Download as PDF mstockstill on DSK3G9T082PROD with NOTICES 54798 Federal Register / Vol. 81, No. 159 / Wednesday, August 17, 2016 / Notices Docket No. EL95–33—Louisiana Public Service Commission et al. v. Entergy Corp. et al. Docket No. EL00–66—Louisiana Public Service Commission, et al. v. Entergy Corp., et al. Docket No. EL01–88—Louisiana Public Service Commission v. Entergy Services, Inc. Docket No. EL09–61—Louisiana Public Service Commission v. Entergy Services, Inc. Docket No. EL10–65—Louisiana Public Service Commission v. Entergy Services, Inc. Docket No. EL14–19—Midcontinent Independent System Operator and Entergy Services, Inc. Docket No. EL16–7—City of Osceola, Arkansas v. Entergy Arkansas, Inc. Docket No. ER10–1350—Entergy Arkansas, Inc. Docket No. ER13–432—Entergy Arkansas, Inc. Docket No. ER13–948—Entergy Arkansas, Inc. Docket No. ER13–1195—Entergy Arkansas, Inc. Docket No. ER13–1508—Entergy Arkansas, Inc. Docket No. ER13–1509—Entergy Gulf States Louisiana, L.L.C. Docket No. ER13–1510—Entergy Louisiana, LLC. Docket No. ER13–1511—Entergy Mississippi, Inc. Docket No. ER13–1512—Entergy New Orleans, Inc. Docket No. ER13–1513—Entergy Texas, Inc. Docket No. ER14–649—Midcontinent Independent System Operator, Inc. Docket No. ER14–693—Entergy Services, Inc. Docket No. ER14–694—Entergy Services, Inc. Docket No. ER14–695—Entergy Services, Inc. Docket No. ER14–696—Entergy Services, Inc. Docket No. ER14–697—Entergy Services, Inc. Docket No. ER14–699—Entergy Services, Inc. Docket No. ER14–700—Entergy Services, Inc. Docket No. ER14–701—Entergy Services, Inc. Docket No. ER14–702—Entergy Arkansas, Inc. Docket No. ER14–703—Entergy Services, Inc. Docket No. ER14–704—Entergy Services, Inc. Docket No. ER14–1640—Entergy Gulf States Louisiana, L.L.C Docket No. ER14–1641—Entergy Louisiana, LLC. Docket No. ER14–1642—Entergy Mississippi, Inc. VerDate Sep<11>2014 16:39 Aug 16, 2016 Jkt 238001 Docket No. ER14–1643—Entergy New Orleans, Inc. Docket No. ER14–1644—Entergy Texas, Inc. Docket No. ER14–2850—Southwest Power Pool, Inc. Docket No. ER14–2851—Southwest Power Pool, Inc. Docket No. ER15–1436—Entergy Gulf States Louisiana, L.L.C. Docket No. ER15–1453—Entergy Arkansas, Inc. Docket No. ER15–1826—Entergy Services, Inc. Docket No. ER16–227—Entergy Arkansas, Inc. Docket No. ER16–1087—Entergy New Orleans, Inc. Docket No. ER16–1251—Entergy Louisiana, LLC. Docket No. ER16–1316—Entergy Services, Inc. Docket No. ER16–1528—Entergy Arkansas, Inc. Docket No. ER16–1806—Entergy Services, Inc. Docket No. ER16–1965—Entergy Louisiana, LLC. Docket No. ER16–2034—Entergy Louisiana, LLC. Docket No. ER16–2124—Entergy New Orleans, Inc. Docket No. ER16–2125—Entergy Louisiana, LLC. Docket No. ER16–2199—Entergy Arkansas, Inc. Docket No. ER16–2200— Midcontinent Independent System Operator, Inc. These meetings are open to the public. For more information, contact Patrick Clarey, Office of Energy Market Regulation, Federal Energy Regulatory Commission at (317) 249–5937 or patrick.clarey@ferc.gov. Dated: August 11, 2016. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2016–19572 Filed 8–16–16; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket Nos. CP16–487–000, PF15–32–000] Northern Natural Gas Company; Notice of Application Take notice that on July 29, 2016, Northern Natural Gas Company (Northern), 1111 South 103rd Street, Omaha, Nebraska 68124–1000, filed in Docket No. CP16–487–000 an application pursuant to section 7(c) of PO 00000 Frm 00013 Fmt 4703 Sfmt 4703 the Natural Gas Act (NGA), and Part 157 of the Commission’s Regulations, requesting authorization to construct and operate 7.86-mile-long 20-inchdiameter pipeline with appurtenances located in Dakota County, Minnesota (Cedar Station Upgrade Project). Northern also requests a predetermination of rolled-in rate treatment, all as more fully set forth in the application which is on file with the Commission and open to public inspection. The filing may also be viewed on the web at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at (866) 208–3676, or TTY, contact (202) 502–8659. Any questions concerning this application may be directed to Michael T. Loeffler, Senior Director, Certificates and External Affairs for Northern, 1111 South 103rd Street, Omaha, Nebraska 68124, or by calling (402) 398–7103. Specifically, Northern designed the Cedar Station Upgrade Project to increase the delivery pressure at Northern’s existing Cedar Station located in Eagan, Minnesota, in accordance with a contractual obligation for Northern States Power Company (NSP–MN). The proposed pipeline will originate at Northern’s existing Rosemount Junction facility in Rosemount, Minnesota and extend to its existing Cedar Station. Northern states that due to mainline constraints upstream of the branch line, the proposed project is not expected to generate incremental capacity that can be sold. The requested order date and proposed in-service date are March 17, 2017 and November 1, 2017 respectively. The project cost is estimated at $49,865,629. On October 9, 2015, the Commission staff granted Northern’s request to utilize the Pre-Filing Process and assigned Docket No. PF15–32–000 to staff activities involved in the above referenced project. Now, as of the filing of the July 29, 2016 application, the PreFiling Process for this project has ended. From this time forward, this proceeding will be conducted in Docket No. CP16– 487–000, as noted in the caption of this Notice. