Reactive Supply Compensation in Markets Operated by Regional Transmission Organizations and Independent System Operators; Supplemental Notice of Workshop, 33526-33527 [2016-12421]
Download as PDF
33526
Federal Register / Vol. 81, No. 102 / Thursday, May 26, 2016 / Notices
comment date. On or before the
comment date, it is not necessary to
serve motions to intervene or protests
on persons other than the Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 5 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5:00 p.m. Eastern
Time on May 26, 2016.
Dated: May 20, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016–12408 Filed 5–25–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. AD16–17–000]
Reactive Supply Compensation in
Markets Operated by Regional
Transmission Organizations and
Independent System Operators;
Supplemental Notice of Workshop
As announced in the Notice of
Workshop issued on March 17, 2016, in
the above-captioned proceeding,1
Federal Energy Regulatory Commission
(Commission) staff will convene a
workshop on June 30, 2016, from 12:00
p.m. (EDT) to 4:00 p.m. (EDT) in the
Commission Meeting Room at 888 First
Street NE., Washington, DC 20426. The
workshop will be open to the public,
and all interested parties are invited to
attend and participate. The workshop
will be led by Commission staff, and
may be attended by one or more
Commissioners.
The purpose of the workshop is to
discuss compensation for Reactive
Supply and Voltage Control (Reactive
Supply) within the Regional
Transmission Organizations (RTOs) and
Independent System Operators (ISOs).
Specifically, the workshop will explore
the types of costs incurred by generators
ISO New England Inc ...............................................................................
Garrison Energy Center, LLC ...................................................................
Newark Energy Center, LLC ....................................................................
Scrubgrass Generating Company, L.P ....................................................
CPV Shore, LLC .......................................................................................
C.P. Crane LLC ........................................................................................
GenOn Energy Management, LLC ...........................................................
NRG Wholesale Generation LP ...............................................................
Talen Energy Marketing, LLC ..................................................................
sradovich on DSK3TPTVN1PROD with NOTICES
Constellation Power Source Generation, LLC .........................................
New Covert Generating Company, LLC ..................................................
Panda Liberty LLC ....................................................................................
Roundtop Energy LLC ..............................................................................
Beaver Dam Energy LLC .........................................................................
FirstEnergy Solutions Corp ......................................................................
Duke Energy Indiana, Inc .........................................................................
Wabash Valley Power Association, Inc ....................................................
Consumers Energy Company ..................................................................
MidAmerican Energy Company ................................................................
Indiana Municipal Power Agency .............................................................
BIF III Holtwood LLC ................................................................................
Seward Generation, LLC ..........................................................................
Northampton Generating Company, L.P ..................................................
for providing Reactive Supply capability
and service; whether those costs are
being recovered solely as compensation
for Reactive Supply or whether recovery
is also through compensation for other
services; and different methods by
which generators receive compensation
for Reactive Supply (e.g., Commissionapproved revenue requirements, marketwide rates, etc.). The workshop will also
explore potential adjustments in
compensation methods based on
changes in Reactive Supply capability
and potential mechanisms to prevent
overcompensation for Reactive Supply.
Attached to this supplemental notice
is an agenda for the workshop,
including Reactive Supply
compensation topics to be considered
for discussion at the workshop.
Questions that speakers should be
prepared to discuss are grouped by
topic.
Discussions at the workshop may
involve issues raised in proceedings that
are pending before the Commission.
These proceedings include, but are not
limited to:
Docket No. ER16–946–001.
Docket No. ER15–2735–000.
Docket Nos. ER15–1706–001, EL15–97–000.
Docket No. ER15–2254–000.
Docket Nos. ER15–2589–000, EL16–4–000.
Docket Nos. ER16–259–000, ER16–332–000, EL16–21–000.
Docket Nos. ER15–2571–000, ER15–2572–000, ER15–2573–000.
Docket Nos. ER16–413–000, ER04–1164–001, EL16–28–000.
Docket Nos. ER16–277–000, ER16–277–001, ER16–277–002, ER16–
277–003, EL16–44–000, EL16–44–001, ER08–1462–001, EL16–32–
000, ER16–1456–000.
Docket Nos. ER16–746–000, ER16–746–001.
Docket No. ER16–1226–000.
Docket No. ER16–1256–001.
Docket No. ER16–1004–000.
