Proposed Information Collection Request; Comment Request, 26546-26551 [2016-10393]

Download as PDF 26546 Federal Register / Vol. 81, No. 85 / Tuesday, May 3, 2016 / Notices eFiling system at https://www.ferc.gov/ docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov. In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. The first page of any filing should include docket number P–10624–025. All filings with the Commission must bear the appropriate heading: ‘‘Comments on Pre-Application Document,’’ ‘‘Study Requests,’’ ‘‘Comments on Scoping Document 1,’’ ‘‘Request for Cooperating Agency Status,’’ or ‘‘Communications to and from Commission Staff.’’ Any individual or entity interested in submitting study requests, commenting on the PAD or SD1, and any agency requesting cooperating status must do so by June 25, 2016. p. Although our current intent is to prepare an environmental assessment (EA), there is the possibility that an Environmental Impact Statement (EIS) will be required. Nevertheless, this meeting will satisfy the NEPA scoping requirements, irrespective of whether an EA or EIS is issued by the Commission. asabaliauskas on DSK3SPTVN1PROD with NOTICES Scoping Meetings Commission staff will hold two scoping meetings in the vicinity of the project at the time and place noted below. The daytime meeting will focus on resource agency, Indian tribes, and non-governmental organization concerns, while the evening meeting is primarily for receiving input from the public. We invite all interested individuals, organizations, and agencies to attend one or both of the meetings, and to assist staff in identifying particular study needs, as well as the scope of environmental issues to be addressed in the environmental document. The times and locations of these meetings are as follows: Daytime Scoping Meeting Date and Time: Thursday, May 12, 2016 at 9:00 a.m. Location: Four Flags Area Chamber of Commerce, 321 E. Main Street, Niles, Michigan 49120. Phone Number: (269) 683–3720. Evening Scoping Meeting Date and Time: Wednesday, May 11, 2016 at 6:30 p.m. VerDate Sep<11>2014 18:53 May 02, 2016 Jkt 238001 Location: Four Flags Area Chamber of Commerce, 321 E. Main Street, Niles, Michigan 49120. Phone Number: (269) 683–3720. Scoping Document 1 (SD1), which outlines the subject areas to be addressed in the environmental document, was mailed to the individuals and entities on the Commission’s mailing list. Copies of SD1 will be available at the scoping meetings, or may be viewed on the web at https://www.ferc.gov, using the ‘‘eLibrary’’ link. Follow the directions for accessing information in paragraph n. Based on all oral and written comments, a Scoping Document 2 (SD2) may be issued. SD2 may include a revised process plan and schedule, as well as a list of issues, identified through the scoping process. Environmental Site Review The potential applicant and Commission staff will conduct an Environmental Site Review of the project on Wednesday, May 11, 2016, starting at 2:00 p.m. All participants should meet at French Paper Dam, located at 100 French Street, Niles, Michigan 49120. All participants are responsible for their own transportation. Please notify Shane Fenske at (269) 683–1100, or fenske@frenchpaper.com by May 6, 2016, if you plan to attend the environmental site review. Meeting Objectives At the scoping meetings, staff will: (1) Initiate scoping of the issues; (2) review and discuss existing conditions and resource management objectives; (3) review and discuss existing information and identify preliminary information and study needs; (4) review and discuss the process plan and schedule for prefiling activity that incorporates the time frames provided for in Part 5 of the Commission’s regulations and, to the extent possible, maximizes coordination of federal, state, and tribal permitting and certification processes; and (5) discuss the appropriateness of any federal or state agency or Indian tribe acting as a cooperating agency for development of an environmental document. Meeting participants should come prepared to discuss their issues and/or concerns. Please review the PAD in preparation for the scoping meetings. Directions on how to obtain a copy of the PAD and SD1 are included in paragraph n of this document. Meeting Procedures The meetings will be recorded by a stenographer and will be placed in the public records of the project. PO 00000 Frm 00021 Fmt 4703 Sfmt 4703 Dated: April 26, 2016. Kimberly D. Bose, Secretary. [FR Doc. 2016–10247 Filed 5–2–16; 8:45 am] BILLING CODE 6717–01–P ENVIRONMENTAL PROTECTION AGENCY [FRL–9946–03–OECA] Proposed Information Collection Request; Comment Request Environmental Protection Agency (EPA). ACTION: Notice. AGENCY: The Environmental Protection Agency is planning to submit the below listed information collection requests (ICR) (See item specific ICR title, EPA ICR Number and OMB Control Number provided in the text) to the Office of Management and Budget (OMB) for review and approval in accordance with the Paperwork Reduction Act (44 U.S.C. 3501 et seq.). Before doing so, EPA is soliciting public comments on specific aspects of the proposed information collection as described below. These are proposed extensions of the currently approved ICRs. An Agency may not conduct or sponsor and a person is not required to respond to a collection of information unless it displays a currently valid OMB control number. DATES: Comments must be submitted on or before July 5, 2016. ADDRESSES: Submit your comments, referencing the Docket ID numbers provided for each item in the text, online using www.regulations.gov (our preferred method), by email to docket.oeca@epa.gov, or by mail to: EPA Docket Center, Environmental Protection Agency, Mail Code 28221T, 1200 Pennsylvania Ave. NW., Washington, DC 20460. EPA’s policy is that all comments received will be included in the public docket without change including any personal information provided, unless the comment includes profanity, threats, information claimed to be Confidential Business Information (CBI) or other information whose disclosure is restricted by statute. FOR FURTHER INFORMATION CONTACT: Patrick Yellin, Monitoring, Assistance, and Media Programs Division, Office of Compliance, Mail Code 2227A, Environmental Protection Agency, 1200 Pennsylvania Ave. NW., Washington, DC 20460; telephone number: (202) 564–2970; fax number: (202) 564–0050; email address: yellin.patrick@epa.gov. SUMMARY: E:\FR\FM\03MYN1.SGM 03MYN1 asabaliauskas on DSK3SPTVN1PROD with NOTICES Federal Register / Vol. 81, No. 85 / Tuesday, May 3, 2016 / Notices SUPPLEMENTARY INFORMATION: Supporting documents which explain in detail the information that the EPA will be collecting are available in the public docket for this ICR. The docket can be viewed online at www.regulations.gov or in person at the EPA Docket Center, EPA West, Room 3334, 1301 Constitution Ave. NW., Washington, DC. The telephone number for the Docket Center is 202–566–1744. For additional information about EPA’s public docket, visit https://www.epa.gov/ dockets. Pursuant to section 3506(c)(2)(A) of the PRA, EPA is soliciting comments and information to enable it to: (i) Evaluate whether the proposed collection of information is necessary for the proper performance of the functions of the Agency, including whether the information will have practical utility; (ii) evaluate the accuracy of the Agency’s estimate of the burden of the proposed collection of information, including the validity of the methodology and assumptions used; (iii) enhance the quality, utility, and clarity of the information to be collected; and (iv) minimize the burden of the collection of information on those who are to respond, including through the use of appropriate automated electronic, mechanical, or other technological collection techniques or other forms of information technology, e.g., permitting electronic submission of responses. Burden is defined at 5 CFR 1320.03(b). EPA will consider the comments received and amend the ICR as appropriate. The final ICR package will then be submitted to OMB for review and approval. At that time, EPA will issue another Federal Register notice to announce the submission of the ICR to OMB and the opportunity to submit additional comments to OMB. General Abstract: For all the listed ICRs in this notice, owners and operators of affected facilities are required to comply with reporting and record keeping requirements for the general provisions of 40 CFR part 60, subpart A or Part 63, Subpart A, as well as the applicable specific standards. This includes submitting initial notifications, performance tests and periodic reports and results, and maintaining records of the occurrence and duration of any startup, shutdown, or malfunction in the operation of an affected facility, or any period during which the monitoring system is inoperative. These reports are used by EPA to determine compliance with the standards. (1) Docket ID Number: EPA–HQ– OECA–2013–0336; Title: NESHAP for VerDate Sep<11>2014 18:53 May 02, 2016 Jkt 238001 Off-Site Waste and Recovery Operations (40 CFR part 63, subpart DD); EPA ICR Number 1717.10, OMB Control Number 2060–0313; Expiration Date: October 31, 2016. Respondents: Waste management and recovery facilities. Respondent’s obligation to respond: Mandatory (40 CFR part 63, subpart DD). Estimated number of respondents: 236 (total). Frequency of response: Initially, occasionally and semiannually. Estimated annual burden: 179,000 hours. Estimated annual cost: $17,500,000, includes $5,810 annualized