Advisory Committee on Reactor Safeguards; Notice of Meeting, 24139-24140 [2016-09561]
Download as PDF
asabaliauskas on DSK3SPTVN1PROD with NOTICES
Federal Register / Vol. 81, No. 79 / Monday, April 25, 2016 / Notices
assurance that adequate funds will be
available to stabilize conditions and
cover onsite cleanup costs associated
with site decontamination, following an
accident that results in the release of a
significant amount of radiological
material. Because VY is permanently
shut down and defueled, it is no longer
possible for the radiological
consequences of design-basis accidents
or other credible events at VY to exceed
the limits of the EPA PAGs at the
exclusion area boundary. The licensee
has evaluated the consequences of
highly unlikely, beyond-design-basis
conditions involving a loss of coolant
from the SFP. The analyses show that
after April 15, 2016, the likelihood of
such an event leading to a large
radiological release is negligible. The
NRC staff’s evaluation of the licensee’s
analyses confirm this conclusion.
The NRC staff also finds that the
licensee’s proposed $50 million level of
onsite insurance is consistent with the
bounding cleanup and decontamination
cost, as discussed in SECY–96–256, to
account for the hypothetical rupture of
a large liquid radiological waste tank at
the VY site, should such an event occur.
Therefore, the staff concludes that the
application of the current requirements
in 10 CFR 50.54(w)(1) to maintain $1.06
billion in onsite insurance coverage is
not necessary to achieve the underlying
purpose of the rule for the permanently
shutdown and defueled VY reactor.
Under 10 CFR 50.12(a)(2)(iii), special
circumstances are present whenever
compliance would result in undue
hardship or other costs that are
significantly in excess of those
contemplated when the regulation was
adopted, or that are significantly in
excess of those incurred by others
similarly situated.
The NRC staff concludes that if the
licensee was required to continue to
maintain an onsite insurance level of
$1.06 billion, the associated insurance
premiums would be in excess of those
necessary and commensurate with the
radiological contamination risks posed
by the site. In addition, such insurance
levels would be significantly in excess
of other decommissioning reactor
facilities that have been granted similar
exemptions by the NRC.
The NRC staff finds that compliance
with the existing rule would result in an
undue hardship or other costs that are
significantly in excess of those
contemplated when the regulation was
adopted and are significantly in excess
of those incurred by others similarly
situated.
Therefore, the special circumstances
required by 10 CFR 50.12(a)(2)(ii) and
10 CFR 50.12(a)(2)(iii) exist.
VerDate Sep<11>2014
19:02 Apr 22, 2016
Jkt 238001
E. Environmental Considerations
The NRC approval of the exemption
to insurance or indemnity requirements
belongs to a category of actions that the
Commission, by rule or regulation, has
declared to be a categorical exclusion,
after first finding that the category of
actions does not individually or
cumulatively have a significant effect on
the human environment. Specifically,
the exemption is categorically excluded
from further analysis under
§ 51.22(c)(25).
Under 10 CFR 51.22(c)(25), granting
of an exemption from the requirements
of any regulation of Chapter I to 10 CFR
is a categorical exclusion provided that
(i) there is no significant hazards
consideration; (ii) there is no significant
change in the types or significant
increase in the amounts of any effluents
that may be released offsite; (iii) there is
no significant increase in individual or
cumulative public or occupational
radiation exposure; (iv) there is no
significant construction impact; (v)
there is no significant increase in the
potential for or consequences from
radiological accidents; and (vi) the
requirements from which an exemption
is sought involve: surety, insurance, or
indemnity requirements.
The Director, Division of
Decommissioning, Uranium Recovery
and Waste Programs, Office of Nuclear
Material Safety and Safeguards, has
determined that approval of the
exemption request involves no
significant hazards consideration
because reducing the licensee’s onsite
property damage insurance for VY does
not (1) involve a significant increase in
the probability or consequences of an
accident previously evaluated; or (2)
create the possibility of a new or
different kind of accident from any
accident previously evaluated; or (3)
involve a significant reduction in a
margin of safety. The exempted
financial protection regulation is
unrelated to the operation of VY.
