long spillway; (3) a reservoir with a
surface area of 573 acres and a storage
capacity of 14,020 acre-feet at a normal
surface elevation of 37 feet mean sea
level (msl); (4) a 770-foot-long, 300-footwide intake channel with a 85-foot-long
retaining wall; (5) a 98-foot-long, 115foot-wide powerhouse, to be built
adjacent to the spillway end of the dam,
containing two generating units with a
total capacity of 9 megawatts; (6) a 1000foot-long, 220-foot-wide tailrace with a
40-foot-long retaining wall; (7) a 4.16/69
kilo-Volt (kV) substation; and (8) a 0.15mile-long, 69 kV transmission line. The
proposed project would have an average
annual generation of 48,690 megawatthours.
Applicant Contact: Mr. Ander
Gonzalez, Energy Resources USA, Inc.,
2655 Le Jeune Road, Suite 804, Coral
Gables, Florida 33134, (954) 248–8425.
FERC Contact: Dustin Wilson,
Dustin.Wilson@ferc.gov, (202) 502–
6528.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36. Comments, motions to
intervene, notices of intent, and
competing applications may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at 1–866–208–3676, or for TTY,
(202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P–14780–000)
in the docket number field to access the
document. For assistance, contact FERC
Online Support.
VerDate Sep<11>2014
18:24 Jul 19, 2016
Jkt 238001
Dated: July 14, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016–17127 Filed 7–19–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14775–000]
Marine Renewable Energy
Collaborative of New England; Notice
of Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
On April 20, 2016, the Marine
Renewable Energy Collaborative of New
England filed an application for a
preliminary permit, pursuant to section
4(f) of the Federal Power Act (FPA),
proposing to study the feasibility of the
Cape Cod Canal and Bourne Tidal Test
Site (Cape Cod Canal Test Site or
project) to be located on the Cape Cod
Canal, near the Town of Bourne, in
Barnstable County, Massachusetts. The
sole purpose of a preliminary permit, if
issued, is to grant the permit holder
priority to file a license application
during the permit term. A preliminary
permit does not authorize the permit
holder to perform any land-disturbing
activities or otherwise enter upon lands
or waters owned by others without the
owners’ permission.
The proposed project would consist
of: (1) A 45-foot-high, 23-foot-wide
support structure; (2) a 25-kilowatt
turbine-generator unit; (3) a 500 to
7,500-foot-long, 13.2-kilovolt (kV)
transmission; and (4) appurtenant
facilities. The estimated average annual
generation of the project would be 54.7
gigawatt-hours. The project would
occupy approximately 0.5 acres of
federal land under the jurisdiction of
the U.S. Army Corps of Engineers.
Applicant Contact: Mr. John Miller,
Executive Director, Marine Renewable
Energy Collaborative of New England,
P.O. Box 479, Marion, Massachusetts
02738; phone: (508) 728–5825.
FERC Contact: Michael Watts; phone:
(202) 502–6123; email: michael.watts@
ferc.gov.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
PO 00000
Frm 00013
Fmt 4703
Sfmt 4703
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–14775–000.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P–14775) in
the docket number field to access the
document. For assistance, contact FERC
Online Support.
Dated: July 14, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016–17126 Filed 7–19–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Effectiveness of Exempt
Wholesale Generator Status
Grande Prairie Wind, LLC .....
La Frontera Holdings, LLC ....
Boulder Solar Power, LLC ....
Electra Wind, LLC .................
Osborn Wind Energy, LLC ....
Oliver Wind III, LLC ...............
Peak View Wind Energy LLC
Blythe Solar II, LLC ...............
Elevation Solar C, LLC .........
EG16–81–
000.
EG16–82–
000.
EG16–83–
000.
EG16–84–
000.
EG16–85–
000.
EG16–86–
000.
EG16–87–
000.
EG16–88–
000.
EG16–89–
000.
Take notice that during the month of
June 2016, the status of the abovecaptioned entities as Exempt Wholesale
Generators became effective by
E:\FR\FM\20JYN1.SGM
20JYN1
47168
Federal Register / Vol. 81, No. 139 / Wednesday, July 20, 2016 / Notices
operation of the Commission’s
regulations. 18 CFR 366.7(a).
Dated: July 14, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary
[FR Doc. 2016–17099 Filed 7–19–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14514–002]
mstockstill on DSK3G9T082PROD with NOTICES
Community of Elfin Cove, DBA Elfin
Cove Utility Commission; Notice of
Successive Preliminary Permit
Application Accepted for Filing and
Soliciting Comments, Motions To
Intervene, and Competing Applications
On July 1, 2016, the Community of
Elfin Cove, DBA Elfin Cove Utility
Commission (Elfin Cove) filed an
application for a successive preliminary
permit, pursuant to section 4(f) of the
Federal Power Act (FPA), to study the
feasibility of the proposed Crooked
Creek and Jim’s Lake Hydroelectric
Project (project) to be located on
Crooked Creek and Jim’s Lake, 70 miles
west of Juneau, in the unincorporated
Sitka Recording District, Alaska. The
sole purpose of a preliminary permit, if
issued, is to grant the permit holder
priority to file a license application
during the permit term. A preliminary
permit does not authorize the permit
holder to perform any land-disturbing
activities or otherwise enter upon lands
or waters owned by others without the
owners’ express permission.
