Download as PDF 14936 Federal Register / Vol. 81, No. 53 / Friday, March 18, 2016 / Notices accessed and by whom. During the testing phase, consider what data should be made public for further analysis and understanding. 6. Crash avoidance capability: Consider the capabilities of AV systems with respect to detecting roadway hazards (other vehicles, pedestrians, animals, etc.) such that common crash scenarios involving these hazards (control loss, crossing paths head-on, etc.) can be detected and either avoided or mitigated. 7. Electronics systems safety: Consider methods and potential documentation that could be produced with respect to functional safety and cybersecurity. 8. Non-passenger AVs: Consider differences between AVs designed for delivery of goods and products that are not intended to have a human operator or potentially even human passengers. 9. Aspects of AV technology that may not be suitable or ready for guidelines. For these areas, information would be useful on alternative approaches to assure safety. 10. Identification of industry voluntary standards, best practices, etc., related to automated vehicle operation. 11. Information AV’s may need to communicate to pedestrians and other vehicles (manual or automated) just as a driver would. Consider situations such as pedestrians crossing a travel lane in a parking lot and how this communication should be accomplished. 12. Other topics needed for operational guidance: Other topics that would be beneficial to address in an operational guidance document to facilitate innovation and safe deployment of these systems on public roadways. Issued in Washington, DC, under authority delegated by 49 CFR 1.95. Nathaniel Beuse, Associate Administrator for Vehicle Safety Research. [FR Doc. 2016–06143 Filed 3–17–16; 8:45 am] been in process for 180 days or more. The reason(s) for delay and the expected completion date for action on each application is provided in association with each identified application. FOR FURTHER INFORMATION CONTACT: Ryan Paquet, Director, Office of Hazardous Materials Special Permits and Approvals, Pipeline and Hazardous Materials Safety Administration, U.S. Department of Transportation, East Building, PHH–30, 1200 New Jersey Avenue SE., Washington, DC 20590– 0001, (202) 366–4535. Key to ‘‘Reason for Delay’’ BILLING CODE 4910–59–P DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration Hazardous Materials: Delayed Applications 1. Awaiting additional information from applicant 2. Extensive public comment under review 3. Application is technically complex and is of significant impact or precedent-setting and requires extensive analysis 4. Staff review delayed by other priority issues or volume of special permit applications Office of Hazardous Materials Safety, Pipeline and Hazardous Materials Safety Administration (PHMSA), DOT. ACTION: List of application delayed more than 180 days. Meaning of Application Number Suffixes In accordance with the requirements of 49 U.S.C. 5117(c), PHMSA is publishing the following list of special permit applications that have Issued in Washington, DC, on March 10, 2016. Donald Burger, Chief, General Approvals and Permits. AGENCY: SUMMARY: Application No. N—New application M—Modification request R—Renewal Request P—Party To Exemption Request Reason for delay Applicant Estimated date of completion Modification to Special Permits 16412–M ........... 15628–M ........... 15610–M ........... 15537–M ........... 7607–M ............. 16035–M ........... 14437–M ........... Nantong CMC Tank Equipment Co. Ltd., Jiangsu, Province ................................................... Chemours Company FC, LLC, Wilmington, DE ....................................................................... TechKnowServ Corp., State College, PA ................................................................................. Alaska Pacific Powder Company, Watkins, CO ....................................................................... Thermo Fisher Scientific, Franklin, MA .................................................................................... LCF Systems, Inc., Scottsdale, AZ .......................................................................................... Columbiana Boiler Company (CBCo), LLC, Columbiana, OH ................................................. 4 4 4 4 4 4 4 03–31–2016 03–31–2016 03–31–2016 04–15–2016 03–31–2016 04–30–2016 02–15–2016 3 3 4 4 4 3 4 4 4 02–29–2016 03–31–2016 03–15–2016 03–31–2016 03–15–2016 03–31–2016 04–15–2016 04–30–2016 04–30–2016 4 03–31–2016 New Special Permit Applications asabaliauskas on DSK3SPTVN1PROD with NOTICES 15767–N 16001–N 16477–N 16495–N 16524–N 16463–N 16571–N 16559–N 16560–N ........... ........... ........... ........... ........... ........... ........... ........... ........... Union Pacific Railroad Company, Omaha, NE ........................................................................ VELTEK ASSOCIATES, INC., Malvern, PA ............................................................................. Hydroid, Inc., Pocasset, MA ..................................................................................................... TransRail Innovation, Inc., Calgary .......................................................................................... Quantum Fuel Systems Technologies Worldwide, Inc., Lake Forest, CA ............................... Salco Products, Lemont, IL ...................................................................................................... Chevron USA Inc., San Ramon, CA ........................................................................................ HTEC Hydrogen Technology & Energy Corporation, North Vancouver, BC; Canada ............ LightSail Energy, Inc., Berkeley, CA ........................................................................................ Party to Special Permits Application 16279–P ........... AEG Environmental Products & Services, Inc.; Westminster, MD .......................................... [FR Doc. 2016–06055 Filed 3–17–16; 8:45 am] BILLING CODE 4910–60–M VerDate Sep<11>2014 19:50 Mar 17, 2016 Jkt 238001 PO 00000 Frm 00115 Fmt 4703 Sfmt 9990 E:\FR\FM\18MRN1.SGM 18MRN1