Accordingly, there is no significant
change in the types or significant
increase in the amounts of any effluents
that may be released offsite; and no
significant increase in individual or
cumulative public or occupational
radiation exposure.
In addition, the exempted regulation
is not associated with construction, so
there is no significant construction
impact. The exempted regulation does
not concern the source term (i.e.,
potential amount of radiation in an
accident), nor mitigation. Therefore,
there is no significant increase in the
potential for, or consequences of, a
radiological accident. In addition, there
PO 00000
Frm 00088
Fmt 4703
Sfmt 4703
24139
would be no significant impacts to
biota, water resources, historic
properties, cultural resources, or
socioeconomic conditions in the region.
Moreover, the requirement for onsite
property damage insurance involves
surety, insurance, and indemnity
matters. Accordingly, the exemption
request meets the eligibility criteria for
categorical exclusion set forth in 10 CFR
51.22(c)(25). Therefore, pursuant to 10
CFR 51.22(b) and 51.22(c)(25), no
environmental impact statement or
environmental assessment need be
prepared in connection with the
approval of this exemption request.
IV. Conclusions
Accordingly, the Commission has
determined that, pursuant to 10 CFR
50.12(a), the exemption from
50.54(w)(1) is authorized by law, will
not present an undue risk to the public
health and safety, and is consistent with
the common defense and security. In
addition, special circumstances are
present as set forth in 10 CFR 50.12.
Therefore, the Commission hereby
grants VY an exemption from the
requirements of 10 CFR 50.54(w)(1). The
exemption will permit VY to lower
minimum required onsite insurance to
$50 million no earlier than April 15,
2016.
The exemption is effective upon
issuance.
Dated at Rockville, Maryland, this 15th day
of April, 2016.
For the Nuclear Regulatory Commission.
John R. Tappert,
Director, Division of Decommissioning,
Uranium Recovery and Waste Programs,
Office of Nuclear Material Safety and
Safeguards.
[FR Doc. 2016–09558 Filed 4–22–16; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
Advisory Committee on Reactor
Safeguards; Notice of Meeting
In accordance with the purposes of
Sections 29 and 182b of the Atomic
Energy Act (42 U.S.C. 2039, 2232b), the
Advisory Committee on Reactor
Safeguards (ACRS) will hold a meeting
on May 5–7, 2016, 11545 Rockville Pike,
Rockville, Maryland.
Thursday, May 5, 2016, Conference
Room T2–B1, 11545 Rockville Pike,
Rockville, Maryland
8:30 a.m.–8:35 a.m.: Opening Remarks
by the ACRS Chairman (Open)—
The ACRS Chairman will make
E:\FR\FM\25APN1.SGM
25APN1
24140
Federal Register / Vol. 81, No. 79 / Monday, April 25, 2016 / Notices
asabaliauskas on DSK3SPTVN1PROD with NOTICES
opening remarks regarding the
conduct of the meeting.
8:35 a.m.–10:00 a.m.: Additional
Guidance to Support the Closure
Plan for the Reevaluation of
Flooding Hazards (Open)—The
Committee will hear presentations
by and hold discussions with
representatives of the NRC staff
regarding implementation of the
mitigating strategies and flooding
hazards reevaluation action plan.
10:15 a.m.–11:45 a.m.: Review of
Fukushima Tier 2 Group 3
Recommendation Regarding Other
Natural Hazards Screening
Evaluations (Open)—The
Committee will hear presentations
by and hold discussions with
representatives of the NRC staff
regarding the reviews of other
natural hazards screening
evaluations.
1:00 p.m.–3:00 p.m.: NuScale Topical
Report TR–0515–13952, Risk
Significance Determination—Use of
RAW Importance Measure (Open/
Closed)—The Committee will hear
presentations by and hold
discussions with representatives of
the NRC staff regarding the safety
evaluation associated with the
subject NuScale topical report.
Note: A portion of this meeting may
be closed in order to discuss and
protect information designated as
proprietary, pursuant to 5 U.S.C.
552b(c)(4).
