Federal Register / Vol. 81, No. 75 / Tuesday, April 19, 2016 / Notices
procurement of a Horizontal Lifeline
Fall Protection Maintenance Tie Back
System (System), the Federal Transit
Administration (FTA) hereby waives its
Buy America requirements, finding that
the materials for which the waiver is
requested are not produced in the
United States in sufficient and
reasonably available quantities and of
satisfactory quality. This waiver is
limited to a single procurement by IPTC
for the System.
DATES: This waiver is effective
immediately.
FOR FURTHER INFORMATION CONTACT:
Laura Ames, FTA Attorney-Advisor, at
(202) 366–2743 or Laura.Ames@dot.gov.
SUPPLEMENTARY INFORMATION: The
purpose of this notice is to announce
that FTA has granted a Buy America
non-availability waiver for IPTC for the
procurement of a Horizontal Lifeline
Fall Protection Maintenance Tie Back
System under 49 U.S.C. 5323(j)(2)(B)
and 49 CFR 661.7(c).
With certain exceptions, FTA’s Buy
America requirements prevent FTA
from obligating an amount that may be
appropriated to carry out its program for
a project unless ‘‘the steel, iron, and
manufactured goods used in the project
are produced in the United States.’’ 49
U.S.C. 5323(j)(1). A manufactured
product is considered produced in the
United States if: (1) All of the
manufacturing processes for the product
take place in the United States; and (2)
all of the components of the product are
of U.S. origin. A component is
considered of U.S. origin if it is
manufactured in the United States,
regardless of the origin of its
subcomponents. 49 CFR 661.5(d). If,
however, FTA determines that ‘‘the
steel, iron, and goods produced in the
United States are not produced in a
sufficient and reasonably available
amount or are not of a satisfactory
quality,’’ then FTA may issue a nonavailability waiver. 49 U.S.C.
5323(j)(2)(B); 49 CFR 661.7(c). ‘‘It will
be presumed that the conditions exist to
grant this non-availability waiver if no
responsive and responsible bid is
received offering an item produced in
the United States.’’ 49 CFR 661.7(c)(1).
IPTC is constructing a Downtown
Transit Center (DTC) in Indianapolis,
Indiana, that will serve as the hub for
public transit. It will include a large
indoor public waiting area and bus bays
while serving pedestrians, cyclists, and
bus riders. Per Occupational Safety and
Health Administration (OSHA)
regulations, IPTC is required to provide
fall protection for employees performing
maintenance on the new building. IPTC
entered into a contract with Weddle
VerDate Sep<11>2014
18:02 Apr 18, 2016
Jkt 238001
Bros. Building Group (WBBG) in early
September 2014 for the construction of
the DTC. WBBG certified in good faith
that it would comply with Buy America.
As part of the project, IPTC issued an
RFP for the complete design, supply,
and installation of a fall protection
maintenance tie-back system to
safeguard personnel to include all cable,
intermediate brackets, end terminations,
and modifications of structural steel as
required for supplementary support of
stanchions, user equipment, and
attachment to roof structure for a
complete and working fall protection
maintenance tie-back system.
Two firms, American Anchor and ProBel Group, responded to the RFP, but
did not certify compliance with the Buy
America regulations. The cables and
tensioning system are not manufactured
domestically for Pro-Bel. The hands-free
set ups are not manufactured
domestically for American Anchor.
IPTC submitted a waiver request based
on non-availability under 49 CFR
661.7(c). FTA also conducted a scouting
search for the fall arrest system through
its Interagency Agreement with the U.S.
Department of Commerce’s National
Institute of Standards and Technology
(NIST). The scouting search did not
identify a domestic manufacturer of a
system that met IPTC’s specifications.
On Tuesday March 22, 2016, and in
accordance with 49 U.S.C. 5323(j)(3)(A),
FTA published a notice in the Federal
Register announcing the Buy America
waiver request (81 FR 15411), seeking
comment from all interested parties,
including potential vendors and
suppliers. The comment period closed
on March 29, 2016, and no comments
were received.
Therefore, based on the information
supplied in support of IPTC’s request
for a Buy America waiver for the
System, including NIST’s inability to
locate a domestic manufacturer that
currently produces a similar system and
the lack of any comments, FTA hereby
waives its Buy America requirements
for the Horizontal Lifeline Fall
Protection Maintenance Tie Back
System on the grounds that the
manufactured product is not available
in the U.S. This waiver is limited to a
single procurement for the Horizontal
Lifeline Fall Protection Maintenance Tie
Back System by IPTC.
Issued on April 14, 2016.
Dana Nifosi,
Deputy Chief Counsel.
