Exelon Generation Company, LLC; Braidwood Station, Units 1 and 2, 48851-48857 [2016-17688]
Download as PDF
Federal Register / Vol. 81, No. 143 / Tuesday, July 26, 2016 / Notices
of children in the household. The BLS
National Longitudinal Survey collects
some information about leave from
employed individuals, but these data
are available only for specific cohorts
and not the entire population.
Information about flexible work
schedules is available through the CPS
Work Schedules and Work at Home
Supplement, but the Supplement has
not been conducted since May 2004.
The proposed Leave Supplement
questions will collect data about leave,
job flexibilities, and work schedules
from a sample of individuals who are
representative of the U.S. civilian
noninstitutional population ages 15 and
over, which is something existing
surveys do not do.
srobinson on DSK5SPTVN1PROD with NOTICES
Desired Focus of Comments
The Bureau of Labor Statistics is
particularly interested in comments
that:
• Evaluate whether the proposed
collection of information is necessary
for the proper performance of the
functions of the agency, including
whether the information will have
practical utility.
• Evaluate the accuracy of the
agency’s estimate of the burden of the
proposed collection of information,
including the validity of the
methodology and assumptions used.
• Enhance the quality, utility, and
clarity of the information to be
collected.
• Minimize the burden of the
collection of information on those who
are to respond, including through the
use of appropriate automated,
electronic, mechanical, or other
technological collection techniques or
other forms of information technology,
e.g., permitting electronic submissions
of responses.
Type of Review: New collection
(Request for a new OMB control
Number).
Agency: Bureau of Labor Statistics.
Title: Leave Supplement to the
American Time Use Survey.
OMB Number: 1220—NEW.
Affected Public: Individuals or
Households.
Total Respondents: 5950.
Frequency: One time.
Total Responses: 5950.
Average Time per Response: 5
minutes.
Estimated Total Burden Hours: 500
hours.
Total Burden Cost (capital/startup):
$0.
Total Burden Cost (operating/
maintenance): $0.
Comments submitted in response to
this notice will be summarized and/or
VerDate Sep<11>2014
20:28 Jul 25, 2016
Jkt 238001
included in the request for Office of
Management and Budget approval of the
information collection request; they also
will become a matter of public record.
Signed at Washington, DC, this 21st day of
July 2016.
Kimberley Hill,
Chief, Division of Management Systems,
Bureau of Labor Statistics.
[FR Doc. 2016–17641 Filed 7–25–16; 8:45 am]
BILLING CODE 4510–24–P
NUCLEAR REGULATORY
COMMISSION
[Docket Nos. 50–456 and 50–457; NRC–
2016–0147]
Exelon Generation Company, LLC;
Braidwood Station, Units 1 and 2
Nuclear Regulatory
Commission.
ACTION: Environmental assessment and
finding of no significant impact;
issuance.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is considering
issuance of amendments to Renewed
Facility Operating License Nos. NPF–72
and NPF–77 issued to Exelon
Generation Company, LLC (Exelon, the
licensee) for operation of Braidwood
Station, Units 1 and 2 (Braidwood),
located in Will County, Illinois. The
proposed amendments would revise the
maximum allowable technical
specification (TS) temperature of the
ultimate heat sink (UHS) for the plant.
The NRC staff is issuing a final
environmental assessment (EA) and
finding of no significant impact (FONSI)
associated with the proposed license
amendments.
DATES: The environmental assessment
and finding of no significant impact
referenced in this document is available
on July 26, 2016.
ADDRESSES: Please refer to Docket ID
NRC–2016–0147 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publically-available
information related to this document
using any of the following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2016–0147. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–415–3463;
email: Carol.Gallagher@nrc.gov. For
technical questions, contact the
individual listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• NRC’s Agencywide Documents
Access and Management System
SUMMARY:
PO 00000
Frm 00116
Fmt 4703
Sfmt 4703
48851
(ADAMS): You may obtain publicly
available documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘ADAMS Public Documents’’ and then
select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The
ADAMS accession number for each
document referenced (if that document
is available in ADAMS) is provided in
a table in the ‘‘Availability of
Documents’’ section of this document.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: Joel
S. Wiebe, Office of Nuclear Reactor
Regulation; U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001; telephone: 301–415–6606; email:
Joel.Wiebe@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Introduction
The NRC is considering issuance of
amendments to Renewed Facility
Operating License Nos. NPF–72 and
NPF–77 issued to Exelon for operation
of Braidwood located in Will County,
Illinois. Exelon submitted its license
amendment request in accordance with
section 50.90 of title 10 of the Code of
Federal Regulations (10 CFR), by letter
dated August 19, 2014 (ADAMS
Accession No. ML14231A902). Exelon
subsequently supplemented its request
as described under ‘‘Description of the
Proposed Action’’ in Section II of this
document. If approved, the license
amendments would increase the
allowable TS temperature limit of the
cooling water supplied to the plant from
the UHS from less than or equal to (≤)
100 degrees Fahrenheit (°F) (37.8
degrees Celsius [°C]) to ≤102 °F (38.9
°C). The NRC staff prepared an EA to
document its findings related to the
proposed license amendments in
accordance with 10 CFR 51.21. Based on
results of the EA documented herein,
the NRC did not identify any significant
environmental impacts associated with
the proposed amendments and is,
therefore, issuing a FONSI in
accordance with 10 CFR 51.32.
II. Environmental Assessment
Plant Site and Environs
Braidwood is located in Will County,
Illinois, approximately 50 miles (mi; 80
kilometers [km]) southwest of the
E:\FR\FM\26JYN1.SGM
26JYN1
srobinson on DSK5SPTVN1PROD with NOTICES
48852
Federal Register / Vol. 81, No. 143 / Tuesday, July 26, 2016 / Notices
Chicago Metropolitan Area and 20 mi
(32 km) south-southwest of Joliet. The
Kankakee River is approximately 5 mi (8
km) east of the eastern site boundary.
An onsite 2,540-acre (ac; 1,030-hectare
[ha]) cooling pond provides condenser
cooling. Cooling water is withdrawn
from the pond through the lake screen
house, which is located at the north end
of the pond. Heated water returns to the
cooling pond through a discharge canal
west of the lake screen house intake that
is separated from the intake by a dike.
The pond typically holds 22,300 acrefeet (27.5 million cubic meters) of water
at any given time. The cooling pond
includes both ‘‘essential’’ and ‘‘nonessential’’ areas. The essential cooling
pond is the portion of the cooling pond
that serves as the UHS for emergency
core cooling, and it consists of a 99-ac
(40-ha) excavated area of the pond
directly in front of the lake screen
house. The essential cooling pond’s
principle functions are to dissipate
residual heat after reactor shutdown and
to dissipate heat after an accident. It is
capable of supplying Braidwood’s
cooling system with 30 days of station
operation without additional makeup
water. For clarity, use of the term
‘‘UHS’’ in this document refers to the
99-ac (40-ha) essential cooling pond,
and use of the term ‘‘cooling pond’’ or
‘‘pond’’ describes the entire 2,540-ac
(1,030-ha) area, which includes both the
essential and non-essential areas.
The cooling pond is part of the
Mazonia-Braidwood State Fish and
Wildlife Area, which encompasses the
majority of the non-UHS area of the
cooling pond as well as Illinois
Department of Natural Resources
(IDNR)-owned lands adjacent to the
Braidwood site to the south and
southwest of the cooling pond. Exelon
and the IDNR have jointly managed the
cooling pond as part of the MazoniaBraidwood State Fish and Wildlife Area
since 1991 pursuant to a long-term lease
agreement. Under the terms of the
agreement, the public has access to the
pond for fishing, waterfowl hunting,
fossil collecting, and other recreational
activities.
The cooling pond is a wastewater
treatment works as defined by Section
301.415 of Title 35 of the Illinois
Administrative Code (35 IAC 301.415).
Under this definition, the cooling pond
is not considered waters of the State
under Illinois Administrative Code (35
IAC 301.440) or waters of the United
States under the Federal Clean Water
Act (40 CFR 230.3(s)), and so the
cooling pond is not subject to State
water quality standards. The cooling
pond can be characterized as a managed
ecosystem where IDNR fish stocking
VerDate Sep<11>2014
20:28 Jul 25, 2016
Jkt 238001
and other human activities primarily
influence the species composition and
population dynamics.
Since the beginning of the lease
agreement between Exelon and IDNR,
the IDNR has stocked the cooling pond
with a variety of game species,
including largemouth bass (Micropterus
salmoides), smallmouth bass (M.
dolomieu), blue catfish (Ictalurus
furcatus), striped bass (Morone
saxatilis), crappie (Pomoxis spp.),
walleye (Sander vitreum), and tiger
muskellunge (Esox masquinongy ×
lucius). IDNR performs annual surveys
to determine which fish to stock based
on fishermen preferences, fish
abundance, different species’ tolerance
to warm waters, predator and prey
dynamics, and other factors. Because of
the high water temperatures
experienced in the summer months,
introductions of warm-water species,
such as largemouth bass and blue
catfish, have been more successful than
introductions of cool-water species,
such as walleye and tiger muskellunge.
Since annual surveys began in 1980,
IDNR has collected 47 species in the
cooling pond. In recent years, bluegill
(Lepomis macrochirus), channel catfish
(Ictalurus punctatus), threadfin shad
(Dorosoma petenense), and common
carp (Cyprinus carpio) have been among
the most abundant species in the
cooling pond. Gizzard shad (Dorosoma
cepedianum), one of the most frequently
affected species during periods of
elevated pond temperatures, have
decreased in abundance dramatically in
recent years, while bluegill, which can
tolerate high temperatures with
relatively high survival, have noticeably
increased in relative abundance. IDNRstocked warm water game species, such
as largemouth bass and blue catfish,
continue to persist in small numbers,
while cooler water stocked species, such
as walleye and tiger muskellunge, no
longer appear in IDNR survey
collections. No Federally-listed species
or designated critical habitats protected
under the Endangered Species Act occur
within or near the cooling pond.
The Kankakee River serves as the
source of makeup water for the cooling
pond. The river also receives
continuous blowdown from the cooling
pond. Water is withdrawn from a small
river screen house located on the
Kankakee River, and liquid effluents
from Braidwood are discharged into the
cooling pond blowdown line, which
subsequently discharges into the
Kankakee River.
