Turners Falls Hydro, LLC; Notice of Intent To File License Application, Filing of Pre-Application Document, Approving use of the Traditional Licensing Process, 25391-25392 [2016-09935]
Download as PDF
Federal Register / Vol. 81, No. 82 / Thursday, April 28, 2016 / Notices
web portal, but if a company is unable
to access the secure web portal it may
submit a cyber incident report through
other means of communication (e.g., fax,
telephone, or United States Postal
Service). DoD contractors report cyber
incidents that affect DoD information,
facilitating cyber situational awareness,
cyber threat information sharing, and
better protection of unclassified defense
information.
Dated: April 25, 2016.
Aaron Siegel,
Alternate OSD Federal Register, Liaison
Officer, Department of Defense.
Dated: April 21, 2016.
C. Pan,
Lieutenant, Judge Advocate General’s Corps,
U.S. Navy, Alternate Federal Register Liaison
Officer.
[FR Doc. 2016–09956 Filed 4–27–16; 8:45 am]
BILLING CODE 3810–FF–P
DEPARTMENT OF ENERGY
[Certification Notice—239]
Notice of Filing of Self-Certification of
Coal Capability Under the Powerplant
and Industrial Fuel Use Act
[FR Doc. 2016–09954 Filed 4–27–16; 8:45 am]
BILLING CODE 5001–06–P
Office of Electricity Delivery
and Energy Reliability, DOE.
ACTION: Notice of filing.
DEPARTMENT OF DEFENSE
SUMMARY:
AGENCY:
Department of the Navy
Notice of Intent To Grant Exclusive
Patent License; IRFlex Corporation
AGENCY:
ACTION:
Department of the Navy, DoD.
Notice.
The Department of the Navy
hereby gives notice of its intent to grant
to IRFlex Corporation, a revocable,
nonassignable, exclusive license to
practice in the field of use of nonlinear,
mid-infrared fiber and fiber devices to
generate and/or guide mid-infrared
sources over long distances (1–500
meters) in the United States, the
Government-owned invention described
in U.S. Patent No. 8,710,470 entitled
‘‘Wavelength and Power Scalable
Waveguiding-Based Infrared Laser
System’’, Navy Case No. 101,907 and
any continuations, divisionals or reissues thereof.
SUMMARY:
Anyone wishing to object to the
grant of this license must file written
objections along with supporting
evidence, if any, not later than May 13,
2016.
DATES:
Written objections are to be
filed with the Naval Research
Laboratory, Code 1004, 4555 Overlook
Avenue SW., Washington, DC 20375–
5320.
ADDRESSES:
Rita
Manak, Head, Technology Transfer
Office, NRL Code 1004, 4555 Overlook
Avenue SW., Washington, DC 20375–
5320, telephone 202–767–3083. Due to
U.S. Postal delays, please fax 202–404–
7920, email: rita.manak@nrl.navy.mil or
use courier delivery to expedite
response.
mstockstill on DSK3G9T082PROD with NOTICES
FOR FURTHER INFORMATION CONTACT:
Authority: 35 U.S.C. 207, 37 CFR part 404.
VerDate Sep<11>2014
22:09 Apr 27, 2016
Jkt 238001
On April 15, 2016,
Mattawoman Energy, LLC, as owner and
operator of a new baseload electric
generating powerplant, submitted a coal
capability self-certification to the
Department of Energy (DOE) pursuant to
section 201(d) of the Powerplant and
Industrial Fuel Use Act of 1978 (FUA),
as amended, and DOE regulations in 10
CFR 501.60 and 501.61. FUA and
regulations thereunder require DOE to
publish a notice of filing of selfcertification in the Federal Register. 42
U.S.C. 8311(d) and 10 CFR 501.61(c).
ADDRESSES: Copies of coal capability
self-certification filings are available for
public inspection, upon request, in the
Office of Electricity Delivery and Energy
Reliability, Mail Code OE–20, Room
8G–024, Forrestal Building, 1000
Independence Avenue SW.,
Washington, DC 20585.
FOR FURTHER INFORMATION CONTACT:
Christopher Lawrence at (202) 586–
5260.
SUPPLEMENTARY INFORMATION: Title II of
FUA, as amended (42 U.S.C. 8301 et
seq.), provides that no new base load
electric powerplant may be constructed
or operated without the capability to use
coal or another alternate fuel as a
primary energy source. Pursuant to FUA
in order to meet the requirement of coal
capability, the owner or operator of such
a facility proposing to use natural gas or
petroleum as its primary energy source
shall certify to the Secretary of Energy
(Secretary) prior to construction, or
prior to operation as a base load electric
powerplant, that such powerplant has
the capability to use coal or another
alternate fuel. Such certification
establishes compliance with FUA
section 201(a) as of the date it is filed
with the Secretary. 42 U.S.C. 8311.
