Download as PDF Federal Register / Vol. 81, No. 109 / Tuesday, June 7, 2016 / Notices efiling.asp. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY, 202–502–8659. In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. The first page of any filing should include Holt Hydroelectric Project No. 2203–015. For further information, contact Jeanne Edwards by telephone at 202– 502–6181 or by email at jeanne.edwards@ferc.gov. Dated: May 31, 2016. Kimberly D. Bose, Secretary. [FR Doc. 2016–13354 Filed 6–6–16; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Windham Solar LLC, Allco Finance Limited; Notice of Petition for Enforcement Docket Nos. asabaliauskas on DSK3SPTVN1PROD with NOTICES EL16–69–000 QF16–362–001 QF16–363–001 QF16–364–001 QF16–365–001 QF16–366–001 QF16–367–001 QF16–368–001 QF16–369–001 QF16–370–001 QF16–371–001 QF16–372–001 QF16–373–001 QF16–374–001 QF16–375–001 QF16–376–001 QF16–377–001 QF16–378–001 QF16–379–001 QF16–380–001 QF16–381–001 QF16–382–001 QF16–383–001 QF16–384–001 QF16–385–001 QF16–386–001 QF16–387–001 Dated: May 26, 2016. Kimberly D. Bose, Secretary. [FR Doc. 2016–13421 Filed 6–6–16; 8:45 am] BILLING CODE 6717–01–P Take notice that on May 25, 2016, pursuant to section 210(h)(2)(B) of the Public Utility Regulatory Policies Act of 1978 (PURPA), 16 U.S.C. 824a–3(h), Windham Solar LLC and Allco Finance Limited filed amendment to its May 19, 2016 filing of Petition for Enforcement requesting the Federal Energy Regulatory Commission (Commission) exercise its authority and initiate enforcement action against the Connecticut Public Utilities Regulatory Authority to remedy its implementation of PURPA, all as more fully explained in the petition. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the VerDate Sep<11>2014 19:13 Jun 06, 2016 Jkt 238001 Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. On or before the comment date, it is not necessary to serve motions to intervene or protests on persons other than the Applicant. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5:00 p.m. Eastern Time on June 15, 2016. DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Notice of Commission Staff Attendance The Federal Energy Regulatory Commission hereby gives notice that members of the Commission’s staff may attend the following meetings related to the transmission planning activities of the PJM Interconnection, L.L.C. (PJM): PJM Planning Committee June 9, 2016, 9:30 a.m.–12:00 p.m. (EST) PJM Transmission Expansion Advisory Committee June 9, 2016, 11:00 a.m.–3:00 p.m. (EST) The above-referenced meetings will be held at: PJM Conference and Training PO 00000 Frm 00020 Fmt 4703 Sfmt 9990 36535 Center, PJM Interconnection 2750 Monroe Boulevard Audubon, PA 19403. The above-referenced meetings are open to stakeholders. Further information may be found at www.pjm.com. The discussions at the meetings described above may address matters at issue in the following proceedings: Docket No. ER16–453, PJM Interconnection, L.L.C. and Northeast Transmission Development, LLC Docket No. ER16–736, PJM Interconnection, L.L.C. Docket No. ER14–972, PJM Interconnection, L.L.C. Docket No. ER14–1485, PJM Interconnection, L.L.C. Docket Nos. ER13–1944, et al., PJM Interconnection, L.L.C., et al. Docket No. ER15–1344, PJM Interconnection, L.L.C. Docket No. ER15–1387, PJM Interconnection, L.L.C. and Potomac Electric Power Company Docket No. ER15–2562, PJM Interconnection, L.L.C. Docket No. ER15–2563, PJM Interconnection, L.L.C. Docket No. EL15–18, Consolidated Edison Company of New York, Inc. v. PJM Interconnection, L.L.C. Docket No. EL15–41, Essential Power Rock Springs, LLC, et. al. v. PJM Interconnection, L.L.C. Docket No. ER15–2114, PJM Interconnection, L.L.C. and Transource West Virginia, LLC Docket No. EL15–79, TransSource, LLC v. PJM Interconnection, L.L.C. Docket No. EL15–95, Delaware Public Service Commission, et. al., v. PJM Interconnection, L.L.C., et. al. Docket No. EL15–67, Linden VFT, LLC v. PJM Interconnection, L.L.C. Docket No. EL05–121, PJM Interconnection, L.L.C. Docket No. ER13–198, PJM Interconnection, L.L.C. Docket No. ER16–1335, PJM Interconnection, L.L.C. Docket No. ER16–1232, PJM Interconnection, L.L.C. Docket No. ER16–1499, PJM Interconnection, L.L.C. For more information, contact the following: Jonathan Fernandez, Office of Energy Market Regulation, Federal Energy Regulatory Commission, (202) 502–6604 Jonathan.Fernandez@ferc.gov; Alina Halay, Office of Energy Market Regulation, Federal Energy Regulatory Commission, (202) 502–6474, Alina.Halay@ferc.gov. Dated: June 1, 2016. Kimberly D. Bose, Secretary. [FR Doc. 2016–13407 Filed 6–6–16; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\07JNN1.SGM 07JNN1