The plant site and environs are
described in greater detail in Chapter 3
of the NRC’s November 2015, Generic
Environmental Impact Statement for
PO 00000
Frm 00117
Fmt 4703
Sfmt 4703
License Renewal of Nuclear Plants:
Regarding Braidwood Station, Units 1
and 2—Final Report (NUREG–1437,
Supplement 55) (herein referred to as
‘‘Braidwood FSEIS’’ [Final
Supplemental Environmental Impact
Statement]). Figure 3–5 on page 3–7 of
the Braidwood FSEIS depicts the
Braidwood plant layout, and Figure 3–
4 on page 3–6 depicts the cooling pond,
including the portion of the pond that
constitutes the essential cooling pond
(or UHS) and the blowdown line to the
Kankakee River.
Description of the Proposed Action
The proposed action would increase
the allowable TS temperature limit of
the cooling water supplied to the plant
from the UHS from ≤100 °F (37.8 °C) to
≤102 °F (38.9 °C). Specifically, the
proposed action would amend TS
3.7.9.2, which currently states, ‘‘Verify
average water temperature of UHS is
≤100 °F.’’ Under the current TS, if the
average UHS temperature as measured
at the discharge of the operating
Essential Service Water system pumps
is greater than 100 °F (37.8 °C), TS 3.7.9
Required Actions A.1 and A.2 would be
entered concurrently and would require
the licensee to place Braidwood in hot
standby (Mode 3) within 6 hours and
cold shutdown (Mode 5) within 36
hours. The proposed action would allow
Braidwood to continue to operate
during times when the UHS indicated
temperature exceeds 100 °F (37.8 °C) but
is less than or equal to 102 °F (38.9 °C).
The proposed action would not modify
the TS Required Actions, Completion
Times, Frequency of Surveillance
Requirement performance, or any other
portion of TS 3.7.9. Therefore, the
proposed amendments would require
the licensee to place Braidwood in
Mode 3 within 6 hours and Mode 5
within 36 hours if the UHS indicated
temperature is greater than 102 °F (38.9
°C).
The proposed action to amend TS
3.7.9.2 is in accordance with the
licensee’s application dated August 19,
2014, as supplemented by letters dated
January 20, 2015, March 31, 2015, April
30, 2015, August 24, 2015, October 9,
2015, October 30, 2015, November 9,
2015, December 16, 2015, February 12,
2016, April 29, 2016, and June 16, 2016.
Need for the Proposed Action
The proposed action is needed to
provide the licensee with operational
flexibility during periods of high UHS
temperatures in order to avoid plant
shutdown. These conditions include
elevated air temperatures, high
humidity, and low wind speed. For
instance, in July 2012, Exelon requested,
E:\FR\FM\26JYN1.SGM
26JYN1
Federal Register / Vol. 81, No. 143 / Tuesday, July 26, 2016 / Notices
srobinson on DSK5SPTVN1PROD with NOTICES
and the NRC approved, Enforcement
Discretion to avoid plant shutdown and
associated transient following
unprecedented hot weather and drought
conditions in northern Illinois that
resulted in the Braidwood average
discharge temperature of the essential
service water pumps used to monitor
compliance with TS 3.7.9.2 to exceed
the limit of ≤100 °F (37.8 °C). The NRC’s
Enforcement Discretion allowed Exelon
to continue to operate Braidwood with
an average UHS water temperature of up
to ≤102 °F (38.9 °C) for a period of 24
hours before Exelon would be required
to place Braidwood in hot standby
(Mode 3) in accordance with TS 3.7.9
Required Action A.1. The Enforcement
Discretion period extended from July 7,
2012, at 3:56 p.m. until July 8, 2012,
3:56 p.m. During that time, the average
UHS water temperature exceeded 100 °F
(37.8 °C). Although Exelon did not
anticipate making a license amendment
request at the time of the NRC’s
Enforcement Discretion, Exelon is
seeking the current license amendments
in anticipation of future meteorological
conditions that may continue to
challenge the current UHS TS
temperature limit of ≤100 °F (37.8 °C).
Environmental Impacts of the Proposed
Action
With regard to radiological impacts,
the proposed action would not result in
any changes in the types of radioactive
effluents that may be released from the
plant offsite. No significant increase in
the amount of any radioactive effluent
released offsite or significant increase in
occupational or public radiation
exposure is expected from the proposed
action. Separate from this EA, the NRC
staff is evaluating the licensee’s safety
analyses of the potential radiological
consequences of an accident that may
result from the proposed action. The
results of the NRC staff’s safety analysis
will be documented in a safety
evaluation (SE). If the NRC staff
concludes in the SE that all pertinent
regulatory requirements related to
radiological effluents are met by the
proposed UHS temperature limit
increase, then the proposed action
would result in no significant
radiological impact to the environment.
The NRC staff’s SE will be issued with
the license amendments, if approved by
the NRC.
With regard to potential nonradiological impacts, raising the
maximum allowable UHS temperature
from ≤100 °F (37.8 °C) to ≤102 °F (38.9
°C) could result in periods of increased
cooling pond water temperatures,
especially during periods of extreme
high air temperatures, high humidity,
VerDate Sep<11>2014
20:28 Jul 25, 2016
Jkt 238001
and low wind. Because the proposed
action would not affect Braidwood’s
licensed thermal power level, the
temperature rise across the condensers
as cooling water travels through the
cooling system would remain constant.
Therefore, if water in the UHS were to
rise to 102 °F (38.9 °C), heated water
returning to the cooling pond through
the discharge canal, which lies west of
the river screen house, would also
experience a corresponding 2 °F (1.1 °C)
increase. That additional heat load
would dissipate across some thermal
gradient as discharged water would
travel down the discharge canal and
through the 99-ac (40-ha) UHS.
Fish kills are likely to occur when
cooling pond temperatures rise above 95
°F (35 °C), the temperature at which
most fish in the cooling pond are
thermally stressed. For example, Section
3.7.4 of the Braidwood FSEIS describes
six fish kill events for the period of 2001
through 2015. The fish kill events,
which occurred in July 2001, August
2001, June 2005, August 2007, June
2009, and July 2012, primarily affected
threadfin shad and gizzard shad,
although bass, catfish, carp, and other
game fish were also affected. Reported
peak temperatures in the cooling pond
during these events ranged from 98.4 °F
(36.9 °C) to over 100 °F (37.8 °C), and
each event resulted in the death of
between 700 to as many as 10,000 fish.
The event identified in Exelon letter
dated April 30, 2014, in which cooling
pond temperatures exceeded 100 °F
(37.8 °C) occurred on July 7 and 8, 2012,
and resulted in the death of
approximately 3,000 gizzard shad and
100 bass, catfish, and carp. This event
coincided with the NRC’s granting of
Enforcement Discretion to allow
Braidwood to continue to operate above
the TS limit of ≤100 °F (37.8 °C) as
previously described in the ‘‘Need for
the Proposed Action’’ section of this
document. The IDNR attributed this
event, as well as four of the other fish
kill events, to high cooling pond
temperatures resulting from Braidwood
operation. Appendix B, Section 4.1 of
the Braidwood renewed facility
operating licenses, requires Exelon to
report to the NRC the occurrence of
unusual or important environmental
events, including fish kills. Since the
issuance of the Braidwood FSEIS in
November 2015, Exelon has not
reported any additional fish kill events
to the NRC.
In Section 4.7.1.3 of the Braidwood
FSEIS, the NRC staff concluded that
thermal impacts associated with
continued operation of Braidwood
during the license renewal term (i.e.,
with a UHS TS limit of ≤100 °F) would
PO 00000
Frm 00118
Fmt 4703
Sfmt 4703
48853
result in SMALL to MODERATE
impacts to aquatic resources in the
cooling pond. MODERATE impacts
would primarily be experienced by
gizzard shad and other non-stocked and
low-heat tolerant species. As part of its
conclusion, the staff also noted that
because the cooling pond is a highly
managed system, any cascading effects
that result from the loss of gizzard shad
(such as reduction in prey for stocked
species, which in turn could affect those
stocked species’ populations) could be
mitigated through IDNR’s annual
stocking and continual management of
the pond.
Regarding the proposed action, the
proposed increase in the allowable UHS
temperature limit would not increase
the likelihood of a fish kill event
attributable to high cooling pond
temperatures because the current TS
limit for the UHS of ≤100 °F (37.8 °C)
already results in cooling pond
temperatures above those at which most
fish species are thermally stressed (95 °F
(35 °C). In effect, if the UHS temperature
rises to the current TS limit, fish within
or near the discharge canal, within the
flow path between the discharge canal
and UHS, or within the UHS itself
would have already experienced
thermal stress and possibly died.
Therefore, an incremental increase in
the allowable UHS water temperature by
2 °F (1.1 °C) and the corresponding
temperature increases within and near
the discharge canal and within the flow
path between the discharge canal and
UHS would not significantly affect the
number of fish kill events experienced
in the cooling pond.
While the proposed action would not
affect the likelihood of a fish kill event
occurring during periods when the
average UHS water temperature
approaches the TS limit, the proposed
action could increase the number of fish
killed per high temperature event. For
fish with thermal tolerances at or near
95 °F (35 °C), there would likely be no
significant difference in the number of
affected fish per high temperature event
because, as already stated, these fish
would have already experienced
thermal stress and possibly died and the
additional temperature increase would
not measurably affect the mortality rate
of these individuals. For fish with
thermal tolerances above 95 °F (35 °C),
such as bluegill, increased mortality is
possible, as described below.
The available scientific literature
provides conflicting information to
support a clear determination of
whether the incremental increase of 2 °F
(1.1 °C) would result in a subsequent
increase in the mortality rate of bluegill
or other high-temperature-tolerant fish
E:\FR\FM\26JYN1.SGM
26JYN1
srobinson on DSK5SPTVN1PROD with NOTICES
48854
Federal Register / Vol. 81, No. 143 / Tuesday, July 26, 2016 / Notices
at temperatures exceeding 100 °F (37.8
°C). For instance, in laboratory studies,
Banner and Van Arman (1973)
demonstrated 85 percent survival of
juvenile bluegill after 24 hours of
exposure to 98.6 °F (37.0 °C) water for
stock acclimated to 91.2 °F (32.9 °C). At
100.0 °F (37.8 °C), survival decreased to
25 percent, and at 100.4 °F (38.0 °C) and
102.0 °F (38.9 °C), no individuals
survived. Even at one hour of exposure
to 102.0 °F (38.9 °C) water, average
survival was relatively low at between
40 to 67.5 percent per replicate.
