National Fuel Gas Supply Corporation; Notice of Application, 23476-23477 [2016-09227]
Download as PDF
23476
Federal Register / Vol. 81, No. 77 / Thursday, April 21, 2016 / Notices
Filed Date: 4/15/16.
Accession Number: 20160415–5143.
Comments Due: 5 p.m. ET 5/6/16.
Docket Numbers: ER16–1425–000.
Applicants: Northern States Power
Company, a Wisconsin corporation.
Description: Tariff Cancellation:
2016–4–15_NSPW Cancel Clarity Tariff
ID Filing to be effective 4/15/2016.
Filed Date: 4/15/16.
Accession Number: 20160415–5144.
Comments Due: 5 p.m. ET 5/6/16.
Docket Numbers: ER16–1426–000.
Applicants: Southwestern Public
Service Company.
Description: Tariff Cancellation:
2016–4–15_SPS Cancel Clarity Tariff ID
Filing to be effective 4/15/2016.
Filed Date: 4/15/16.
Accession Number: 20160415–5150.
Comments Due: 5 p.m. ET 5/6/16.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: April 15, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016–09224 Filed 4–20–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP16–125–000]
jstallworth on DSK7TPTVN1PROD with NOTICES
National Fuel Gas Supply Corporation;
Notice of Application
Take notice that on April 4, 2016,
National Fuel Gas Supply Corporation
(National Fuel), 6363 Main Street,
Williamsville, New York 14221, filed an
application pursuant to sections 7(b)
and 7(c) of the Natural Gas Act (NGA),
and Part 157 of the Commission’s
regulations requesting authority to
construct, replace, and abandon existing
VerDate Sep<11>2014
13:27 Apr 20, 2016
Jkt 238001
pipelines and modify compressor
facilities along the T2K, TNY, and KNY
natural gas pipelines, all as more fully
set forth in the application which is on
file with the Commission and open to
public inspection. The cost for the
proposed project work is $29,382,602.
Any questions concerning this
application should be directed to Laura
P. Berloth, Attorney, National Fuel Gas
Supply Corporation, 6363 Main Street,
Williamsville, New York 14221–5887,
by phone at (716) 857–7001, by fax at
(716) 857–7206, or by email at berlothl@
natfuel.com.
Specifically, National Fuel seeks to;
(i) construct and operate 1.2 miles of
new 20-inch-diameter pipeline, adding
2,600 dekatherms per day (Dth/d) of
new firm service capacity (Line T2K
Install); (ii) replace approximately 6.7
miles of 20-inch-diameter bare steel
pipeline with 7.0 miles of new 24-inchdiameter coated pipeline (Line TNY
Replacement); and (iii) abandon
approximately 14.9 miles of 20-inchdiameter bare steel pipeline (Line KNY
Abandonment), all located in Erie
County, New York.
The filing is available for review at
the Commission in the Public Reference
Room or may be viewed on the
Commission’s Web site web at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
Pursuant to section 157.9 of the
Commission’s rules (18 CFR 157.9),
within 90 days of this Notice, the
Commission staff will either: Complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule will serve to notify
federal and state agencies of the timing
for the completion of all necessary
reviews, and the subsequent need to
complete all federal authorizations
within 90 days of the date of issuance
of the Commission staff’s FEIS or EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
to the proceedings for this project
should, on or before the comment date
stated below, file with the Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
5 copies of filings made with the
Commission and must mail a copy to
the applicant and to every other party in
the proceeding. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenters will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically should submit an original
E:\FR\FM\21APN1.SGM
21APN1
Federal Register / Vol. 81, No. 77 / Thursday, April 21, 2016 / Notices
and 7 copies of the protest or
intervention to the Federal Energy
regulatory Commission, 888 First Street
NE., Washington, DC 20426.
Comment Date: 5:00 p.m. Eastern
Time on May 6, 2016.