capital or operation & maintenance (O&M) costs. Changes in Estimates: There is no change in burden hours from the previous ICR. (2) Docket ID Number: EPA–HQ– OECA–2012–0679; Title: NESHAP for Petroleum Refineries: Catalytic Cracking Units, Reforming and Sulfur Units (40 CFR part 63, subpart UUU); EPA ICR Number 1844.07, OMB Control Number 2060–0554; Expiration Date: October 31, 2016. Respondents: Petroleum refineries with catalytic cracking units, catalytic reforming units and/or sulfur recovery units. Respondent’s obligation to respond: Mandatory (40 CFR part 63, subpart UUU). Estimated number of respondents: 123 (total). Frequency of response: Initially, occasionally, and semiannually. Estimated annual burden: 10,200 hours. Estimated annual cost: $9,400,000, includes $8,400,000 annualized capital or O&M costs. Changes in Estimates: There is an expected increase in burden hours due to expected modification of existing facilities. (3) Docket ID Number: EPA–HQ– OECA–2013–0338; Title: NESHAP for the Manufacture of Amino/Phenolic Resins (40 CFR part 63, subpart OOO); EPA ICR Number 1869.08, OMB Control Number 2060–0434; Expiration Date: October 31, 2016. Respondents: Facilities that manufacture amino/phenolic resins. Respondent’s obligation to respond: Mandatory (40 CFR part 63, subpart OOO). Estimated number of respondents: 37 (total). Frequency of response: Initially, occasionally, and semiannually. Estimated annual burden: 22,400 hours. PO 00000 Frm 00022 Fmt 4703 Sfmt 4703 26547 Estimated annual cost: $2,200,000, includes $14,800 annualized capital or O&M costs. Changes in Estimates: There is no change in burden hours from the previous ICR. (4) Docket ID Number: EPA–HQ– OECA–2013–0341; Title: NESHAP for Plywood and Composite Products (40 CFR parts 63, Subpart DDDD); EPA ICR Number 1984.06, OMB Control Number 2060–0552; Expiration Date: October 31, 2016. Respondents: Plywood and composite wood products (PCWP) facilities. Respondent’s obligation to respond: Mandatory (40 CFR part 63, subpart DDDD). Estimated number of respondents: 228 (total). Frequency of response: Initially, occasionally, and semiannually. Estimated annual burden: 11,700 hours. Estimated annual cost: $1,160,000, includes $16,000 annualized capital or O&M costs. Changes in Estimates: There is no change in burden hours from the previous ICR. (5) Docket ID Number: EPA–HQ– OECA–2013–0318; Title: NSPS for Magnetic Tape Coating Facilities (40 CFR part 60, subpart SSS); EPA ICR Number 1135.12, OMB Control Number 2060–0171; Expiration Date: November 30, 2016. Respondents: Magnetic tape coating facilities constructed or modified after January 22, 1986. Respondent’s obligation to respond: Mandatory (40 CFR part 60, subpart SSS). Estimated number of respondents: 6 (total). Frequency of response: Initially, occasionally and semiannually. Estimated annual burden: 2,020 hours. Estimated annual cost: $283,000, includes $86,400 annualized capital or O&M costs. Changes in Estimates: There is no change in burden hours from the previous ICR. (6) Docket ID Number: EPA–HQ– OECA–2013–0334; Title: NSPS for Secondary Brass and Bronze Production, Primary Copper Smelters, Primary Zinc Smelters, Primary Lead Smelters, Primary Aluminum Reduction Plants, and Ferroalloy Production Facilities (40 CFR part 60, subparts M, P, Q, R, S, Z); EPA ICR Number 1604.11, OMB Control Number 2060–0110; Expiration Date: November 30, 2016. Respondents: Secondary brass or bronze production facilities; primary E:\FR\FM\03MYN1.SGM 03MYN1 asabaliauskas on DSK3SPTVN1PROD with NOTICES 26548 Federal Register / Vol. 81, No. 85 / Tuesday, May 3, 2016 / Notices copper, primary zinc, and primary lead facilities; primary aluminum reduction facilities; and ferroalloy production facilities. Respondent’s obligation to respond: Mandatory (40 CFR part 60, subparts M, P, Q, R, S, and Z). Estimated number of respondents: 19 (total). Frequency of response: Initially, occasionally, semiannually, and annually. Estimated annual burden: 4,960 hours. Estimated annual cost: $612,000 includes $127,000 annualized capital or O&M costs. Changes in Estimates: There is no change in burden hours from the previous ICR. (7) Docket ID Number: EPA–HQ– OECA–2013–0339; Title: NESHAP for Boat Manufacturing (40 CFR part 63, subpart VVVV); EPA ICR Number 1966.06, OMB Control Number 2060– 0546; Expiration Date: November 30, 2016. Respondents: Boat manufacturing facilities. Respondent’s obligation to respond: Mandatory (40 CFR part 63, subpart VVVV); Estimated number of respondents: 144 (total). Frequency of response: Initially, occasionally, and semiannually. Estimated annual burden: 23,500 hours. Estimated annual cost: $2,300,000, includes $800 annualized capital or O&M costs. Changes in Estimates: There is no change in burden hours from the previous ICR. (8) Docket ID Number: EPA–HQ– OECA–2013–0345; Title: NESHAP for Metal Can Manufacturing Surface Coating (40 CFR part 63, subpart KKKK); EPA ICR Number 2079.06, OMB Control Number 2060–0541; Expiration Date: November 30, 2016. Respondents: Metal can manufacturing facilities that use 1,500 gallons or more of surface coatings. Respondent’s obligation to respond: Mandatory (40 CFR part 63, subpart KKKK). Estimated number of respondents: 5 (total). Frequency of response: Initially, occasionally and semiannually. Estimated annual burden: 1,940 hours. Estimated annual cost: $196,000, includes $6,000 annualized capital or O&M costs. Changes in Estimates: There is no change in burden hours from the previous ICR. VerDate Sep<11>2014 18:53 May 02, 2016 Jkt 238001 (9) Docket ID Number: EPA–HQ– OECA–2013–0313; Title: NSPS for Stationary Gas Turbines (40 CFR part 60, subpart GG); EPA ICR Number 1071.12, OMB Control Number 2060– 0028; Expiration Date: December 31, 2016. Respondents: Stationary gas turbines. Respondent’s obligation to respond: Mandatory (40 CFR part 60, subpart GG). Estimated number of respondents: 535 (total). Frequency of response: Initially and semiannually. Estimated annual burden: 68,400 hours. Estimated annual cost: $6,700,000, includes $0 annualized capital or O&M costs. Changes in Estimates: There is no change in burden hours from the previous ICR. (10) Docket ID Number: EPA–HQ– OECA–2013–0333; Title: Standards of Performance for Air Emission Standards for Tanks, Surface Impoundments and Containers (40 CFR part 264, subpart CC and 40 CFR part 265, subpart CC); EPA ICR Number 1593.10, OMB Control Number 2060–0318; Expiration Date: December 31, 2016. Respondents: Facilities that treat, store, or dispose of hazardous wastes in tanks, surface impoundments, and containers. Respondent’s obligation to respond: Mandatory (40 CFR part 264, subpart CC and 40 CFR part 265, subpart CC). Estimated number of respondents: 6,200 (total). Frequency of response: Occasionally. Estimated annual burden: 712,000 hours. Estimated annual cost: $82,100,000, includes $12,400,000 annualized capital or O&M costs. Changes in Estimates: There is no change in burden hours from the previous ICR. (11) Docket ID Number: EPA–HQ– OECA–2013–0335; Title: NESHAP for Aerospace Manufacturing and Rework Facilities (40 CFR part 63, subpart GG); EPA ICR Number 1687.10, OMB Control Number 2060–0314; Expiration Date: December 31, 2016. Respondents: Aerospace manufacturing and rework facilities. Respondent’s obligation to respond: Mandatory (40 CFR part 63, subpart GG). Estimated number of respondents: 136 (total). Frequency of response: Initially, occasionally, and semiannually. Estimated annual burden: 141,000 hours. PO 00000 Frm 00023 Fmt 4703 Sfmt 4703 Estimated annual cost: $13,900,000, includes $136,000 annualized capital or O&M costs. Changes in Estimates: There is no change in burden hours from the previous ICR. (12) Docket ID Number: EPA–HQ– OECA–2013–0340; Title: NESHAP for Stationary Reciprocating Internal Combustion Engines (40 CFR part 63, subpart ZZZZ); EPA ICR Number 1975.10, OMB Control Number 2060– 0548; Expiration Date: December 31, 2016. Respondents: Stationary reciprocating internal combustion engines. Respondent’s obligation to respond: Mandatory (40 CFR part 63, subpart ZZZZ). Estimated number of respondents: 903,000 (total). Frequency of response: Initially, occasionally, semiannually, and annually. Estimated annual burden: 3,430,000 hours. Estimated annual cost: $425,000,000, includes $27,900,000 annualized capital or O&M costs. Changes in Estimates: There is an expected increase in burden hours due to an increase in the respondent universe. (13) Docket ID Number: EPA–HQ– OECA–2013–0346; Title: NESHAP for Acrylic/Modacrylic Fibers Prod., Carbon Black Prod., Chemical Mfg: Chromium Compounds, Flexible Polyurethane Foam Production/Fabrication, Lead Acid Battery Mfg, Wood Preserving (40 CFR part 63, subparts LLLLLL, MMMMMM, NNNNNN, OOOOOO, PPPPPP, and QQQQQQ); EPA ICR Number 2256.05, OMB Control Number 2060–0598; Expiration Date: December 31, 2016. Respondents: Acrylic or modacrylic fibers production plants, carbon black production plants, chemical manufacturing that use chromite ore as the basic feedstock, flexible polyurethane foam manufacturing or fabrication facilities, lead acid battery manufacturing facilities, and wood preserving facilities. Respondent’s obligation to respond: Mandatory (40 CFR part 63, subparts LLLLLL, MMMMMM, NNNNNN, OOOOOO, PPPPPP, and QQQQQQ). Estimated number of respondents: 956 (total). Frequency of response: Initially, occasionally, and semiannually. Estimated annual burden: 3,220 hours. Estimated annual cost: $315,000, includes $0 annualized capital or O&M costs. E:\FR\FM\03MYN1.SGM 03MYN1 