Agencies

[Federal Register Volume 81, Number 53 (Friday, March 18, 2016)]
[Notices]
[Page 14936]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-06055]


-----------------------------------------------------------------------

DEPARTMENT OF TRANSPORTATION

Pipeline and Hazardous Materials Safety Administration


Hazardous Materials: Delayed Applications

AGENCY: Office of Hazardous Materials Safety, Pipeline and Hazardous 
Materials Safety Administration (PHMSA), DOT.

ACTION: List of application delayed more than 180 days.

-----------------------------------------------------------------------

SUMMARY: In accordance with the requirements of 49 U.S.C. 5117(c), 
PHMSA is publishing the following list of special permit applications 
that have been in process for 180 days or more. The reason(s) for delay 
and the expected completion date for action on each application is 
provided in association with each identified application.

FOR FURTHER INFORMATION CONTACT: Ryan Paquet, Director, Office of 
Hazardous Materials Special Permits and Approvals, Pipeline and 
Hazardous Materials Safety Administration, U.S. Department of 
Transportation, East Building, PHH-30, 1200 New Jersey Avenue SE., 
Washington, DC 20590-0001, (202) 366-4535.

Key to ``Reason for Delay''

1. Awaiting additional information from applicant
2. Extensive public comment under review
3. Application is technically complex and is of significant impact 
or precedent-setting and requires extensive analysis
4. Staff review delayed by other priority issues or volume of 
special permit applications

Meaning of Application Number Suffixes

N--New application
M--Modification request
R--Renewal Request
P--Party To Exemption Request

    Issued in Washington, DC, on March 10, 2016.
Donald Burger,
Chief, General Approvals and Permits.

----------------------------------------------------------------------------------------------------------------
                                                                                    Reason for    Estimated date
            Application No.                             Applicant                      delay       of completion
----------------------------------------------------------------------------------------------------------------
                                         Modification to Special Permits
----------------------------------------------------------------------------------------------------------------
16412-M................................  Nantong CMC Tank Equipment Co. Ltd.,                  4      03-31-2016
                                          Jiangsu, Province.
15628-M................................  Chemours Company FC, LLC, Wilmington,                 4      03-31-2016
                                          DE.
15610-M................................  TechKnowServ Corp., State College, PA..               4      03-31-2016
15537-M................................  Alaska Pacific Powder Company, Watkins,               4      04-15-2016
                                          CO.
7607-M.................................  Thermo Fisher Scientific, Franklin, MA.               4      03-31-2016
16035-M................................  LCF Systems, Inc., Scottsdale, AZ......               4      04-30-2016
14437-M................................  Columbiana Boiler Company (CBCo), LLC,                4      02-15-2016
                                          Columbiana, OH.
----------------------------------------------------------------------------------------------------------------
                                         New Special Permit Applications
----------------------------------------------------------------------------------------------------------------
15767-N................................  Union Pacific Railroad Company, Omaha,                3      02-29-2016
                                          NE.
16001-N................................  VELTEK ASSOCIATES, INC., Malvern, PA...               3      03-31-2016
16477-N................................  Hydroid, Inc., Pocasset, MA............               4      03-15-2016
16495-N................................  TransRail Innovation, Inc., Calgary....               4      03-31-2016
16524-N................................  Quantum Fuel Systems Technologies                     4      03-15-2016
                                          Worldwide, Inc., Lake Forest, CA.
16463-N................................  Salco Products, Lemont, IL.............               3      03-31-2016
16571-N................................  Chevron USA Inc., San Ramon, CA........               4      04-15-2016
16559-N................................  HTEC Hydrogen Technology & Energy                     4      04-30-2016
                                          Corporation, North Vancouver, BC;
                                          Canada.
16560-N................................  LightSail Energy, Inc., Berkeley, CA...               4      04-30-2016
----------------------------------------------------------------------------------------------------------------
                                      Party to Special Permits Application
----------------------------------------------------------------------------------------------------------------
16279-P................................  AEG Environmental Products & Services,                4      03-31-2016
                                          Inc.; Westminster, MD.
----------------------------------------------------------------------------------------------------------------

[FR Doc. 2016-06055 Filed 3-17-16; 8:45 am]