[FR Doc. 2016–08990 Filed 4–18–16; 8:45 am]
BILLING CODE 4910–57–P
PO 00000
Frm 00112
Fmt 4703
Sfmt 4703
23075
DEPARTMENT OF TRANSPORTATION
Federal Transit Administration
[Docket No. FTA–2016–0006]
Notice of Buy America Waiver for Steel
Excavator With a Continuous Wield
Platform
AGENCY:
Federal Transit Administration,
DOT.
ACTION:
Notice of Buy America waiver.
In response to the request of
Metro North Railroad (MNR) for a Buy
America non-availability waiver for the
procurement of a steel excavator with a
continuous wield platform (CWP), the
Federal Transit Administration (FTA)
hereby waives its Buy America
requirements, finding that the materials
for which the waiver is requested are
not produced in the United States in
sufficient and reasonably available
quantities and of satisfactory quality.
This waiver is limited to a single
procurement by MNR for the CWP.
DATES: This waiver is effective
immediately.
SUMMARY:
FOR FURTHER INFORMATION CONTACT:
Laura Ames, FTA Attorney-Advisor, at
(202) 366–2743 or laura.ames@dot.gov.
SUPPLEMENTARY INFORMATION: The
purpose of this notice is to announce
that FTA has granted a Buy America
non-availability waiver for MNR for the
procurement of a steel excavator with a
CWP, under 49 U.S.C. 5323(j)(2)(B) and
49 CFR 661.7(c).
With certain exceptions, FTA’s Buy
America requirements prevent FTA
from obligating an amount that may be
appropriated to carry out its program for
a project unless ‘‘the steel, iron, and
manufactured goods used in the project
are produced in the United States.’’ 49
U.S.C. 5323(j)(1). Under 49 U.S.C.
5323(j)(2)(C), rolling stock must contain
more than 60 percent domestic content
and final assembly must occur in the
U.S. The CWP is subject to the rolling
stock requirements. 49 CFR 661.3.
MNR operates commuter rail service
spanning 787 track miles. MRN has a
large length of track along the shore line
and flooding along the line can occur
regularly at many of these locations. The
risk of flooding can be reduced by
keeping drainage infrastructure clear of
debris. Specialized equipment such as
the CWP can quickly clear the right of
way after storms enabling the
resumption of passenger train service.
After Hurricane Sandy, MNR leased a
CWP, but given limited availability, as
well as the higher cost of leasing, MNR
believes that purchase of the CWP is
necessary to ensure that it will be
E:\FR\FM\19APN1.SGM
19APN1
mstockstill on DSK4VPTVN1PROD with NOTICES
23076
Federal Register / Vol. 81, No. 75 / Tuesday, April 19, 2016 / Notices
available to expedite service restoration
and was provided funding to purchase
such equipment from FTA through the
emergency relief funds allocated for
Superstorm Sandy.
A CWP is a support vehicle train
which consists of several platforms
suitable for holding/hauling and picking
up or distributing a variety of materials,
such as rocks, riprap, dirt or debris. The
equipment is similar to an excavator
which has an articulated arm, with the
main difference being that it rides on
rails and sits on a connected platform
where it can dump or pick up material
from in order to perform its functions.
The main tasks for which the MNR uses
the CWP is shoreline stabilization/
restoration and for removing debris from
the right-of-way after storms.
MNR prepared and advertised a
solicitation for the CWP on January 9,
2015. On February 5, 2015, BRRI, a
Canadian firm, submitted a Certificate of
Non-Compliance because the final
assembly of the equipment would take
place in Canada, although content of the
material used would be 77% domestic
origin.
MNR did extensive follow-up after
receiving only one bid, including
contacting seven vendors who did not
submit bids and undertaking research to
determine whether a CWP that met both
the domestic content and the final
assembly requirements of Buy America
was available. One company that did
not submit a bid stated that although it
could meet the Buy America
requirements, it was not interested in
bidding on the project at this time.
Accordingly, MNR requested a nonavailability waiver of the Buy America
requirements for final assembly
pursuant to 49 U.S.C. 5323 (j)(2)(B).
On March 22, 2016, and in
accordance with 49 U.S.C. 5323(j)(3)(A),
FTA published a notice in the Federal
Register announcing the MNR Buy
America waiver request (81 FR 15407),
seeking comment from all interested
parties, including potential vendors and
suppliers. The comment period closed
on March 29, 2016, and no comments
were received. Based on the
representations from MNR and the lack
of any comments, FTA is granting a
non-availability waiver for final
assembly only of the CWP. This waiver
is limited to the final assembly
requirement for a single procurement of
the CWP described above by MNR.
Issued on April 14, 2016.
Dana Nifosi,
Deputy Chief Counsel.
