Tennessee Gas Pipeline Company, L.L.C.; Notice of Revised Schedule for Environmental Review of the Abandonment and Capacity Restoration Project, 62493 [2016-21748]
Download as PDF
Federal Register / Vol. 81, No. 175 / Friday, September 9, 2016 / Notices
Hardship and Competitive
Disadvantage
In absence of a favorable
determination, the Robot design would
have to be modified in order to add a
switch that would implement the same
isolation obtained by the isolating tape.
The cost in addition to the current bill
of materials would be around 0.3 USD,
but the real burden is that this switch
would have to be added only to enable
the measurement of the true energy
consumption and would not bring any
real benefit for the user. Indeed, as
prescribed by the test procedure, if the
switch is made accessible to users, it
could result in inadvertent operations.
The reliability of the Robot might be
affected, including, but not limited to:
• Preventing the Robot from being
controlled remotely as intended;
• Random malfunction and bad user
experience; and
• Abrupt abortion of software
upgrades with the typical consequences
(i.e., software corruption).
The actual cost cannot be easily
quantified in advance, but would
disparage the Dyson brand.
Likely Success of the Petition
Our proposal is in compliance with
the test method’s intent of measuring
the energy efficiency parameters of
battery chargers, as it ensures that such
energy consumption is still measured. It
does not add unnecessary burden to the
work of the test technician when
applying the test procedure. It is also a
proposal that would benefit other
manufacturers of consumer products
employing advanced connectivity
features by providing more flexibility at
evaluating compliance with the relevant
energy metrics.
Appendix A—Access to the Battery
Terminal
See the following Web site for Appendix A
pictures: https://www.regulations.gov/
#!docketDetail;D=EERE-2016-BT-WAV-0034.
asabaliauskas on DSK3SPTVN1PROD with NOTICES
Appendix B—Power Consumption
Graphs
(B.1a)
Battery Control 1—Robot control powered
from the battery
The battery charger periodically refills the
energy used by the non-charging
functionalities (red trace). By isolating the
terminal only the power drawn by the battery
is accounted (blue trace).
See the following Web site for Appendix
B.1a graphs: https://www.regulations.gov/
#!docketDetail;D=EERE-2016-BT-WAV-0034.
(B.1b)
Battery Control 1—Circuit diagram
See the following Web site for Appendix
B.1b graphs: https://www.regulations.gov/
#!docketDetail;D=EERE-2016-BT-WAV-0034.
VerDate Sep<11>2014
17:11 Sep 08, 2016
Jkt 238001
(B.2a)
Battery Control 2—Robot control powered
from the mains
The battery charger provides energy in
parallel both to the battery and to the noncharging functionalities (red trace). By
isolating the terminal only the power drawn
by the battery is accounted (blue trace).
See the following Web site for Appendix
B.2a graphs: https://www.regulations.gov/
#!docketDetail;D=EERE-2016-BT-WAV-0034.
(B.2b)
Battery Control 2—Circuit diagram
See the following Web site for Appendix
B.2b graphs: https://www.regulations.gov/
#!docketDetail;D=EERE-2016-BT-WAV-0034.
[FR Doc. 2016–21749 Filed 9–8–16; 8:45 am]
BILLING CODE 6450–01–P
62493
Dated: September 2, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016–21748 Filed 9–8–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP15–557–000]
Total Peaking Services, LLC; Notice of
Schedule for Environmental Review of
the Vaporization Capacity Increase and
Bog Compressor Project
Schedule for Environmental Review
On September 23, 2015, Total Peaking
Services, LLC (Total Peaking) filed an
application in Docket No. CP15–557–
000 requesting a Certificate of Public
Convenience and Necessity pursuant to
Section 7(c) of the Natural Gas Act to
construct and operate certain liquefied
natural gas facilities. The proposed
project is known as the Vaporization
Capacity Increase and BOG Compressor
Project (Project), and would increase the
vaporization send out capacity at Total
Peaking’s Milford, Connecticut facility
from 90 million cubic feet per day
(MMcf/d) to 105 MMcf/d, along with the
construction and operation of an
additional boil-off gas compressor unit.
On October 7, 2015, the Federal
Energy Regulatory Commission
(Commission or FERC) issued its Notice
of Application for the Project. Among
other things, that notice alerted agencies
issuing federal authorizations of the
requirement to complete all necessary
reviews and to reach a final decision on
a request for a federal authorization
within 90 days of the date of issuance
of the Commission staff’s Environmental
Assessment (EA) for the Project. This
instant notice identifies the FERC staff’s
planned schedule for the completion of
the EA for the Project.
Issuance of the EA: November 2,
2016.
90-day Federal Authorization
Decision Deadline: January 31, 2017.
If a schedule change becomes
necessary, an additional notice will be
provided so that the relevant agencies
are kept informed of the project’s
progress.
Schedule for Environmental Review
Issuance of EA October 14, 2016
90-day Federal Authorization Decision
Deadline January 12, 2017
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the Project’s
progress.
Additional Information
Project Description
The Project would include
modifications at Total Peaking’s
Milford, Connecticut facility. Total
Peaking would remove its existing
vaporizers and install a single vaporizer
operating at 105 MMcf/d as well as a
heater system for the new vaporizer.
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP15–88–000]
Tennessee Gas Pipeline Company,
L.L.C.; Notice of Revised Schedule for
Environmental Review of the
Abandonment and Capacity
Restoration Project
This notice identifies the Federal
Energy Regulatory Commission
(Commission or FERC) staff’s revised
schedule for the completion of the
environmental assessment (EA) for
Tennessee Gas Pipeline Company,
L.L.C.’s (Tennessee) Abandonment and
Capacity Restoration Project. The first
notice of schedule, issued on June 30,
2016, identified September 2, 2016 as
the EA issuance date. However,
Tennessee provided modifications to
the proposed facilities that require
additional time for staff to consider.
Therefore, staff has revised the schedule
for issuance of the EA.
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription
(https://www.ferc.gov/docs-filing/
esubscription.asp).
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
E:\FR\FM\09SEN1.SGM
09SEN1
Agencies
[Federal Register Volume 81, Number 175 (Friday, September 9, 2016)]
[Notices]
[Page 62493]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-21748]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP15-88-000]
Tennessee Gas Pipeline Company, L.L.C.; Notice of Revised
Schedule for Environmental Review of the Abandonment and Capacity
Restoration Project
This notice identifies the Federal Energy Regulatory Commission
(Commission or FERC) staff's revised schedule for the completion of the
environmental assessment (EA) for Tennessee Gas Pipeline Company,
L.L.C.'s (Tennessee) Abandonment and Capacity Restoration Project. The
first notice of schedule, issued on June 30, 2016, identified September
2, 2016 as the EA issuance date. However, Tennessee provided
modifications to the proposed facilities that require additional time
for staff to consider. Therefore, staff has revised the schedule for
issuance of the EA.
Schedule for Environmental Review
Issuance of the EA: November 2, 2016.
90-day Federal Authorization Decision Deadline: January 31, 2017.
If a schedule change becomes necessary, an additional notice will
be provided so that the relevant agencies are kept informed of the
project's progress.
Additional Information
In order to receive notification of the issuance of the EA and to
keep track of all formal issuances and submittals in specific dockets,
the Commission offers a free service called eSubscription (https://www.ferc.gov/docs-filing/esubscription.asp).
Dated: September 2, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016-21748 Filed 9-8-16; 8:45 am]
BILLING CODE 6717-01-P