The proposed project would consist of
two developments, the Upper System
and the Lower System.
The Upper System would consist of:
(1) A 20-foot-long, 4-foot-wide, 4-foottall diversion structure to divert up to 5
cubic feet per second (cfs) from Crooked
Creek; (2) a 1,200-foot-long, 1-footdiameter buried penstock; (3) a 20-footlong, 20-foot-wide powerhouse
containing a 35-kilowatt (kW) crossflow
turbine/generator; (4) a 50-foot-long, 8foot-wide, 3-foot-deep cobble-lined
tailrace discharging flows into Jim’s
Lake; and (5) appurtenant facilities.
The Lower System would consist of:
(1) A 220-foot-long, 20-foot-high rockfill embankment dam and intake at the
outlet to Jim’s Lake; (2) a 2,050-footlong, 1.2-foot-diameter buried penstock;
(3) a 24-foot-long, 24-foot-wide
powerhouse containing a 105-kW Pelton
turbine/generator; (4) a 150-foot-long, 8foot-wide, 3-foot-deep cobble-lined
VerDate Sep<11>2014
18:24 Jul 19, 2016
Jkt 238001
tailrace discharging flows into Port
Althorp; and (5) appurtenant facilities.
The 300-foot-long, 7.2/12.47 kV
buried transmission line from the upper
powerhouse would converge with the
2,800-foot-long, 7.2/12.47 kV buried
transmission line from the lower
powerhouse into a single 8,400-footlong, 7.2/12.47 kV buried transmission
line extending to Elfin Cove’s existing
7.2/12.47-kV distribution network.
The estimated annual generation of
the project would be 655.5 megawatthours. The project would be partially
located on 60 acres of federal lands
managed by the U.S. Forest Service in
the Tongass National Forest.
Applicant Contact: Joel Groves,
Polarconsult Alaska, Inc., 1503 West
33rd Avenue, Number 310, Anchorage,
AK 99503; phone: (907) 258–2420 x204.
FERC Contact: Sean O’Neill; phone:
(202) 502–6462.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–14514–002.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of the Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–14514) in the docket number field to
access the document. For assistance,
contact FERC Online Support.
Dated: July 14, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016–17125 Filed 7–19–16; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00014
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP16–474–000]
High Point Gas Transmission, LLC;
Notice of Application
Take notice that on July 1, 2016, High
Point Gas Transmission, LLC, 1400 16th
Street, Suite 310, Denver, Colorado
80202, filed in Docket No. CP16–474–
000 an application pursuant to section
7(b) of the Natural Gas Act (NGA) for
authorization to abandon by sale to
Cayenne Pipeline, LLC (Cayenne)
approximately 61.3 miles of 12–22-inchdiameter pipeline facilities in
Plaquemines and St. Bernard Parishes,
Louisiana. Upon completion of the sale,
Cayenne will make certain changes to
the facilities to enable it to transport
natural gas liquids, all as more fully set
forth in the application which is on file
with the Commission and open to
public inspection. The filing is available
for review at the Commission in the
Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
at FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
Any questions concerning these
applications may be directed to Dennis
J. Kelly, Senior Counsel, High Point Gas
Transmission, LLC, 1400 16th Street,
Suite 310, Denver, Colorado 80202, by
telephone at (720) 457–6076.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: Complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
E:\FR\FM\20JYN1.SGM
20JYN1
Agencies
[Federal Register Volume 81, Number 139 (Wednesday, July 20, 2016)]
[Notices]
[Pages 47167-47168]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-17099]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice of Effectiveness of Exempt Wholesale Generator Status
------------------------------------------------------------------------
------------------------------------------------------------------------
Grande Prairie Wind, LLC................. EG16-81-000.
La Frontera Holdings, LLC................ EG16-82-000.
Boulder Solar Power, LLC................. EG16-83-000.
Electra Wind, LLC........................ EG16-84-000.
Osborn Wind Energy, LLC.................. EG16-85-000.
Oliver Wind III, LLC..................... EG16-86-000.
Peak View Wind Energy LLC................ EG16-87-000.
Blythe Solar II, LLC..................... EG16-88-000.
Elevation Solar C, LLC................... EG16-89-000.
------------------------------------------------------------------------
Take notice that during the month of June 2016, the status of the
above-captioned entities as Exempt Wholesale Generators became
effective by
[[Page 47168]]
operation of the Commission's regulations. 18 CFR 366.7(a).
Dated: July 14, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary
[FR Doc. 2016-17099 Filed 7-19-16; 8:45 am]