Dated: April 15, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016–09227 Filed 4–20–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 7656–012]
jstallworth on DSK7TPTVN1PROD with NOTICES
John A. Dodson; Notice of Proposed
Termination of License by Implied
Surrender and Soliciting Comments,
Protests and Motions To Intervene
Take notice that the following
hydroelectric proceeding has been
initiated by the Commission:
a. Type of Proceeding: Proposed
Termination of License by Implied
Surrender.
b. Project No.: 7656–012.
c. Date Initiated: April 14, 2016.
d. Licensee: John A. Dodson.
e. Name and Location of Project:
Buttermilk Falls Hydroelectric Project
located on Buttermilk Falls Brook, in
Orange County, New York.
f. Filed Pursuant to: Standard Article
16.
g. Licensee Contact Information: Mr.
John A. Dodson, P.O. Box 221, Highland
Falls, New York 10928, Phone: (914)
446–7704.
h. FERC Contact: Mr. Ashish Desai,
(202) 502–8370, Ashish.Desai@ferc.gov.
i. Deadline for filing comments,
protests, and motions to intervene is 30
days from the issuance date of this
notice by the Commission. The
Commission strongly encourages
electronic filing. Please file comments,
protests, and motions to intervene using
the Commission’s eFiling system at
https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
VerDate Sep<11>2014
13:27 Apr 20, 2016
Jkt 238001
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–7656–012.
j. Description of Project Facilities: (1)
An 18-inch-high, 15-foot-long dam; (2)
an 18-inch-diameter, 400-foot-long PVC
penstock; (3) a powerhouse containing
two generating units for a total installed
capacity of 79 kilowatts; (4) a 300-footlong, 480-volt transmission line; and (5)
appurtenant facilities.
k. Description of Proceeding: The
licensee is in violation of standard
Article 16 of its license issued on June
24, 1986 (35 FERC ¶ 62,532). Article 16
states, in part: If the Licensee shall
abandon or discontinue good faith
operation of the project or refuse or
neglect to comply with the terms of the
license and the lawful orders of the
Commission mailed to the record
address of the Licensee or its agent, the
Commission will deem it to be the
intent of the Licensee to surrender the
license.
Commission records indicate that the
project has not been operated since the
fall of 2012 when heavy storms flooded
the powerhouse. Due to an ongoing
property rights dispute involving access
to and the use of lands needed for
project purposes, the licensee has been
reluctant to repair the project and return
it to service. In addition, the licensee
has not responded to several
Commission requests to file a plan and
schedule to restore project operation in
a timely manner.
l. This notice is available for review
and reproduction at the Commission in
the Public Reference Room, Room 2A,
888 First Street NE., Washington, DC
20426. The notice and other project
records may also be viewed on the
Commission’s Web site at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the Docket number (P–7656–012)
excluding the last three digits in the
docket number field to access the
notice. You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, call toll-free (866) 208–
3676 or email FERCOnlineSupport@
ferc.gov. For TTY, call (202) 502–8659.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, and
.214. In determining the appropriate
action to take, the Commission will
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
23477
consider all protests or other comments
filed, but only those who file a motion
to intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
o. Filing and Service of Responsive
Documents: Any filing must (1) bear in
all capital letters the title
‘‘COMMENTS,’’ ‘‘PROTEST,’’ or
‘‘MOTION TO INTERVENE’’ as
applicable; (2) set forth in the heading
the name of the applicant and the
project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. All
comments, motions to intervene, or
protests must set forth their evidentiary
basis and otherwise comply with the
requirements of 18 CFR 4.34(b). All
comments, protests, or motions to
intervene should relate to project works
which are the subject of the implied
surrender. A copy of any protest or
motion to intervene must be served
upon each representative of the
applicant specified in the particular
application. If an intervener files
comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency. A copy of all
other filings in reference to this
application must be accompanied by
proof of service on all persons listed in
the service list prepared by the
Commission in this proceeding in
accordance with 18 CFR 4.34(b) and
385.2010.
Dated: April 15, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016–09228 Filed 4–20–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP16–121–000; PF15–28–000]
National Grid LNG LLC; Notice of
Application
Take notice that on April 1, 2016,
National Grid LNG LLC (NGLNG),
having its principal place of business at
40 Sylvan Rd, Waltham, MA 02451,
E:\FR\FM\21APN1.SGM
21APN1
Agencies
[Federal Register Volume 81, Number 77 (Thursday, April 21, 2016)]
[Notices]
[Pages 23476-23477]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-09227]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP16-125-000]
National Fuel Gas Supply Corporation; Notice of Application
Take notice that on April 4, 2016, National Fuel Gas Supply
Corporation (National Fuel), 6363 Main Street, Williamsville, New York
14221, filed an application pursuant to sections 7(b) and 7(c) of the
Natural Gas Act (NGA), and Part 157 of the Commission's regulations
requesting authority to construct, replace, and abandon existing
pipelines and modify compressor facilities along the T2K, TNY, and KNY
natural gas pipelines, all as more fully set forth in the application
which is on file with the Commission and open to public inspection. The
cost for the proposed project work is $29,382,602.