Docket Nos. ER16–1032–000, EL16–51–000.
Docket Nos. ER15–1510–000, ER15–1510–001.
Docket Nos. ER16–200–000, ER16–201–000, ER16–200–002.
Docket Nos. ER16–435–001, ER16–444–001.
Docket No. ER16–1058–000.
Docket No. ER16–1062–000.
Docket No. EL16–14–000.
Docket No. ER16–1530–000.
Docket No. ER16–1344–000.
Docket No. ER13–1431–001.
This workshop will be transcribed
and webcast. Transcripts of the
workshop will be available for a fee
from Ace-Federal Reporters, Inc. at (202)
347–3700. A free webcast of this event
will be available through www.ferc.gov.
Anyone with internet access who wants
to view this event can do so by
navigating to the Calendar of Events at
www.ferc.gov and locating this event in
the Calendar. The event will contain a
link to its webcast. The Capitol
1 Reactive Supply Compensation in Markets
Operated by Regional Transmission Organizations
and Independent System Operators, Docket No.
AD16–17–000 (Mar. 17, 2016) (Notice of
Workshop).
VerDate Sep<11>2014
18:47 May 25, 2016
Jkt 238001
PO 00000
Frm 00068
Fmt 4703
Sfmt 4703
E:\FR\FM\26MYN1.SGM
26MYN1
Federal Register / Vol. 81, No. 102 / Thursday, May 26, 2016 / Notices
sradovich on DSK3TPTVN1PROD with NOTICES
Connection provides technical support
for webcasts and offers the option of
listening to the workshop via phonebridge for a fee. If you have any
questions, visit
www.CapitolConnection.org or call (703)
993–3100. Those interested in attending
the workshop or viewing the webcast
are encouraged to register at https://
www.ferc.gov/whats-new/registration/
06-30-16-form.asp.
Commission workshops are accessible
under section 508 of the Rehabilitation
Act of 1973. For accessibility
accommodations, please send an email
to accessibility@ferc.gov, call (866) 208–
3372 (toll free) or (202) 208–8659 (TTY),
or send a FAX to (202) 208–2106 with
the required accommodations.
Those who wish to file written
comments may do so by July 28, 2016.
The Commission strongly encourages
electronic filing. Please file comments
using the Commission’s eFiling system
at https://www.ferc.gov/docs-filing/
efiling.asp. For assistance, please
contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number AD16–17–000.
All comments will be placed in the
Commission’s public files and will be
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
www.ferc.gov using the eLibrary link.
Enter AD16–17–000 in the docket
number field to access documents. For
assistance, please contact FERC Online
Support.
For more information about this
workshop, please contact:
Sam Wellborn (Technical Information),
Office of Energy Market Regulation—
East, Federal Energy Regulatory
Commission, 888 First Street NE.,
Washington, DC 20426, (202) 502–
6288, samuel.wellborn@ferc.gov.
Gretchen Kershaw (Legal Information),
Office of the General Counsel, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC
20426, (202) 502–8213,
gretchen.kershaw@ferc.gov.
Sarah McKinley (Logistical
Information), Office of External
Affairs, Federal Energy Regulatory
Commission, 888 First Street NE.,
Washington, DC 20426, (202) 502–
8004, sarah.mckinley@ferc.gov.
VerDate Sep<11>2014
18:47 May 25, 2016
Jkt 238001
Dated: May 19, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016–12421 Filed 5–25–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP16–459–000]
Texas Gas Transmission, LLC; Notice
of Request Under Blanket
Authorization
Take notice that on May 12, 2016,
Texas Gas Transmission, LLC (Texas
Gas), 9 Greenway Plaza, Suite 2800,
Houston, Texas 77046, filed in Docket
No. CP16–459–000, a prior notice
request pursuant to sections 157.205
and 157.216 of the Commission’s
regulations under the Natural Gas Act
(NGA). Texas Gas seeks authorization to
abandon one injection/withdrawal well
and related facilities in its Graham Lake
natural gas storage facility (Graham
Lake), located in Muhlenberg County,
Kentucky. Texas Gas states that
plugging and abandoning the well will
have no effect on the certificated
physical parameters of Graham Lake,
including total inventory, reservoir
pressure, reservoir and buffer
boundaries, and certificated capacity.