asabaliauskas on DSK3SPTVN1PROD with NOTICES Federal Register / Vol. 81, No. 85 / Tuesday, May 3, 2016 / Notices Changes in Estimates: There is no change in burden hours from the previous ICR. (14) Docket ID Number: EPA–HQ– OECA–2013–0301; Title: NESHAP for Beryllium (40 CFR part 61, subpart C); EPA ICR Number 0193.12, OMB Control Number 2060–0092; Expiration Date: January 31, 2017. Respondents: Facilities processing beryllium and its derivatives. Respondent’s obligation to respond: Mandatory (40 CFR part 61, subpart C). Estimated number of respondents: 33 (total). Frequency of response: Initially, occasionally, and monthly. Estimated annual burden: 2,630 hours. Estimated annual cost: $292,000, includes $35,000 annualized capital or O&M costs. Changes in Estimates: There is no change in burden hours from the previous ICR. (15) Docket ID Number: EPA–HQ– OECA–2013–0310; Title: NSPS for Sewage Sludge Treatment Plants (40 CFR part 60, subpart O); EPA ICR Number 1063.13, OMB Control Number 2060–0035; Expiration Date: January 31, 2017. Respondents: Sewage sludge treatment plants. Respondent’s obligation to respond: Mandatory (40 CFR part 60, subpart O). Estimated number of respondents: 112 (total). Frequency of response: Initially, occasionally and semiannually. Estimated annual burden: 12,500. Estimated annual cost: $5,180,000, includes $3,960,000 annualized capital or O&M costs. Changes in Estimates: There is an increase in burden due to expected construction of new facilities or modifications of existing facilities. (16) Docket ID Number: EPA–HQ– OECA–2013–0314; Title: NSPS for Phosphate Rock Plants (40 CFR part 60, subpart NN); EPA ICR Number 1078.11, OMB Control Number 2060–0111; Expiration Date: January 31, 2017. Respondents: Phosphate rock facilities that commenced construction or reconstruction after September 21, 1979. Respondent’s obligation to respond: Mandatory (40 CFR part 60, subpart NN). Estimated number of respondents: 14 (total). Frequency of response: Initially, occasionally and semiannually. Estimated annual burden: 1,720 hours. VerDate Sep<11>2014 18:53 May 02, 2016 Jkt 238001 Estimated annual cost: $302,000, includes $133,000 annualized capital or O&M costs. Changes in Estimates: There is an expected increase in burden due to an increase in the number of new or modified sources. (17) Docket ID Number: EPA–HQ– OECA–2013–0329; Title: NSPS for Rubber Tire Manufacturing (40 CFR part 60, subpart BBB); EPA ICR Number 1158.12, OMB Control Number 2060– 0156; Expiration Date: January 31, 2017. Respondents: Rubber tire manufacturing plants that commenced construction or modification after January 20, 1983. Respondent’s obligation to respond: Mandatory (40 CFR part 60, subpart BBB). Estimated number of respondents: 41 (total). Frequency of response: Initially, occasionally, semiannually, and annually. Estimated annual burden: 17,700 hours. Estimated annual cost: $1,750,000, includes $16,400 annualized capital or O&M costs. Changes in Estimates: There is no change in burden hours from the previous ICR. (18) Docket ID Number: EPA–HQ– OECA–2013–0331; Title: NSPS for New Residential Wood Heaters (40 CFR part 60, subpart AAA); EPA ICR Number 1176.12, OMB Control Number 2060– 0161; Expiration Date: January 31, 2017. Respondents: Manufacturers, retailers, and certification laboratories of new residential wood heaters. Respondent’s obligation to respond: Mandatory (40 CFR part 60, subpart AAA). Estimated number of respondents: 947 (total). Frequency of response: Initially and occasionally. Estimated annual burden: 11,700 hours. Estimated annual cost: $2,890,000, includes $1,740,000 annualized capital or O&M costs. Changes in Estimates: There is no change in burden hours from the previous ICR. (19) Docket ID Number: EPA–HQ– OECA–2013–0342; Title: NESHAP for Lime Manufacturing (40 CFR part 63, subpart AAAAA); EPA ICR Number 2072.06, OMB Control Number 2060– 0544; Expiration Date: January 31, 2017. Respondents: Lime manufacturing plants. Respondent’s obligation to respond: Mandatory (40 CFR part 63, subpart AAAAA). PO 00000 Frm 00024 Fmt 4703 Sfmt 4703 26549 Estimated number of respondents: 65 (total). Frequency of response: Initially, occasionally, and semiannually. Estimated annual burden: 15,400 hours. Estimated annual cost: $1,820,000, includes $312,000 annualized capital or O&M costs. Changes in Estimates: There is an increase in burden hours from the previous ICR due to an expected increase in the number of respondents. (20) Docket ID Number: EPA–HQ– OECA–2013–0302; Title: NSPS for Graphic Arts Industry (40 CFR part 60, subpart QQ); EPA ICR Number 0657.12, OMB Control Number 2060–0105; Expiration Date: February 28, 2017. Respondents: Graphics arts facilities. Respondent’s obligation to respond: Mandatory (40 CFR part 60, subpart QQ). Estimated number of respondents: 20 (total). Frequency of response: Initially, occasionally and semiannually. Estimated annual burden: 1,800 hours. Estimated annual cost: $176,000, includes $0 annualized capital or O&M costs. Changes in Estimates: There is an increase in burden hours from the previous ICR due to an expected increase in respondent universe. (21) Docket ID Number: EPA–HQ– OECA–2013–0325; Title: NESHAP for Benzene Emission from Benzene Storage Vessels and Coke-By-Product Recovery Plants (40 CFR part 61, subparts L and Y); EPA ICR Number 1080.15, OMB Control Number 2060–0185; Expiration Date: March 31, 2017. Respondents: Owners or operators of benzene storage vessels and coke byproduct recovery plants. Respondent’s obligation to respond: Mandatory (40 CFR part 61, subparts L and Y). Estimated number of respondents: 21 (total). Frequency of response: Initially, occasionally, semiannually, and annually. Estimated annual burden: 3,190 hours. Estimated annual cost: $312,000, includes $0 annualized capital or O&M costs. Changes in Estimates: There is no change in burden hours from the previous ICR. (22) Docket ID Number: EPA–HQ– OECA–2013–0319; Title: NSPS for VOC Emissions from Petroleum Refinery Wastewater Systems (40 CFR part 60, subpart QQQ); EPA ICR Number E:\FR\FM\03MYN1.SGM 03MYN1 asabaliauskas on DSK3SPTVN1PROD with NOTICES 26550 Federal Register / Vol. 81, No. 85 / Tuesday, May 3, 2016 / Notices 1136.12, OMB Control Number 2060– 0172; Expiration Date: March 31, 2017. Respondents: Petroleum refineries with wastewater systems. Respondent’s obligation to respond: Mandatory (40 CFR part 60, subpart QQQ). Estimated number of respondents: 135 (total). Frequency of response: Initially, occasionally, and semiannually. Estimated annual burden: 9,240 hours. Estimated annual cost: $922,000, includes $17,600 annualized capital or O&M costs. Changes in Estimates: There is no change in burden hours from the previous ICR. (23) Docket ID Number: EPA–HQ– OECA–2013–0353; Title: NSPS for Stationary Spark Ignition Internal Combustion Engines (40 CFR part 60, subpart JJJJ); EPA ICR Number 2227.05, OMB Control Number 2060–0610; Expiration Date: March 31, 2017. Respondents: Stationary spark ignition internal combustion engines. Respondent’s obligation to respond: Mandatory (40 CFR part 60, subpart JJJJ). Estimated number of respondents: 17,600 (total). Frequency of response: Initially and annually. Estimated annual burden: 23,300 hours. Estimated annual cost: $4,640,000, includes $2,360,000 annualized capital or O&M costs. Changes in Estimates: There is an expected increase in burden hours from the previous ICR due to growth in the respondent universe. (24) Docket ID Number: EPA–HQ– OECA–2013–0321; Title: NSPS for Sewage Sludge Incinerators (40 CFR part 60, subpart LLLL); EPA ICR Number 2369.04, OMB Control Number 2060–0658; Expiration Date: March 31, 2017. Respondents: New or modified sewage sludge incinerators. Respondent’s obligation to respond: Mandatory (40 CFR part 60, subpart LLLL). Estimated number of respondents: 4 (total). Frequency of response: Initially, occasionally, and annually. Estimated annual burden: 798 hours. Estimated annual cost: $448,000, includes $370,000 annualized capital or O&M costs. Changes in Estimates: There is an expected increase in burden hours from the previous ICR due to growth in the respondent universe. (25) Docket ID Number: EPA–HQ– OECA–2013–0317; Title: NESHAP for VerDate Sep<11>2014 18:53 May 02, 2016 Jkt 238001 Gold Mine Ore Processing (40 CFR part 63, subpart EEEEEEE); EPA ICR Number 2383.04, OMB Control Number 2060– 0659; Expiration Date: March 31, 2017. Respondents: Gold mine ore processing and production facilities. Respondent’s obligation to respond: Mandatory (40 CFR part 63, subpart EEEEEEE). Estimated number of respondents: 21 (total). Frequency of response: Initially, occasionally, semiannually, and annually. Estimated annual burden: 2,360 hours. Estimated annual cost: $445,000, includes $227,000 annualized capital or O&M costs. Changes in Estimates: There is no change in burden hours from the previous ICR. (26) Docket ID Number: EPA–HQ– OECA–2016–0009; Title: NESHAP for Group IV Polymers and Resins (40 CFR part 63, subpart JJJ); EPA ICR Number 2457.03, OMB Control Number 2060– 0682; Expiration Date: March 31, 2017. Respondents: Thermoplastic resin production facilities. Respondent’s obligation to respond: Mandatory (40 CFR part 63, subpart JJJ). Estimated number of respondents: 31 (total). Frequency of response: Semiannually. Estimated annual burden: 459 hours. Estimated annual cost: $1,110,000, includes $542,000 annualized capital or O&M costs. (27) Docket ID Number: EPA–HQ– OECA–2014–0063; Title: NESHAP for Polyether Polyols Production (40 CFR part 63, subpart