3:00 p.m.–6:00 p.m.: Preparation of
ACRS Reports (Open/Closed)—The
Committee will discuss proposed
ACRS reports on matters discussed
during this meeting. Note: A
portion of this meeting may be
closed in order to discuss and
protect information designated as
proprietary, pursuant to 5 U.S.C.
552b(c)(4).
Friday, May 6, 2016, Conference Room
T2–B1, 11545 Rockville Pike, Rockville,
Maryland
8:35 a.m.–10:00 a.m.: Future ACRS
Activities/Report of the Planning
and Procedures Subcommittee
(Open/Closed)—The Committee
will discuss the recommendations
of the Planning and Procedures
Subcommittee regarding items
proposed for consideration by the
Full Committee during future ACRS
Meetings, and matters related to the
conduct of ACRS business,
including anticipated workload and
member assignments. Note: A
portion of this meeting may be
closed pursuant to 5 U.S.C.
552b(c)(2) and (6) to discuss
organizational and personnel
VerDate Sep<11>2014
19:02 Apr 22, 2016
Jkt 238001
matters that relate solely to internal
personnel rules and practices of
ACRS, and information the release
of which would constitute a clearly
unwarranted invasion of personal
privacy.
10:00 a.m.–10:15 a.m.: Reconciliation of
ACRS Comments and
Recommendations (Open)—The
Committee will discuss the
responses from the NRC Executive
Director for Operations to
comments and recommendations
included in recent ACRS reports
and letters.
10:30 a.m.–6:00 p.m.: Preparation of
ACRS Reports (Open/Closed)—The
Committee will continue its
discussion of proposed ACRS
reports discussed during this
meeting. Note: A portion of this
meeting may be closed in order to
discuss and protect information
designated as proprietary, pursuant
to 5 U.S.C. 552b(c)(4).
Saturday, May 7, 2016, Conference
Room T2–B1, 11545 Rockville Pike,
Rockville, Maryland
8:30 a.m.–11:30 a.m.: Preparation of
ACRS Reports (Open/Closed)—The
Committee will continue its
discussion of proposed ACRS
reports. Note: A portion of this
meeting may be closed in order to
discuss and protect information
designated as proprietary, pursuant
to 5 U.S.C. 552b(c)(4).
11:30 a.m.–12:00 p.m.: Miscellaneous
(Open)—The Committee will
continue its discussion related to
the conduct of Committee activities
and specific issues that were not
completed during previous
meetings.
Procedures for the conduct of and
participation in ACRS meetings were
published in the Federal Register on
October 21, 2015 (80 FR 63846). In
accordance with those procedures, oral
or written views may be presented by
members of the public, including
representatives of the nuclear industry.
Persons desiring to make oral statements
should notify Quynh Nguyen, Cognizant
ACRS Staff (Telephone: 301–415–5844,
Email: Quynh.Nguyen@nrc.gov), 5 days
before the meeting, if possible, so that
appropriate arrangements can be made
to allow necessary time during the
meeting for such statements. In view of
the possibility that the schedule for
ACRS meetings may be adjusted by the
Chairman as necessary to facilitate the
conduct of the meeting, persons
planning to attend should check with
the Cognizant ACRS staff if such
rescheduling would result in major
inconvenience.
PO 00000
Frm 00089
Fmt 4703
Sfmt 9990
Thirty-five hard copies of each
presentation or handout should be
provided 30 minutes before the meeting.
In addition, one electronic copy of each
presentation should be emailed to the
Cognizant ACRS Staff one day before
meeting. If an electronic copy cannot be
provided within this timeframe,
presenters should provide the Cognizant
ACRS Staff with a CD containing each
presentation at least 30 minutes before
the meeting.
In accordance with Subsection 10(d)
of Public Law 92–463 and 5 U.S.C.
552b(c), certain portions of this meeting
may be closed, as specifically noted
above. Use of still, motion picture, and
television cameras during the meeting
may be limited to selected portions of
the meeting as determined by the
Chairman. Electronic recordings will be
permitted only during the open portions
of the meeting.
