Paterson Municipal Utilities Authority, Great Falls Hydroelectric Company, City of Paterson, New Jersey; Notice of Application for Transfer of License, and Soliciting Comments and Motions To Intervene, 14437-14438 [2016-06024]
Download as PDF
asabaliauskas on DSK3SPTVN1PROD with NOTICES
Federal Register / Vol. 81, No. 52 / Thursday, March 17, 2016 / Notices
significantly affecting the quality of the
human environment.
The West Virginia Department of
Environmental Protection participated
as a cooperating agency in the
preparation of the EA. Cooperating
agencies have jurisdiction by law or
special expertise with respect to
resources potentially affected by the
proposal and participate in the NEPA
analysis.
The EA addresses the potential
environmental effects of the
construction, modification, and
operation of the following facilities
associated with the Project:
• Four new compressor stations (CS):
Two in Kanawha County, West Virginia
(CS 118A and CS 119A); one in Madison
County, Kentucky (CS 875); and one in
Davidson County, Tennessee (CS 563);
and
• modifications (including
abandonment and replacement of
certain compression units, system
components, and associated facilities) at
the existing Clay City Compressor
Station in Powell County, Kentucky (CS
106), and the existing Catlettsburg
Compressor Station in Boyd County,
Kentucky (CS 114).
The FERC staff mailed copies of the
EA to federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American tribes;
potentially affected landowners and
other interested individuals and groups;
and newspapers and libraries in the
project area. Paper copy versions of the
EA were mailed to those specifically
requesting them; all others received a
CD version. In addition, the EA is
available for public viewing on the
FERC’s Web site (www.ferc.gov) using
the eLibrary link. A limited number of
copies of the EA are available for
distribution and public inspection at:
Federal Energy Regulatory Commission,
Public Reference Room, 888 First Street
NE., Room 2A, Washington, DC 20426,
(202) 502–8371.
Any person wishing to comment on
the EA may do so. Your comments
should focus on the potential
environmental effects, reasonable
alternatives, and measures to avoid or
lessen environmental impacts. The more
specific your comments, the more useful
they will be. To ensure that your
comments are properly recorded and
considered prior to a Commission
decision on the proposal, it is important
that the FERC receives your comments
on or before April 11, 2016.
For your convenience, there are three
methods you can use to submit your
comments to the Commission. In all
VerDate Sep<11>2014
17:03 Mar 16, 2016
Jkt 238001
instances, please reference the project
docket number (CP15–77–000) with
your submission. The Commission
encourages electronic filing of
comments and has expert staff available
to assist you at (202) 502–8258 or
efiling@ferc.gov.
(1) You can file your comments
electronically using the eComment
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. This is an easy
method for submitting brief, text-only
comments on a project;
(2) You can also file your comments
electronically using the eFiling feature
on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. With eFiling,
you can provide comments in a variety
of formats by attaching them as a file
with your submission. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ You must select
the type of filing you are making. If you
are filing a comment on a particular
project, please select ‘‘Comment on a
Filing’’; or
(3) You can file a paper copy of your
comments by mailing them to the
following address: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE., Room
1A, Washington, DC 20426.
Any person seeking to become a party
to the proceeding must file a motion to
intervene pursuant to Rule 214 of the
Commission’s Rules of Practice and
Procedures (Title 18 Code of Federal
Regulations Part 385.214).1 Only
intervenors have the right to seek
rehearing of the Commission’s decision.
The Commission grants affected
landowners and others with
environmental concerns intervenor
status upon showing good cause by
stating that they have a clear and direct
interest in this proceeding that no other
party can adequately represent. Simply
filing environmental comments will not
give you intervenor status, but you do
not need intervenor status to have your
comments considered.
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC Web
site (www.ferc.gov) using the eLibrary
link. Click on the eLibrary link, click on
‘‘General Search,’’ and enter the docket
number excluding the last three digits in
the Docket Number field (i.e., CP15–77).
Be sure you have selected an
appropriate date range. For assistance,
please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free
1 See the previous discussion on the methods for
filing comments.
PO 00000
Frm 00028
Fmt 4703
Sfmt 4703
14437
at (866) 208–3676, or for TTY, contact
(202) 502–8659. The eLibrary link also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Dated: March 11, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–06022 Filed 3–16–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2814–023]
Paterson Municipal Utilities Authority,
Great Falls Hydroelectric Company,
City of Paterson, New Jersey; Notice of
Application for Transfer of License,
and Soliciting Comments and Motions
To Intervene
On February 26 2016, Paterson
Municipal Utilities Authority (PMUA)
and Great Falls Hydroelectric Company
(Great Falls) (transferors/co-licensees)
and the City of Paterson, New Jersey
(transferee/City of Paterson) (Successor
in Interest to PMUA) filed an
application for the transfer of license for
the Great Falls Project No. 2814, located
on the Passaic River in Passaic County,
New Jersey.
Applicants seek Commission approval
to transfer the license for the Great Falls
Project from PMUA and Great Falls who
are currently co-licensees to Great Falls
and the City of Paterson who will
become co-licensees.