PPP); EPA ICR Number 1811.10, OMB Control Number 2060– 0415; Expiration Date: May 31, 2017. Respondents: Polyether polyols production facilities. Respondent’s obligation to respond: Mandatory (40 CFR part 63, subpart PPP). Estimated number of respondents: 23 (total). Frequency of response: Occasionally and semiannually. Estimated annual burden: 3,700 hours. Estimated annual cost: $433,000, includes $226,000 annualized capital or O&M costs. Changes in Estimates: There is no change in burden hours from the previous ICR. (28) Docket ID Number: EPA–HQ– OECA–2013–0303; Title: NSPS for Equipment Leaks of VOC in Petroleum Refineries (40 CFR part 60, subparts GGG and GGGa); EPA ICR Number 0983.15, OMB Control Number 2060– 0067; Expiration Date: June 30, 2017. PO 00000 Frm 00025 Fmt 4703 Sfmt 4703 Respondents: Petroleum refineries. Respondent’s obligation to respond: Mandatory (40 CFR part 60, subparts GGG and GGGa). Estimated number of respondents: 130 (total). Frequency of response: Initially, occasionally, and semiannually. Estimated annual burden: 24,900 hours. Estimated annual cost: $2,430,000, includes $0 annualized capital or O&M costs. Changes in Estimates: There is no change in burden hours from the previous ICR. (29) Docket ID Number: EPA–HQ– OECA–2013–0350; Title: The Consolidated Air Rule (CAR) for the Synthetic Organic Chemical Manufacturing Industry (SOCMI); EPA ICR Number 1854.10, OMB Control Number 2060–0443; Expiration Date: June 30, 2017. Respondents: Synthetic organic chemical manufacturing facilities. Respondent’s obligation to respond: Mandatory (40 CFR part 65). Estimated number of respondents: 4,620 (total). Frequency of response: Initially, occasionally, semiannually and annually. Estimated annual burden: 2,130,000 hours. Estimated annual cost: $309,000,000, includes $101,000,000 annualized capital or O&M costs. Changes in Estimates: There is an expected increase in burden hours from the previous ICR due to growth in the respondent universe. (30) Docket ID Number: EPA–HQ– OECA–2013–0315; Title: NSPS for Commercial and Industrial Solid Waste Incineration (CISWI) Units (40 CFR part 60, subpart CCCC); EPA ICR Number 2384.04, OMB Control Number 2060– 0662; Expiration Date: June 30, 2017. Respondents: Commercial and industrial solid waste incineration units. Respondent’s obligation to respond: Mandatory (40 CFR part 60, subpart CCCC). Estimated number of respondents: 4 (total). Frequency of response: Initially, occasionally, semiannually, and annually. Estimated annual burden: 1,040 hours. Estimated annual cost: $451,000, includes $350,000 annualized capital or O&M costs. Changes in Estimates: There is an expected increase in burden hours from the previous ICR due to growth in the respondent universe. E:\FR\FM\03MYN1.SGM 03MYN1 Federal Register / Vol. 81, No. 85 / Tuesday, May 3, 2016 / Notices (31) Docket ID Number: EPA–HQ– OECA–2014–0034; Title: NSPS for Kraft Pulp Mills (40 CFR part 60, subpart BB); EPA ICR Number 2485.03, OMB Control Number 2060–0690; Expiration Date: June 30, 2017. Respondents: Kraft pulp mills. Respondent’s obligation to respond: Mandatory (40 CFR part 60, subpart BB). Estimated number of respondents: 4 (total). Frequency of response: Initially, occasionally, and semiannually. Estimated annual burden: 1,910 hours. Estimated annual cost: $753,000, includes $567,000 annualized capital or O&M costs. Changes in Estimates: There is an expected increase in burden hours from the previous ICR due to growth in the respondent universe. (32) Docket ID Number: EPA–HQ– OECA–2013–0316; Title: NSPS for Onshore Natural Gas Processing Plants (40 CFR part 60, subparts KKK and LLL); EPA ICR Number 1086.12, OMB Control Number 2060–0120; Expiration Date: August 31, 2017. Respondents: Onshore natural gas processing plants. Respondent’s obligation to respond: Mandatory (40 CFR part 60, subparts KKK and LLL). Estimated number of respondents: 577 (total). Frequency of response: Initially, occasionally, and semiannually. Estimated annual burden: 122,000 hours. Estimated annual cost: $12,000,000, includes $68,400 annualized capital or O&M costs. Changes in Estimates: There is no change in burden hours from the previous ICR. Dated: April 18, 2016. Edward J. Messina, Director, Monitoring, Assistance and Media Programs Division. [FR Doc. 2016–10393 Filed 5–2–16; 8:45 am] BILLING CODE 6560–50–P ENVIRONMENTAL PROTECTION AGENCY asabaliauskas on DSK3SPTVN1PROD with NOTICES [FRL–9945–99–OA] Notification of a Public Meeting and Public Teleconference of the Chartered Science Advisory Board Environmental Protection Agency (EPA). ACTION: Notice. AGENCY: The Environmental Protection Agency (EPA) Science Advisory Board SUMMARY: VerDate Sep<11>2014 18:53 May 02, 2016 Jkt 238001 (SAB) Staff Office announces a public meeting and a public teleconference of the chartered SAB to conduct a quality review of a draft SAB report on an assessment of potential impacts of hydraulic fracturing on drinking water resources and to receive briefings on topics of interest for possible future SAB advice. DATES: The public meeting will be held on Tuesday, June 14, 2016, from 8:30 a.m. to 5:00 p.m. and Wednesday, June 15, 2016, from 8:30 a.m. to 1:00 p.m. The teleconference, if needed to accommodate registered public speakers, will be held on June 8, 2016 from 2:00 p.m. to 5:00 p.m. (Eastern Time). ADDRESSES: The meeting will be held at the Westin Alexandria, 400 Courthouse Square, Alexandria, VA 22314. FOR FURTHER INFORMATION CONTACT: Any member of the public who wants further information concerning the meeting may contact Mr. Thomas Carpenter, Designated Federal Officer (DFO), EPA Science Advisory Board (1400R), U.S. Environmental Protection Agency, 1200 Pennsylvania Avenue NW., Washington, DC 20460; via telephone/voice mail (202) 564–4885, or email at carpenter.thomas@epa.gov. General information concerning the SAB can be found on the EPA Web site at https:// www.epa.gov/sab. Technical Contact for EPA’s Draft Report: Any technical questions concerning EPA’s draft report, Assessment of the Potential Impacts of Hydraulic Fracturing for Oil and Gas on Drinking Water Resources (May 2015 External Review Draft, EPA/600/R–15/ 047), should be directed to Dr. Jeffrey Frithsen, National Center for Environmental Assessment, Office of Research and Development, U.S. EPA, 1200 Pennsylvania Avenue NW., Mail Code 8601P, Washington, DC 20460, telephone (703) 347–8623 or via email at frithsen.jeff@epa.gov. SUPPLEMENTARY INFORMATION: Background: The SAB was established pursuant to the Environmental Research, Development, and Demonstration Authorization Act (ERDDAA), codified at 42 U.S.C. 4365, to provide independent scientific and technical advice to the Administrator on the scientific and technical basis for Agency positions and regulations. The SAB is a Federal Advisory Committee chartered under the Federal Advisory Committee Act (FACA), 5 U.S.C., App. 2. The SAB will comply with the provisions of FACA and all appropriate SAB Staff Office procedural policies. Pursuant to FACA and EPA policy, notice is hereby given that the SAB will PO 00000 Frm 00026 Fmt 4703 Sfmt 4703 26551 hold a public meeting to discuss and deliberate on the topics below. (1) Quality review of the SAB Draft 4– 26–16 Review of EPA’s draft Assessment of the Potential Impacts of Hydraulic Fracturing for Oil and Gas on Drinking Water Resources. The EPA’s Office of Research and Development (ORD) requested the SAB to conduct a peer review of the draft assessment report concerning the relationship between hydraulic fracturing and drinking water in the United States. The purpose of the report, Assessment of the Potential Impacts of Hydraulic Fracturing for Oil and Gas on Drinking Water Resources (May 2015 External Review Draft, EPA/ 600/R–15/047), is to synthesize available scientific literature and data to assess the potential for hydraulic fracturing for oil and gas to impact the quality or quantity of drinking water resources, and identify factors affecting the frequency or severity of any potential impacts. The SAB Hydraulic Fracturing Research Advisory Panel conducted a peer review of the EPA draft assessment and the chartered SAB will conduct a quality review of the panel’s draft report. Quality review is a key function of the chartered SAB. Draft reports prepared by SAB committees, panels, or work groups must be reviewed and approved by the chartered SAB before transmittal to the EPA Administrator. Consistent with FACA, the chartered SAB makes a determination in a public meeting about each draft report and determines whether the report is ready to be transmitted to the EPA Administrator. Background on the current advisory activity, Assessment of the Potential Impacts of Hydraulic Fracturing for Oil and Gas on Drinking Water Resources, can be found on the SAB Web site at https://yosemite.epa.gov/sab/ sabproduct.nsf//LookupWebProjects CurrentBOARD/F7A9DB9ABBAC0 15785257E540052DD54?Open Document. (2) Briefings from representatives of the EPA and other EPA advisory Committees on topics of interest for possible future SAB advice. If the SAB Staff Office determines that there will be insufficient time during the June 14–15, 2016 meeting to accommodate the members of the public who registered in advance to provide oral public comments, the teleconference will be held on June 8, 2016 to provide additional time for oral public comments. Availability of Meeting Materials: A meeting agenda and other materials for the meeting will be placed on the SAB Web site at https://epa.gov/sab. E:\FR\FM\03MYN1.SGM 03MYN1

