Notice of Extension of Rate Schedules, 18607-18608 [2016-07288]
Download as PDF
mstockstill on DSK4VPTVN1PROD with NOTICES
Federal Register / Vol. 81, No. 62 / Thursday, March 31, 2016 / Notices
of siting the transmission line, the span
between structures would also provide some
flexibility for avoiding floodplains. That is,
in some areas it would be reasonable to
minimize the number of structures in a
floodplain by controlling the spans or to
place the structures outside the floodplain,
which would then be spanned by the
transmission line.’’
If a transmission structure would be
required to be sited in a floodplain, it would
be designed and constructed to meet the
anticipated design loads from a maximallycredible flooding event in accordance with
applicable regulatory standards. Therefore, a
flooding event would be unlikely to result in
the failure of a transmission structure.
In the unlikely event that structure failure
did occur as a result of a flooding event, the
system repair would be similar to failures
from other off-normal events. As presented in
the Final EIS comment response document
(Appendix Q, page 3–307), ‘‘Temporary
interruption of the power transmission
system could occur to the Project from a
variety of off-normal events such as natural
disasters, terrorism, or accidents. The Project
would be designed to prevent outages from
these events to the maximum extent
practicable. While it stands to reason that
interruption of a smaller regional power
transmission system would impact a smaller
customer base than a larger system, neither
situation is necessarily considered
disastrous. There are multiple thousands of
miles of aboveground electrical transmission
lines providing electrical power to
consumers over long distances in the United
States. Interruptions of power have occurred
to power transmission systems in the past
and have been mitigated and power restored
through standard industry, engineering, and
security practices. The Project alone would
not represent a critically high percentage of
power transmission service to consumers
nationally and therefore temporary
disruption of the grid would be considered
manageable. The Applicant would operate
the system and respond to any unplanned
outages according to those practices and
identified EPMs, BMPs, plans and
procedures, and applicable regulatory
requirements.’’
Clean Line has provided additional
information in their Operations and
Maintenance Plan (Section 3.12; Corrective
Actions), which states, ‘‘To minimize the
frequency and duration of corrective
activities, Clean Line has designed robust
structures that incorporate the appropriate
NESC [National Electric Safety Code]
requirements. Current engineering plans call
for stop-structures every 5–10 miles to
prevent cascading events. Clean Line plans to
utilize weather-monitoring systems currently
in place in the project area . . . and to
communicate elevated risk levels to
interconnecting utilities in order to ensure
operational readiness. A spare parts
inventory will be put in place along the route
to address both high and low probability
weather events. Standby contracts for labor
and emergency equipment will provide for
quick responses to any outages. A spare parts
inventory will include information on critical
components and parts, storage location, and
VerDate Sep<11>2014
19:09 Mar 30, 2016
Jkt 238001
lead times/current availability for
replacement parts.’’
Comment. Mr. Fuksa’s email states that the
National Park Service added the Fuksa
portion of the Chisholm Trail to the National
Registry of Historic Places (NRHP) in
September 2015, and designated the John and
Mary Fuksa Family Farm (including
dustbowl-era farmyard, buildings, and
structures) as a national historic area and
added it to the NRHP in December 2015. Mr.
Fuksa urges DOE to adopt Alternative Route
2B instead of the Applicant Proposed Route
in this location.
Response. The location of the Chisholm
Trail relative to the Applicant Proposed
Route is identified and discussed in Section
3.9.5.2 of the Final EIS. Impacts to property
structures would be addressed through
micrositing within the 1,000-foot-wide
corridor and implementing EPM LU–5,
which states that Clean Line will make
reasonable efforts, consistent with design
criteria, to accommodate requests from
individual landowners to adjust the siting of
the ROW on their properties. These
adjustments may include consideration of
routes along or parallel to existing divisions
of land (e.g., agricultural fields and parcel
boundaries) and existing compatible linear
infrastructure (e.g., roads, transmission lines,
and pipelines), with the intent of reducing
the impact of the ROW on private properties.
DOE has developed a Programmatic
Agreement that, in accordance with the
regulations that implement Section 106 of the
NHPA, provides a framework for the
assessment of potential Project effects to
historic properties (this would include
potential effects to the Fuksa portion of the
Chisholm Trail and the John and Mary Fuksa
Family Farm), and adoption of strategies to
resolve potential effects.
[FR Doc. 2016–07282 Filed 3–30–16; 8:45 am]
BILLING CODE 6450–01–P
DEPARTMENT OF ENERGY
Notice of Extension of Rate Schedules
Southeastern Power
Administration, DOE.
ACTION: Notice of Rate Extension.