Agencies

[Federal Register Volume 81, Number 109 (Tuesday, June 7, 2016)]
[Notices]
[Page 36535]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-13421]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission


Windham Solar LLC, Allco Finance Limited; Notice of Petition for 
Enforcement

------------------------------------------------------------------------
 
------------------------------------------------------------------------
Docket Nos.
------------------------------------------------------------------------
             EL16-69-000                         QF16-375-001
            QF16-362-001                         QF16-376-001
            QF16-363-001                         QF16-377-001
            QF16-364-001                         QF16-378-001
            QF16-365-001                         QF16-379-001
            QF16-366-001                         QF16-380-001
            QF16-367-001                         QF16-381-001
            QF16-368-001                         QF16-382-001
            QF16-369-001                         QF16-383-001
            QF16-370-001                         QF16-384-001
            QF16-371-001                         QF16-385-001
            QF16-372-001                         QF16-386-001
            QF16-373-001                         QF16-387-001
            QF16-374-001
------------------------------------------------------------------------

    Take notice that on May 25, 2016, pursuant to section 210(h)(2)(B) 
of the Public Utility Regulatory Policies Act of 1978 (PURPA), 16 
U.S.C. 824a-3(h), Windham Solar LLC and Allco Finance Limited filed 
amendment to its May 19, 2016 filing of Petition for Enforcement 
requesting the Federal Energy Regulatory Commission (Commission) 
exercise its authority and initiate enforcement action against the 
Connecticut Public
    Utilities Regulatory Authority to remedy its implementation of 
PURPA, all as more fully explained in the petition.
    Any person desiring to intervene or to protest this filing must 
file in accordance with Rules 211 and 214 of the Commission's Rules of 
Practice and Procedure (18 CFR 385.211, 385.214). Protests will be 
considered by the Commission in determining the appropriate action to 
be taken, but will not serve to make protestants parties to the 
proceeding. Any person wishing to become a party must file a notice of 
intervention or motion to intervene, as appropriate. Such notices, 
motions, or protests must be filed on or before the comment date. On or 
before the comment date, it is not necessary to serve motions to 
intervene or protests on persons other than the Applicant.
    The Commission encourages electronic submission of protests and 
interventions in lieu of paper using the ``eFiling'' link at https://www.ferc.gov. Persons unable to file
    electronically should submit an original and 5 copies of the 
protest or intervention to the Federal Energy Regulatory Commission, 
888 First Street NE., Washington, DC 20426.
    This filing is accessible on-line at https://www.ferc.gov, using the 
``eLibrary'' link and is available for review in the Commission's 
Public Reference Room in Washington, DC. There is an ``eSubscription'' 
link on the Web site that enables subscribers to receive email 
notification when a document is added to a subscribed docket(s). For 
assistance with any FERC Online service, please email 
FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free). For 
TTY, call (202) 502-8659.
    Comment Date: 5:00 p.m. Eastern Time on June 15, 2016.

    Dated: May 26, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016-13421 Filed 6-6-16; 8:45 am]
 BILLING CODE 6717-01-P