Applicants’ Contact: For transferors:
Mr. Robert Gates, Executive Vice
President of Operations, Eagle Creek
Renewable Energy, LLC, 65 Madison
Avenue, Suite 500, Morristown, NJ
07960, Phone: 973–998–8400, Email:
Bob.gates@eaglecreekre.com and Mr.
Joshua E. Adrian, Duncan, Weinberg,
Genzer & Pembroke, P.C., 1615 M Street,
NW., Suite 800, Washington, DC 20036,
Phone: 202–467–6370, Email: jea@
dwgp.com. For transferee: Mr. BenDavid Seligman, Esq., 2nd Asst. Corp.
Counsel, City of Paterson, New Jersey,
E:\FR\FM\17MRN1.SGM
17MRN1
14438
Federal Register / Vol. 81, No. 52 / Thursday, March 17, 2016 / Notices
155 Market Street, Paterson, NJ 07505,
Phone 973–321–1366, Email:
bseligman@patersonnj.gov and Ms. Julia
S. Wood, Van Ness Feldman, LLP, 1050
Thomas Jefferson St. NW., Suite 700,
Washington, DC 20007, Phone: 202–
298–1800, Email: jsw@vnf.com.
FERC Contact: Patricia W. Gillis (202)
502–8735, patricia.gillis@ferc.gov.
Deadline for filing comments, motions
to intervene, and protests: 15 days from
the date that the Commission issues this
notice. The Commission strongly
encourages electronic filing. Please file
comments, motions to intervene, and
protests using the Commission’s eFiling
system at https://www.ferc.gov/docsfiling/efiling.asp. Commenters can
submit brief comments up to 6,000
characters, without prior registration,
using the eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–2814–023.
Dated: March 11, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–06024 Filed 3–16–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
asabaliauskas on DSK3SPTVN1PROD with NOTICES
Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC11–35–000.
Applicants: NSTAR, Northeast
Utilities.
Description: Informational Filing of
Eversource Energy Service Company.
Filed Date: 2/29/16.
Accession Number: 20160229–5193.
Comments Due: 5 p.m. ET 3/22/16.
Docket Numbers: EC16–83–000.
Applicants: High Lonesome Mesa
Wind Holdings, LLC, High Lonesome
Holdings, LLC.
Description: Amendment to February
29, 2016 Application for Authorization
under Section 203 of the Federal Power
Act of High Lonesome Holdings, LLC, et
al.
Filed Date: 3/10/16.
VerDate Sep<11>2014
17:03 Mar 16, 2016
Jkt 238001
Accession Number: 20160310–5212.
Comments Due: 5 p.m. ET 3/21/16.
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG16–69–000.
Applicants: Roswell Solar, LLC.
Description: Notice of SelfCertification of Exempt Wholesale
Generator Status of Roswell Solar, LLC.
Filed Date: 3/11/16.
Accession Number: 20160311–5047.
Comments Due: 5 p.m. ET 4/1/16.
Docket Numbers: EG16–70–000.
Applicants: Chaves County Solar,
LLC.
Description: Notice of SelfCertification of Exempt Wholesale
Generator Status of Chaves County
Solar, LLC.
Filed Date: 3/11/16.
Accession Number: 20160311–5050.
Comments Due: 5 p.m. ET 4/1/16.
Take notice that the Commission
received the following electric rate
filings:.
Docket Numbers: ER13–96–008.
Applicants: Black Hills Power, Inc.
Description: Compliance filing:
Compliance Filing to Correct eTariff
Record to be effective 10/1/2015.
Filed Date: 3/10/16.
Accession Number: 20160310–5184.
Comments Due: 5 p.m. ET 3/31/16.
Docket Numbers: ER13–97–008.
Applicants: Black Hills/Colorado
Electric Utility Co.
Description: Compliance filing:
Compliance Filing to Correct eTariff
Record to be effective 10/1/2015.
Filed Date: 3/10/16.
Accession Number: 20160310–5185.
Comments Due: 5 p.m. ET 3/31/16.
Docket Numbers: ER13–120–008.
Applicants: Cheyenne Light, Fuel and
Power Company.
Description: Compliance filing:
Compliance Filing to Correct eTariff
Record to be effective 10/1/2015.
Filed Date: 3/10/16.
Accession Number: 20160310–5186.
Comments Due: 5 p.m. ET 3/31/16.
Docket Numbers: ER15–1218–002;
ER15–2224–001.
Applicants: Solar Star California XIII,
LLC, Solar Star Colorado III, LLC.
Description: Notice of Non-Material
Change in Status of Solar Star California
XIII, LLC and Solar Star Colorado III,
LLC.
Filed Date: 3/10/16.
Accession Number: 20160310–5206.
Comments Due: 5 p.m. ET 3/31/16.
Docket Numbers: ER16–168–002.
Applicants: New York Independent
System Operator, Inc.
Description: Compliance filing:
NYISO compliance re: unauthorized
PO 00000
Frm 00029
Fmt 4703
Sfmt 4703
natural gas use to be effective 2/18/
2016.
