Pacific Gas & Electric Company; Notice of Intent To File License Application, Filing of Pre-Application Document, Approving Use of the Traditional Licensing Process, 57901-57902 [2016-20284]
Download as PDF
mstockstill on DSK3G9T082PROD with NOTICES
Federal Register / Vol. 81, No. 164 / Wednesday, August 24, 2016 / Notices
7206, or by email at
websterk@natfuel.com.
Any person or the Commission’s Staff
may, within 60 days after the issuance
of the instant notice by the Commission,
file pursuant to Rule 214 of the
Commission’s Procedural Rules (18 CFR
385.214) a motion to intervene or notice
of intervention and, pursuant to section
157.205 of the Commission’s
Regulations under the NGA (18 CFR
157.205) a protest to the request. If no
protest is filed within the time allowed
therefore, the proposed activity shall be
deemed to be authorized effective the
day after the time allowed for protest. If
a protest is filed and not withdrawn
within 30 days after the time allowed
for filing a protest, the instant request
shall be treated as an application for
authorization pursuant to section 7 of
the NGA.
Pursuant to Section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: Complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding, or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenters will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
VerDate Sep<11>2014
20:16 Aug 23, 2016
Jkt 238001
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests,
and interventions via the internet in lieu
of paper. See 18 CFR 385.2001(a) (1) (iii)
and the instructions on the
Commission’s Web site (www.ferc.gov)
under the ‘‘e-Filing’’ link. Persons
unable to file electronically should
submit an original and 5 copies of the
protest or intervention to the Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
Dated: August 18, 2016.
Kimberly D. Bose,
Secretary.
57901
necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: August 17, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016–20287 Filed 8–23–16; 8:45 am]
BILLING CODE 6717–01–P
[FR Doc. 2016–20276 Filed 8–23–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
DEPARTMENT OF ENERGY
[Project No. 10821–004]
Federal Energy Regulatory
Commission
Pacific Gas & Electric Company;
Notice of Intent To File License
Application, Filing of Pre-Application
Document, Approving Use of the
Traditional Licensing Process
Combined Notice of Filings
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
Filings Instituting Proceedings
Docket Number: PR16–61–001.
Applicants: Black Hills Gas
Distribution LLC.
Description: Tariff filing per
284.123(b), (e): Amended Statement of
Operation Conditions to be effective 6/
1/2016; Filing Type: 1270.
Filed Date: 8/15/2016.
Accession Number: 201608155177,
https://elibrary.ferc.gov/idmws/doc_
info.asp?accession_num=201604155222.
Comments Due: 5 p.m. ET 9/2/16.
284.123(g) Protests Due: 5 p.m. ET 9/
2/16.
Docket Numbers: RP16–1173–000.
Applicants: First ECA Midstream
LLC.
Description: Compliance filing Tariff
filing in compliance with Docket No.
CP16–35–000 to be effective 9/15/2016.
Filed Date: 8/16/16.
Accession Number: 20160816–5245.
Comments Due: 5 p.m. ET 8/29/16.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5 p.m. Eastern
time on the specified date(s). Protests
may be considered, but intervention is
PO 00000
Frm 00025
Fmt 4703
Sfmt 4703
a. Type of Filing: Notice of Intent to
a File License Application and Request
to Use the Traditional Licensing
Process.
b. Project No.: 10821–004.
c. Date Filed: June 30, 2016.
d. Submitted By: Pacific Gas &
Electric Company (PG&E).
e. Name of Project: Camp Far West
Transmission Line Project.
f. Location: The project is a
transmission line-only project located in
Placer and Yuba Counties, California.
The project occupies 10.9 acres of
federal land administered by Beale Air
Force Base, Department of Defense.
g. Filed Pursuant to: 18 CFR 5.3 of the
Commission’s regulations.
h. Potential Applicant Contact: Mark
Stewart, Electric FERC License
Coordinator, 4636 Missouri Flat Road,
Placerville, CA 95667; (530) 621–7243;
email—m9s5@pge.com.
i. FERC Contact: Quinn Emmering at
(202) 502–6382; or email at
quinn.emmering@ferc.gov.
j. PG&E filed its request to use the
Traditional Licensing Process on June
30, 2016. PG&E provided public notice
of its request on June 9 and June 10,
2016. In a letter dated August 18, 2016,
the Director of the Division of
Hydropower Licensing approved
PG&E’s request to use the Traditional
Licensing Process.