AGENCY:
The Deputy Secretary of the
Department of Energy confirmed and
approved an extension of Rate
Schedules JW–1–J and JW–2–F through
September 30, 2016. This short 11 day
extension will allow the billing and rate
terms to align going forward in the new
rate to be proposed effective October 1,
2016 and to be announced in a separate
Federal Register Notice.
DATES: Approval of extension of the rate
schedules is effective September 20,
2016.
FOR FURTHER INFORMATION CONTACT:
Virgil G. Hobbs III, Assistant
Administrator, Finance & Marketing,
Southeastern Power Administration,
Department of Energy, 1166 Athens
SUMMARY:
PO 00000
Frm 00044
Fmt 4703
Sfmt 4703
18607
Tech Road, Elberton, Georgia 30635–
6711, (706) 213–3800.
SUPPLEMENTARY INFORMATION: The
Commission, by Order issued December
22, 2011, in Docket No. EF11–12–000,
confirmed and approved Wholesale
Power Rate Schedules JW–1–J and JW–
2–F for a period ending September 19,
2016.
Dated: March 25, 2016.
Elizabeth Sherwood-Randall,
Deputy Secretary.
Department of Energy
Deputy Secretary
Rate Order No. SEPA–60.
In the Matter of: Southeastern Power
Administration—Jim Woodruff Project Power
Rates
Order Confirming and Approving
Power Rates On an Interim Basis
Pursuant to Sections 302(a) of the
Department of Energy Organization Act,
Public Law 95–91, the functions of the
Secretary of the Interior and the Federal
Power Commission under Section 5 of
the Flood Control Act of 1944, 16 U.S.C.
825s, relating to the Southeastern Power
Administration (‘‘Southeastern’’ or
‘‘SEPA’’) were transferred to and vested
in the Secretary of Energy. By
Delegation Order No. 00–037.00A,
effective October 25, 2013, the Secretary
of Energy delegated to Southeastern’s
Administrator the authority to develop
power and transmission rates, delegated
to the Deputy Secretary of Energy the
authority to confirm, approve, and place
in effect such rates on an interim basis,
and delegated to the Federal Energy
Regulatory Commission
(‘‘Commission’’) the authority to
confirm, approve, and place into effect
on a final basis or to disapprove rates
developed by the Administrator under
the delegation. This rate order is issued
by the Deputy Secretary pursuant to
said delegation.
Pursuant to 10 CFR 903.23(b), an
existing rate may be extended on a
temporary basis by the Deputy Secretary
without advanced notice or comment.
The Deputy Secretary shall publish said
extension in the Federal Register and
promptly advise the Commission of the
extension.
Background
Power from the Jim Woodruff Project
is presently sold under Wholesale
Power Rate Schedules JW–1–J and JW–
2–F. These rate schedules were
approved by the Commission on
December 22, 2011, for a period ending
September 19, 2016 (137 FERC
¶62,248). Effective June 21, 2015,
Southeastern, Duke Energy Florida, and
E:\FR\FM\31MRN1.SGM
31MRN1
18608
Federal Register / Vol. 81, No. 62 / Thursday, March 31, 2016 / Notices
the preference customers agreed to a
change in the billing cycle to conform
to the calendar month. Previously, the
billing cycle occurred on the 20th of
each month. This rate extension is to
cover the transition period in the billing
cycle before implementing new rate
schedules.
Discussion
System Repayment
An examination of Southeastern’s
revised system power repayment study,
prepared in February, 2016, for the Jim
Woodruff Project, shows that with the
extended rates, all system power costs
are paid within the 50-year repayment
period required by existing law and
DOE Order RA 6120.2.
Environmental Impact
Southeastern has reviewed the
possible environmental impacts of the
rate adjustment under consideration and
has concluded the extended rates would
not significantly affect the quality of the
human environment within the meaning
of the National Environmental Policy
Act of 1969. The proposed action is not
a major Federal action for which
preparation of an Environmental Impact
Statement is required.
Availability of Information
Information regarding these rates,
including studies, and other supporting
materials, is available for public review
in the offices of Southeastern Power
Administration, 1166 Athens Tech
Road, Elberton, Georgia 30635–6711.
[FR Doc. 2016–07288 Filed 3–30–16; 8:45 am]
BILLING CODE 6450–01–P
DEPARTMENT OF ENERGY
Office of Energy Efficiency and
Renewable Energy
[Docket Number: EERE–2016–BT–STD–
0013]
Notice of Application From Green
Electronics for a Small Business
Exemption Regarding Certain Products
From the Department of Energy’s
External Power Supply Energy
Conservation Standards
Office of Energy Efficiency and
Renewable Energy, Department of
Energy.
ACTION: Notice of application for
exemption and request for comment.
mstockstill on DSK4VPTVN1PROD with NOTICES
AGENCY:
This notice announces receipt
of and publishes an application
submitted by Green Electronics for a
small business exemption from the U.S.