However, in another laboratory study,
Cairns (1956 in Banner and Van Arman
1973) demonstrated that if juvenile
bluegill were acclimated to higher
temperatures at 3.6 °F (2.0 °C) per day,
individuals could tolerate water
temperatures up to 102.6 °F (39.2 °C)
with 80 percent survival after 24 hours
of exposure.
Although these studies provide
inconsistent thermal tolerance limits,
information from past fish kill events
indicates that Cairns’ results better
describe the cooling pond’s bluegill
population because Exelon has not
reported bluegill as one of the species
that has been affected by past high
temperature events, including the July
2012 event during which the cooling
pond exceeded 100 °F (37.8 °C).
Therefore, bluegill are likely acclimating
to temperature rises at a rate that allows
those individuals to remain in high
temperature areas until temperatures
decrease or that allows individuals time
to seek refuge in cooler areas of the
pond. Alternately, if Banner and Van
Arman’s results were more predictive,
75 percent or more of bluegill
individuals in high temperature areas of
the cooling pond could be expected to
die at temperatures approaching or
exceeding 100 °F (37.8 °C) for 24 hours,
and shorter exposure time would likely
result in the death of some reduced
percentage of bluegill individuals.
Exposure to temperatures approaching
102.0 °F (38.9 °C) for at least one hour
would also result in observable deaths.
However, as stated previously, Exelon
has not reported bluegill as one of the
species that has been affected during
past fish kills. Consequently, the NRC
staff assumes that bluegill and other
high-temperature-tolerant species in the
cooling pond would experience effects
similar to those observed in Cairn’s
study.
Based on Cairn’s results, the proposed
action’s incremental increase of 2 °F (1.1
°C) could result in the death of some
additional high-temperature-tolerant
individuals, especially in cases where
cooling pond temperatures rise
dramatically over a short period of time
VerDate Sep<11>2014
20:28 Jul 25, 2016
Jkt 238001
(more than 3.6 °F (2.0 °C) in a 24-hour
period). These additional deaths would
likely occur in the region of the UHS
nearest to the intake because this water,
which is likely near or slightly above
100 °F (37.8 °C) under current
operations, could rise by an average of
an additional 2 °F (1.1 °C). This scenario
could create conditions just above those
individuals’ thermal tolerances.
Effectively, this area of the UHS, which
would have been within the upper
thermal limit of habitable conditions for
high-temperature-tolerant individuals
under the current TS limit, would likely
become uninhabitable under the
proposed action’s TS limit of ≤102 °F
(38.9 °C). Therefore, high-temperaturetolerant individuals in this area that
would survive under current conditions
could experience thermal stress and
possibly die under the proposed action.
Nonetheless, for all fish species (those
with thermal tolerances above and
below 95 °F [35 °C]), the discharge
canal, flow path between the discharge
canal and the UHS, and the UHS itself
is a small portion of the cooling pond.
Therefore, while an incremental
increase of the UHS to ≤102 °F (38.9 °C)
would likely increase the area over
which cooling pond temperatures
would rise, the majority of the cooling
pond would remain at tolerable
temperatures, and individuals would be
able to seek refuge in those cooler areas.
Therefore, only fish within or near the
discharge canal, within the flow path
between the discharge canal and UHS,
or within the UHS itself at the time of
elevated temperatures, would likely be
affected, and fish would experience
such effects to lessening degrees over
the thermal gradient that extends from
the discharge canal. This would result
in no significant difference in the
number of fish killed per high
temperature event resulting from the
proposed action when compared to
current operations for those species
with thermal tolerances at or near 95 °F
(35 °C) and an insignificant increase in
the number of individuals affected for
species with thermal tolerances above
95 °F (35 °C), such as bluegill.
Additionally, the cooling pond is a
managed ecosystem in which fish
stocking, fishing pressure, and predatorprey relationships constitute the
primary population pressures. Fish
populations affected by fish kills
generally recover quickly, and therefore,
fish kills do not appear to significantly
influence the fish community structure.
This is demonstrated by the fact that the
species that are most often affected by
high temperature events (threadfin shad
and gizzard shad) are also among the
PO 00000
Frm 00119
Fmt 4703
Sfmt 4703
most abundant species in the cooling
pond. Managed species would continue
to be assessed and stocked by the IDNR
on an annual basis in accordance with
the lease agreement between Exelon and
IDNR. Continued stocking would
mitigate any minor effects resulting
from the proposed action. Accordingly,
the NRC staff concludes that the
proposed action would not result in
significant impacts to aquatic resources
in the cooling pond.
Some terrestrial species, such as birds
or other wildlife, rely on fish or other
aquatic resources from the cooling pond
as a source of food. The NRC staff does
not expect any significant impacts to
birds or other wildlife because, if a fish
kill occurs, the number of dead fish
would be a small proportion of the total
population of fish in the cooling pond.
Furthermore, during fish kills, birds and
other wildlife could consume many of
the floating, dead fish. Additionally and
as described previously, the NRC staff
does not expect that the proposed action
would result in a significant difference
in the number or intensity of fish kill
events.
With regard to water resources and
ecological resources along and within
the Kankakee River, the Illinois
Environmental Protection Agency
(IEPA) imposes regulatory controls on
Braidwood’s thermal effluent through
Title 35, Environmental Protection,
Section 302, ‘‘Water Quality Standards,’’
of the Illinois Administrative Code (35
IAC 302) and through the National
Pollutant Discharge Elimination System
(NPDES) permitting process pursuant to
the Clean Water Act. Section 302 of the
Illinois Administrative Code stipulates
that ‘‘[t]he maximum temperature rise
shall not exceed 2.8 °C (5 °F) above
natural receiving water body
temperatures,’’ (35 IAC 302.211(d)) and
that ‘‘[w]ater temperature at
representative locations in the main
river shall at no time exceed 33.7 °C (93
°F) from April through November and
17.7 °C (63 °F) in other months’’ (35 IAC
302.211(e)). Additional stipulations
pertaining to the mixing zone further
protect water resources and biota from
thermal effluents. Special Condition 4 of
Braidwood NPDES permit no.
IL0048321 mirrors these temperature
requirements and also requires that
water temperature at the edge of the
mixing zone not exceed 60 °F (15.6 °C)
from December through March during
more than 1 percent of the hours in a
12-month period and that at no time
shall the water temperature at such
locations exceed the maximum limits by
more than 3 °F (1.6 °C) (i.e., 63 °F [17.2
°C]). Under the proposed action,
Braidwood thermal effluent would
E:\FR\FM\26JYN1.SGM
26JYN1
srobinson on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 81, No. 143 / Tuesday, July 26, 2016 / Notices
continue to be limited by the Illinois
Administrative Code and the Braidwood
NPDES permit to ensure that Braidwood
operations do not create adverse effects
on water resources or ecological
resources along or within the Kankakee
River. In the past 5 years, Exelon
applied for and the IEPA granted one
provisional variance to allow higherthan-permitted temperatures at the edge
of the discharge mixing zone caused by
a period of extremely warm weather and
little to no precipitation. Exelon
reported no fish kills or other events to
the IEPA or the NRC that would indicate
adverse environmental effects resulting
from the provisional variance. The
details of this provisional variance are
described in Section 4.7.1.3 of the
Braidwood FSEIS. Under the proposed
action, Exelon would remain subject to
these Federal and State regulatory
controls. The NRC staff finds it
reasonable to assume that Exelon’s
continued compliance with, and the
State’s continued enforcement of, the
Illinois Administrative Code and the
Braidwood NPDES permit would ensure
that Kankakee River water resources and
ecological resources are protected.
Further, the proposed action would not
alter the types or amount of effluents
being discharged to the river as
blowdown. Therefore, the NRC staff
does not expect any significant impacts
to water resources or ecological
resources within and along the
Kankakee River as a result of raising the
maximum allowable UHS temperature
limit.
During its license renewal
environmental review, the NRC staff
consulted with the U.S. Fish and
Wildlife Service (FWS) pursuant to
section 7 of the Endangered Species Act
concerning Federally-listed species.
During that consultation, the NRC found
that the sheepnose (Plethobasus
cyphyus) and snuffbox (Epioblasma
triquetra) mussels, northern long-eared
bat (Myotis septentrionalis), and eastern
massasauga (Sistrurus catenatus) had
the potential to occur in the areas that
would be directly or indirectly affected
by license renewal (i.e., the action area).
In September 2015, Exelon transmitted
to the NRC and the FWS the results of
a mussel survey, which documented the
absence of Federally-listed mussels near
the Braidwood discharge site in the
Kankakee River. Based on this survey
and other information described in the
Braidwood FSEIS, the NRC concluded
that the license renewal may affect, but
is not likely to adversely affect the
sheepnose mussel. For the remaining
VerDate Sep<11>2014
20:28 Jul 25, 2016
Jkt 238001
species, the NRC determined that
license renewal would have no effect on
the snuffbox, northern long-eared bat,
and eastern massasauga. The FWS
concurred with the NRC’s ‘‘not likely to
adversely affect’’ determination in a
letter dated October 20, 2015. The
results of the consultation are further
summarized in the January 27, 2016,
Record of Decision for Braidwood
license renewal. As previously
described, the proposed increase in the
allowable UHS temperature limit would
not affect water resources or ecological
resources along and within the
Kankakee River. The proposed action
would also not result in any disturbance
or other impacts to terrestrial habitats.
Because impacts would be confined to
the cooling pond and no Federallylisted species or designated critical
habitats have been identified within or
near the cooling pond, the NRC staff
concludes that the proposed action
would have no effect on Federally-listed
species or critical habitat. Accordingly,
consultation with the FWS for the
proposed action is not necessary
because Federal agencies are not
required to consult with the FWS if the
agency determines that an action will
have no effect on listed species or
critical habitat as stated in the U.S. Fish
and Wildlife Service Endangered
Species Consultations: Frequently
Asked Questions, dated July 15, 2013.
The NRC staff has identified no
foreseeable land use, visual resource,
noise, or waste management impacts
given that the proposed action would
not result in any physical changes to
Braidwood facilities or equipment or
changes any land uses on or off site. The
NRC staff has identified no air quality
impacts given that the proposed action
would not result in air emissions
beyond what would be experienced
during current operations. Additionally,
there would be no socioeconomic,
environmental justice, or historic and
cultural resource impacts associated
with the proposed action since no
physical change would occur beyond
the site boundaries and any impacts
would be limited to the cooling pond.
