Columbia Gas Transmission, LLC; Notice of Schedule for Environmental Review of the SM-80 MAOP Restoration Project, 22260 [2016-08687]
Download as PDF
22260
Federal Register / Vol. 81, No. 73 / Friday, April 15, 2016 / Notices
DEPARTMENT OF ENERGY
SM–80 Loop 1 and other existing
easements for 3.8 of the 3.9 miles.
ENVIRONMENTAL PROTECTION
AGENCY
Federal Energy Regulatory
Commission
Background
[EPA–HQ–OPP–2016–0198; FRL–9944–61]
On October 15, 2015, the Commission
issued a Notice of Intent to Prepare an
Environmental Assessment for the
Proposed SM–80 MAOP Restoration
Project and Request for Comments on
Environmental Issues (NOI). The NOI
was sent to affected landowners; federal,
state, and local government agencies;
elected officials; environmental and
public interest groups; Native American
tribes; other interested parties; and local
libraries and newspapers. In response to
the NOI, the Commission received
comments from two landowners. The
primary issues raised by the
commentors are the potential for soil
and water contamination, impacts on
wildlife, air, and noise, and cumulative
impacts.
Pesticide Program Dialogue
Committee; Notice of Public Meeting
[Docket No. CP15–549–000]
Columbia Gas Transmission, LLC;
Notice of Schedule for Environmental
Review of the SM–80 MAOP
Restoration Project
On September 2, 2015, Columbia Gas
Transmission, LLC (Columbia) filed an
application in Docket No. CP15–549–
000 requesting a Certificate of Public
Convenience and Necessity pursuant to
Sections 7(c) and 7(b) of the Natural Gas
Act to abandon, construct, and operate
certain natural gas pipeline facilities in
Wayne County, West Virginia. The
proposed project is known as the SM–
80 MAOP Restoration Project (Project)
and would restore the maximum
allowable operating pressure of part of
the SM–80 system.
On September 15, 2015, the Federal
Energy Regulatory Commission
(Commission or FERC) issued its Notice
of Application for the Project. Among
other things, that notice alerted agencies
issuing federal authorizations of the
requirement to complete all necessary
reviews and to reach a final decision on
a request for a federal authorization
within 90 days of the date of issuance
of the Commission staff’s Environmental
Assessment (EA) for the Project. This
instant notice identifies the FERC staff’s
planned schedule for the completion of
the EA for the Project.
Schedule for Environmental Review
Issuance of EA—5/18/16
90-Day Federal Authorization Decision
Deadline—8/16/16
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the Project’s
progress.
asabaliauskas on DSK3SPTVN1PROD with NOTICES
Project Description
Columbia proposes to abandon in
place about 3.3 miles of 30-inchdiameter pipeline and associated
aboveground appurtenances located on
its existing SM–80 natural gas
transmission system located in Wayne
County, West Virginia. This section
would be abandoned due to its age and
condition. Columbia would also
construct about 3.9 miles of 30-inchdiameter pipeline to replace the
abandoned pipeline. The new pipeline
would be co-located with the existing
VerDate Sep<11>2014
17:27 Apr 14, 2016
Jkt 238001
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC Web
site (www.ferc.gov). Using the
‘‘eLibrary’’ link, select ‘‘General Search’’
from the eLibrary menu, enter the
selected date range and ‘‘Docket
Number’’ excluding the last three digits
(i.e., CP15–549), and follow the
instructions. For assistance with access
to eLibrary, the helpline can be reached
at (866) 208–3676, TTY (202) 502–8659,
or at FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC Web site also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Dated: April 11, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–08687 Filed 4–14–16; 8:45 am]
BILLING CODE 6717–01–P
1 A pipeline loop is a segment of pipe constructed
parallel to an existing pipeline to increase capacity.
PO 00000
Frm 00053
Fmt 4703
Sfmt 4703
Environmental Protection
Agency (EPA).
ACTION: Notice.
AGENCY:
Pursuant to the Federal
Advisory Committee Act (FACA), EPA’s
Office of Pesticide Programs is
announcing a public meeting of the
Pesticide Program Dialogue Committee
(PPDC) on May 18–19, 2016. This
meeting provides advice and
recommendations to the EPA
Administrator on issues associated with
pesticide regulatory development and
reform initiatives, evolving public
policy and program implementation
issues, and science issues associated
with evaluating and reducing risks from
use of pesticides.
DATES: The meeting will be held on
Wednesday, May 18, 2016, from 9 a.m.
to 5:00 p.m., and Thursday, May 19,
2016, from 9 a.m. to 12:00 p.m.
Agenda: A draft agenda will be posted
on or before May 4, 2016.
Accommodations requests: To request
accommodation of a disability, please
contact the person listed under FOR
FURTHER INFORMATION CONTACT,
preferably at least 10 days prior to the
meeting, to give EPA as much time as
possible to process your request.