[FR Doc. 2016–08978 Filed 4–18–16; 8:45 am]
BILLING CODE 4910–57–P
VerDate Sep<11>2014
18:02 Apr 18, 2016
Jkt 238001
DEPARTMENT OF TRANSPORTATION
Federal Transit Administration
[Docket No. FTA–2016–0002]
Notice of Buy America Waiver for a
Radio Communications System
AGENCY:
Federal Transit Administration,
DOT.
ACTION:
Notice of Buy America waiver.
In response to the request of
the Kansas City Area Transportation
Authority (KCATA) for a Buy America
waiver for a DMR Tier III Trunked UHF
Voice radio system that is compatible
with its current system, the Federal
Transit Administration (FTA) hereby
waives its Buy America requirements
finding that the materials for which a
waiver is requested are not produced in
the United States in sufficient and
reasonably available quantities and of a
satisfactory quality. This waiver is
limited to a single procurement by
KCATA for the DMR Tier III Trunked
UHF Voice radio system.
DATES: This waiver is effective
immediately.
SUMMARY:
FOR FURTHER INFORMATION CONTACT:
Laura Ames, FTA Attorney-Advisor, at
(202) 366–2743 or laura.ames@dot.gov.
SUPPLEMENTARY INFORMATION: The
purpose of this notice is to announce
that FTA has granted a Buy America
non-availability waiver for KCATA’s
procurement of a DMR Tier III Trunked
UHF radio system under 49 U.S.C.
5323(j)(2)(B) and 49 CFR 661.7(c).
With certain exceptions, FTA’s Buy
America requirements prevent FTA
from obligating an amount that may be
appropriated to carry out its program for
a project unless ‘‘the steel, iron, and
manufactured goods used in the project
are produced in the United States.’’ 49
U.S.C. 5323(j)(1). A manufactured
product is considered produced in the
United States if: (1) All of the
manufacturing processes for the product
take place in the United States; and (2)
all of the components of the product are
of U.S. origin. A component is
considered of U.S. origin if it is
manufactured in the United States,
regardless of the origin of its
subcomponents. 49 CFR 661.5(d). If,
however, FTA determines that ‘‘the
steel, iron, and goods produced in the
United States are not produced in a
sufficient and reasonably available
amount or are not of a satisfactory
quality,’’ then FTA may issue a nonavailability waiver. 49 U.S.C.
5323(j)(2)(B); 49 CFR 661.7(c).
KCATA provides public
transportation services in the Kansas
PO 00000
Frm 00113
Fmt 4703
Sfmt 4703
City, Missouri, metropolitan area,
operating in seven counties. KCATA’s
current radio system was purchased in
2002 and fully activated in 2005. The
radio system is analog and operates on
two separate channels. It has limited
growth capabilities, issues with ‘‘talk
over,’’ inaccessible voice connections,
and escalating maintenance costs.
KCATA is in the process of upgrading
its radio system.
As part of its plan to upgrade the
radio system, KCATA issued a Request
for Proposals (RFP) on December 16,
2014, seeking a ‘‘turnkey project that
includes a DMR Tier III Trunked UHF
Voice radio system, full integration of
the radio system with the Trapeze
TransitMaster CAD/AVL system, and
extended maintenance and support.’’
KCATA only received one response to
the RFP. Tait North America (Tait)
expressed interest in the project but
noted that it is headquartered in New
Zealand and that a majority of the
products supplied for the project would
be assembled in New Zealand, making
them non-compliant with Buy America.
Neither KCATA nor FTA has
identified any companies in the United
States that can meet the Buy America
requirements for this project. FTA also
conducted a scouting search for a U.S.
manufacturer of a comparable radio
system through its Interagency
Agreement with the U.S. Department of
Commerce’s National Institute of
Standards and Technology (NIST). The
scouting search did not result in
identifying any domestic manufacturers
who could provide the equipment
required by KCATA.
On Wednesday, March 22, 2016, and
in accordance with 49 U.S.C.
5323(j)(3)(A), FTA published a notice in
the Federal Register (81 FR 15410)
requesting public comment on, among
other topics, the merits of KCATA’s
waiver request and potential effects of
granting the waiver. The public
comment period closed on March 29,
2016. FTA received only once comment.
Selex ES, a subsidiary of an Italian
company with its North America
headquarters in Overland Park, Kansas,
commented that although it did not
submit a proposal to KCATA’s RFP, it
can supply a DMR Tier III Trunked
Radio Systems similar to the system
proposed by Tait, arguing that Selex ES
is a ‘‘local’’ option for KCATA.