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding; or E:\FR\FM\17AUN1.SGM 17AUN1 mstockstill on DSK3G9T082PROD with NOTICES Federal Register / Vol. 81, No. 159 / Wednesday, August 17, 2016 / Notices issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s EA. There are two ways to become involved in the Commission’s review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below, file with the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission’s Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit five copies of filings made with the Commission and must mail a copy to the applicant and to every other party in the proceeding. Only parties to the proceeding can ask for court review of Commission orders in the proceeding. However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission’s rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commentors will be placed on the Commission’s environmental mailing list, will receive VerDate Sep<11>2014 16:39 Aug 16, 2016 Jkt 238001 copies of the environmental documents, and will be notified of meetings associated with the Commission’s environmental review process. Environmental commentors will not be required to serve copies of filed documents on all other parties. However, the non-party commentors will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically should submit original and five copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. Comment Date: 5:00 p.m. Eastern Time on September 1, 2016. Dated: August 11, 2016. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2016–19570 Filed 8–16–16; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket Nos. CP16–486–000, PF16–3–000] Notice of Application Millennium Pipeline Company, LLC Take notice that on July 29, 2016, Millennium Pipeline Company (Millennium), One Blue Hill Plaza, Pearl River, New York 10965, filed in Docket No. CP16–486–000 an application pursuant to section 7(c) of the Natural Gas Act (NGA), and Part 157 of the Commission’s Regulations, requesting a certificate of public convenience and necessity authorizing their Eastern System Upgrade Project. This project will provide an additional 223 million cubic feet per day (MMcf/d) of firm transportation capacity from Millennium’s Corning Compressor Station (CS) to an existing interconnection with Algonquin Gas Transmission, LLC located in Ramapo, New York, all as more fully set forth in the application which is on file with the Commission and open to public inspection. The filing may also be viewed on the web at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket PO 00000 Frm 00014 Fmt 4703 Sfmt 4703 54799 number excluding the last three digits in the docket number field to access the document. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at (866) 208–3676, or TTY, contact (202) 502–8659. Any questions concerning this application may be directed to Georgia Carter, Vice President and General Counsel, Millennium Pipeline Company, LLC, 109 North Post Oak Lane, Suite 210, Houston, TX 77024, by calling 804–921–1408, or emailing carter@millenniumpipeline.com. Specifically, Millennium proposes to construct, operate, and maintain (1) Approximately 7.8-miles of 30- and 36inch-diameter pipeline loop in Orange County, New York; (2) a new 22,400 horsepower (HP) compressor station in Sullivan County, New York; (3) additional 22,400 HP at the existing Hancock Compressor Station in Delaware County, New York; (4) modifications to the existing Ramapo Meter and Regulator Station in Rockland County, New York; (5) modifications to the Wagoner Interconnect in Orange County, New York; (6) additional pipeline appurtenant facilities at the existing Huguenot and Westtown Meter and Regulating Stations in Orange County, New York; and (7) an alternate interconnect to the 16-inch-diameter Valley Lateral at milepost 7.6 of the Project. Millennium states that 202.5 MMcf/d of project capacity is committed under precedent agreements with local distribution companies and municipalities. Millennium requests that that the Commission issue the requested authorizations by July 31, 2017, in order to allow Millennium sufficient time to meet a targeted inservice date in September 2018. Millennium proposes to charge negotiated rates to its project shippers and existing Rate Schedule FT–1 rates for service on the expansion capacity created by the project. The cost of the project is $275,000,000. On February 5, 2016, the Commission staff granted Millennium’s request to utilize the Pre-Filing Process and assigned Docket No. PF16–3–000 to staff activities involved in the above referenced project. Now, as of the filing of the July 29, 2016 application, the PreFiling Process for this project has ended. From this time forward, this proceeding will be conducted in Docket No. CP16– 486–000, as noted in the caption of this Notice. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the E:\FR\FM\17AUN1.SGM 17AUN1