k. With this notice, we are initiating
informal consultation with the U.S. Fish
and Wildlife Service and NOAA
Fisheries under section 7 of the
E:\FR\FM\24AUN1.SGM
24AUN1
mstockstill on DSK3G9T082PROD with NOTICES
57902
Federal Register / Vol. 81, No. 164 / Wednesday, August 24, 2016 / Notices
Endangered Species Act and the joint
agency regulations thereunder at 50
CFR, Part 402; and NOAA Fisheries
under section 305(b) of the MagnusonStevens Fishery Conservation and
Management Act and implementing
regulations at 50 CFR 600.920. We are
also initiating consultation with the
California State Historic Preservation
Officer, as required by section 106,
National Historic Preservation Act, and
the implementing regulations of the
Advisory Council on Historic
Preservation at 36 CFR 800.2.
l. With this notice, we are designating
PG&E as the Commission’s non-federal
representative for carrying out informal
consultation pursuant to section 7 of the
Endangered Species Act and section
305(b) of the Magnuson-Stevens Fishery
Conservation and Management Act; and
consultation pursuant to section 106 of
the National Historic Preservation Act.
m. PG&E filed a Pre-Application
Document (PAD; including a proposed
process plan and schedule) with the
Commission, pursuant to 18 CFR 5.6 of
the Commission’s regulations.
n. A copy of the PAD is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site (https://
www.ferc.gov), using the ‘‘eLibrary’’
link. Enter the docket number,
excluding the last three digits in the
docket number field to access the
document. For assistance, contact FERC
Online Support at
FERCONlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). A copy is also available for
inspection and reproduction at the
address in paragraph h.
o. The licensee states its unequivocal
intent to submit an application for a
new license for Project No. 10821–004.
Pursuant to 18 CFR 16.8, 16.9, and 16.10
each application for a new license and
any competing license applications
must be filed with the Commission at
least 24 months prior to the expiration
of the existing license. All applications
for licensing this project must be filed
by June 30, 2019.
p. Register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filing and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
Dated: August 18, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016–20284 Filed 8–23–16; 8:45 am]
BILLING CODE 6717–01–P
VerDate Sep<11>2014
20:16 Aug 23, 2016
Jkt 238001
Dated: August 18, 2016.
Kimberly D. Bose,
Secretary.
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[FR Doc. 2016–20281 Filed 8–23–16; 8:45 am]
[Docket No. OR16–22–000]
BILLING CODE 6717–01–P
EnLink Crude Pipeline, LLC; Notice of
Petition for Declaratory Order
Take notice that on August 16, 2016,
pursuant to Rule 207(a)(2) of the Federal
Energy Regulatory Commission’s
(Commission) Rules of Practice and
Procedure, 18 CFR 385.207(a)(2) (2015),
EnLink Crude Pipeline, LLC (‘‘EnLink’’),
filed a petition for a declaratory order
approving the overall tariff and rate
structure for EnLink’s new pipeline
system in the Midland Basin in Texas
that will gather and transport crude oil
from origin points located in Upton
County, Texas and Midland County,
Texas to the SunVit Midland Terminal
and the Enterprise Midland Terminal,
both in Midland County, Texas, all as
more fully explained in the petition.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. Anyone filing a motion
to intervene or protest must serve a copy
of that document on the Petitioner.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 5 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern time
on September 16, 2016.
PO 00000
Frm 00026
Fmt 4703
Sfmt 4703
ENVIRONMENTAL PROTECTION
AGENCY
[EPA–HQ–OPP–2016–0427; FRL–9950–47]
Public Meeting; Data That Support the
Registration of Plant-Incorporated
Protectants (PIPs)
Environmental Protection
Agency (EPA).
ACTION: Notice.
AGENCY:
The Environmental Protection
Agency (EPA) will hold a one-day
public symposium on the types of data
that support the registration of plantincorporated protectants (PIPs). The
symposium is open to the public and
can be attended in person and online.
DATES: The meeting will be held on
September 29, 2016, from
approximately 9:00 a.m. to 5:00 p.m.
Sign-in begins at 8:30 a.m.
If you wish to participate in person,
we encourage registration on or before
September 26, 2016.
If you wish to attend in person and
would like to request accommodation
for a disability, please follow the
registration link under III. How Can I
Request to Participate in this Meeting?
and follow the prompts for in-person
attendance. In order to give EPA as
much time as possible to process your
request, we encourage participants to
request accommodations at least 10 days
prior to the meeting.