Agencies

[Federal Register Volume 81, Number 85 (Tuesday, May 3, 2016)]
[Notices]
[Pages 26546-26551]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-10393]


=======================================================================
-----------------------------------------------------------------------

ENVIRONMENTAL PROTECTION AGENCY

[FRL-9946-03-OECA]


Proposed Information Collection Request; Comment Request

AGENCY: Environmental Protection Agency (EPA).

ACTION: Notice.

-----------------------------------------------------------------------

SUMMARY: The Environmental Protection Agency is planning to submit the 
below listed information collection requests (ICR) (See item specific 
ICR title, EPA ICR Number and OMB Control Number provided in the text) 
to the Office of Management and Budget (OMB) for review and approval in 
accordance with the Paperwork Reduction Act (44 U.S.C. 3501 et seq.). 
Before doing so, EPA is soliciting public comments on specific aspects 
of the proposed information collection as described below. These are 
proposed extensions of the currently approved ICRs. An Agency may not 
conduct or sponsor and a person is not required to respond to a 
collection of information unless it displays a currently valid OMB 
control number.

DATES: Comments must be submitted on or before July 5, 2016.

ADDRESSES: Submit your comments, referencing the Docket ID numbers 
provided for each item in the text, online using www.regulations.gov 
(our preferred method), by email to docket.oeca@epa.gov, or by mail to: 
EPA Docket Center, Environmental Protection Agency, Mail Code 28221T, 
1200 Pennsylvania Ave. NW., Washington, DC 20460.
    EPA's policy is that all comments received will be included in the 
public docket without change including any personal information 
provided, unless the comment includes profanity, threats, information 
claimed to be Confidential Business Information (CBI) or other 
information whose disclosure is restricted by statute.

FOR FURTHER INFORMATION CONTACT: Patrick Yellin, Monitoring, 
Assistance, and Media Programs Division, Office of Compliance, Mail 
Code 2227A, Environmental Protection Agency, 1200 Pennsylvania Ave. 
NW., Washington, DC 20460; telephone number: (202) 564-2970; fax 
number: (202) 564-0050; email address: yellin.patrick@epa.gov.

[[Page 26547]]


SUPPLEMENTARY INFORMATION: Supporting documents which explain in detail 
the information that the EPA will be collecting are available in the 
public docket for this ICR. The docket can be viewed online at 
www.regulations.gov or in person at the EPA Docket Center, EPA West, 
Room 3334, 1301 Constitution Ave. NW., Washington, DC. The telephone 
number for the Docket Center is 202-566-1744. For additional 
information about EPA's public docket, visit https://www.epa.gov/dockets.
    Pursuant to section 3506(c)(2)(A) of the PRA, EPA is soliciting 
comments and information to enable it to: (i) Evaluate whether the 
proposed collection of information is necessary for the proper 
performance of the functions of the Agency, including whether the 
information will have practical utility; (ii) evaluate the accuracy of 
the Agency's estimate of the burden of the proposed collection of 
information, including the validity of the methodology and assumptions 
used; (iii) enhance the quality, utility, and clarity of the 
information to be collected; and (iv) minimize the burden of the 
collection of information on those who are to respond, including 
through the use of appropriate automated electronic, mechanical, or 
other technological collection techniques or other forms of information 
technology, e.g., permitting electronic submission of responses. Burden 
is defined at 5 CFR 1320.03(b). EPA will consider the comments received 
and amend the ICR as appropriate. The final ICR package will then be 
submitted to OMB for review and approval. At that time, EPA will issue 
another Federal Register notice to announce the submission of the ICR 
to OMB and the opportunity to submit additional comments to OMB.
    General Abstract: For all the listed ICRs in this notice, owners 
and operators of affected facilities are required to comply with 
reporting and record keeping requirements for the general provisions of 
40 CFR part 60, subpart A or Part 63, Subpart A, as well as the 
applicable specific standards. This includes submitting initial 
notifications, performance tests and periodic reports and results, and 
maintaining records of the occurrence and duration of any startup, 
shutdown, or malfunction in the operation of an affected facility, or 
any period during which the monitoring system is inoperative. These 
reports are used by EPA to determine compliance with the standards.

    (1) Docket ID Number: EPA-HQ-OECA-2013-0336; Title: NESHAP for Off-
Site Waste and Recovery Operations (40 CFR part 63, subpart DD); EPA 
ICR Number 1717.10, OMB Control Number 2060-0313; Expiration Date: 
October 31, 2016.
    Respondents: Waste management and recovery facilities.
    Respondent's obligation to respond: Mandatory (40 CFR part 63, 
subpart DD).
    Estimated number of respondents: 236 (total).
    Frequency of response: Initially, occasionally and semiannually.
    Estimated annual burden: 179,000 hours.
    Estimated annual cost: $17,500,000, includes $5,810 annualized 
capital or operation & maintenance (O&M) costs.
    Changes in Estimates: There is no change in burden hours from the 
previous ICR.