Any questions concerning this application should be directed to
Laura P. Berloth, Attorney, National Fuel Gas Supply Corporation, 6363
Main Street, Williamsville, New York 14221-5887, by phone at (716) 857-
7001, by fax at (716) 857-7206, or by email at berlothl@natfuel.com.
Specifically, National Fuel seeks to; (i) construct and operate 1.2
miles of new 20-inch-diameter pipeline, adding 2,600 dekatherms per day
(Dth/d) of new firm service capacity (Line T2K Install); (ii) replace
approximately 6.7 miles of 20-inch-diameter bare steel pipeline with
7.0 miles of new 24-inch-diameter coated pipeline (Line TNY
Replacement); and (iii) abandon approximately 14.9 miles of 20-inch-
diameter bare steel pipeline (Line KNY Abandonment), all located in
Erie County, New York.
The filing is available for review at the Commission in the Public
Reference Room or may be viewed on the Commission's Web site web at
https://www.ferc.gov using the ``eLibrary'' link. Enter the docket
number excluding the last three digits in the docket number field to
access the document. For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call toll-free, (886) 208-3676 or TYY,
(202) 502-8659.
Pursuant to section 157.9 of the Commission's rules (18 CFR 157.9),
within 90 days of this Notice, the Commission staff will either:
Complete its environmental assessment (EA) and place it into the
Commission's public record (eLibrary) for this proceeding or issue a
Notice of Schedule for Environmental Review. If a Notice of Schedule
for Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the final environmental impact statement (FEIS) or EA for this
proposal. The filing of the EA in the Commission's public record for
this proceeding or the issuance of a Notice of Schedule will serve to
notify federal and state agencies of the timing for the completion of
all necessary reviews, and the subsequent need to complete all federal
authorizations within 90 days of the date of issuance of the Commission
staff's FEIS or EA.
There are two ways to become involved in the Commission's review of
this project. First, any person wishing to obtain legal status by
becoming a party to the proceedings for this project should, on or
before the comment date stated below, file with the Federal Energy
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a
motion to intervene in accordance with the requirements of the
Commission's Rules of Practice and Procedure (18 CFR 385.214 or
385.211) and the Regulations under the NGA (18 CFR 157.10). A person
obtaining party status will be placed on the service list maintained by
the Secretary of the Commission and will receive copies of all
documents filed by the applicant and by all other parties. A party must
submit 5 copies of filings made with the Commission and must mail a
copy to the applicant and to every other party in the proceeding. Only
parties to the proceeding can ask for court review of Commission orders
in the proceeding.
However, a person does not have to intervene in order to have
comments considered. The second way to participate is by filing with
the Secretary of the Commission, as soon as possible, an original and
two copies of comments in support of or in opposition to this project.
The Commission will consider these comments in determining the
appropriate action to be taken, but the filing of a comment alone will
not serve to make the filer a party to the proceeding. The Commission's
rules require that persons filing comments in opposition to the project
provide copies of their protests only to the party or parties directly
involved in the protest.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commenters will be
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with the Commission's environmental review process.
Environmental commenters will not be required to serve copies of filed
documents on all other parties. However, the non-party commenters will
not receive copies of all documents filed by other parties or issued by
the Commission (except for the mailing of environmental documents
issued by the Commission) and will not have the right to seek court
review of the Commission's final order.
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the ``eFiling'' link
at https://www.ferc.gov. Persons unable to file electronically should
submit an original
[[Page 23477]]
and 7 copies of the protest or intervention to the Federal Energy
regulatory Commission, 888 First Street NE., Washington, DC 20426.
Comment Date: 5:00 p.m. Eastern Time on May 6, 2016.
Dated: April 15, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016-09227 Filed 4-20-16; 8:45 am]