encompasses all areas
subject to ground disturbance (examples
include construction right-of-way,
contractor/pipe storage yards,
compressor stations, and access roads).
Our EA for this project will document
our findings on the impacts on historic
properties and summarize the status of
consultations under section 106.
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the project. We will
update the environmental mailing list as
the analysis proceeds to ensure that we
send the information related to this
environmental review to all individuals,
organizations, and government entities
interested in and/or potentially affected
by the proposed project.
Copies of the EA will be sent to the
environmental mailing list for public
review and comment. If you would
prefer to receive a paper copy of the
document instead of the CD version or
would like to remove your name from
4 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, Part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
E:\FR\FM\20SEN1.SGM
20SEN1
Federal Register / Vol. 81, No. 182 / Tuesday, September 20, 2016 / Notices
the mailing list, please return the
attached Information Request (appendix
2).
Becoming an Intervenor
In addition to involvement in the EA
scoping process, you may want to
become an ‘‘intervenor’’ which is an
official party to the Commission’s
proceeding. Intervenors play a more
formal role in the process and are able
to file briefs, appear at hearings, and be
heard by the courts if they choose to
appeal the Commission’s final ruling.
An intervenor formally participates in
the proceeding by filing a request to
intervene.
Instructions for becoming an
intervenor are in the ‘‘Document-less
Intervention Guide’’ under the ‘‘e-filing’’
link on the Commission’s Web site.
Motions to intervene are more fully
described at https://www.ferc.gov/
resources/guides/how-to/intervene.asp.
sradovich on DSK3GMQ082PROD with NOTICES
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC Web
site at www.ferc.gov using the
‘‘eLibrary’’ link. Click on the eLibrary
link, click on ‘‘General Search’’ and
enter the docket number, excluding the
last three digits in the Docket Number
field (i.e., CP16–488–000). Be sure you
have selected an appropriate date range.
For assistance, please contact FERC
Online Support at FercOnlineSupport@
ferc.gov or toll free at (866) 208–3676, or
for TTY, contact (202) 502–8659. The
eLibrary link also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Dated: September 14, 2016.
Kimberly D. Bose,
Secretary.
DEPARTMENT OF ENERGY
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Federal Energy Regulatory
Commission
Implementation Issues Under the
Public Utility Regulatory Policies Act
of 1978; Notice Inviting Post-Technical
Conference Comments
On June 29, 2016, Federal Energy
Regulatory Commission (Commission)
staff conducted a technical conference
to discuss implementation issues related
to the Public Utility Regulatory Policies
Act of 1978 (PURPA).1 The Commission
invites post-technical conference
comments on the following two matters:
(1) The use of the ‘‘one-mile rule’’ to
determine the size of an entity seeking
certification as a small power
production qualifying facility (QF); and
(2) minimum standards for PURPApurchase contracts.
All interested persons are invited to
file post-technical conference comments
on these two matters, including the
questions listed in the attachment to
this Notice. Commenters need not
respond to all questions asked.
Commenters may reference material
previously filed in this docket,
including the technical conference
transcript, but are encouraged to submit
new or additional information rather
than reiterate information that is already
in the record. In particular, Commenters
are encouraged, when possible, to
provide examples in support of their
answers. These comments are due on or
before November 7, 2016.
For further information about this
Notice, please contact:
Adam Alvarez (Technical Information),
Office of Energy Market Regulation,
Federal Energy Regulatory
Commission, 888 First Street NE.,
Washington, DC 20426, (202) 502–
6734, adam.alvarez@ferc.gov.
Loni Silva (Legal Information), Office of
General Counsel, Federal Energy
Regulatory Commission, 888 First
Street NE., Washington, DC 20426,
(202) 502–6233, loni.silva@ferc.gov.
Dated: September 6, 2016.
Kimberly D. Bose,
Secretary.
BILLING CODE 6717–01–P
[FR Doc. 2016–22600 Filed 9–19–16; 8:45 am]
VerDate Sep<11>2014
17:13 Sep 19, 2016
[Project No. 2387–003]
[Docket No. AD16–16–000]
[FR Doc. 2016–22598 Filed 9–19–16; 8:45 am]
1 16
BILLING CODE 6717–01–P
Jkt 238001
64455
PO 00000
U.S.C. 2601 et seq. (2012).