Although Selex ES markets, designs,
stages, ships, and services DMR Tier III
Trunked Radio Systems and is based in
Kansas, Selex ES does not provide a
system that is compliant with FTA’s
Buy America requirement for
manufactured goods. As noted above,
Buy America applies to manufactured
E:\FR\FM\19APN1.SGM
19APN1
Agencies
[Federal Register Volume 81, Number 75 (Tuesday, April 19, 2016)]
[Notices]
[Pages 23075-23076]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-08978]
-----------------------------------------------------------------------
DEPARTMENT OF TRANSPORTATION
Federal Transit Administration
[Docket No. FTA-2016-0006]
Notice of Buy America Waiver for Steel Excavator With a
Continuous Wield Platform
AGENCY: Federal Transit Administration, DOT.
ACTION: Notice of Buy America waiver.
-----------------------------------------------------------------------
SUMMARY: In response to the request of Metro North Railroad (MNR) for a
Buy America non-availability waiver for the procurement of a steel
excavator with a continuous wield platform (CWP), the Federal Transit
Administration (FTA) hereby waives its Buy America requirements,
finding that the materials for which the waiver is requested are not
produced in the United States in sufficient and reasonably available
quantities and of satisfactory quality. This waiver is limited to a
single procurement by MNR for the CWP.
DATES: This waiver is effective immediately.
FOR FURTHER INFORMATION CONTACT: Laura Ames, FTA Attorney-Advisor, at
(202) 366-2743 or laura.ames@dot.gov.
SUPPLEMENTARY INFORMATION: The purpose of this notice is to announce
that FTA has granted a Buy America non-availability waiver for MNR for
the procurement of a steel excavator with a CWP, under 49 U.S.C.
5323(j)(2)(B) and 49 CFR 661.7(c).
With certain exceptions, FTA's Buy America requirements prevent FTA
from obligating an amount that may be appropriated to carry out its
program for a project unless ``the steel, iron, and manufactured goods
used in the project are produced in the United States.'' 49 U.S.C.
5323(j)(1). Under 49 U.S.C. 5323(j)(2)(C), rolling stock must contain
more than 60 percent domestic content and final assembly must occur in
the U.S. The CWP is subject to the rolling stock requirements. 49 CFR
661.3.
MNR operates commuter rail service spanning 787 track miles. MRN
has a large length of track along the shore line and flooding along the
line can occur regularly at many of these locations. The risk of
flooding can be reduced by keeping drainage infrastructure clear of
debris. Specialized equipment such as the CWP can quickly clear the
right of way after storms enabling the resumption of passenger train
service. After Hurricane Sandy, MNR leased a CWP, but given limited
availability, as well as the higher cost of leasing, MNR believes that
purchase of the CWP is necessary to ensure that it will be
[[Page 23076]]
available to expedite service restoration and was provided funding to
purchase such equipment from FTA through the emergency relief funds
allocated for Superstorm Sandy.
A CWP is a support vehicle train which consists of several
platforms suitable for holding/hauling and picking up or distributing a
variety of materials, such as rocks, riprap, dirt or debris. The
equipment is similar to an excavator which has an articulated arm, with
the main difference being that it rides on rails and sits on a
connected platform where it can dump or pick up material from in order
to perform its functions. The main tasks for which the MNR uses the CWP
is shoreline stabilization/restoration and for removing debris from the
right-of-way after storms.
MNR prepared and advertised a solicitation for the CWP on January
9, 2015. On February 5, 2015, BRRI, a Canadian firm, submitted a
Certificate of Non-Compliance because the final assembly of the
equipment would take place in Canada, although content of the material
used would be 77% domestic origin.
MNR did extensive follow-up after receiving only one bid, including
contacting seven vendors who did not submit bids and undertaking
research to determine whether a CWP that met both the domestic content
and the final assembly requirements of Buy America was available. One
company that did not submit a bid stated that although it could meet
the Buy America requirements, it was not interested in bidding on the
project at this time. Accordingly, MNR requested a non-availability
waiver of the Buy America requirements for final assembly pursuant to
49 U.S.C. 5323 (j)(2)(B).
On March 22, 2016, and in accordance with 49 U.S.C. 5323(j)(3)(A),
FTA published a notice in the Federal Register announcing the MNR Buy
America waiver request (81 FR 15407), seeking comment from all
interested parties, including potential vendors and suppliers. The
comment period closed on March 29, 2016, and no comments were received.
Based on the representations from MNR and the lack of any comments, FTA
is granting a non-availability waiver for final assembly only of the
CWP. This waiver is limited to the final assembly requirement for a
single procurement of the CWP described above by MNR.
Issued on April 14, 2016.
Dana Nifosi,
Deputy Chief Counsel.
[FR Doc. 2016-08978 Filed 4-18-16; 8:45 am]