ACRS meeting agendas, meeting
transcripts, and letter reports are
available through the NRC Public
Document Room at pdr.resource@
nrc.gov, or by calling the PDR at 1–800–
397–4209, or from the Publicly
Available Records System (PARS)
component of NRC’s document system
(ADAMS) which is accessible from the
NRC Web site at https://www.nrc.gov/
reading-rm/adams.html or https://
www.nrc.gov/reading-rm/doccollections/ACRS/.
Video teleconferencing service is
available for observing open sessions of
ACRS meetings. Those wishing to use
this service should contact Mr. Theron
Brown, ACRS Audio Visual Technician
(301–415–8066), between 7:30 a.m. and
3:45 p.m. (ET), at least 10 days before
the meeting to ensure the availability of
this service. Individuals or
organizations requesting this service
will be responsible for telephone line
charges and for providing the
equipment and facilities that they use to
establish the video teleconferencing
link. The availability of video
teleconferencing services is not
guaranteed.
Dated at Rockville, Maryland, this 19th day
of April, 2016.
For the Nuclear Regulatory Commission.
Andrew L. Bates,
Advisory Committee Management Officer.
[FR Doc. 2016–09561 Filed 4–22–16; 8:45 am]
BILLING CODE 7590–01–P
E:\FR\FM\25APN1.SGM
25APN1
Agencies
[Federal Register Volume 81, Number 79 (Monday, April 25, 2016)]
[Notices]
[Pages 24139-24140]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-09561]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
Advisory Committee on Reactor Safeguards; Notice of Meeting
In accordance with the purposes of Sections 29 and 182b of the
Atomic Energy Act (42 U.S.C. 2039, 2232b), the Advisory Committee on
Reactor Safeguards (ACRS) will hold a meeting on May 5-7, 2016, 11545
Rockville Pike, Rockville, Maryland.
Thursday, May 5, 2016, Conference Room T2-B1, 11545 Rockville Pike,
Rockville, Maryland
8:30 a.m.-8:35 a.m.: Opening Remarks by the ACRS Chairman (Open)--The
ACRS Chairman will make
[[Page 24140]]
opening remarks regarding the conduct of the meeting.
8:35 a.m.-10:00 a.m.: Additional Guidance to Support the Closure Plan
for the Reevaluation of Flooding Hazards (Open)--The Committee will
hear presentations by and hold discussions with representatives of the
NRC staff regarding implementation of the mitigating strategies and
flooding hazards reevaluation action plan.
10:15 a.m.-11:45 a.m.: Review of Fukushima Tier 2 Group 3
Recommendation Regarding Other Natural Hazards Screening Evaluations
(Open)--The Committee will hear presentations by and hold discussions
with representatives of the NRC staff regarding the reviews of other
natural hazards screening evaluations.
1:00 p.m.-3:00 p.m.: NuScale Topical Report TR-0515-13952, Risk
Significance Determination--Use of RAW Importance Measure (Open/
Closed)--The Committee will hear presentations by and hold discussions
with representatives of the NRC staff regarding the safety evaluation
associated with the subject NuScale topical report. Note: A portion of
this meeting may be closed in order to discuss and protect information
designated as proprietary, pursuant to 5 U.S.C. 552b(c)(4).
3:00 p.m.-6:00 p.m.: Preparation of ACRS Reports (Open/Closed)--The
Committee will discuss proposed ACRS reports on matters discussed
during this meeting. Note: A portion of this meeting may be closed in
order to discuss and protect information designated as proprietary,
pursuant to 5 U.S.C. 552b(c)(4).
Friday, May 6, 2016, Conference Room T2-B1, 11545 Rockville Pike,
Rockville, Maryland
8:35 a.m.-10:00 a.m.: Future ACRS Activities/Report of the Planning and
Procedures Subcommittee (Open/Closed)--The Committee will discuss the
recommendations of the Planning and Procedures Subcommittee regarding
items proposed for consideration by the Full Committee during future
ACRS Meetings, and matters related to the conduct of ACRS business,
including anticipated workload and member assignments. Note: A portion
of this meeting may be closed pursuant to 5 U.S.C. 552b(c)(2) and (6)
to discuss organizational and personnel matters that relate solely to
internal personnel rules and practices of ACRS, and information the
release of which would constitute a clearly unwarranted invasion of
personal privacy.