Frm 00028
Fmt 4703
Sfmt 4703
City of Holyoke Gas and Electric
Department; Notice of Application
Tendered for Filing With the
Commission and Soliciting Additional
Study Requests and Establishing
Procedural Schedule for Relicensing
and a Deadline for Submission of Final
Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New License.
b. Project No.: 2387–003.
c. Date filed: August 31, 2016.
d. Applicant: City of Holyoke Gas and
Electric Department.
e. Name of Project: Holyoke Number
2 Hydroelectric Project.
f. Location: Between the first and
second level canals on the Holyoke
Canal System adjacent to the
Connecticut River, in the city of
Holyoke in Hampden County,
Massachusetts. The project does not
occupy federal land.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Paul Ducheney,
Superintendent, City of Holyoke Gas
and Electric Department, 99 Suffolk
Street, Holyoke, MA 01040, (413) 536–
9340 or ducheney@hged.com.
i. FERC Contact: Kyle Olcott, (202)
502–8963 or kyle.olcott@ferc.gov.
j. Cooperating agencies: Federal, state,
local, and tribal agencies with
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
document should follow the
instructions for filing such requests
described in item l below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See, 94
FERC ¶ 61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian Tribe, or
person believes that an additional
scientific study should be conducted in
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
E:\FR\FM\20SEN1.SGM
20SEN1
Agencies
[Federal Register Volume 81, Number 182 (Tuesday, September 20, 2016)]
[Notices]
[Pages 64453-64455]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-22600]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No.CP16-488-000]
Natural Gas Pipeline Company of America; Notice of Intent To
Prepare an Environmental Assessment for the Proposed Gulf Coast
Expansion Project, and Request for Comments on Environmental Issues
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Gulf Coast Expansion Project
involving construction and operation of facilities by Natural Gas
Pipeline Company of America, LLC (Natural) in Cass and Wharton
Counties, Texas. The Commission will use this EA in its decision-making
process to determine whether the Project is in the public convenience
and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the project. You can make a difference by providing us with
your specific comments or concerns about the project. Your comments
should focus on the potential environmental effects, reasonable
alternatives, and measures to avoid or lessen environmental impacts.
Your input will help the Commission staff determine what issues they
need to evaluate in the EA. To ensure that your comments are timely and
properly recorded, please send your comments so that the Commission
receives them in Washington, DC on or before October 14, 2016.
If you sent comments on this project to the Commission before the
opening of this docket on August 1, 2016, you will need to file those
comments in Docket No. CP16-488-000 to ensure they are considered as
part of this proceeding.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this proposed
project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the proposed facilities. The company
would seek to negotiate a mutually acceptable agreement. However, if
the Commission approves the project, that approval conveys with it the
right of eminent domain. Therefore, if easement negotiations fail to
produce an agreement, the pipeline company could initiate condemnation
proceedings where compensation would be determined in accordance with
state law.
Natural provided landowners with a fact sheet prepared by the FERC
entitled ``An Interstate Natural Gas Facility On My Land? What Do I
Need To Know?'' This fact sheet addresses a number of typically asked
questions, including the use of eminent domain and how to participate
in the Commission's proceedings. It is also available for viewing on
the FERC Web site (www.ferc.gov).
Public Participation
For your convenience, there are three methods you can use to submit
your comments to the Commission. The Commission encourages electronic
filing of comments and has expert staff available to assist you at
(202) 502-8258 or efiling@ferc.gov. Please carefully follow these
instructions so that your comments are properly recorded.
(1) You can file your comments electronically using the eComment
feature on the Commission's Web site (www.ferc.gov) under the link to
[[Page 64454]]
Documents and Filings. This is an easy method for submitting brief,
text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. With eFiling, you can provide comments in a
variety of formats by attaching them as a file with your submission.
New eFiling users must first create an account by clicking on
``eRegister.'' If you are filing a comment on a particular project,
please select ``Comment on a Filing'' as the filing type; or
(3) You can file a paper copy of your comments by mailing them to
the following address. Be sure to reference the project docket number
(CP16-488-000) with your submission: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission, 888 First Street NE., Room 1A,
Washington, DC 20426.
Summary of the Proposed Project
Natural proposes to construct and operate a new compressor station,
identified as Compressor Station 394 (CS 394), and a new approximately
4,000-foot-long, 30-inch-diameter lateral, with connections to
Natural's existing Gulf Coast Line and A/G Line in Cass County, Texas.