ADDRESSES: The PPDC Meeting will be
held at 1 Potomac Yard South, 2777 S.
Crystal Drive, Arlington, VA, in the
lobby-level Conference Center.
EPA’s Potomac Yard South Bldg. is
approximately 1 mile from the Crystal
City Metro Station.
FOR FURTHER INFORMATION CONTACT: Dea
Zimmerman, Office of Pesticide
Programs (LC–8J), Environmental
Protection Agency, 77 W. Jackson
Boulevard, Chicago, IL 60604; telephone
number: (312) 353–6344; email address:
zimmerman.dea@epa.gov.
SUPPLEMENTARY INFORMATION:
SUMMARY:
I. General Information
A. Does this action apply to me?
You may be potentially affected by
this action if you work in an agricultural
setting, or if you are concerned about
implementation of the Federal
Insecticide, Fungicide, and Rodenticide
Act (FIFRA); the Federal Food, Drug,
and Cosmetic Act (FFDCA); and the
amendments to both of these major
pesticide laws by the Food Quality
Protection Act (FQPA) of 1996; the
E:\FR\FM\15APN1.SGM
15APN1
Agencies
[Federal Register Volume 81, Number 73 (Friday, April 15, 2016)]
[Notices]
[Page 22260]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-08687]
[[Page 22260]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP15-549-000]
Columbia Gas Transmission, LLC; Notice of Schedule for
Environmental Review of the SM-80 MAOP Restoration Project
On September 2, 2015, Columbia Gas Transmission, LLC (Columbia)
filed an application in Docket No. CP15-549-000 requesting a
Certificate of Public Convenience and Necessity pursuant to Sections
7(c) and 7(b) of the Natural Gas Act to abandon, construct, and operate
certain natural gas pipeline facilities in Wayne County, West Virginia.
The proposed project is known as the SM-80 MAOP Restoration Project
(Project) and would restore the maximum allowable operating pressure of
part of the SM-80 system.
On September 15, 2015, the Federal Energy Regulatory Commission
(Commission or FERC) issued its Notice of Application for the Project.
Among other things, that notice alerted agencies issuing federal
authorizations of the requirement to complete all necessary reviews and
to reach a final decision on a request for a federal authorization
within 90 days of the date of issuance of the Commission staff's
Environmental Assessment (EA) for the Project. This instant notice
identifies the FERC staff's planned schedule for the completion of the
EA for the Project.
Schedule for Environmental Review
Issuance of EA--5/18/16
90-Day Federal Authorization Decision Deadline--8/16/16
If a schedule change becomes necessary, additional notice will be
provided so that the relevant agencies are kept informed of the
Project's progress.
Project Description
Columbia proposes to abandon in place about 3.3 miles of 30-inch-
diameter pipeline and associated aboveground appurtenances located on
its existing SM-80 natural gas transmission system located in Wayne
County, West Virginia. This section would be abandoned due to its age
and condition. Columbia would also construct about 3.9 miles of 30-
inch-diameter pipeline to replace the abandoned pipeline. The new
pipeline would be co-located with the existing SM-80 Loop \1\ and other
existing easements for 3.8 of the 3.9 miles.
---------------------------------------------------------------------------
\1\ A pipeline loop is a segment of pipe constructed parallel to
an existing pipeline to increase capacity.
---------------------------------------------------------------------------
Background
On October 15, 2015, the Commission issued a Notice of Intent to
Prepare an Environmental Assessment for the Proposed SM-80 MAOP
Restoration Project and Request for Comments on Environmental Issues
(NOI). The NOI was sent to affected landowners; federal, state, and
local government agencies; elected officials; environmental and public
interest groups; Native American tribes; other interested parties; and
local libraries and newspapers. In response to the NOI, the Commission
received comments from two landowners. The primary issues raised by the
commentors are the potential for soil and water contamination, impacts
on wildlife, air, and noise, and cumulative impacts.
Additional Information
In order to receive notification of the issuance of the EA and to
keep track of all formal issuances and submittals in specific dockets,
the Commission offers a free service called eSubscription. This can
reduce the amount of time you spend researching proceedings by
automatically providing you with notification of these filings,
document summaries, and direct links to the documents. Go to
www.ferc.gov/docs-filing/esubscription.asp.
Additional information about the Project is available from the
Commission's Office of External Affairs at (866) 208-FERC or on the
FERC Web site (www.ferc.gov). Using the ``eLibrary'' link, select
``General Search'' from the eLibrary menu, enter the selected date
range and ``Docket Number'' excluding the last three digits (i.e.,
CP15-549), and follow the instructions. For assistance with access to
eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-
8659, or at FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC
Web site also provides access to the texts of formal documents issued
by the Commission, such as orders, notices, and rule makings.
Dated: April 11, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-08687 Filed 4-14-16; 8:45 am]
BILLING CODE 6717-01-P