Department of Energy’s (DOE) energy
SUMMARY:
VerDate Sep<11>2014
19:09 Mar 30, 2016
Jkt 238001
conservation standards for direct
operation external power supplies
(application) pertaining to certain basic
models imported by Green Electronics.
Specifically, the application requests a
one-year exemption from compliance
with the standard beginning on
February 10, 2016, the compliance date
for such standard. DOE is publishing the
non-confidential portion of Green
Electronics’ application and soliciting
comments, data, and information
concerning Green Electronics’
application.
DATES: DOE will accept comments, data,
and information until May 31, 2016.
ADDRESSES: You may submit comments,
identified by docket/case number, by
any of the following methods:
• Federal eRulemaking Portal: https://
www.regulations.gov. Follow the
instructions for submitting comments.
• Email: ExemptionExt
PowerSupply2016STD0013@ee.doe.gov.
Include ‘‘docket/case number’’ in the
subject line of the message.
• Mail: Ms. Brenda Edwards, U.S.
Department of Energy, Building
Technologies Office, Mailstop EE–5B,
1000 Independence Avenue SW.,
Washington, DC 20585–0121.
Telephone: (202) 586–2945. Please
submit one signed original paper copy.
• Hand Delivery/Courier: Ms. Brenda
Edwards, U.S. Department of Energy,
Building Technologies Office, 950
L’Enfant Plaza SW., Suite 600,
Washington, DC 20024. Please submit
one signed original paper copy.
FOR FURTHER INFORMATION CONTACT: Ms.
Ashley Armstrong, U.S. Department of
Energy, Building Technologies Office,
Mail Stop EE–5B, Forrestal Building,
1000 Independence Avenue SW.,
Washington, DC 20585–0121.
Telephone: (202) 586–0371. Email:
ashley.armstrong@ee.doe.gov.
Mr. Michael Kido, U.S. Department of
Energy, Office of the General Counsel,
Mail Stop GC–33, Forrestal Building,
1000 Independence Avenue SW.,
Washington, DC 20585–0103.
Telephone: (202) 586–8145. Email:
Michael.kido@hq.doe.gov.
SUPPLEMENTARY INFORMATION:
I. Background and Authority
Title III of the Energy Policy and
Conservation Act of 1975 (42 U.S.C.
6291, et seq.; ‘‘EPCA’’ or, in context,
‘‘the Act’’) sets forth a variety of
provisions designed to improve energy
efficiency. (All references to EPCA refer
to the statute as amended through the
Energy Efficiency Improvement Act of
2015—Pub. L. 114–11 (April 30, 2015).)
Part B of title III, which for editorial
reasons was re-designated as Part A
PO 00000
Frm 00045
Fmt 4703
Sfmt 4703
upon incorporation into the U.S. Code
(42 U.S.C. 6291–6309, as codified),
establishes the ‘‘Energy Conservation
Program for Consumer Products Other
Than Automobiles.’’ External power
supplies are among the products
affected by these provisions.
Under EPCA, the energy conservation
program consists essentially of four
parts: (1) Testing, (2) labeling, (3)
Federal energy conservation standards,
and (4) certification and enforcement
procedures. The testing requirements
consist of test procedures that
manufacturers of covered products must
use as the basis for (1) certifying to DOE
that their products comply with the
applicable energy conservation
standards adopted under EPCA, and (2)
making representations about the
efficiency of those products. Similarly,
DOE must use these test procedures to
determine whether the products comply
with any relevant standards
promulgated under EPCA.
Consistent with EPCA, DOE has
undertaken several rulemakings
concerning external power supplies
(‘‘EPSs’’). Specifically, DOE issued a
final rule on March 27, 2009, that
defined and added terms and
definitions relevant to EPSs to 10 CFR
part 430, subpart B, Appendix Z
(hereafter referred to as Appendix Z).
See 74 FR 13318. In June 2011, DOE
further amended Appendix Z by adding
a test method for multiple-voltage EPSs.
76 FR 31750 (June 1, 2011). In addition
to the test procedure rulemaking
activities, DOE undertook a rulemaking
to establish energy conservation
standards for EPSs. After releasing a
preliminary analysis and issuing a
notice of proposed rulemaking, DOE
published a final rule (hereafter referred
to as 2014 standards rulemaking)
prescribing new standards for some
non-Class A EPSs and amended
standards for some Class A EPSs. See 79
FR 7845 (Feb. 10, 2014). As part of this
rulemaking, DOE established new
definitions for direct operation EPSs
and indirect operation EPSs in 10 CFR
430.2. Direct operation EPSs, regardless
of whether they are Class A or non-Class
A EPSs, are subject to more stringent
standards than the statutorily-prescribed
Level IV standard requirements. The
standards for direct operation EPSs are
identified via a Level VI marking per 10
CFR 430.32(w)(4) and are hereafter
referred to as Level VI standards in this
document. DOE did not establish any
standards for indirect operation EPSs.