Natural is also requesting authorization to abandon two compressor
units at its Compressor Station 301 (CS 301) located in Wharton County,
Texas. The Project would provide about 460,000 dekatherms of
incremental southbound transportation capacity from existing receipt
points on Natural's Gulf Coast System to delivery points in Natural's
South Texas Zone.
The general location of the project facilities is shown in appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of appendices were sent to all those
receiving this notice in the mail and are available at www.ferc.gov
using the link called ``eLibrary'' or from the Commission's Public
Reference Room, 888 First Street NE., Washington, DC 20426, or call
(202) 502-8371. For instructions on connecting to eLibrary, refer to
the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the proposed facilities would disturb about 39.9
acres of land for the aboveground facilities and the pipeline.
Following construction, Natural would maintain about 27.3 acres for
permanent operation of the project's facilities. The remaining 12.6
acres would only be used for construction and be allowed to revegetate.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
\2\ to discover and address concerns the public may have about
proposals. This process is referred to as ``scoping.'' The main goal of
the scoping process is to focus the analysis in the EA on the important
environmental issues. By this notice, the Commission requests public
comments on the scope of the issues to address in the EA. We will
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------
\2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EA we will discuss impacts that could occur as a result of
the construction and operation of the proposed project under these
general headings:
geology and soils;
land use;
water resources, fisheries, and wetlands;
cultural resources;
vegetation and wildlife;
air quality and noise;
endangered and threatened species;
public safety; and
cumulative impacts.
We will also evaluate reasonable alternatives to the proposed
project or portions of the project, and make recommendations on how to
lessen or avoid impacts on the various resource areas.
The EA will present our independent analysis of the issues. The EA
will be available in the public record through eLibrary (for directions
on the use of eLibrary, please see the additional page 6). Depending on
the comments received during the scoping process, we may also publish
and distribute the EA to the public for an allotted comment period. We
will consider all comments on the EA before making our recommendations
to the Commission. To ensure we have the opportunity to consider and
address your comments, please carefully follow the instructions in the
Public Participation section, beginning on page 2.
With this notice, we are asking agencies with jurisdiction by law
and/or special expertise with respect to the environmental issues of
this project to formally cooperate with us in the preparation of the
EA.\3\ Agencies that would like to request cooperating agency status
should follow the instructions for filing comments provided under the
Public Participation section of this notice.
---------------------------------------------------------------------------
\3\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
---------------------------------------------------------------------------
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, we are using this notice to initiate consultation
with the applicable Texas State Historic Preservation Office (SHPO),
and to solicit their views and those of other government agencies,
interested agencies, interested Indian tribes, and the public on the
project's potential effects on historic properties.\4\ We will define
the project-specific Area of Potential Effects (APE) in consultation
with the SHPO as the project develops. On natural gas facility
projects, the APE at a minimum encompasses all areas subject to ground
disturbance (examples include construction right-of-way, contractor/
pipe storage yards, compressor stations, and access roads). Our EA for
this project will document our findings on the impacts on historic
properties and summarize the status of consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project. We will update the environmental mailing list
as the analysis proceeds to ensure that we send the information related
to this environmental review to all individuals, organizations, and
government entities interested in and/or potentially affected by the
proposed project.
Copies of the EA will be sent to the environmental mailing list for
public review and comment. If you would prefer to receive a paper copy
of the document instead of the CD version or would like to remove your
name from
[[Page 64455]]
the mailing list, please return the attached Information Request
(appendix 2).
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an ``intervenor'' which is an official party to the
Commission's proceeding. Intervenors play a more formal role in the
process and are able to file briefs, appear at hearings, and be heard
by the courts if they choose to appeal the Commission's final ruling.
An intervenor formally participates in the proceeding by filing a
request to intervene.
Instructions for becoming an intervenor are in the ``Document-less
Intervention Guide'' under the ``e-filing'' link on the Commission's
Web site. Motions to intervene are more fully described at https://www.ferc.gov/resources/guides/how-to/intervene.asp.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number,
excluding the last three digits in the Docket Number field (i.e., CP16-
488-000). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Dated: September 14, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016-22600 Filed 9-19-16; 8:45 am]
BILLING CODE 6717-01-P