Grand River Dam Authority; Notice Granting Waiver Request To Reduce Comment Period From 60 to 30 Days on Draft Amendment Application, 21861 [2016-08412]
Download as PDF
Federal Register / Vol. 81, No. 71 / Wednesday, April 13, 2016 / Notices
Applicants: Golden Pass Pipeline
LLC.
Description: Compliance filing
Revised Tariff Records per 03/29/2016
Order Re: Orders 587–W and 809 to be
effective 4/20/2016.
Filed Date: 4/4/16.
Accession Number: 20160404–5264.
Comments Due: 5 p.m. ET 4/18/16.
Any person desiring to protest in any
of the above proceedings must file in
accordance with Rule 211 of the
Commission’s Regulations (18 CFR
385.211) on or before 5:00 p.m. Eastern
time on the specified comment date.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: April 5, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–08416 Filed 4–12–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP15–520–000]
Tennessee Gas Pipeline Company,
L.L.C.; Notice of Revised Schedule for
Environmental Review of the Triad
Expansion Project
asabaliauskas on DSK3SPTVN1PROD with NOTICES
This notice identifies the Federal
Energy Regulatory Commission staff’s
revised schedule for the completion of
the Environmental Assessment (EA) for
Tennessee Gas Pipeline Company,
L.L.C.’s (Tennessee) Triad Expansion
Project. The previous notice of
schedule, issued on December 9, 2015,
identified April 6, 2016 as the issuance
date of the EA. On February 12, 2016,
Commission staff received supplemental
information regarding a route variation
from Tennessee that requires a revised
schedule for issuance of the EA.
Schedule for Environmental Review
Issuance of EA—June 15, 2016
90-Day Federal Authorization Decision
Deadline—September 13, 2016
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the Project’s
progress.
VerDate Sep<11>2014
17:41 Apr 12, 2016
Jkt 238001
Additional Information
In order to receive notification of the
issuance of the final EA and to keep
track of all formal issuances and
submittals in specific dockets, the
Commission offers a free service called
eSubscription. Go to www.ferc.gov/docsfiling/esubscription.asp.
Dated: April 5, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–08411 Filed 4–12–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 1494–433]
Grand River Dam Authority; Notice
Granting Waiver Request To Reduce
Comment Period From 60 to 30 Days
on Draft Amendment Application
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Application Type: Request to
reduce the comment period from 60 to
30 days for a draft amendment
application to permanently modify the
reservoir elevation rule curve under
Article 401 of the project license.
b. Project No: 1494–433.
c. Date Filed: March 15, 2016.
d. Applicant: Grand River Dam
Authority (GRDA).
e. Name of Project: Pensacola
Hydroelectric Project.
f. Location: The project is located on
the Grand River in Craig, Delaware,
Mayes, and Ottawa Counties, Oklahoma.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Tamara Jahnke,
Grand River Dam Authority, 226 West
Dwain Willis Ave., P.O. Box 409, Vinita,
OK 74301; telephone (918) 256–5545.
i. FERC Contact: B. Peter Yarrington,
telephone (202) 502–6129 and email
peter.yarrington@ferc.gov; or Linda
Stewart, telephone (202) 502–6680 and
email linda.stewart@ferc.gov.
j. Description of Waiver Request and
Decision: On March 15, 2016, GRDA
filed with the Commission: (1) A draft
amendment application to permanently
modify the reservoir elevation rule
curve under Article 401 of the Pensacola
Project for Grand Lake O’ the Cherokees,
(2) a request for a temporary variance
contained in the draft amendment
application, and (3) a waiver request to
reduce from 60 to 30 days the comment
period for resource agencies, Indian
PO 00000
Frm 00026
Fmt 4703
Sfmt 4703
21861
tribes, and other stakeholders to provide
comments to GRDA on its draft of the
amendment application mentioned
above before GRDA files it with the
Commission. The Commission’s
regulations at 4.38(a)(7) require GRDA
to provide resource agencies, Indian
tribes, and other stakeholders 60 days to
provide comments on the draft
amendment application. GRDA requests
Commission approval of a 30-day
comment period to expedite the
Commission’s review of any final
application filed with the Commission.