    (2) Docket ID Number: EPA-HQ-OECA-2012-0679; Title: NESHAP for 
Petroleum Refineries: Catalytic Cracking Units, Reforming and Sulfur 
Units (40 CFR part 63, subpart UUU); EPA ICR Number 1844.07, OMB 
Control Number 2060-0554; Expiration Date: October 31, 2016.
    Respondents: Petroleum refineries with catalytic cracking units, 
catalytic reforming units and/or sulfur recovery units.
    Respondent's obligation to respond: Mandatory (40 CFR part 63, 
subpart UUU).
    Estimated number of respondents: 123 (total).
    Frequency of response: Initially, occasionally, and semiannually.
    Estimated annual burden: 10,200 hours.
    Estimated annual cost: $9,400,000, includes $8,400,000 annualized 
capital or O&M costs.
    Changes in Estimates: There is an expected increase in burden hours 
due to expected modification of existing facilities.

    (3) Docket ID Number: EPA-HQ-OECA-2013-0338; Title: NESHAP for the 
Manufacture of Amino/Phenolic Resins (40 CFR part 63, subpart OOO); EPA 
ICR Number 1869.08, OMB Control Number 2060-0434; Expiration Date: 
October 31, 2016.
    Respondents: Facilities that manufacture amino/phenolic resins.
    Respondent's obligation to respond: Mandatory (40 CFR part 63, 
subpart OOO).
    Estimated number of respondents: 37 (total).
    Frequency of response: Initially, occasionally, and semiannually.
    Estimated annual burden: 22,400 hours.
    Estimated annual cost: $2,200,000, includes $14,800 annualized 
capital or O&M costs.
    Changes in Estimates: There is no change in burden hours from the 
previous ICR.

    (4) Docket ID Number: EPA-HQ-OECA-2013-0341; Title: NESHAP for 
Plywood and Composite Products (40 CFR parts 63, Subpart DDDD); EPA ICR 
Number 1984.06, OMB Control Number 2060-0552; Expiration Date: October 
31, 2016.
    Respondents: Plywood and composite wood products (PCWP) facilities.
    Respondent's obligation to respond: Mandatory (40 CFR part 63, 
subpart DDDD).
    Estimated number of respondents: 228 (total).
    Frequency of response: Initially, occasionally, and semiannually.
    Estimated annual burden: 11,700 hours.
    Estimated annual cost: $1,160,000, includes $16,000 annualized 
capital or O&M costs.
    Changes in Estimates: There is no change in burden hours from the 
previous ICR.

    (5) Docket ID Number: EPA-HQ-OECA-2013-0318; Title: NSPS for 
Magnetic Tape Coating Facilities (40 CFR part 60, subpart SSS); EPA ICR 
Number 1135.12, OMB Control Number 2060-0171; Expiration Date: November 
30, 2016.
    Respondents: Magnetic tape coating facilities constructed or 
modified after January 22, 1986.
    Respondent's obligation to respond: Mandatory (40 CFR part 60, 
subpart SSS).
    Estimated number of respondents: 6 (total).
    Frequency of response: Initially, occasionally and semiannually.
    Estimated annual burden: 2,020 hours.
    Estimated annual cost: $283,000, includes $86,400 annualized 
capital or O&M costs.
    Changes in Estimates: There is no change in burden hours from the 
previous ICR.

    (6) Docket ID Number: EPA-HQ-OECA-2013-0334; Title: NSPS for 
Secondary Brass and Bronze Production, Primary Copper Smelters, Primary 
Zinc Smelters, Primary Lead Smelters, Primary Aluminum Reduction 
Plants, and Ferroalloy Production Facilities (40 CFR part 60, subparts 
M, P, Q, R, S, Z); EPA ICR Number 1604.11, OMB Control Number 2060-
0110; Expiration Date: November 30, 2016.
    Respondents: Secondary brass or bronze production facilities; 
primary

[[Page 26548]]

copper, primary zinc, and primary lead facilities; primary aluminum 
reduction facilities; and ferroalloy production facilities.
    Respondent's obligation to respond: Mandatory (40 CFR part 60, 
subparts M, P, Q, R, S, and Z).
    Estimated number of respondents: 19 (total).
    Frequency of response: Initially, occasionally, semiannually, and 
annually.
    Estimated annual burden: 4,960 hours.
    Estimated annual cost: $612,000 includes $127,000 annualized 
capital or O&M costs.
    Changes in Estimates: There is no change in burden hours from the 
previous ICR.

    (7) Docket ID Number: EPA-HQ-OECA-2013-0339; Title: NESHAP for Boat 
Manufacturing (40 CFR part 63, subpart VVVV); EPA ICR Number 1966.06, 
OMB Control Number 2060-0546; Expiration Date: November 30, 2016.
    Respondents: Boat manufacturing facilities.
    Respondent's obligation to respond: Mandatory (40 CFR part 63, 
subpart VVVV);
    Estimated number of respondents: 144 (total).
    Frequency of response: Initially, occasionally, and semiannually.
    Estimated annual burden: 23,500 hours.
    Estimated annual cost: $2,300,000, includes $800 annualized capital 
or O&M costs.
    Changes in Estimates: There is no change in burden hours from the 
previous ICR.

    (8) Docket ID Number: EPA-HQ-OECA-2013-0345; Title: NESHAP for 
Metal Can Manufacturing Surface Coating (40 CFR part 63, subpart KKKK); 
EPA ICR Number 2079.06, OMB Control Number 2060-0541; Expiration Date: 
November 30, 2016.
    Respondents: Metal can manufacturing facilities that use 1,500 
gallons or more of surface coatings.
    Respondent's obligation to respond: Mandatory (40 CFR part 63, 
subpart KKKK).
    Estimated number of respondents: 5 (total).
    Frequency of response: Initially, occasionally and semiannually.
    Estimated annual burden: 1,940 hours.
    Estimated annual cost: $196,000, includes $6,000 annualized capital 
or O&M costs.
    Changes in Estimates: There is no change in burden hours from the 
previous ICR.

    (9) Docket ID Number: EPA-HQ-OECA-2013-0313; Title: NSPS for 
Stationary Gas Turbines (40 CFR part 60, subpart GG); EPA ICR Number 
1071.12, OMB Control Number 2060-0028; Expiration Date: December 31, 
2016.
    Respondents: Stationary gas turbines.
    Respondent's obligation to respond: Mandatory (40 CFR part 60, 
subpart GG).
    Estimated number of respondents: 535 (total).
    Frequency of response: Initially and semiannually.
    Estimated annual burden: 68,400 hours.
    Estimated annual cost: $6,700,000, includes $0 annualized capital 
or O&M costs.
    Changes in Estimates: There is no change in burden hours from the 
previous ICR.

    (10) Docket ID Number: EPA-HQ-OECA-2013-0333; Title: Standards of 
Performance for Air Emission Standards for Tanks, Surface Impoundments 
and Containers (40 CFR part 264, subpart CC and 40 CFR part 265, 
subpart CC); EPA ICR Number 1593.10, OMB Control Number 2060-0318; 
Expiration Date: December 31, 2016.
    Respondents: Facilities that treat, store, or dispose of hazardous 
wastes in tanks, surface impoundments, and containers.
    Respondent's obligation to respond: Mandatory (40 CFR part 264, 
subpart CC and 40 CFR part 265, subpart CC).
    Estimated number of respondents: 6,200 (total).
    Frequency of response: Occasionally.
    Estimated annual burden: 712,000 hours.
    Estimated annual cost: $82,100,000, includes $12,400,000 annualized 
capital or O&M costs.
    Changes in Estimates: There is no change in burden hours from the 
previous ICR.

    (11) Docket ID Number: EPA-HQ-OECA-2013-0335; Title: NESHAP for 
Aerospace Manufacturing and Rework Facilities (40 CFR part 63, subpart 
GG); EPA ICR Number 1687.10, OMB Control Number 2060-0314; Expiration 
Date: December 31, 2016.
    Respondents: Aerospace manufacturing and rework facilities.
    Respondent's obligation to respond: Mandatory (40 CFR part 63, 
subpart GG).
    Estimated number of respondents: 136 (total).
    Frequency of response: Initially, occasionally, and semiannually.
    Estimated annual burden: 141,000 hours.
    Estimated annual cost: $13,900,000, includes $136,000 annualized 
capital or O&M costs.
    Changes in Estimates: There is no change in burden hours from the 
previous ICR.

