EcoEléctrica, L.P.; Notice of Application, 60000 [2016-20973]

Download as PDF 60000 Federal Register / Vol. 81, No. 169 / Wednesday, August 31, 2016 / Notices requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: August 25, 2016. Kimberly D. Bose, Secretary. [FR Doc. 2016–20972 Filed 8–30–16; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP16–492–000] mstockstill on DSK3G9T082PROD with NOTICES ´ EcoElectrica, L.P.; Notice of Application Take notice that on July 11, 2016, ´ ´ EcoElectrica, L.P. (EcoElectrica), Road 337, Km. 3.7, Bo. Tallaboa Poniente, ˜ Penuelas, PR 00624, filed an application in Docket No. CP16–492–000 under section 3 of the Natural Gas Act (NGA), and Part 153 and 380 of the Commission’s regulations for an amendment to the authorization granted by the Commission on May 15, 1996 in Docket No. CP95–35–000, as subsequently amended on April 16, 2009 in Docket No. CP95–35–001, and on June 19, 2014 in Docket No. CP13– ´ 516–000. EcoElectrica requests authorization to amend its current NGA Section 3 authorization to use inherent spare capacity within the existing LNG vaporizers, to supply the Puerto Rico Electric Power Authority (PREPA) an additional 93 million standard cubic feet (MMscf/d) of natural gas, all as more fully set forth in the application which is on file with the Commission and open to public inspection. This filing is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, please contact FERC Online Support at FERCOnlineSupport@ ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. Any questions regarding this application should be directed to Jaime ´ L. Sanabria, EcoElectrica, L.P., Road 337, Km. 3.7, Bo. Tallaboa Poniente, ˜ Penuelas, PR 00624, (787) 759–0202, or by email at jaime.sanabria@ ecoelectrica.com. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, VerDate Sep<11>2014 21:59 Aug 30, 2016 Jkt 238001 within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. There are two ways to become involved in the Commission’s review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below, file with the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission’s Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit 5 copies of filings made with the Commission and must mail a copy to the applicant and to every other party in the proceeding. Only parties to the proceeding can ask for court review of Commission orders in the proceeding. However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission’s rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest. Persons who wish to comment only on the environmental review of this PO 00000 Frm 00025 Fmt 4703 Sfmt 4703 project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commentors will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission’s environmental review process. Environmental commentors will not be required to serve copies of filed documents on all other parties. However, the non-party commentors will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: September 15, 2016. Dated: August 25, 2016. Kimberly D. Bose, Secretary. [FR Doc. 2016–20973 Filed 8–30–16; 8:45 am] BILLING CODE 6717–01–P FEDERAL COMMUNICATIONS COMMISSION [OMB 3060–1159] Information Collection Being Submitted for Review and Approval to the Office of Management and Budget Federal Communications Commission. ACTION: Notice and request for comments. AGENCY: As part of its continuing effort to reduce paperwork burdens, and as SUMMARY: E:\FR\FM\31AUN1.SGM 31AUN1

Agencies

[Federal Register Volume 81, Number 169 (Wednesday, August 31, 2016)]
[Notices]
[Page 60000]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-20973]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP16-492-000]


EcoEl[eacute]ctrica, L.P.; Notice of Application

    Take notice that on July 11, 2016, EcoEl[eacute]ctrica, L.P. 
(EcoEl[eacute]ctrica), Road 337, Km. 3.7, Bo. Tallaboa Poniente, 
Pe[ntilde]uelas, PR 00624, filed an application in Docket No. CP16-492-
000 under section 3 of the Natural Gas Act (NGA), and Part 153 and 380 
of the Commission's regulations for an amendment to the authorization 
granted by the Commission on May 15, 1996 in Docket No. CP95-35-000, as 
subsequently amended on April 16, 2009 in Docket No. CP95-35-001, and 
on June 19, 2014 in Docket No. CP13-516-000. EcoEl[eacute]ctrica 
requests authorization to amend its current NGA Section 3 authorization 
to use inherent spare capacity within the existing LNG vaporizers, to 
supply the Puerto Rico Electric Power Authority (PREPA) an additional 
93 million standard cubic feet (MMscf/d) of natural gas, all as more 
fully set forth in the application which is on file with the Commission 
and open to public inspection. This filing is available for review at 
the Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at https://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, please 
contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free 
at (866) 208-3676, or for TTY, contact (202) 502-8659.
    Any questions regarding this application should be directed to 
Jaime L. Sanabria, EcoEl[eacute]ctrica, L.P., Road 337, Km. 3.7, Bo. 
Tallaboa Poniente, Pe[ntilde]uelas, PR 00624, (787) 759-0202, or by 
email at jaime.sanabria@ecoelectrica.com.
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below, file with the Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit 5 copies of filings made with the Commission and must mail a 
copy to the applicant and to every other party in the proceeding. Only 
parties to the proceeding can ask for court review of Commission orders 
in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commentors will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commentors will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentors will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFiling'' link 
at https://www.ferc.gov. Persons unable to file electronically should 
submit an original and 5 copies of the protest or intervention to the 
Federal Energy Regulatory Commission, 888 First Street NE., Washington, 
DC 20426.
    This filing is accessible on-line at https://www.ferc.gov, using the 
``eLibrary'' link and is available for review in the Commission's 
Public Reference Room in Washington, DC. There is an ``eSubscription'' 
link on the Web site that enables subscribers to receive email 
notification when a document is added to a subscribed docket(s). For 
assistance with any FERC Online service, please email 
FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free). For 
TTY, call (202) 502-8659.
    Comment Date: September 15, 2016.

    Dated: August 25, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016-20973 Filed 8-30-16; 8:45 am]
 BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.