Agencies

[Federal Register Volume 81, Number 159 (Wednesday, August 17, 2016)]
[Notices]
[Pages 54798-54799]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-19570]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. CP16-487-000, PF15-32-000]


Northern Natural Gas Company; Notice of Application

    Take notice that on July 29, 2016, Northern Natural Gas Company 
(Northern), 1111 South 103rd Street, Omaha, Nebraska 68124-1000, filed 
in Docket No. CP16-487-000 an application pursuant to section 7(c) of 
the Natural Gas Act (NGA), and Part 157 of the Commission's 
Regulations, requesting authorization to construct and operate 7.86-
mile-long 20-inch-diameter pipeline with appurtenances located in 
Dakota County, Minnesota (Cedar Station Upgrade Project). Northern also 
requests a predetermination of rolled-in rate treatment, all as more 
fully set forth in the application which is on file with the Commission 
and open to public inspection.
    The filing may also be viewed on the web at https://www.ferc.gov 
using the ``eLibrary'' link. Enter the docket number excluding the last 
three digits in the docket number field to access the document. For 
assistance, please contact FERC Online Support at 
FERCOnlineSupport@ferc.gov or toll free at (866) 208-3676, or TTY, 
contact (202) 502-8659.
    Any questions concerning this application may be directed to 
Michael T. Loeffler, Senior Director, Certificates and External Affairs 
for Northern, 1111 South 103rd Street, Omaha, Nebraska 68124, or by 
calling (402) 398-7103.
    Specifically, Northern designed the Cedar Station Upgrade Project 
to increase the delivery pressure at Northern's existing Cedar Station 
located in Eagan, Minnesota, in accordance with a contractual 
obligation for Northern States Power Company (NSP-MN). The proposed 
pipeline will originate at Northern's existing Rosemount Junction 
facility in Rosemount, Minnesota and extend to its existing Cedar 
Station. Northern states that due to mainline constraints upstream of 
the branch line, the proposed project is not expected to generate 
incremental capacity that can be sold. The requested order date and 
proposed in-service date are March 17, 2017 and November 1, 2017 
respectively. The project cost is estimated at $49,865,629.
    On October 9, 2015, the Commission staff granted Northern's request 
to utilize the Pre-Filing Process and assigned Docket No. PF15-32-000 
to staff activities involved in the above referenced project. Now, as 
of the filing of the July 29, 2016 application, the Pre-Filing Process 
for this project has ended. From this time forward, this proceeding 
will be conducted in Docket No. CP16-487-000, as noted in the caption 
of this Notice.
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or

[[Page 54799]]

issue a Notice of Schedule for Environmental Review. If a Notice of 
Schedule for Environmental Review is issued, it will indicate, among 
other milestones, the anticipated date for the Commission staff's 
issuance of the EA for this proposal. The filing of the EA in the 
Commission's public record for this proceeding or the issuance of a 
Notice of Schedule for Environmental Review will serve to notify 
federal and state agencies of the timing for the completion of all 
necessary reviews, and the subsequent need to complete all federal 
authorizations within 90 days of the date of issuance of the Commission 
staff's EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below, file with the Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit five copies of filings made with the Commission and must mail a 
copy to the applicant and to every other party in the proceeding. Only 
parties to the proceeding can ask for court review of Commission orders 
in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commentors will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commentors will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentors will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFiling'' link 
at https://www.ferc.gov. Persons unable to file electronically should 
submit original and five copies of the protest or intervention to the 
Federal Energy Regulatory Commission, 888 First Street NE., Washington, 
DC 20426.
    Comment Date: 5:00 p.m. Eastern Time on September 1, 2016.

    Dated: August 11, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-19570 Filed 8-16-16; 8:45 am]
 BILLING CODE 6717-01-P