Texas Gas proposes to perform these
activities under its blanket certificate
issued in Docket No. CP82–407–000, all
as more fully set forth in the application
which is on file with the Commission
and open to public inspection.
The filing may be viewed on the web
at https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
at FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
Any questions regarding this
application should be directed to J. Kyle
Stephens, Vice President, Regulatory
Affairs, Texas Gas Transmission, LLC, 9
Greenway Plaza, Suite 2800, Houston,
Texas, 77046, or by calling (713) 479–
8033 (telephone) or (713) 479–1818 (fax)
kyle.stephens@bwpmlp.com.
Any person or the Commission’s Staff
may, within 60 days after the issuance
of the instant notice by the Commission,
file pursuant to Rule 214 of the
Commission’s Procedural Rules (18 CFR
385.214) a motion to intervene or notice
of intervention and, pursuant to section
157.205 of the Commission’s
Regulations under the NGA (18 CFR
PO 00000
Frm 00069
Fmt 4703
Sfmt 4703
33527
157.205) a protest to the request. If no
protest is filed within the time allowed
therefore, the proposed activity shall be
deemed to be authorized effective the
day after the time allowed for protest. If
a protest is filed and not withdrawn
within 30 days after the time allowed
for filing a protest, the instant request
shall be treated as an application for
authorization pursuant to section 7 of
the NGA.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: Complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding, or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenters will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests,
and interventions via the internet in lieu
of paper. See 18 CFR 385.2001(a) (1) (iii)
and the instructions on the
Commission’s Web site (www.ferc.gov)
under the ‘‘e-Filing’’ link. Persons
unable to file electronically should
submit an original and 5 copies of the
protest or intervention to the Federal
E:\FR\FM\26MYN1.SGM
26MYN1
Agencies
[Federal Register Volume 81, Number 102 (Thursday, May 26, 2016)]
[Notices]
[Pages 33526-33527]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-12421]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. AD16-17-000]
Reactive Supply Compensation in Markets Operated by Regional
Transmission Organizations and Independent System Operators;
Supplemental Notice of Workshop
As announced in the Notice of Workshop issued on March 17, 2016, in
the above-captioned proceeding,\1\ Federal Energy Regulatory Commission
(Commission) staff will convene a workshop on June 30, 2016, from 12:00
p.m. (EDT) to 4:00 p.m. (EDT) in the Commission Meeting Room at 888
First Street NE., Washington, DC 20426. The workshop will be open to
the public, and all interested parties are invited to attend and
participate. The workshop will be led by Commission staff, and may be
attended by one or more Commissioners.
---------------------------------------------------------------------------
\1\ Reactive Supply Compensation in Markets Operated by Regional
Transmission Organizations and Independent System Operators, Docket
No. AD16-17-000 (Mar. 17, 2016) (Notice of Workshop).
---------------------------------------------------------------------------
The purpose of the workshop is to discuss compensation for Reactive
Supply and Voltage Control (Reactive Supply) within the Regional
Transmission Organizations (RTOs) and Independent System Operators
(ISOs). Specifically, the workshop will explore the types of costs
incurred by generators for providing Reactive Supply capability and
service; whether those costs are being recovered solely as compensation
for Reactive Supply or whether recovery is also through compensation
for other services; and different methods by which generators receive
compensation for Reactive Supply (e.g., Commission-approved revenue
requirements, market-wide rates, etc.). The workshop will also explore
potential adjustments in compensation methods based on changes in
Reactive Supply capability and potential mechanisms to prevent
overcompensation for Reactive Supply.
Attached to this supplemental notice is an agenda for the workshop,
including Reactive Supply compensation topics to be considered for
discussion at the workshop. Questions that speakers should be prepared
to discuss are grouped by topic.
Discussions at the workshop may involve issues raised in
proceedings that are pending before the Commission. These proceedings
include, but are not limited to:
------------------------------------------------------------------------
------------------------------------------------------------------------
ISO New England Inc.................... Docket No. ER16-946-001.
Garrison Energy Center, LLC............ Docket No. ER15-2735-000.
Newark Energy Center, LLC.............. Docket Nos. ER15-1706-001, EL15-
97-000.
Scrubgrass Generating Company, L.P..... Docket No. ER15-2254-000.
CPV Shore, LLC......................... Docket Nos. ER15-2589-000, EL16-
4-000.