ADDRESSES: The meeting will be held at
the Environmental Protection Agency,
Conference Center Room S1204/06,
Lobby Level, One Potomac Yard (South
Bldg.), 2777 S. Crystal Dr., Arlington,
VA 22202.
FOR FURTHER INFORMATION CONTACT:
Wiebke Tapken, Biopesticides and
Pollution Prevention Division (7511P),
Office of Pesticide Programs,
Environmental Protection Agency, 1200
Pennsylvania Ave. NW., Washington,
DC 20460–0001; main telephone
number: (703) 305–7090; email address:
BPPDFRNotices@epa.gov.
SUPPLEMENTARY INFORMATION:
SUMMARY:
I. General Information
A. Does this action apply to me?
This action is directed to the public
in general. This action may, however, be
of interest to persons who are or may be
required to conduct testing of pesticidal
E:\FR\FM\24AUN1.SGM
24AUN1
Agencies
[Federal Register Volume 81, Number 164 (Wednesday, August 24, 2016)]
[Notices]
[Pages 57901-57902]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-20284]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 10821-004]
Pacific Gas & Electric Company; Notice of Intent To File License
Application, Filing of Pre-Application Document, Approving Use of the
Traditional Licensing Process
a. Type of Filing: Notice of Intent to a File License Application
and Request to Use the Traditional Licensing Process.
b. Project No.: 10821-004.
c. Date Filed: June 30, 2016.
d. Submitted By: Pacific Gas & Electric Company (PG&E).
e. Name of Project: Camp Far West Transmission Line Project.
f. Location: The project is a transmission line-only project
located in Placer and Yuba Counties, California. The project occupies
10.9 acres of federal land administered by Beale Air Force Base,
Department of Defense.
g. Filed Pursuant to: 18 CFR 5.3 of the Commission's regulations.
h. Potential Applicant Contact: Mark Stewart, Electric FERC License
Coordinator, 4636 Missouri Flat Road, Placerville, CA 95667; (530) 621-
7243; email_m9s5@pge.com.
i. FERC Contact: Quinn Emmering at (202) 502-6382; or email at
quinn.emmering@ferc.gov.
j. PG&E filed its request to use the Traditional Licensing Process
on June 30, 2016. PG&E provided public notice of its request on June 9
and June 10, 2016. In a letter dated August 18, 2016, the Director of
the Division of Hydropower Licensing approved PG&E's request to use the
Traditional Licensing Process.
k. With this notice, we are initiating informal consultation with
the U.S. Fish and Wildlife Service and NOAA Fisheries under section 7
of the
[[Page 57902]]
Endangered Species Act and the joint agency regulations thereunder at
50 CFR, Part 402; and NOAA Fisheries under section 305(b) of the
Magnuson-Stevens Fishery Conservation and Management Act and
implementing regulations at 50 CFR 600.920. We are also initiating
consultation with the California State Historic Preservation Officer,
as required by section 106, National Historic Preservation Act, and the
implementing regulations of the Advisory Council on Historic
Preservation at 36 CFR 800.2.
l. With this notice, we are designating PG&E as the Commission's
non-federal representative for carrying out informal consultation
pursuant to section 7 of the Endangered Species Act and section 305(b)
of the Magnuson-Stevens Fishery Conservation and Management Act; and
consultation pursuant to section 106 of the National Historic
Preservation Act.
m. PG&E filed a Pre-Application Document (PAD; including a proposed
process plan and schedule) with the Commission, pursuant to 18 CFR 5.6
of the Commission's regulations.
n. A copy of the PAD is available for review at the Commission in
the Public Reference Room or may be viewed on the Commission's Web site
(https://www.ferc.gov), using the ``eLibrary'' link. Enter the docket
number, excluding the last three digits in the docket number field to
access the document. For assistance, contact FERC Online Support at
FERCONlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). A copy is also available for inspection and reproduction at
the address in paragraph h.
o. The licensee states its unequivocal intent to submit an
application for a new license for Project No. 10821-004. Pursuant to 18
CFR 16.8, 16.9, and 16.10 each application for a new license and any
competing license applications must be filed with the Commission at
least 24 months prior to the expiration of the existing license. All
applications for licensing this project must be filed by June 30, 2019.
p. Register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filing and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
Dated: August 18, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016-20284 Filed 8-23-16; 8:45 am]