The following owner of a proposed
new baseload electric generating
powerplant has filed a self-certification
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
25391
of coal-capability with DOE pursuant to
FUA section 201(d) and in accordance
with DOE regulations in 10 CFR 501.60
and 501.61:
OWNER: Mattawoman Energy, LLC,
CAPACITY: 990 megawatts (MW)
PLANT LOCATION: 14175 Brandywine
Road, Brandywine, MD 20613
IN-SERVICE DATE: 10/31/2018
Issued in Washington, DC, on April 21,
2016.
Christopher Lawrence,
Electricity Policy Analyst, Office of Electricity
Delivery and Energy Reliability.
[FR Doc. 2016–10013 Filed 4–27–16; 8:45 am]
BILLING CODE 6450–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2622–012]
Turners Falls Hydro, LLC; Notice of
Intent To File License Application,
Filing of Pre-Application Document,
Approving use of the Traditional
Licensing Process
a. Type of Filing: Notice of Intent To
File License Application and Request
To Use the Traditional Licensing
Process.
b. Project No.: 2622–012.
c. Date Filed: February 26, 2016.
d. Submitted By: Turners Falls Hydro,
LLC (Turners Falls Hydro).
e. Name of Project: Turners Falls
Hydro Project.
f. Location: On the Connecticut River
in Franklin County, Massachusetts. No
federal lands are occupied by the project
works or located within the project
boundary.
g. Filed Pursuant to: 18 CFR 5.3 of the
Commission’s regulations.
h. Potential Applicant Contact: Peter
Clarke, Turners Falls Hydro, LLC, P.O.
Box 149, Hamilton, MA 01936; (978)
468–3999.
i. FERC Contact: Bill Connelly at (202)
502–8587; or email at william.connelly@
ferc.gov.
j. Turners Falls Hydro filed its request
to use the Traditional Licensing Process
on February 26, 2016. Turners Falls
Hydro provided public notice of its
request on March 3 and March 10, 2016.
In a letter dated April 22, 2016, the
Director of the Division of Hydropower
Licensing approved Turners Falls
Hydro’s request to use the Traditional
Licensing Process.
k. With this notice, we are initiating
informal consultation with the U.S. Fish
and Wildlife Service and NOAA
Fisheries under section 7 of the
E:\FR\FM\28APN1.SGM
28APN1
25392
Federal Register / Vol. 81, No. 82 / Thursday, April 28, 2016 / Notices
Endangered Species Act and the joint
agency regulations there under at 50
CFR part 402 and implementing
regulations at 50 CFR 600.920. We are
also initiating consultation with the
Massachusetts State Historic
Preservation Officer, as required by
section 106, National Historic
Preservation Act, and the implementing
regulations of the Advisory Council on
Historic Preservation at 36 CFR 800.2.
l. Turners Falls Hydro filed a PreApplication Document (PAD; including
a proposed process plan and schedule)
with the Commission, pursuant to 18
CFR 5.6 of the Commission’s
regulations.
m. A copy of the PAD is available for
electronic review at the Commission in
the Public Reference Room or may be
viewed on the Commission’s Web site
(https://www.ferc.gov), using the
‘‘eLibrary’’ link. Enter the docket
number, excluding the last three digits
in the docket number field to access the
document. For assistance, contact FERC
Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). A copy is also available for
inspection and reproduction at the
address in paragraph h.
n. The licensee states its unequivocal
intent to submit an application for a
new license for Project No. 2622.
Pursuant to 18 CFR 16.8, 16.9, and 16.10
each application for a new license and
any competing license applications
must be filed with the Commission at
least 24 months prior to the expiration
of the existing license. All applications
for license for this project must be filed
by February 28, 2019.
o. Register online at https://www.ferc.
gov/docs-filing/esubscription.asp to be
notified via email of new filing and
issuances related to this or other
pending projects. For assistance, contact
FERC Online Support.
Dated: April 22, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016–09935 Filed 4–27–16; 8:45 am]
mstockstill on DSK3G9T082PROD with NOTICES
BILLING CODE 6717–01–P
VerDate Sep<11>2014
22:09 Apr 27, 2016
Jkt 238001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14768–000]
Energy Resources USA Inc.; Notice Of
Preliminary Permit Application
Accepted For Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
On March 11, 2016, the Energy
Resources USA Inc. filed an application
for a preliminary permit under section
4(f) of the Federal Power Act proposing
to study the feasibility of the proposed
Salamonie Lake Dam Hydroelectric
Project No. 14768–000, to be located at
the existing Salamonie Lake Dam on the
Salamonie River, near the town of
Wabash, in Wabash County, Indiana.
The Salamonie Lake Dam is owned by
the United States government and
operated by the U.S. Army Corps of
Engineers, Louisville District.
The proposed project would consist
of: (1) A new 15-foot by 10-foot by 90foot-long concrete conduit; (2) a new 98foot by 45-foot reinforced concrete
powerhouse containing two 2.5megawatt (MW) vertical Kaplan turbinegenerators having a total combined
generating capacity of 5 MW; (3) a new
300-foot-long by 95-foot-wide tailrace;
(4) a new 60-foot-long by 50-foot-wide
substation with a 6-mega-volt-ampere
4.16/69-kilovolt three-phase step-up
transformer; (5) a new 2-mile-long, 69kilovolt transmission line; and (6)
appurtenant facilities. The project
would have an estimated annual
generation of 13.76 gigawatt-hours.