C.P. Crane LLC......................... Docket Nos. ER16-259-000, ER16-
332-000, EL16-21-000.
GenOn Energy Management, LLC........... Docket Nos. ER15-2571-000, ER15-
2572-000, ER15-2573-000.
NRG Wholesale Generation LP............ Docket Nos. ER16-413-000, ER04-
1164-001, EL16-28-000.
Talen Energy Marketing, LLC............ Docket Nos. ER16-277-000, ER16-
277-001, ER16-277-002, ER16-
277-003, EL16-44-000, EL16-44-
001, ER08-1462-001, EL16-32-
000, ER16-1456-000.
Constellation Power Source Generation, Docket Nos. ER16-746-000, ER16-
LLC. 746-001.
New Covert Generating Company, LLC..... Docket No. ER16-1226-000.
Panda Liberty LLC...................... Docket No. ER16-1256-001.
Roundtop Energy LLC.................... Docket No. ER16-1004-000.
Beaver Dam Energy LLC.................. Docket Nos. ER16-1032-000, EL16-
51-000.
FirstEnergy Solutions Corp............. Docket Nos. ER15-1510-000, ER15-
1510-001.
Duke Energy Indiana, Inc............... Docket Nos. ER16-200-000, ER16-
201-000, ER16-200-002.
Wabash Valley Power Association, Inc... Docket Nos. ER16-435-001, ER16-
444-001.
Consumers Energy Company............... Docket No. ER16-1058-000.
MidAmerican Energy Company............. Docket No. ER16-1062-000.
Indiana Municipal Power Agency......... Docket No. EL16-14-000.
BIF III Holtwood LLC................... Docket No. ER16-1530-000.
Seward Generation, LLC................. Docket No. ER16-1344-000.
Northampton Generating Company, L.P.... Docket No. ER13-1431-001.
------------------------------------------------------------------------
This workshop will be transcribed and webcast. Transcripts of the
workshop will be available for a fee from Ace-Federal Reporters, Inc.
at (202) 347-3700. A free webcast of this event will be available
through www.ferc.gov. Anyone with internet access who wants to view
this event can do so by navigating to the Calendar of Events at
www.ferc.gov and locating this event in the Calendar. The event will
contain a link to its webcast. The Capitol
[[Page 33527]]
Connection provides technical support for webcasts and offers the
option of listening to the workshop via phone-bridge for a fee. If you
have any questions, visit www.CapitolConnection.org or call (703) 993-
3100. Those interested in attending the workshop or viewing the webcast
are encouraged to register at https://www.ferc.gov/whats-new/registration/06-30-16-form.asp.
Commission workshops are accessible under section 508 of the
Rehabilitation Act of 1973. For accessibility accommodations, please
send an email to accessibility@ferc.gov, call (866) 208-3372 (toll
free) or (202) 208-8659 (TTY), or send a FAX to (202) 208-2106 with the
required accommodations.
Those who wish to file written comments may do so by July 28, 2016.
The Commission strongly encourages electronic filing. Please file
comments using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online
Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper
copy to: Secretary, Federal Energy Regulatory Commission, 888 First
Street NE., Washington, DC 20426. The first page of any filing should
include docket number AD16-17-000.
All comments will be placed in the Commission's public files and
will be available for review at the Commission in the Public Reference
Room or may be viewed on the Commission's Web site at www.ferc.gov
using the eLibrary link. Enter AD16-17-000 in the docket number field
to access documents. For assistance, please contact FERC Online
Support.
For more information about this workshop, please contact:
Sam Wellborn (Technical Information), Office of Energy Market
Regulation--East, Federal Energy Regulatory Commission, 888 First
Street NE., Washington, DC 20426, (202) 502-6288,
samuel.wellborn@ferc.gov.
Gretchen Kershaw (Legal Information), Office of the General Counsel,
Federal Energy Regulatory Commission, 888 First Street NE., Washington,
DC 20426, (202) 502-8213, gretchen.kershaw@ferc.gov.
Sarah McKinley (Logistical Information), Office of External Affairs,
Federal Energy Regulatory Commission, 888 First Street NE., Washington,
DC 20426, (202) 502-8004, sarah.mckinley@ferc.gov.
Dated: May 19, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016-12421 Filed 5-25-16; 8:45 am]
BILLING CODE 6717-01-P