10:00 a.m.-10:15 a.m.: Reconciliation of ACRS Comments and
Recommendations (Open)--The Committee will discuss the responses from
the NRC Executive Director for Operations to comments and
recommendations included in recent ACRS reports and letters.
10:30 a.m.-6:00 p.m.: Preparation of ACRS Reports (Open/Closed)--The
Committee will continue its discussion of proposed ACRS reports
discussed during this meeting. Note: A portion of this meeting may be
closed in order to discuss and protect information designated as
proprietary, pursuant to 5 U.S.C. 552b(c)(4).
Saturday, May 7, 2016, Conference Room T2-B1, 11545 Rockville Pike,
Rockville, Maryland
8:30 a.m.-11:30 a.m.: Preparation of ACRS Reports (Open/Closed)--The
Committee will continue its discussion of proposed ACRS reports. Note:
A portion of this meeting may be closed in order to discuss and protect
information designated as proprietary, pursuant to 5 U.S.C. 552b(c)(4).
11:30 a.m.-12:00 p.m.: Miscellaneous (Open)--The Committee will
continue its discussion related to the conduct of Committee activities
and specific issues that were not completed during previous meetings.
Procedures for the conduct of and participation in ACRS meetings
were published in the Federal Register on October 21, 2015 (80 FR
63846). In accordance with those procedures, oral or written views may
be presented by members of the public, including representatives of the
nuclear industry. Persons desiring to make oral statements should
notify Quynh Nguyen, Cognizant ACRS Staff (Telephone: 301-415-5844,
Email: Quynh.Nguyen@nrc.gov), 5 days before the meeting, if possible,
so that appropriate arrangements can be made to allow necessary time
during the meeting for such statements. In view of the possibility that
the schedule for ACRS meetings may be adjusted by the Chairman as
necessary to facilitate the conduct of the meeting, persons planning to
attend should check with the Cognizant ACRS staff if such rescheduling
would result in major inconvenience.
Thirty-five hard copies of each presentation or handout should be
provided 30 minutes before the meeting. In addition, one electronic
copy of each presentation should be emailed to the Cognizant ACRS Staff
one day before meeting. If an electronic copy cannot be provided within
this timeframe, presenters should provide the Cognizant ACRS Staff with
a CD containing each presentation at least 30 minutes before the
meeting.
In accordance with Subsection 10(d) of Public Law 92-463 and 5
U.S.C. 552b(c), certain portions of this meeting may be closed, as
specifically noted above. Use of still, motion picture, and television
cameras during the meeting may be limited to selected portions of the
meeting as determined by the Chairman. Electronic recordings will be
permitted only during the open portions of the meeting.
ACRS meeting agendas, meeting transcripts, and letter reports are
available through the NRC Public Document Room at pdr.resource@nrc.gov,
or by calling the PDR at 1-800-397-4209, or from the Publicly Available
Records System (PARS) component of NRC's document system (ADAMS) which
is accessible from the NRC Web site at https://www.nrc.gov/reading-rm/adams.html or https://www.nrc.gov/reading-rm/doc-collections/ACRS/.
Video teleconferencing service is available for observing open
sessions of ACRS meetings. Those wishing to use this service should
contact Mr. Theron Brown, ACRS Audio Visual Technician (301-415-8066),
between 7:30 a.m. and 3:45 p.m. (ET), at least 10 days before the
meeting to ensure the availability of this service. Individuals or
organizations requesting this service will be responsible for telephone
line charges and for providing the equipment and facilities that they
use to establish the video teleconferencing link. The availability of
video teleconferencing services is not guaranteed.
Dated at Rockville, Maryland, this 19th day of April, 2016.
For the Nuclear Regulatory Commission.
Andrew L. Bates,
Advisory Committee Management Officer.
[FR Doc. 2016-09561 Filed 4-22-16; 8:45 am]
BILLING CODE 7590-01-P