Based on the foregoing analysis, the
NRC staff concludes that the proposed
action would have no significant
environmental impacts.
Environmental Impacts of the
Alternatives to the Proposed Action
As an alternative to the proposed
action, the NRC considered denial of the
proposed amendments (i.e., the ‘‘noaction’’ alternative). Denial of the
PO 00000
Frm 00120
Fmt 4703
Sfmt 4703
48855
proposed amendments would result in
no change in current environmental
conditions and impacts at Braidwood.
Alternative Use of Resources
This action does not involve the use
of any resources not previously
considered in NUREG–1437,
Supplement 55, Generic Environmental
Impact Statement for License Renewal
of Nuclear Plants: Regarding Braidwood
Station, Units 1 and 2—Final Report.
Agencies and Persons Consulted
The staff did not enter into
consultation with any other Federal
agency or with the State of Illinois
regarding the environmental impact of
the proposed action. However, on May
11, 2016, the NRC notified the Illinois
State official, Mr. Alwyn C. Settles,
Nuclear Facility Section Head, of the
Bureau of Nuclear Facility Safety of the
proposed amendments. The State
official had no comments.
III. Finding of No Significant Impact
The NRC is considering issuing
amendments for Renewed Facility
Operating License Nos. NPF–72 and
NPF–77, issued to Exelon for operation
of Braidwood to increase the allowable
TS 3.7.9.2 temperature limit of the
cooling water supplied to the plant from
the UHS from ≤100 °F (38.9 °C) to
≤102 °F (38.9 °C).
On the basis of the EA included in
Section II above and incorporated by
reference in this finding, the NRC
concludes that the proposed action
would not have significant effects on the
quality of the human environment. The
NRC’s evaluation considered
information provided in the licensee’s
application and associated supplements
as well as the NRC’s independent
review of other relevant environmental
documents. Section IV below lists the
environmental documents related to the
proposed action and includes
information on the availability of these
documents. Based on its findings, the
NRC has decided not to prepare an
environmental impact statement for the
proposed action.
IV. Availability of Documents
The following table identifies the
documents cited in this document and
related to the NRC’s FONSI. These
documents are available for public
inspection online through ADAMS at
https://www.nrc.gov/reading-rm/
adams.html or in person at the NRC’s
PDR as previously described.
E:\FR\FM\26JYN1.SGM
26JYN1
48856
Federal Register / Vol. 81, No. 143 / Tuesday, July 26, 2016 / Notices
ADAMS
Accession No.
Document
License Amendment Request and Associated Supplements
Exelon Generation Company, LLC ......................................................................................................................................................
Request for a License Amendment to Braidwood Station, Units 1 and 2, Technical Specification 3.7.9, ‘‘Ultimate Heat Sink.’’
Dated August 19, 2014.
Exelon Generation Company, LLC ......................................................................................................................................................
Supplemental Information in Support of Request for a License Amendment to Braidwood Station, Units 1 and 2, Technical
Specification 3.7.9, ‘‘Ultimate Heat Sink.’’ Dated January 20, 2015.
Exelon Generation Company, LLC ......................................................................................................................................................
Response to Request for Additional Information Regarding Request for a License Amendment to Braidwood Station, Units 1 and
2, Technical Specification 3.7.9, ‘‘Ultimate Heat Sink.’’ Dated March 31, 2015.
Exelon Generation Company, LLC ......................................................................................................................................................
Response to Request for Additional Information Regarding Request for a License Amendment to Braidwood Station, Units 1 and
2, Technical Specification 3.7.9, ‘‘Ultimate Heat Sink.’’ Dated April 30, 2015.
Exelon Generation Company, LLC ......................................................................................................................................................
Supplemental Information in Support of Request for a License Amendment to Braidwood Station, Units 1 and 2, Technical
Specification 3.7.9, ‘‘Ultimate Heat Sink.’’ Dated August 24, 2015.
Exelon Generation Company, LLC ......................................................................................................................................................
Response to Request for Additional Information Regarding Request for a License Amendment to Braidwood Station, Units 1 and
2, Technical Specification 3.7.9, ‘‘Ultimate Heat Sink.’’ Dated October 9, 2015.
Exelon Generation Company, LLC ......................................................................................................................................................
Response to Request for Additional Information Regarding Request for a License Amendment to Braidwood Station, Units 1 and
2, Technical Specification 3.7.9, ‘‘Ultimate Heat Sink.’’ Dated October 30, 2015.
Exelon Generation Company, LLC ......................................................................................................................................................
Response to Request for Additional Information Regarding Request for a License Amendment to Braidwood Station, Units 1 and
2, Technical Specification 3.7.9, ‘‘Ultimate Heat Sink.’’ Dated November 9, 2015.
Exelon Generation Company, LLC ......................................................................................................................................................
Response to Request for Additional Information Regarding Request for a License Amendment to Braidwood Station, Units 1 and
2, Technical Specification 3.7.9, ‘‘Ultimate Heat Sink.’’ Dated December 16, 2015.
Exelon Generation Company, LLC ......................................................................................................................................................
Supplemental Information in Support of Request for a License Amendment to Braidwood Station, Units 1 and 2, Technical
Specification 3.7.9, ‘‘Ultimate Heat Sink.’’ Dated February 12, 2016.
Exelon Generation Company, LLC ......................................................................................................................................................
Response to Request for Additional Information Regarding Request for a License Amendment to Braidwood Station, Units 1 and
2, Technical Specification 3.7.9, ‘‘Ultimate Heat Sink.’’ Dated April 29, 2016.
Exelon Generation Company, LLC ......................................................................................................................................................
Supplemental Information Regarding Request for a License Amendment to Braidwood Station, Units 1 and 2, Technical Specification 3.7.9, ‘‘Ultimate Heat Sink.’’ Dated June 17, 2016.
ML14231A902
ML15020A246
ML15090A604
ML15120A396
ML15236A144
ML15282A345
ML15303A326
ML15313A254
ML15364A369
ML16043A496
ML16123A014
ML16169A139
srobinson on DSK5SPTVN1PROD with NOTICES
Other Referenced Documents
Cairns J. 1956. Effects of heat on fish. Industrial Wastes, 1:180–183 ...............................................................................................
Banner A, Van Arman JA. 1973. Thermal effects on eggs, larvae and juveniles of bluegill sunfish. Washington, DC: U.S. Environmental Protection Agency. EPA–R3–73–041.
Ecological Specialists, Inc. ...................................................................................................................................................................
Final Report: Five Year Post-Construction Monitoring of the Unionid Community Near the Braidwood Station Kankakee River
Discharge. Dated September 2015.
Exelon Generation Company, LLC ......................................................................................................................................................
Request for Enforcement Discretion for Technical Specification 3.7.9, ‘‘Ultimate Heat Sink.’’ Dated July 10, 2012.
Exelon Generation Company, LLC ......................................................................................................................................................
Licensee Event Report 2012–004–01—Notice of Enforcement Discretion Received for Ultimate Heat Sink Temperature Exceeding Technical Specifications Requirements Due to Prolonged Hot Weather. Dated September 5, 2012.
Exelon Generation Company, LLC ......................................................................................................................................................
Licensee Event Report 2012–004–01—Notice of Enforcement Discretion Received for Ultimate Heat Sink Temperature Exceeding Technical Specifications Requirements Due to Prolonged Hot Weather. Dated December 13, 2012.
Exelon Generation Company, LLC ......................................................................................................................................................
Byron and Braidwood Stations, Units 1 and 2, License Renewal Application, Braidwood Station Applicant’s Environmental Report, Responses to Requests for Additional Information, Environmental RAIs AQ–11 to AQ–15. Dated April 30, 2014.
Exelon Generation Company, LLC ......................................................................................................................................................
Braidwood, Units 1 and 2—Transmittal of Report Titled ‘‘Five Year Post-Construction Monitoring of the Unionid Community Near
the Braidwood Station Kankakee River Discharge Location.’’ Dated September 2015.
Illinois Environmental Protection Agency .............................................................................................................................................
Exelon Generation Company, LLC—Braidwood Station, Units 1 and 2, National Pollutant Discharge Elimination System
(NPDES) Permit No. IL0048321. Issued on July 31, 2014
U.S. Fish and Wildlife Service .............................................................................................................................................................
Endangered Species Consultations: Frequently Asked Questions. Dated July 15, 2013.
U.S. Fish and Wildlife Service .............................................................................................................................................................
Concurrence Letter Concluding Informal Consultation with the NRC for Braidwood License Renewal. Dated October 20, 2015.
U.S. Nuclear Regulatory Commission .................................................................................................................................................
Notice of Enforcement Discretion for Exelon Generation Company, LLC, Regarding Braidwood Station. Dated July 12, 2012.
U.S. Nuclear Regulatory Commission .................................................................................................................................................
Generic Environmental Impact Statement for License Renewal of Nuclear Plants: Regarding Braidwood Plant, Units 1 and 2—
Final Report (NUREG–1437, Supplement 55). Dated November 30, 2015.
VerDate Sep<11>2014
20:28 Jul 25, 2016
Jkt 238001
PO 00000
Frm 00121
Fmt 4703
Sfmt 4703
E:\FR\FM\26JYN1.SGM
26JYN1
n/a (1)
n/a (1)
ML15274A087
ML12192A637
ML12249A256
ML12349A174
ML14339A044
ML15274A093
ML14227A712
ML16120A505
ML15299A013
ML12194A681
ML15314A814
Federal Register / Vol. 81, No. 143 / Tuesday, July 26, 2016 / Notices
48857
Document
ADAMS
Accession No.
U.S. Nuclear Regulatory Commission .................................................................................................................................................
Exelon Generation Company, LLC; Docket No. STN 50–456; Braidwood Station, Unit 1 Renewed Facility Operating License.
Issued on January 27, 2016
U.S. Nuclear Regulatory Commission .................................................................................................................................................
Exelon Generation Company, LLC; Docket No. STN 50–457; Braidwood Station, Unit 2 Renewed Facility Operating License.
Issued on January 27, 2016.
U.S. Nuclear Regulatory Commission .................................................................................................................................................
Record of Decision; U.S. Nuclear Regulatory Commission; Docket Nos. 50–456 and 560–457; License Renewal Application for
Braidwood Station, Units 1 and 2. Dated January 27, 2016.