    (12) Docket ID Number: EPA-HQ-OECA-2013-0340; Title: NESHAP for 
Stationary Reciprocating Internal Combustion Engines (40 CFR part 63, 
subpart ZZZZ); EPA ICR Number 1975.10, OMB Control Number 2060-0548; 
Expiration Date: December 31, 2016.
    Respondents: Stationary reciprocating internal combustion engines.
    Respondent's obligation to respond: Mandatory (40 CFR part 63, 
subpart ZZZZ).
    Estimated number of respondents: 903,000 (total).
    Frequency of response: Initially, occasionally, semiannually, and 
annually.
    Estimated annual burden: 3,430,000 hours.
    Estimated annual cost: $425,000,000, includes $27,900,000 
annualized capital or O&M costs.
    Changes in Estimates: There is an expected increase in burden hours 
due to an increase in the respondent universe.

    (13) Docket ID Number: EPA-HQ-OECA-2013-0346; Title: NESHAP for 
Acrylic/Modacrylic Fibers Prod., Carbon Black Prod., Chemical Mfg: 
Chromium Compounds, Flexible Polyurethane Foam Production/Fabrication, 
Lead Acid Battery Mfg, Wood Preserving (40 CFR part 63, subparts 
LLLLLL, MMMMMM, NNNNNN, OOOOOO, PPPPPP, and QQQQQQ); EPA ICR Number 
2256.05, OMB Control Number 2060-0598; Expiration Date: December 31, 
2016.
    Respondents: Acrylic or modacrylic fibers production plants, carbon 
black production plants, chemical manufacturing that use chromite ore 
as the basic feedstock, flexible polyurethane foam manufacturing or 
fabrication facilities, lead acid battery manufacturing facilities, and 
wood preserving facilities.
    Respondent's obligation to respond: Mandatory (40 CFR part 63, 
subparts LLLLLL, MMMMMM, NNNNNN, OOOOOO, PPPPPP, and QQQQQQ).
    Estimated number of respondents: 956 (total).
    Frequency of response: Initially, occasionally, and semiannually.
    Estimated annual burden: 3,220 hours.
    Estimated annual cost: $315,000, includes $0 annualized capital or 
O&M costs.

[[Page 26549]]

    Changes in Estimates: There is no change in burden hours from the 
previous ICR.

    (14) Docket ID Number: EPA-HQ-OECA-2013-0301; Title: NESHAP for 
Beryllium (40 CFR part 61, subpart C); EPA ICR Number 0193.12, OMB 
Control Number 2060-0092; Expiration Date: January 31, 2017.
    Respondents: Facilities processing beryllium and its derivatives.
    Respondent's obligation to respond: Mandatory (40 CFR part 61, 
subpart C).
    Estimated number of respondents: 33 (total).
    Frequency of response: Initially, occasionally, and monthly.
    Estimated annual burden: 2,630 hours.
    Estimated annual cost: $292,000, includes $35,000 annualized 
capital or O&M costs.
    Changes in Estimates: There is no change in burden hours from the 
previous ICR.

    (15) Docket ID Number: EPA-HQ-OECA-2013-0310; Title: NSPS for 
Sewage Sludge Treatment Plants (40 CFR part 60, subpart O); EPA ICR 
Number 1063.13, OMB Control Number 2060-0035; Expiration Date: January 
31, 2017.
    Respondents: Sewage sludge treatment plants.
    Respondent's obligation to respond: Mandatory (40 CFR part 60, 
subpart O).
    Estimated number of respondents: 112 (total).
    Frequency of response: Initially, occasionally and semiannually.
    Estimated annual burden: 12,500.
    Estimated annual cost: $5,180,000, includes $3,960,000 annualized 
capital or O&M costs.
    Changes in Estimates: There is an increase in burden due to 
expected construction of new facilities or modifications of existing 
facilities.

    (16) Docket ID Number: EPA-HQ-OECA-2013-0314; Title: NSPS for 
Phosphate Rock Plants (40 CFR part 60, subpart NN); EPA ICR Number 
1078.11, OMB Control Number 2060-0111; Expiration Date: January 31, 
2017.
    Respondents: Phosphate rock facilities that commenced construction 
or reconstruction after September 21, 1979.
    Respondent's obligation to respond: Mandatory (40 CFR part 60, 
subpart NN).
    Estimated number of respondents: 14 (total).
    Frequency of response: Initially, occasionally and semiannually.
    Estimated annual burden: 1,720 hours.
    Estimated annual cost: $302,000, includes $133,000 annualized 
capital or O&M costs.
    Changes in Estimates: There is an expected increase in burden due 
to an increase in the number of new or modified sources.

    (17) Docket ID Number: EPA-HQ-OECA-2013-0329; Title: NSPS for 
Rubber Tire Manufacturing (40 CFR part 60, subpart BBB); EPA ICR Number 
1158.12, OMB Control Number 2060-0156; Expiration Date: January 31, 
2017.
    Respondents: Rubber tire manufacturing plants that commenced 
construction or modification after January 20, 1983.
    Respondent's obligation to respond: Mandatory (40 CFR part 60, 
subpart BBB).
    Estimated number of respondents: 41 (total).
    Frequency of response: Initially, occasionally, semiannually, and 
annually.
    Estimated annual burden: 17,700 hours.
    Estimated annual cost: $1,750,000, includes $16,400 annualized 
capital or O&M costs.
    Changes in Estimates: There is no change in burden hours from the 
previous ICR.

    (18) Docket ID Number: EPA-HQ-OECA-2013-0331; Title: NSPS for New 
Residential Wood Heaters (40 CFR part 60, subpart AAA); EPA ICR Number 
1176.12, OMB Control Number 2060-0161; Expiration Date: January 31, 
2017.
    Respondents: Manufacturers, retailers, and certification 
laboratories of new residential wood heaters.
    Respondent's obligation to respond: Mandatory (40 CFR part 60, 
subpart AAA).
    Estimated number of respondents: 947 (total).
    Frequency of response: Initially and occasionally.
    Estimated annual burden: 11,700 hours.
    Estimated annual cost: $2,890,000, includes $1,740,000 annualized 
capital or O&M costs.
    Changes in Estimates: There is no change in burden hours from the 
previous ICR.

    (19) Docket ID Number: EPA-HQ-OECA-2013-0342; Title: NESHAP for 
Lime Manufacturing (40 CFR part 63, subpart AAAAA); EPA ICR Number 
2072.06, OMB Control Number 2060-0544; Expiration Date: January 31, 
2017.
    Respondents: Lime manufacturing plants.
    Respondent's obligation to respond: Mandatory (40 CFR part 63, 
subpart AAAAA).
    Estimated number of respondents: 65 (total).
    Frequency of response: Initially, occasionally, and semiannually.
    Estimated annual burden: 15,400 hours.
    Estimated annual cost: $1,820,000, includes $312,000 annualized 
capital or O&M costs.
    Changes in Estimates: There is an increase in burden hours from the 
previous ICR due to an expected increase in the number of respondents.

    (20) Docket ID Number: EPA-HQ-OECA-2013-0302; Title: NSPS for 
Graphic Arts Industry (40 CFR part 60, subpart QQ); EPA ICR Number 
0657.12, OMB Control Number 2060-0105; Expiration Date: February 28, 
2017.
    Respondents: Graphics arts facilities.
    Respondent's obligation to respond: Mandatory (40 CFR part 60, 
subpart QQ).
    Estimated number of respondents: 20 (total).
    Frequency of response: Initially, occasionally and semiannually.
    Estimated annual burden: 1,800 hours.
    Estimated annual cost: $176,000, includes $0 annualized capital or 
O&M costs.
    Changes in Estimates: There is an increase in burden hours from the 
previous ICR due to an expected increase in respondent universe.

    (21) Docket ID Number: EPA-HQ-OECA-2013-0325; Title: NESHAP for 
Benzene Emission from Benzene Storage Vessels and Coke-By-Product 
Recovery Plants (40 CFR part 61, subparts L and Y); EPA ICR Number 
1080.15, OMB Control Number 2060-0185; Expiration Date: March 31, 2017.
    Respondents: Owners or operators of benzene storage vessels and 
coke by-product recovery plants.
    Respondent's obligation to respond: Mandatory (40 CFR part 61, 
subparts L and Y).
    Estimated number of respondents: 21 (total).
    Frequency of response: Initially, occasionally, semiannually, and 
annually.
    Estimated annual burden: 3,190 hours.
    Estimated annual cost: $312,000, includes $0 annualized capital or 
O&M costs.
    Changes in Estimates: There is no change in burden hours from the 
previous ICR.