However, indirect operation EPSs that
meet the definition of a Class A EPS, are
required to meet the statutory Level IV
standards already established in EPCA.
While the Level IV standards have been
E:\FR\FM\31MRN1.SGM
31MRN1
Agencies
[Federal Register Volume 81, Number 62 (Thursday, March 31, 2016)]
[Notices]
[Pages 18607-18608]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-07288]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Notice of Extension of Rate Schedules
AGENCY: Southeastern Power Administration, DOE.
ACTION: Notice of Rate Extension.
-----------------------------------------------------------------------
SUMMARY: The Deputy Secretary of the Department of Energy confirmed and
approved an extension of Rate Schedules JW-1-J and JW-2-F through
September 30, 2016. This short 11 day extension will allow the billing
and rate terms to align going forward in the new rate to be proposed
effective October 1, 2016 and to be announced in a separate Federal
Register Notice.
DATES: Approval of extension of the rate schedules is effective
September 20, 2016.
FOR FURTHER INFORMATION CONTACT: Virgil G. Hobbs III, Assistant
Administrator, Finance & Marketing, Southeastern Power Administration,
Department of Energy, 1166 Athens Tech Road, Elberton, Georgia 30635-
6711, (706) 213-3800.
SUPPLEMENTARY INFORMATION: The Commission, by Order issued December 22,
2011, in Docket No. EF11-12-000, confirmed and approved Wholesale Power
Rate Schedules JW-1-J and JW-2-F for a period ending September 19,
2016.
Dated: March 25, 2016.
Elizabeth Sherwood-Randall,
Deputy Secretary.
Department of Energy
Deputy Secretary
Rate Order No. SEPA-60.
In the Matter of: Southeastern Power Administration--Jim
Woodruff Project Power Rates
Order Confirming and Approving Power Rates On an Interim Basis
Pursuant to Sections 302(a) of the Department of Energy
Organization Act, Public Law 95-91, the functions of the Secretary of
the Interior and the Federal Power Commission under Section 5 of the
Flood Control Act of 1944, 16 U.S.C. 825s, relating to the Southeastern
Power Administration (``Southeastern'' or ``SEPA'') were transferred to
and vested in the Secretary of Energy. By Delegation Order No. 00-
037.00A, effective October 25, 2013, the Secretary of Energy delegated
to Southeastern's Administrator the authority to develop power and
transmission rates, delegated to the Deputy Secretary of Energy the
authority to confirm, approve, and place in effect such rates on an
interim basis, and delegated to the Federal Energy Regulatory
Commission (``Commission'') the authority to confirm, approve, and
place into effect on a final basis or to disapprove rates developed by
the Administrator under the delegation. This rate order is issued by
the Deputy Secretary pursuant to said delegation.
Pursuant to 10 CFR 903.23(b), an existing rate may be extended on a
temporary basis by the Deputy Secretary without advanced notice or
comment. The Deputy Secretary shall publish said extension in the
Federal Register and promptly advise the Commission of the extension.
Background
Power from the Jim Woodruff Project is presently sold under
Wholesale Power Rate Schedules JW-1-J and JW-2-F. These rate schedules
were approved by the Commission on December 22, 2011, for a period
ending September 19, 2016 (137 FERC ]62,248). Effective June 21, 2015,
Southeastern, Duke Energy Florida, and
[[Page 18608]]
the preference customers agreed to a change in the billing cycle to
conform to the calendar month. Previously, the billing cycle occurred
on the 20th of each month. This rate extension is to cover the
transition period in the billing cycle before implementing new rate
schedules.
Discussion
System Repayment
An examination of Southeastern's revised system power repayment
study, prepared in February, 2016, for the Jim Woodruff Project, shows
that with the extended rates, all system power costs are paid within
the 50-year repayment period required by existing law and DOE Order RA
6120.2.
Environmental Impact
Southeastern has reviewed the possible environmental impacts of the
rate adjustment under consideration and has concluded the extended
rates would not significantly affect the quality of the human
environment within the meaning of the National Environmental Policy Act
of 1969. The proposed action is not a major Federal action for which
preparation of an Environmental Impact Statement is required.
Availability of Information
Information regarding these rates, including studies, and other
supporting materials, is available for public review in the offices of
Southeastern Power Administration, 1166 Athens Tech Road, Elberton,
Georgia 30635-6711.
[FR Doc. 2016-07288 Filed 3-30-16; 8:45 am]
BILLING CODE 6450-01-P