ML053040362
1 These
ML15322A317
references are subject to copyright laws and are, therefore, not reproduced in ADAMS.
Dated at Rockville, Maryland, this 18th day
of July 2016.
For the Nuclear Regulatory Commission.
Joel S. Wiebe,
Senior Project Manager, Plant Licensing
Branch III–2, Division of Operating Reactor
Licensing, Office of Nuclear Reactor
Regulation.
[FR Doc. 2016–17688 Filed 7–25–16; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[NRC–2016–0053]
Program-Specific Guidance About
Possession Licenses for
Manufacturing and Distribution
Nuclear Regulatory
Commission.
ACTION: Draft NUREG; extension of
comment period.
AGENCY:
On July 13, 2016, the U.S.
Nuclear Regulatory Commission (NRC)
solicited comments on draft NUREG–
1556, Volume 12, Revision 1,
‘‘Consolidated Guidance About
Materials Licenses: Program-Specific
Guidance About Possession Licenses for
Manufacturing and Distribution.’’ The
public comment period was originally
scheduled to close on August 12, 2016.
The NRC has decided to extend the
public comment period to allow more
time for members of the public to
develop and submit their comments.
DATES: The due date of comments
requested in the document published on
July 13, 2016 (81 FR 45308) is extended.
Comments should be filed no later than
August 26, 2016. Comments received
after this date will be considered if it is
practical to do so, but the NRC is able
to ensure consideration only for
comments received on or before this
date.
SUMMARY:
srobinson on DSK5SPTVN1PROD with NOTICES
ML053040366
You may submit comments
by any of the following methods (unless
this document describes a different
method for submitting comments on a
specific subject):
ADDRESSES:
VerDate Sep<11>2014
20:28 Jul 25, 2016
Jkt 238001
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2016–0053. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–415–3463;
email: Carol.Gallagher@nrc.gov. For
technical questions, contact the
individual listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• Mail comments to: Cindy Bladey,
Office of Administration, Mail Stop:
OWFN–12–H08, U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001.
For additional direction on accessing
information and submitting comments,
see ‘‘Obtaining Information and
Submitting Comments’’ in the
SUPPLEMENTARY INFORMATION section of
this document.
FOR FURTHER INFORMATION CONTACT:
Anthony McMurtray, Office of Nuclear
Material Safety and Safeguards; U.S.
Nuclear Regulatory Commission,
Washington, DC 20555–0001; telephone:
301–415–2746; email:
Anthony.McMurtray@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Obtaining Information and
Submitting Comments
A. Obtaining Information
Please refer to Docket ID NRC–2016–
0053 when contacting the NRC about
the availability of information regarding
this document. You may obtain
publicly-available information related to
this action by the following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2016–0053.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘ADAMS Public Documents’’ and then
select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
PO 00000
Frm 00122
Fmt 4703
Sfmt 4703
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The draft
NUREG–1556, Volume 12, Revision 1, is
available in ADAMS under Accession
No. ML16182A163.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
The draft NUREG–1556, Volume 12,
Revision 1, is also available on the
NRC’s public Web site on: (1) The
‘‘Consolidated Guidance About
Materials Licenses (NUREG–1556)’’
page at https://www.nrc.gov/reading-rm/
doc-collections/nuregs/staff/sr1556/;
and (2) the ‘‘Draft NUREG-Series
Publications for Comment’’ page at
https://www.nrc.gov/public-involve/doccomment.html#nuregs.
B. Submitting Comments
Please include Docket ID NRC–2016–
0053 in the subject line of your
comment submission, in order to ensure
that the NRC is able to make your
comment submission available to the
public in this docket.
The NRC cautions you not to include
identifying or contact information that
you do not want publicly disclosed in
your comment submission. The NRC
will post all comment submissions at
https://www.regulations.gov as well as
enter the comment submissions into
ADAMS, and the NRC does not
routinely edit comment submissions to
remove identifying or contact
information.
If you are requesting or aggregating
comments from other persons for
submission to the NRC, you should
inform these persons that they should
not to include identifying or contact
information that they do not want to be
publicly disclosed in their comment
submission.
II. Discussion
On July 13, 2016, the NRC solicited
comments on draft NUREG–1556,
Volume 12, Revision 1, ‘‘Consolidated
Guidance About Materials Licenses:
Program-Specific Guidance About
E:\FR\FM\26JYN1.SGM
26JYN1
Agencies
[Federal Register Volume 81, Number 143 (Tuesday, July 26, 2016)]
[Notices]
[Pages 48851-48857]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-17688]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-456 and 50-457; NRC-2016-0147]
Exelon Generation Company, LLC; Braidwood Station, Units 1 and 2
AGENCY: Nuclear Regulatory Commission.
ACTION: Environmental assessment and finding of no significant impact;
issuance.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is considering
issuance of amendments to Renewed Facility Operating License Nos. NPF-
72 and NPF-77 issued to Exelon Generation Company, LLC (Exelon, the
licensee) for operation of Braidwood Station, Units 1 and 2
(Braidwood), located in Will County, Illinois. The proposed amendments
would revise the maximum allowable technical specification (TS)
temperature of the ultimate heat sink (UHS) for the plant. The NRC
staff is issuing a final environmental assessment (EA) and finding of
no significant impact (FONSI) associated with the proposed license
amendments.
DATES: The environmental assessment and finding of no significant
impact referenced in this document is available on July 26, 2016.
ADDRESSES: Please refer to Docket ID NRC-2016-0147 when contacting the
NRC about the availability of information regarding this document. You
may obtain publically-available information related to this document
using any of the following methods:
Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2016-0147. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: Carol.Gallagher@nrc.gov. For technical questions, contact
the individual listed in the FOR FURTHER INFORMATION CONTACT section of
this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS,
please contact the NRC's Public Document Room (PDR) reference staff at
1-800-397-4209, 301-415-4737, or by email to pdr.resource@nrc.gov. The
ADAMS accession number for each document referenced (if that document
is available in ADAMS) is provided in a table in the ``Availability of
Documents'' section of this document.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: Joel S. Wiebe, Office of Nuclear
Reactor Regulation; U.S. Nuclear Regulatory Commission, Washington, DC
20555-0001; telephone: 301-415-6606; email: Joel.Wiebe@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Introduction
The NRC is considering issuance of amendments to Renewed Facility
Operating License Nos. NPF-72 and NPF-77 issued to Exelon for operation
of Braidwood located in Will County, Illinois. Exelon submitted its
license amendment request in accordance with section 50.90 of title 10
of the Code of Federal Regulations (10 CFR), by letter dated August 19,
2014 (ADAMS Accession No. ML14231A902). Exelon subsequently
supplemented its request as described under ``Description of the
Proposed Action'' in Section II of this document. If approved, the
license amendments would increase the allowable TS temperature limit of
the cooling water supplied to the plant from the UHS from less than or
equal to (<=) 100 degrees Fahrenheit ([deg]F) (37.8 degrees Celsius
[[deg]C]) to <=102[emsp14][deg]F (38.9 [deg]C). The NRC staff prepared
an EA to document its findings related to the proposed license
amendments in accordance with 10 CFR 51.21. Based on results of the EA
documented herein, the NRC did not identify any significant
environmental impacts associated with the proposed amendments and is,
therefore, issuing a FONSI in accordance with 10 CFR 51.32.
II. Environmental Assessment
Plant Site and Environs
Braidwood is located in Will County, Illinois, approximately 50
miles (mi; 80 kilometers [km]) southwest of the
[[Page 48852]]
Chicago Metropolitan Area and 20 mi (32 km) south-southwest of Joliet.
The Kankakee River is approximately 5 mi (8 km) east of the eastern
site boundary. An onsite 2,540-acre (ac; 1,030-hectare [ha]) cooling
pond provides condenser cooling. Cooling water is withdrawn from the
pond through the lake screen house, which is located at the north end
of the pond. Heated water returns to the cooling pond through a
discharge canal west of the lake screen house intake that is separated
from the intake by a dike. The pond typically holds 22,300 acre-feet
(27.5 million cubic meters) of water at any given time. The cooling
pond includes both ``essential'' and ``non-essential'' areas. The
essential cooling pond is the portion of the cooling pond that serves
as the UHS for emergency core cooling, and it consists of a 99-ac (40-
ha) excavated area of the pond directly in front of the lake screen
house. The essential cooling pond's principle functions are to
dissipate residual heat after reactor shutdown and to dissipate heat
after an accident. It is capable of supplying Braidwood's cooling
system with 30 days of station operation without additional makeup
water. For clarity, use of the term ``UHS'' in this document refers to
the 99-ac (40-ha) essential cooling pond, and use of the term ``cooling
pond'' or ``pond'' describes the entire 2,540-ac (1,030-ha) area, which
includes both the essential and non-essential areas.
The cooling pond is part of the Mazonia-Braidwood State Fish and
Wildlife Area, which encompasses the majority of the non-UHS area of
the cooling pond as well as Illinois Department of Natural Resources
(IDNR)-owned lands adjacent to the Braidwood site to the south and
southwest of the cooling pond. Exelon and the IDNR have jointly managed
the cooling pond as part of the Mazonia-Braidwood State Fish and
Wildlife Area since 1991 pursuant to a long-term lease agreement. Under
the terms of the agreement, the public has access to the pond for
fishing, waterfowl hunting, fossil collecting, and other recreational
activities.
The cooling pond is a wastewater treatment works as defined by
Section 301.415 of Title 35 of the Illinois Administrative Code (35 IAC
301.415). Under this definition, the cooling pond is not considered
waters of the State under Illinois Administrative Code (35 IAC 301.440)
or waters of the United States under the Federal Clean Water Act (40
CFR 230.3(s)), and so the cooling pond is not subject to State water
quality standards. The cooling pond can be characterized as a managed
ecosystem where IDNR fish stocking and other human activities primarily
influence the species composition and population dynamics.