The Commission issued a public
notice of GRDA’s waiver request on
March 16, 2016 requesting comments,
motions to intervene, and protests by
March 31, 2016. The Modoc Tribe of
Oklahoma filed a protest and comments
on March 31, 2016. However, the protest
and comments are related to any final
amendment application GRDA may file
with the Commission. The protest and
comments did not address the waiver
request described in the Commission’s
public notice. No other protests or
comments were received. Since there
were no objections to GRDA’s waiver
request to reduce the comment period
from 60 to 30 days as described above,
the waiver is approved and comments
on GRDA’s draft amendment
application must be submitted to GRDA
within the requested 30-day period (due
by April 14, 2016).
Note that the Modoc Tribe’s concerns
and comments contained in its March
31, 2016 letter, have been filed with the
Commission and will be considered in
the Commission’s review of any final
amendment application GRDA files
with the Commission.
Dated: April 5, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–08412 Filed 4–12–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2246–000]
Yuba County Water Agency; Notice of
Authorization for Continued Project
Operation
On April 28, 2014 Yuba County Water
Agency, licensee for the Yuba River
Project, filed an Application for a New
License pursuant to the Federal Power
Act (FPA) and the Commission’s
regulations thereunder. The Yuba River
Project facilities are located on the Yuba
River, North Yuba River, the Middle
E:\FR\FM\13APN1.SGM
13APN1
Agencies
[Federal Register Volume 81, Number 71 (Wednesday, April 13, 2016)]
[Notices]
[Page 21861]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-08412]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 1494-433]
Grand River Dam Authority; Notice Granting Waiver Request To
Reduce Comment Period From 60 to 30 Days on Draft Amendment Application
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Application Type: Request to reduce the comment period from 60
to 30 days for a draft amendment application to permanently modify the
reservoir elevation rule curve under Article 401 of the project
license.
b. Project No: 1494-433.
c. Date Filed: March 15, 2016.
d. Applicant: Grand River Dam Authority (GRDA).
e. Name of Project: Pensacola Hydroelectric Project.
f. Location: The project is located on the Grand River in Craig,
Delaware, Mayes, and Ottawa Counties, Oklahoma.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Tamara Jahnke, Grand River Dam Authority, 226
West Dwain Willis Ave., P.O. Box 409, Vinita, OK 74301; telephone (918)
256-5545.
i. FERC Contact: B. Peter Yarrington, telephone (202) 502-6129 and
email peter.yarrington@ferc.gov; or Linda Stewart, telephone (202) 502-
6680 and email linda.stewart@ferc.gov.
j. Description of Waiver Request and Decision: On March 15, 2016,
GRDA filed with the Commission: (1) A draft amendment application to
permanently modify the reservoir elevation rule curve under Article 401
of the Pensacola Project for Grand Lake O' the Cherokees, (2) a request
for a temporary variance contained in the draft amendment application,
and (3) a waiver request to reduce from 60 to 30 days the comment
period for resource agencies, Indian tribes, and other stakeholders to
provide comments to GRDA on its draft of the amendment application
mentioned above before GRDA files it with the Commission. The
Commission's regulations at 4.38(a)(7) require GRDA to provide resource
agencies, Indian tribes, and other stakeholders 60 days to provide
comments on the draft amendment application. GRDA requests Commission
approval of a 30-day comment period to expedite the Commission's review
of any final application filed with the Commission.
The Commission issued a public notice of GRDA's waiver request on
March 16, 2016 requesting comments, motions to intervene, and protests
by March 31, 2016. The Modoc Tribe of Oklahoma filed a protest and
comments on March 31, 2016. However, the protest and comments are
related to any final amendment application GRDA may file with the
Commission. The protest and comments did not address the waiver request
described in the Commission's public notice. No other protests or
comments were received. Since there were no objections to GRDA's waiver
request to reduce the comment period from 60 to 30 days as described
above, the waiver is approved and comments on GRDA's draft amendment
application must be submitted to GRDA within the requested 30-day
period (due by April 14, 2016).
Note that the Modoc Tribe's concerns and comments contained in its
March 31, 2016 letter, have been filed with the Commission and will be
considered in the Commission's review of any final amendment
application GRDA files with the Commission.
Dated: April 5, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-08412 Filed 4-12-16; 8:45 am]