Applicant Contact: Mr. Ander
Gonzalez, 350 Lincoln Road, 2nd Floor,
Miami, FL 33139; telephone (954) 248–
8425.
FERC Contact: Sergiu Serban, (202)
502–6211.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36. The Commission strongly
encourages electronic filing. Please file
comments, motions to intervene, notices
of intent, and competing applications
using the Commission’s eFiling system
at https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://www.ferc.
gov/docs-filing/ecomment.asp. You
must include your name and contact
information at the end of your
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
comments. For assistance, please
contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–14768–000.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P–14768) in
the docket number field to access the
document. For assistance, contact FERC
Online Support.
Dated: April 22, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016–09937 Filed 4–27–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14767–000]
Energy Resources USA INC.;Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
April 22, 2016.
On March 11, 2016, the Energy
Resources USA Inc. filed an application
for a preliminary permit under section
4(f) of the Federal Power Act proposing
to study the feasibility of the proposed
Monroe Lake Dam Hydroelectric Project
No. 14767–000, to be located at the
existing Mississinewa Lake Dam on the
Salt Creek River, near the town of
Bloomington, in Monroe County,
Indiana. The Monroe Lake Dam is
owned by the United States government
and operated by the U.S. Army Corps of
Engineers, Louisville District.
The proposed project would consist
of: (1) A new 15-foot by 10-foot by 90foot-long concrete conduit; (2) a new 98foot by 45-foot reinforced concrete
powerhouse containing two 2-megawatt
(MW) vertical Kaplan turbine-generators
having a total combined generating
capacity of 4 MW; (3) a new 300-footlong by 95-foot-wide tailrace; (4) a new
60-foot-long by 50-foot-wide substation
with a 5-mega-volt-ampere 4.16/69kilovolt three-phase step-up
transformer; (5) a new 3-mile-long, 69kilovolt transmission line; and (6)
appurtenant facilities. The project
E:\FR\FM\28APN1.SGM
28APN1
Agencies
[Federal Register Volume 81, Number 82 (Thursday, April 28, 2016)]
[Notices]
[Pages 25391-25392]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-09935]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2622-012]
Turners Falls Hydro, LLC; Notice of Intent To File License
Application, Filing of Pre-Application Document, Approving use of the
Traditional Licensing Process
a. Type of Filing: Notice of Intent To File License Application and
Request To Use the Traditional Licensing Process.
b. Project No.: 2622-012.
c. Date Filed: February 26, 2016.
d. Submitted By: Turners Falls Hydro, LLC (Turners Falls Hydro).
e. Name of Project: Turners Falls Hydro Project.
f. Location: On the Connecticut River in Franklin County,
Massachusetts. No federal lands are occupied by the project works or
located within the project boundary.
g. Filed Pursuant to: 18 CFR 5.3 of the Commission's regulations.
h. Potential Applicant Contact: Peter Clarke, Turners Falls Hydro,
LLC, P.O. Box 149, Hamilton, MA 01936; (978) 468-3999.
i. FERC Contact: Bill Connelly at (202) 502-8587; or email at
william.connelly@ferc.gov.
j. Turners Falls Hydro filed its request to use the Traditional
Licensing Process on February 26, 2016. Turners Falls Hydro provided
public notice of its request on March 3 and March 10, 2016. In a letter
dated April 22, 2016, the Director of the Division of Hydropower
Licensing approved Turners Falls Hydro's request to use the Traditional
Licensing Process.
k. With this notice, we are initiating informal consultation with
the U.S. Fish and Wildlife Service and NOAA Fisheries under section 7
of the
[[Page 25392]]
Endangered Species Act and the joint agency regulations there under at
50 CFR part 402 and implementing regulations at 50 CFR 600.920. We are
also initiating consultation with the Massachusetts State Historic
Preservation Officer, as required by section 106, National Historic
Preservation Act, and the implementing regulations of the Advisory
Council on Historic Preservation at 36 CFR 800.2.
l. Turners Falls Hydro filed a Pre-Application Document (PAD;
including a proposed process plan and schedule) with the Commission,
pursuant to 18 CFR 5.6 of the Commission's regulations.
m. A copy of the PAD is available for electronic review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site (https://www.ferc.gov), using the ``eLibrary''
link. Enter the docket number, excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll
free), or (202) 502-8659 (TTY). A copy is also available for inspection
and reproduction at the address in paragraph h.
n. The licensee states its unequivocal intent to submit an
application for a new license for Project No. 2622. Pursuant to 18 CFR
16.8, 16.9, and 16.10 each application for a new license and any
competing license applications must be filed with the Commission at
least 24 months prior to the expiration of the existing license. All
applications for license for this project must be filed by February 28,
2019.
o. Register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filing and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
Dated: April 22, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016-09935 Filed 4-27-16; 8:45 am]
BILLING CODE 6717-01-P