Since the beginning of the lease agreement between Exelon and IDNR,
the IDNR has stocked the cooling pond with a variety of game species,
including largemouth bass (Micropterus salmoides), smallmouth bass (M.
dolomieu), blue catfish (Ictalurus furcatus), striped bass (Morone
saxatilis), crappie (Pomoxis spp.), walleye (Sander vitreum), and tiger
muskellunge (Esox masquinongy x lucius). IDNR performs annual surveys
to determine which fish to stock based on fishermen preferences, fish
abundance, different species' tolerance to warm waters, predator and
prey dynamics, and other factors. Because of the high water
temperatures experienced in the summer months, introductions of warm-
water species, such as largemouth bass and blue catfish, have been more
successful than introductions of cool-water species, such as walleye
and tiger muskellunge. Since annual surveys began in 1980, IDNR has
collected 47 species in the cooling pond. In recent years, bluegill
(Lepomis macrochirus), channel catfish (Ictalurus punctatus), threadfin
shad (Dorosoma petenense), and common carp (Cyprinus carpio) have been
among the most abundant species in the cooling pond. Gizzard shad
(Dorosoma cepedianum), one of the most frequently affected species
during periods of elevated pond temperatures, have decreased in
abundance dramatically in recent years, while bluegill, which can
tolerate high temperatures with relatively high survival, have
noticeably increased in relative abundance. IDNR-stocked warm water
game species, such as largemouth bass and blue catfish, continue to
persist in small numbers, while cooler water stocked species, such as
walleye and tiger muskellunge, no longer appear in IDNR survey
collections. No Federally-listed species or designated critical
habitats protected under the Endangered Species Act occur within or
near the cooling pond.
The Kankakee River serves as the source of makeup water for the
cooling pond. The river also receives continuous blowdown from the
cooling pond. Water is withdrawn from a small river screen house
located on the Kankakee River, and liquid effluents from Braidwood are
discharged into the cooling pond blowdown line, which subsequently
discharges into the Kankakee River.
The plant site and environs are described in greater detail in
Chapter 3 of the NRC's November 2015, Generic Environmental Impact
Statement for License Renewal of Nuclear Plants: Regarding Braidwood
Station, Units 1 and 2--Final Report (NUREG-1437, Supplement 55)
(herein referred to as ``Braidwood FSEIS'' [Final Supplemental
Environmental Impact Statement]). Figure 3-5 on page 3-7 of the
Braidwood FSEIS depicts the Braidwood plant layout, and Figure 3-4 on
page 3-6 depicts the cooling pond, including the portion of the pond
that constitutes the essential cooling pond (or UHS) and the blowdown
line to the Kankakee River.
Description of the Proposed Action
The proposed action would increase the allowable TS temperature
limit of the cooling water supplied to the plant from the UHS from
<=100 [deg]F (37.8 [deg]C) to <=102 [deg]F (38.9 [deg]C). Specifically,
the proposed action would amend TS 3.7.9.2, which currently states,
``Verify average water temperature of UHS is <=100 [deg]F.'' Under the
current TS, if the average UHS temperature as measured at the discharge
of the operating Essential Service Water system pumps is greater than
100 [deg]F (37.8 [deg]C), TS 3.7.9 Required Actions A.1 and A.2 would
be entered concurrently and would require the licensee to place
Braidwood in hot standby (Mode 3) within 6 hours and cold shutdown
(Mode 5) within 36 hours. The proposed action would allow Braidwood to
continue to operate during times when the UHS indicated temperature
exceeds 100 [deg]F (37.8 [deg]C) but is less than or equal to 102
[deg]F (38.9 [deg]C). The proposed action would not modify the TS
Required Actions, Completion Times, Frequency of Surveillance
Requirement performance, or any other portion of TS 3.7.9. Therefore,
the proposed amendments would require the licensee to place Braidwood
in Mode 3 within 6 hours and Mode 5 within 36 hours if the UHS
indicated temperature is greater than 102 [deg]F (38.9 [deg]C).
The proposed action to amend TS 3.7.9.2 is in accordance with the
licensee's application dated August 19, 2014, as supplemented by
letters dated January 20, 2015, March 31, 2015, April 30, 2015, August
24, 2015, October 9, 2015, October 30, 2015, November 9, 2015, December
16, 2015, February 12, 2016, April 29, 2016, and June 16, 2016.
Need for the Proposed Action
The proposed action is needed to provide the licensee with
operational flexibility during periods of high UHS temperatures in
order to avoid plant shutdown. These conditions include elevated air
temperatures, high humidity, and low wind speed. For instance, in July
2012, Exelon requested,
[[Page 48853]]
and the NRC approved, Enforcement Discretion to avoid plant shutdown
and associated transient following unprecedented hot weather and
drought conditions in northern Illinois that resulted in the Braidwood
average discharge temperature of the essential service water pumps used
to monitor compliance with TS 3.7.9.2 to exceed the limit of <=100
[deg]F (37.8 [deg]C). The NRC's Enforcement Discretion allowed Exelon
to continue to operate Braidwood with an average UHS water temperature
of up to <=102 [deg]F (38.9 [deg]C) for a period of 24 hours before
Exelon would be required to place Braidwood in hot standby (Mode 3) in
accordance with TS 3.7.9 Required Action A.1. The Enforcement
Discretion period extended from July 7, 2012, at 3:56 p.m. until July
8, 2012, 3:56 p.m. During that time, the average UHS water temperature
exceeded 100 [deg]F (37.8 [deg]C). Although Exelon did not anticipate
making a license amendment request at the time of the NRC's Enforcement
Discretion, Exelon is seeking the current license amendments in
anticipation of future meteorological conditions that may continue to
challenge the current UHS TS temperature limit of <=100 [deg]F (37.8
[deg]C).
Environmental Impacts of the Proposed Action
With regard to radiological impacts, the proposed action would not
result in any changes in the types of radioactive effluents that may be
released from the plant offsite. No significant increase in the amount
of any radioactive effluent released offsite or significant increase in
occupational or public radiation exposure is expected from the proposed
action. Separate from this EA, the NRC staff is evaluating the
licensee's safety analyses of the potential radiological consequences
of an accident that may result from the proposed action. The results of
the NRC staff's safety analysis will be documented in a safety
evaluation (SE). If the NRC staff concludes in the SE that all
pertinent regulatory requirements related to radiological effluents are
met by the proposed UHS temperature limit increase, then the proposed
action would result in no significant radiological impact to the
environment. The NRC staff's SE will be issued with the license
amendments, if approved by the NRC.
With regard to potential non-radiological impacts, raising the
maximum allowable UHS temperature from <=100 [deg]F (37.8 [deg]C) to
<=102 [deg]F (38.9 [deg]C) could result in periods of increased cooling
pond water temperatures, especially during periods of extreme high air
temperatures, high humidity, and low wind. Because the proposed action
would not affect Braidwood's licensed thermal power level, the
temperature rise across the condensers as cooling water travels through
the cooling system would remain constant. Therefore, if water in the
UHS were to rise to 102 [deg]F (38.9 [deg]C), heated water returning to
the cooling pond through the discharge canal, which lies west of the
river screen house, would also experience a corresponding 2 [deg]F (1.1
[deg]C) increase. That additional heat load would dissipate across some
thermal gradient as discharged water would travel down the discharge
canal and through the 99-ac (40-ha) UHS.
Fish kills are likely to occur when cooling pond temperatures rise
above 95 [deg]F (35 [deg]C), the temperature at which most fish in the
cooling pond are thermally stressed. For example, Section 3.7.4 of the
Braidwood FSEIS describes six fish kill events for the period of 2001
through 2015. The fish kill events, which occurred in July 2001, August
2001, June 2005, August 2007, June 2009, and July 2012, primarily
affected threadfin shad and gizzard shad, although bass, catfish, carp,
and other game fish were also affected. Reported peak temperatures in
the cooling pond during these events ranged from 98.4 [deg]F (36.9
[deg]C) to over 100 [deg]F (37.8 [deg]C), and each event resulted in
the death of between 700 to as many as 10,000 fish. The event
identified in Exelon letter dated April 30, 2014, in which cooling pond
temperatures exceeded 100 [deg]F (37.8 [deg]C) occurred on July 7 and
8, 2012, and resulted in the death of approximately 3,000 gizzard shad
and 100 bass, catfish, and carp. This event coincided with the NRC's
granting of Enforcement Discretion to allow Braidwood to continue to
operate above the TS limit of <=100 [deg]F (37.8 [deg]C) as previously
described in the ``Need for the Proposed Action'' section of this
document. The IDNR attributed this event, as well as four of the other
fish kill events, to high cooling pond temperatures resulting from
Braidwood operation. Appendix B, Section 4.1 of the Braidwood renewed
facility operating licenses, requires Exelon to report to the NRC the
occurrence of unusual or important environmental events, including fish
kills. Since the issuance of the Braidwood FSEIS in November 2015,
Exelon has not reported any additional fish kill events to the NRC.
In Section 4.7.1.3 of the Braidwood FSEIS, the NRC staff concluded
that thermal impacts associated with continued operation of Braidwood
during the license renewal term (i.e., with a UHS TS limit of <=100
[deg]F) would result in SMALL to MODERATE impacts to aquatic resources
in the cooling pond. MODERATE impacts would primarily be experienced by
gizzard shad and other non-stocked and low-heat tolerant species. As
part of its conclusion, the staff also noted that because the cooling
pond is a highly managed system, any cascading effects that result from
the loss of gizzard shad (such as reduction in prey for stocked
species, which in turn could affect those stocked species' populations)
could be mitigated through IDNR's annual stocking and continual
management of the pond.
Regarding the proposed action, the proposed increase in the
allowable UHS temperature limit would not increase the likelihood of a
fish kill event attributable to high cooling pond temperatures because
the current TS limit for the UHS of <=100 [deg]F (37.8 [deg]C) already
results in cooling pond temperatures above those at which most fish
species are thermally stressed (95 [deg]F (35 [deg]C). In effect, if
the UHS temperature rises to the current TS limit, fish within or near
the discharge canal, within the flow path between the discharge canal
and UHS, or within the UHS itself would have already experienced
thermal stress and possibly died. Therefore, an incremental increase in
the allowable UHS water temperature by 2 [deg]F (1.1 [deg]C) and the
corresponding temperature increases within and near the discharge canal
and within the flow path between the discharge canal and UHS would not
significantly affect the number of fish kill events experienced in the
cooling pond.
While the proposed action would not affect the likelihood of a fish
kill event occurring during periods when the average UHS water
temperature approaches the TS limit, the proposed action could increase
the number of fish killed per high temperature event. For fish with
thermal tolerances at or near 95 [deg]F (35 [deg]C), there would likely
be no significant difference in the number of affected fish per high
temperature event because, as already stated, these fish would have
already experienced thermal stress and possibly died and the additional
temperature increase would not measurably affect the mortality rate of
these individuals. For fish with thermal tolerances above 95 [deg]F (35
[deg]C), such as bluegill, increased mortality is possible, as
described below.