    (22) Docket ID Number: EPA-HQ-OECA-2013-0319; Title: NSPS for VOC 
Emissions from Petroleum Refinery Wastewater Systems (40 CFR part 60, 
subpart QQQ); EPA ICR Number

[[Page 26550]]

1136.12, OMB Control Number 2060-0172; Expiration Date: March 31, 2017.
    Respondents: Petroleum refineries with wastewater systems.
    Respondent's obligation to respond: Mandatory (40 CFR part 60, 
subpart QQQ).
    Estimated number of respondents: 135 (total).
    Frequency of response: Initially, occasionally, and semiannually.
    Estimated annual burden: 9,240 hours.
    Estimated annual cost: $922,000, includes $17,600 annualized 
capital or O&M costs.
    Changes in Estimates: There is no change in burden hours from the 
previous ICR.

    (23) Docket ID Number: EPA-HQ-OECA-2013-0353; Title: NSPS for 
Stationary Spark Ignition Internal Combustion Engines (40 CFR part 60, 
subpart JJJJ); EPA ICR Number 2227.05, OMB Control Number 2060-0610; 
Expiration Date: March 31, 2017.
    Respondents: Stationary spark ignition internal combustion engines.
    Respondent's obligation to respond: Mandatory (40 CFR part 60, 
subpart JJJJ).
    Estimated number of respondents: 17,600 (total).
    Frequency of response: Initially and annually.
    Estimated annual burden: 23,300 hours.
    Estimated annual cost: $4,640,000, includes $2,360,000 annualized 
capital or O&M costs.
    Changes in Estimates: There is an expected increase in burden hours 
from the previous ICR due to growth in the respondent universe.

    (24) Docket ID Number: EPA-HQ-OECA-2013-0321; Title: NSPS for 
Sewage Sludge Incinerators (40 CFR part 60, subpart LLLL); EPA ICR 
Number 2369.04, OMB Control Number 2060-0658; Expiration Date: March 
31, 2017.
    Respondents: New or modified sewage sludge incinerators.
    Respondent's obligation to respond: Mandatory (40 CFR part 60, 
subpart LLLL).
    Estimated number of respondents: 4 (total).
    Frequency of response: Initially, occasionally, and annually.
    Estimated annual burden: 798 hours.
    Estimated annual cost: $448,000, includes $370,000 annualized 
capital or O&M costs.
    Changes in Estimates: There is an expected increase in burden hours 
from the previous ICR due to growth in the respondent universe.

    (25) Docket ID Number: EPA-HQ-OECA-2013-0317; Title: NESHAP for 
Gold Mine Ore Processing (40 CFR part 63, subpart EEEEEEE); EPA ICR 
Number 2383.04, OMB Control Number 2060-0659; Expiration Date: March 
31, 2017.
    Respondents: Gold mine ore processing and production facilities.
    Respondent's obligation to respond: Mandatory (40 CFR part 63, 
subpart EEEEEEE).
    Estimated number of respondents: 21 (total).
    Frequency of response: Initially, occasionally, semiannually, and 
annually.
    Estimated annual burden: 2,360 hours.
    Estimated annual cost: $445,000, includes $227,000 annualized 
capital or O&M costs.
    Changes in Estimates: There is no change in burden hours from the 
previous ICR.

    (26) Docket ID Number: EPA-HQ-OECA-2016-0009; Title: NESHAP for 
Group IV Polymers and Resins (40 CFR part 63, subpart JJJ); EPA ICR 
Number 2457.03, OMB Control Number 2060-0682; Expiration Date: March 
31, 2017.
    Respondents: Thermoplastic resin production facilities.
    Respondent's obligation to respond: Mandatory (40 CFR part 63, 
subpart JJJ).
    Estimated number of respondents: 31 (total).
    Frequency of response: Semiannually.
    Estimated annual burden: 459 hours.
    Estimated annual cost: $1,110,000, includes $542,000 annualized 
capital or O&M costs.

    (27) Docket ID Number: EPA-HQ-OECA-2014-0063; Title: NESHAP for 
Polyether Polyols Production (40 CFR part 63, subpart PPP); EPA ICR 
Number 1811.10, OMB Control Number 2060-0415; Expiration Date: May 31, 
2017.
    Respondents: Polyether polyols production facilities.
    Respondent's obligation to respond: Mandatory (40 CFR part 63, 
subpart PPP).
    Estimated number of respondents: 23 (total).
    Frequency of response: Occasionally and semiannually.
    Estimated annual burden: 3,700 hours.
    Estimated annual cost: $433,000, includes $226,000 annualized 
capital or O&M costs.
    Changes in Estimates: There is no change in burden hours from the 
previous ICR.

    (28) Docket ID Number: EPA-HQ-OECA-2013-0303; Title: NSPS for 
Equipment Leaks of VOC in Petroleum Refineries (40 CFR part 60, 
subparts GGG and GGGa); EPA ICR Number 0983.15, OMB Control Number 
2060-0067; Expiration Date: June 30, 2017.
    Respondents: Petroleum refineries.
    Respondent's obligation to respond: Mandatory (40 CFR part 60, 
subparts GGG and GGGa).
    Estimated number of respondents: 130 (total).
    Frequency of response: Initially, occasionally, and semiannually.
    Estimated annual burden: 24,900 hours.
    Estimated annual cost: $2,430,000, includes $0 annualized capital 
or O&M costs.
    Changes in Estimates: There is no change in burden hours from the 
previous ICR.

    (29) Docket ID Number: EPA-HQ-OECA-2013-0350; Title: The 
Consolidated Air Rule (CAR) for the Synthetic Organic Chemical 
Manufacturing Industry (SOCMI); EPA ICR Number 1854.10, OMB Control 
Number 2060-0443; Expiration Date: June 30, 2017.
    Respondents: Synthetic organic chemical manufacturing facilities.
    Respondent's obligation to respond: Mandatory (40 CFR part 65).
    Estimated number of respondents: 4,620 (total).
    Frequency of response: Initially, occasionally, semiannually and 
annually.
    Estimated annual burden: 2,130,000 hours.
    Estimated annual cost: $309,000,000, includes $101,000,000 
annualized capital or O&M costs.
    Changes in Estimates: There is an expected increase in burden hours 
from the previous ICR due to growth in the respondent universe.

    (30) Docket ID Number: EPA-HQ-OECA-2013-0315; Title: NSPS for 
Commercial and Industrial Solid Waste Incineration (CISWI) Units (40 
CFR part 60, subpart CCCC); EPA ICR Number 2384.04, OMB Control Number 
2060-0662; Expiration Date: June 30, 2017.
    Respondents: Commercial and industrial solid waste incineration 
units.
    Respondent's obligation to respond: Mandatory (40 CFR part 60, 
subpart CCCC).
    Estimated number of respondents: 4 (total).
    Frequency of response: Initially, occasionally, semiannually, and 
annually.
    Estimated annual burden: 1,040 hours.
    Estimated annual cost: $451,000, includes $350,000 annualized 
capital or O&M costs.
    Changes in Estimates: There is an expected increase in burden hours 
from the previous ICR due to growth in the respondent universe.


[[Page 26551]]


    (31) Docket ID Number: EPA-HQ-OECA-2014-0034; Title: NSPS for Kraft 
Pulp Mills (40 CFR part 60, subpart BB); EPA ICR Number 2485.03, OMB 
Control Number 2060-0690; Expiration Date: June 30, 2017.
    Respondents: Kraft pulp mills.
    Respondent's obligation to respond: Mandatory (40 CFR part 60, 
subpart BB).
    Estimated number of respondents: 4 (total).
    Frequency of response: Initially, occasionally, and semiannually.
    Estimated annual burden: 1,910 hours.
    Estimated annual cost: $753,000, includes $567,000 annualized 
capital or O&M costs.
    Changes in Estimates: There is an expected increase in burden hours 
from the previous ICR due to growth in the respondent universe.

    (32) Docket ID Number: EPA-HQ-OECA-2013-0316; Title: NSPS for 
Onshore Natural Gas Processing Plants (40 CFR part 60, subparts KKK and 
LLL); EPA ICR Number 1086.12, OMB Control Number 2060-0120; Expiration 
Date: August 31, 2017.
    Respondents: Onshore natural gas processing plants.
    Respondent's obligation to respond: Mandatory (40 CFR part 60, 
subparts KKK and LLL).
    Estimated number of respondents: 577 (total).
    Frequency of response: Initially, occasionally, and semiannually.
    Estimated annual burden: 122,000 hours.
    Estimated annual cost: $12,000,000, includes $68,400 annualized 
capital or O&M costs.
    Changes in Estimates: There is no change in burden hours from the 
previous ICR.

    Dated: April 18, 2016.
Edward J. Messina,
Director, Monitoring, Assistance and Media Programs Division.
[FR Doc. 2016-10393 Filed 5-2-16; 8:45 am]
 BILLING CODE 6560-50-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.