Vineland Municipal Electric Utility v. Atlantic City Electric Company; Notice of Complaint, 28856 [2016-10906]

Download as PDF asabaliauskas on DSK3SPTVN1PROD with NOTICES 28856 Federal Register / Vol. 81, No. 90 / Tuesday, May 10, 2016 / Notices Comments Due: 5 p.m. ET 5/20/16. Docket Numbers: ER16–1544–000. Applicants: Southwest Power Pool, Inc. Description: Compliance filing: Compliance Filing Revising Westar Energy’s Formula Rate Template to be effective 8/20/2014. Filed Date: 4/29/16. Accession Number: 20160429–5390. Comments Due: 5 p.m. ET 5/20/16. Docket Numbers: ER16–1545–000. Applicants: PJM Interconnection, L.L.C. Description: Tariff Cancellation: Notice of Cancellation of ISA No. 3045 and ICSA No. 3046, Queue No. Q65 to be effective 6/27/2016. Filed Date: 4/29/16. Accession Number: 20160429–5424. Comments Due: 5 p.m. ET 5/20/16. Docket Numbers: ER16–1546–000. Applicants: Southwest Power Pool, Inc. Description: § 205(d) Rate Filing: Arkansas Electric Cooperative Corporation Formula Rate to be effective 7/1/2016. Filed Date: 4/29/16. Accession Number: 20160429–5439. Comments Due: 5 p.m. ET 5/20/16. Docket Numbers: ER16–1547–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Amendment to ISAs 1867 & 4128, Queues NQ#117 & NQ#124, per Assignment to be effective 6/1/2015. Filed Date: 4/29/16. Accession Number: 20160429–5446. Comments Due: 5 p.m. ET 5/20/16. Docket Numbers: ER16–1548–000. Applicants: California Independent System Operator Corporation. Description: § 205(d) Rate Filing: 2016–04–29 Mesquite Solar 3 LGIA to be effective 6/1/2016. Filed Date: 4/29/16. Accession Number: 20160429–5456. Comments Due: 5 p.m. ET 5/20/16. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, VerDate Sep<11>2014 17:33 May 09, 2016 Jkt 238001 service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: April 29, 2016. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2016–10865 Filed 5–9–16; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. EL16–60–000] Vineland Municipal Electric Utility v. Atlantic City Electric Company; Notice of Complaint Take notice that on April 26, 2016, pursuant to sections 205, 206, 306, and 309 of the Federal Power Act (FPA) 1 and Rules 206 and 217 of the Federal Energy Regulatory Commission’s (Commission) Rules of Practice and Procedure,2 Vineland Municipal Electric Utility (Vineland or Complainant) filed a formal complaint against Atlantic City Electric Company (ACE or Respondent). Vineland is seeking an order granting full and immediate refunds of all amounts paid in violation of the Interconnection Agreement and PJM Open Access Transmission Tariff (PJM OATT). Vineland is alleging ACE’s decision to, without prior notice or approval from Vineland, apply a Reconciliation Factor to Vineland’s five coincident hourly metered loads for the purpose of calculating Vineland’s capacity obligation, is in violation of the Interconnection Agreement and the PJM OATT, as more fully explained in the complaint. Complainant certifies that copies of the Complaint were served on the contacts for the Respondents. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. The Respondent’s answer and all interventions, or protests must be filed on or before the comment date. 1 16 2 18 PO 00000 U.S.C. 824d, 824e, 825e, and 825h (2016). CFR 385.206, 385.217 (2016). Frm 00039 Fmt 4703 Sfmt 4703 The Respondent’s answer, motions to intervene, and protests must be served on the Complainants. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5:00 p.m. Eastern Time on May 16, 2016. Dated: April 28, 2016. Kimberly D. Bose, Secretary. [FR Doc. 2016–10906 Filed 5–9–16; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Notice of Commission Staff Attendance The Federal Energy Regulatory Commission hereby gives notice that members of the Commission’s staff may attend the following meetings related to the transmission planning activities of the PJM Interconnection, L.L.C. (PJM): PJM Planning Committee May 12, 2016, 9:30 a.m.–12:00 p.m. (EST) PJM Transmission Expansion Advisory Committee May 12, 2016, 11:00 a.m.–3:00 p.m. (EST) The above-referenced meetings will be held at: PJM Conference and Training Center, PJM Interconnection, 2750 Monroe Boulevard, Audubon, PA 19403. The above-referenced meetings are open to stakeholders. Further information may be found at www.pjm.com. E:\FR\FM\10MYN1.SGM 10MYN1

Agencies

[Federal Register Volume 81, Number 90 (Tuesday, May 10, 2016)]
[Notices]
[Page 28856]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-10906]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. EL16-60-000]


Vineland Municipal Electric Utility v. Atlantic City Electric 
Company; Notice of Complaint

    Take notice that on April 26, 2016, pursuant to sections 205, 206, 
306, and 309 of the Federal Power Act (FPA) \1\ and Rules 206 and 217 
of the Federal Energy Regulatory Commission's (Commission) Rules of 
Practice and Procedure,\2\ Vineland Municipal Electric Utility 
(Vineland or Complainant) filed a formal complaint against Atlantic 
City Electric Company (ACE or Respondent). Vineland is seeking an order 
granting full and immediate refunds of all amounts paid in violation of 
the Interconnection Agreement and PJM Open Access Transmission Tariff 
(PJM OATT). Vineland is alleging ACE's decision to, without prior 
notice or approval from Vineland, apply a Reconciliation Factor to 
Vineland's five coincident hourly metered loads for the purpose of 
calculating Vineland's capacity obligation, is in violation of the 
Interconnection Agreement and the PJM OATT, as more fully explained in 
the complaint.
---------------------------------------------------------------------------

    \1\ 16 U.S.C. 824d, 824e, 825e, and 825h (2016).
    \2\ 18 CFR 385.206, 385.217 (2016).
---------------------------------------------------------------------------

    Complainant certifies that copies of the Complaint were served on 
the contacts for the Respondents.
    Any person desiring to intervene or to protest this filing must 
file in accordance with Rules 211 and 214 of the Commission's Rules of 
Practice and Procedure (18 CFR 385.211 and 385.214). Protests will be 
considered by the Commission in determining the appropriate action to 
be taken, but will not serve to make protestants parties to the 
proceeding. Any person wishing to become a party must file a notice of 
intervention or motion to intervene, as appropriate. The Respondent's 
answer and all interventions, or protests must be filed on or before 
the comment date. The Respondent's answer, motions to intervene, and 
protests must be served on the Complainants.
    The Commission encourages electronic submission of protests and 
interventions in lieu of paper using the ``eFiling'' link at https://www.ferc.gov. Persons unable to file electronically should submit an 
original and 5 copies of the protest or intervention to the Federal 
Energy Regulatory Commission, 888 First Street, NE., Washington, DC 
20426.
    This filing is accessible on-line at https://www.ferc.gov, using the 
``eLibrary'' link and is available for review in the Commission's 
Public Reference Room in Washington, DC. There is an ``eSubscription'' 
link on the Web site that enables subscribers to receive email 
notification when a document is added to a subscribed docket(s). For 
assistance with any FERC Online service, please email 
FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free). For 
TTY, call (202) 502-8659.
    Comment Date: 5:00 p.m. Eastern Time on May 16, 2016.

    Dated: April 28, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016-10906 Filed 5-9-16; 8:45 am]
 BILLING CODE 6717-01-P