The available scientific literature provides conflicting
information to support a clear determination of whether the incremental
increase of 2 [deg]F (1.1 [deg]C) would result in a subsequent increase
in the mortality rate of bluegill or other high-temperature-tolerant
fish
[[Page 48854]]
at temperatures exceeding 100 [deg]F (37.8 [deg]C). For instance, in
laboratory studies, Banner and Van Arman (1973) demonstrated 85 percent
survival of juvenile bluegill after 24 hours of exposure to 98.6 [deg]F
(37.0 [deg]C) water for stock acclimated to 91.2 [deg]F (32.9 [deg]C).
At 100.0 [deg]F (37.8 [deg]C), survival decreased to 25 percent, and at
100.4 [deg]F (38.0 [deg]C) and 102.0 [deg]F (38.9 [deg]C), no
individuals survived. Even at one hour of exposure to 102.0 [deg]F
(38.9 [deg]C) water, average survival was relatively low at between 40
to 67.5 percent per replicate. However, in another laboratory study,
Cairns (1956 in Banner and Van Arman 1973) demonstrated that if
juvenile bluegill were acclimated to higher temperatures at 3.6 [deg]F
(2.0 [deg]C) per day, individuals could tolerate water temperatures up
to 102.6 [deg]F (39.2 [deg]C) with 80 percent survival after 24 hours
of exposure.
Although these studies provide inconsistent thermal tolerance
limits, information from past fish kill events indicates that Cairns'
results better describe the cooling pond's bluegill population because
Exelon has not reported bluegill as one of the species that has been
affected by past high temperature events, including the July 2012 event
during which the cooling pond exceeded 100 [deg]F (37.8 [deg]C).
Therefore, bluegill are likely acclimating to temperature rises at a
rate that allows those individuals to remain in high temperature areas
until temperatures decrease or that allows individuals time to seek
refuge in cooler areas of the pond. Alternately, if Banner and Van
Arman's results were more predictive, 75 percent or more of bluegill
individuals in high temperature areas of the cooling pond could be
expected to die at temperatures approaching or exceeding 100 [deg]F
(37.8 [deg]C) for 24 hours, and shorter exposure time would likely
result in the death of some reduced percentage of bluegill individuals.
Exposure to temperatures approaching 102.0 [deg]F (38.9 [deg]C) for at
least one hour would also result in observable deaths. However, as
stated previously, Exelon has not reported bluegill as one of the
species that has been affected during past fish kills. Consequently,
the NRC staff assumes that bluegill and other high-temperature-tolerant
species in the cooling pond would experience effects similar to those
observed in Cairn's study.
Based on Cairn's results, the proposed action's incremental
increase of 2 [deg]F (1.1 [deg]C) could result in the death of some
additional high-temperature-tolerant individuals, especially in cases
where cooling pond temperatures rise dramatically over a short period
of time (more than 3.6 [deg]F (2.0 [deg]C) in a 24-hour period). These
additional deaths would likely occur in the region of the UHS nearest
to the intake because this water, which is likely near or slightly
above 100 [deg]F (37.8 [deg]C) under current operations, could rise by
an average of an additional 2 [deg]F (1.1 [deg]C). This scenario could
create conditions just above those individuals' thermal tolerances.
Effectively, this area of the UHS, which would have been within the
upper thermal limit of habitable conditions for high-temperature-
tolerant individuals under the current TS limit, would likely become
uninhabitable under the proposed action's TS limit of <=102 [deg]F
(38.9 [deg]C). Therefore, high-temperature-tolerant individuals in this
area that would survive under current conditions could experience
thermal stress and possibly die under the proposed action.
Nonetheless, for all fish species (those with thermal tolerances
above and below 95 [deg]F [35 [deg]C]), the discharge canal, flow path
between the discharge canal and the UHS, and the UHS itself is a small
portion of the cooling pond. Therefore, while an incremental increase
of the UHS to <=102 [deg]F (38.9 [deg]C) would likely increase the area
over which cooling pond temperatures would rise, the majority of the
cooling pond would remain at tolerable temperatures, and individuals
would be able to seek refuge in those cooler areas. Therefore, only
fish within or near the discharge canal, within the flow path between
the discharge canal and UHS, or within the UHS itself at the time of
elevated temperatures, would likely be affected, and fish would
experience such effects to lessening degrees over the thermal gradient
that extends from the discharge canal. This would result in no
significant difference in the number of fish killed per high
temperature event resulting from the proposed action when compared to
current operations for those species with thermal tolerances at or near
95 [deg]F (35 [deg]C) and an insignificant increase in the number of
individuals affected for species with thermal tolerances above 95
[deg]F (35 [deg]C), such as bluegill. Additionally, the cooling pond is
a managed ecosystem in which fish stocking, fishing pressure, and
predator-prey relationships constitute the primary population
pressures. Fish populations affected by fish kills generally recover
quickly, and therefore, fish kills do not appear to significantly
influence the fish community structure. This is demonstrated by the
fact that the species that are most often affected by high temperature
events (threadfin shad and gizzard shad) are also among the most
abundant species in the cooling pond. Managed species would continue to
be assessed and stocked by the IDNR on an annual basis in accordance
with the lease agreement between Exelon and IDNR. Continued stocking
would mitigate any minor effects resulting from the proposed action.
Accordingly, the NRC staff concludes that the proposed action would not
result in significant impacts to aquatic resources in the cooling pond.
Some terrestrial species, such as birds or other wildlife, rely on
fish or other aquatic resources from the cooling pond as a source of
food. The NRC staff does not expect any significant impacts to birds or
other wildlife because, if a fish kill occurs, the number of dead fish
would be a small proportion of the total population of fish in the
cooling pond. Furthermore, during fish kills, birds and other wildlife
could consume many of the floating, dead fish. Additionally and as
described previously, the NRC staff does not expect that the proposed
action would result in a significant difference in the number or
intensity of fish kill events.
With regard to water resources and ecological resources along and
within the Kankakee River, the Illinois Environmental Protection Agency
(IEPA) imposes regulatory controls on Braidwood's thermal effluent
through Title 35, Environmental Protection, Section 302, ``Water
Quality Standards,'' of the Illinois Administrative Code (35 IAC 302)
and through the National Pollutant Discharge Elimination System (NPDES)
permitting process pursuant to the Clean Water Act. Section 302 of the
Illinois Administrative Code stipulates that ``[t]he maximum
temperature rise shall not exceed 2.8 [deg]C (5 [deg]F) above natural
receiving water body temperatures,'' (35 IAC 302.211(d)) and that
``[w]ater temperature at representative locations in the main river
shall at no time exceed 33.7 [deg]C (93 [deg]F) from April through
November and 17.7 [deg]C (63 [deg]F) in other months'' (35 IAC
302.211(e)). Additional stipulations pertaining to the mixing zone
further protect water resources and biota from thermal effluents.
Special Condition 4 of Braidwood NPDES permit no. IL0048321 mirrors
these temperature requirements and also requires that water temperature
at the edge of the mixing zone not exceed 60 [deg]F (15.6 [deg]C) from
December through March during more than 1 percent of the hours in a 12-
month period and that at no time shall the water temperature at such
locations exceed the maximum limits by more than 3 [deg]F (1.6 [deg]C)
(i.e., 63 [deg]F [17.2 [deg]C]). Under the proposed action, Braidwood
thermal effluent would
[[Page 48855]]
continue to be limited by the Illinois Administrative Code and the
Braidwood NPDES permit to ensure that Braidwood operations do not
create adverse effects on water resources or ecological resources along
or within the Kankakee River. In the past 5 years, Exelon applied for
and the IEPA granted one provisional variance to allow higher-than-
permitted temperatures at the edge of the discharge mixing zone caused
by a period of extremely warm weather and little to no precipitation.
Exelon reported no fish kills or other events to the IEPA or the NRC
that would indicate adverse environmental effects resulting from the
provisional variance. The details of this provisional variance are
described in Section 4.7.1.3 of the Braidwood FSEIS. Under the proposed
action, Exelon would remain subject to these Federal and State
regulatory controls. The NRC staff finds it reasonable to assume that
Exelon's continued compliance with, and the State's continued
enforcement of, the Illinois Administrative Code and the Braidwood
NPDES permit would ensure that Kankakee River water resources and
ecological resources are protected. Further, the proposed action would
not alter the types or amount of effluents being discharged to the
river as blowdown. Therefore, the NRC staff does not expect any
significant impacts to water resources or ecological resources within
and along the Kankakee River as a result of raising the maximum
allowable UHS temperature limit.
During its license renewal environmental review, the NRC staff
consulted with the U.S. Fish and Wildlife Service (FWS) pursuant to
section 7 of the Endangered Species Act concerning Federally-listed
species. During that consultation, the NRC found that the sheepnose
(Plethobasus cyphyus) and snuffbox (Epioblasma triquetra) mussels,
northern long-eared bat (Myotis septentrionalis), and eastern
massasauga (Sistrurus catenatus) had the potential to occur in the
areas that would be directly or indirectly affected by license renewal
(i.e., the action area). In September 2015, Exelon transmitted to the
NRC and the FWS the results of a mussel survey, which documented the
absence of Federally-listed mussels near the Braidwood discharge site
in the Kankakee River. Based on this survey and other information
described in the Braidwood FSEIS, the NRC concluded that the license
renewal may affect, but is not likely to adversely affect the sheepnose
mussel. For the remaining species, the NRC determined that license
renewal would have no effect on the snuffbox, northern long-eared bat,
and eastern massasauga. The FWS concurred with the NRC's ``not likely
to adversely affect'' determination in a letter dated October 20, 2015.
The results of the consultation are further summarized in the January
27, 2016, Record of Decision for Braidwood license renewal. As
previously described, the proposed increase in the allowable UHS
temperature limit would not affect water resources or ecological
resources along and within the Kankakee River. The proposed action
would also not result in any disturbance or other impacts to
terrestrial habitats. Because impacts would be confined to the cooling
pond and no Federally-listed species or designated critical habitats
have been identified within or near the cooling pond, the NRC staff
concludes that the proposed action would have no effect on Federally-
listed species or critical habitat. Accordingly, consultation with the
FWS for the proposed action is not necessary because Federal agencies
are not required to consult with the FWS if the agency determines that
an action will have no effect on listed species or critical habitat as
stated in the U.S. Fish and Wildlife Service Endangered Species
Consultations: Frequently Asked Questions, dated July 15, 2013.
The NRC staff has identified no foreseeable land use, visual
resource, noise, or waste management impacts given that the proposed
action would not result in any physical changes to Braidwood facilities
or equipment or changes any land uses on or off site. The NRC staff has
identified no air quality impacts given that the proposed action would
not result in air emissions beyond what would be experienced during
current operations. Additionally, there would be no socioeconomic,
environmental justice, or historic and cultural resource impacts
associated with the proposed action since no physical change would
occur beyond the site boundaries and any impacts would be limited to
the cooling pond.
Based on the foregoing analysis, the NRC staff concludes that the
proposed action would have no significant environmental impacts.
Environmental Impacts of the Alternatives to the Proposed Action
As an alternative to the proposed action, the NRC considered denial
of the proposed amendments (i.e., the ``no-action'' alternative).
Denial of the proposed amendments would result in no change in current
environmental conditions and impacts at Braidwood.
Alternative Use of Resources
This action does not involve the use of any resources not
previously considered in NUREG-1437, Supplement 55, Generic
Environmental Impact Statement for License Renewal of Nuclear Plants:
Regarding Braidwood Station, Units 1 and 2--Final Report.
Agencies and Persons Consulted
The staff did not enter into consultation with any other Federal
agency or with the State of Illinois regarding the environmental impact
of the proposed action. However, on May 11, 2016, the NRC notified the
Illinois State official, Mr. Alwyn C. Settles, Nuclear Facility Section
Head, of the Bureau of Nuclear Facility Safety of the proposed
amendments. The State official had no comments.
III. Finding of No Significant Impact
The NRC is considering issuing amendments for Renewed Facility
Operating License Nos. NPF-72 and NPF-77, issued to Exelon for
operation of Braidwood to increase the allowable TS 3.7.9.2 temperature
limit of the cooling water supplied to the plant from the UHS from
<=100[emsp14][deg]F (38.9 [deg]C) to <=102[emsp14][deg]F (38.9 [deg]C).
On the basis of the EA included in Section II above and
incorporated by reference in this finding, the NRC concludes that the
proposed action would not have significant effects on the quality of
the human environment. The NRC's evaluation considered information
provided in the licensee's application and associated supplements as
well as the NRC's independent review of other relevant environmental
documents. Section IV below lists the environmental documents related
to the proposed action and includes information on the availability of
these documents. Based on its findings, the NRC has decided not to
prepare an environmental impact statement for the proposed action.
IV. Availability of Documents
The following table identifies the documents cited in this document
and related to the NRC's FONSI. These documents are available for
public inspection online through ADAMS at https://www.nrc.gov/reading-rm/adams.html or in person at the NRC's PDR as previously described.
[[Page 48856]]
------------------------------------------------------------------------
Document ADAMS Accession No.
------------------------------------------------------------------------
License Amendment Request and Associated Supplements
------------------------------------------------------------------------
Exelon Generation Company, LLC............ ML14231A902
Request for a License Amendment to
Braidwood Station, Units 1 and 2,
Technical Specification 3.7.9, ``Ultimate
Heat Sink.'' Dated August 19, 2014.
Exelon Generation Company, LLC............ ML15020A246
Supplemental Information in Support of
Request for a License Amendment to
Braidwood Station, Units 1 and 2,
Technical Specification 3.7.9, ``Ultimate
Heat Sink.'' Dated January 20, 2015.
Exelon Generation Company, LLC............ ML15090A604
Response to Request for Additional
Information Regarding Request for a
License Amendment to Braidwood Station,
Units 1 and 2, Technical Specification
3.7.9, ``Ultimate Heat Sink.'' Dated
March 31, 2015.
Exelon Generation Company, LLC............ ML15120A396
Response to Request for Additional
Information Regarding Request for a
License Amendment to Braidwood Station,
Units 1 and 2, Technical Specification
3.7.9, ``Ultimate Heat Sink.'' Dated
April 30, 2015.
Exelon Generation Company, LLC............ ML15236A144
Supplemental Information in Support of
Request for a License Amendment to
Braidwood Station, Units 1 and 2,
Technical Specification 3.7.9, ``Ultimate
Heat Sink.'' Dated August 24, 2015.
Exelon Generation Company, LLC............ ML15282A345
Response to Request for Additional
Information Regarding Request for a
License Amendment to Braidwood Station,
Units 1 and 2, Technical Specification
3.7.9, ``Ultimate Heat Sink.'' Dated
October 9, 2015.
Exelon Generation Company, LLC............ ML15303A326
Response to Request for Additional
Information Regarding Request for a
License Amendment to Braidwood Station,
Units 1 and 2, Technical Specification
3.7.9, ``Ultimate Heat Sink.'' Dated
October 30, 2015.
Exelon Generation Company, LLC............ ML15313A254
Response to Request for Additional
Information Regarding Request for a
License Amendment to Braidwood Station,
Units 1 and 2, Technical Specification
3.7.9, ``Ultimate Heat Sink.'' Dated
November 9, 2015.
Exelon Generation Company, LLC............ ML15364A369
Response to Request for Additional
Information Regarding Request for a
License Amendment to Braidwood Station,
Units 1 and 2, Technical Specification
3.7.9, ``Ultimate Heat Sink.'' Dated
December 16, 2015.
Exelon Generation Company, LLC............ ML16043A496
Supplemental Information in Support of
Request for a License Amendment to
Braidwood Station, Units 1 and 2,
Technical Specification 3.7.9, ``Ultimate
Heat Sink.'' Dated February 12, 2016.
Exelon Generation Company, LLC............ ML16123A014
Response to Request for Additional
Information Regarding Request for a
License Amendment to Braidwood Station,
Units 1 and 2, Technical Specification
3.7.9, ``Ultimate Heat Sink.'' Dated
April 29, 2016.
Exelon Generation Company, LLC............ ML16169A139
Supplemental Information Regarding Request
for a License Amendment to Braidwood
Station, Units 1 and 2, Technical
Specification 3.7.9, ``Ultimate Heat
Sink.'' Dated June 17, 2016.
------------------------------------------------------------------------
Other Referenced Documents
------------------------------------------------------------------------
Cairns J. 1956. Effects of heat on fish. n/a \(1)\
Industrial Wastes, 1:180-183.
Banner A, Van Arman JA. 1973. Thermal n/a \(1)\
effects on eggs, larvae and juveniles of
bluegill sunfish. Washington, DC: U.S.
Environmental Protection Agency. EPA-R3-
73-041.
Ecological Specialists, Inc............... ML15274A087
Final Report: Five Year Post-Construction
Monitoring of the Unionid Community Near
the Braidwood Station Kankakee River
Discharge. Dated September 2015.
Exelon Generation Company, LLC............ ML12192A637
Request for Enforcement Discretion for
Technical Specification 3.7.9, ``Ultimate
Heat Sink.'' Dated July 10, 2012.
Exelon Generation Company, LLC............ ML12249A256
Licensee Event Report 2012-004-01--Notice
of Enforcement Discretion Received for
Ultimate Heat Sink Temperature Exceeding
Technical Specifications Requirements Due
to Prolonged Hot Weather. Dated September
5, 2012.
Exelon Generation Company, LLC............ ML12349A174
Licensee Event Report 2012-004-01--Notice
of Enforcement Discretion Received for
Ultimate Heat Sink Temperature Exceeding
Technical Specifications Requirements Due
to Prolonged Hot Weather. Dated December
13, 2012.
Exelon Generation Company, LLC............ ML14339A044
Byron and Braidwood Stations, Units 1 and
2, License Renewal Application, Braidwood
Station Applicant's Environmental Report,
Responses to Requests for Additional
Information, Environmental RAIs AQ-11 to
AQ-15. Dated April 30, 2014.
Exelon Generation Company, LLC............ ML15274A093
Braidwood, Units 1 and 2--Transmittal of
Report Titled ``Five Year Post-
Construction Monitoring of the Unionid
Community Near the Braidwood Station
Kankakee River Discharge Location.''
Dated September 2015.
Illinois Environmental Protection Agency.. ML14227A712
Exelon Generation Company, LLC--Braidwood
Station, Units 1 and 2, National
Pollutant Discharge Elimination System
(NPDES) Permit No. IL0048321. Issued on
July 31, 2014
U.S. Fish and Wildlife Service............ ML16120A505
Endangered Species Consultations:
Frequently Asked Questions. Dated July
15, 2013.
U.S. Fish and Wildlife Service............ ML15299A013
Concurrence Letter Concluding Informal
Consultation with the NRC for Braidwood
License Renewal. Dated October 20, 2015.
U.S. Nuclear Regulatory Commission........ ML12194A681
Notice of Enforcement Discretion for
Exelon Generation Company, LLC, Regarding
Braidwood Station. Dated July 12, 2012.
U.S. Nuclear Regulatory Commission........ ML15314A814
Generic Environmental Impact Statement for
License Renewal of Nuclear Plants:
Regarding Braidwood Plant, Units 1 and 2--
Final Report (NUREG-1437, Supplement 55).
Dated November 30, 2015.
[[Page 48857]]
U.S. Nuclear Regulatory Commission........ ML053040362
Exelon Generation Company, LLC; Docket No.
STN 50-456; Braidwood Station, Unit 1
Renewed Facility Operating License.
Issued on January 27, 2016
U.S. Nuclear Regulatory Commission........ ML053040366
Exelon Generation Company, LLC; Docket No.
STN 50-457; Braidwood Station, Unit 2
Renewed Facility Operating License.
Issued on January 27, 2016.
U.S. Nuclear Regulatory Commission........ ML15322A317
Record of Decision; U.S. Nuclear
Regulatory Commission; Docket Nos. 50-456
and 560-457; License Renewal Application
for Braidwood Station, Units 1 and 2.
Dated January 27, 2016.
------------------------------------------------------------------------
\1\ These references are subject to copyright laws and are, therefore,
not reproduced in ADAMS.
Dated at Rockville, Maryland, this 18th day of July 2016.
For the Nuclear Regulatory Commission.
Joel S. Wiebe,
Senior Project Manager, Plant Licensing Branch III-2, Division of
Operating Reactor Licensing, Office of Nuclear Reactor Regulation.
[FR Doc. 2016-17688 Filed 7-25-16; 8:45 am]