Filed Date: 3/11/16.
Accession Number: 20160311–5051.
Comments Due: 5 p.m. ET 4/1/16.
Docket Numbers: ER16–532–001.
Applicants: PJM Interconnection,
L.L.C.
Description: Compliance filing:
Compliance Filing per 2/12/16 Order in
Docket No. ER16–532 to be effective 2/
15/2016.
Filed Date: 3/11/16.
Accession Number: 20160311–5197.
Comments Due: 5 p.m. ET 4/1/16.
Docket Numbers: ER16–917–001;
ER14–2458–001; ER11–3013–005;
ER10–2872–005; ER10–2870–006;
ER10–2868–005; ER10–2865–006;
ER10–2860–007.
Applicants: TC Ironwood LLC,
TransCanada Power Marketing Ltd,
TransCanada Energy Sales Ltd., TC
Ravenswood, LLC, TransCanada Maine
Wind Development Inc., TransCanada
Hydro Northeast Inc., Ocean State
Power LLC, Coolidge Power LLC.
Description: Amendment to March 2,
2016 Notice of Non-Material Change in
Status of TransCanada MBR Sellers.
Filed Date: 3/8/16.
Accession Number: 20160308–5148.
Comments Due: 5 p.m. ET 3/18/16.
Docket Numbers: ER16–1135–000.
Applicants: Healthy Planet Partners
Energy Company, LLC.
Description: Tariff Cancellation:
MBRA Amendment Cancellation to be
effective 3/31/2016.
Filed Date: 3/11/16.
Accession Number: 20160311–5007.
Comments Due: 5 p.m. ET 4/1/16.
Docket Numbers: ER16–1136–000.
Applicants: Southwest Power Pool,
Inc.
Description: § 205(d) Rate Filing:
1154R12 Associated Electric
Cooperative NITSA and NOA to be
effective 3/1/2016.
Filed Date: 3/11/16.
Accession Number: 20160311–5049.
Comments Due: 5 p.m. ET 4/1/16.
Docket Numbers: ER16–1138–000.
Applicants: PJM Interconnection,
L.L.C.
Description: Request of PJM
Interconnection, L.L.C. for Limited
Tariff Waiver and Expedited Treatment.
Filed Date: 3/11/16.
Accession Number: 20160311–5083.
Comments Due: 5 p.m. ET 03/21/16.
Docket Numbers: ER16–1142–000.
Applicants: Innovative Solar 43, LLC.
Description: Tariff Cancellation:
Innovative Solar 43, LLC Notice of
Cancellation to be effective 3/12/2016.
Filed Date: 3/11/16.
E:\FR\FM\17MRN1.SGM
17MRN1
Agencies
[Federal Register Volume 81, Number 52 (Thursday, March 17, 2016)]
[Notices]
[Pages 14437-14438]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-06024]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2814-023]
Paterson Municipal Utilities Authority, Great Falls Hydroelectric
Company, City of Paterson, New Jersey; Notice of Application for
Transfer of License, and Soliciting Comments and Motions To Intervene
On February 26 2016, Paterson Municipal Utilities Authority (PMUA)
and Great Falls Hydroelectric Company (Great Falls) (transferors/co-
licensees) and the City of Paterson, New Jersey (transferee/City of
Paterson) (Successor in Interest to PMUA) filed an application for the
transfer of license for the Great Falls Project No. 2814, located on
the Passaic River in Passaic County, New Jersey.
Applicants seek Commission approval to transfer the license for the
Great Falls Project from PMUA and Great Falls who are currently co-
licensees to Great Falls and the City of Paterson who will become co-
licensees.
Applicants' Contact: For transferors: Mr. Robert Gates, Executive
Vice President of Operations, Eagle Creek Renewable Energy, LLC, 65
Madison Avenue, Suite 500, Morristown, NJ 07960, Phone: 973-998-8400,
Email: Bob.gates@eaglecreekre.com and Mr. Joshua E. Adrian, Duncan,
Weinberg, Genzer & Pembroke, P.C., 1615 M Street, NW., Suite 800,
Washington, DC 20036, Phone: 202-467-6370, Email: jea@dwgp.com. For
transferee: Mr. Ben-David Seligman, Esq., 2nd Asst. Corp. Counsel, City
of Paterson, New Jersey,
[[Page 14438]]
155 Market Street, Paterson, NJ 07505, Phone 973-321-1366, Email:
bseligman@patersonnj.gov and Ms. Julia S. Wood, Van Ness Feldman, LLP,
1050 Thomas Jefferson St. NW., Suite 700, Washington, DC 20007, Phone:
202-298-1800, Email: jsw@vnf.com.
FERC Contact: Patricia W. Gillis (202) 502-8735,
patricia.gillis@ferc.gov.
Deadline for filing comments, motions to intervene, and protests:
15 days from the date that the Commission issues this notice. The
Commission strongly encourages electronic filing. Please file comments,
motions to intervene, and protests using the Commission's eFiling
system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can
submit brief comments up to 6,000 characters, without prior
registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information
at the end of your comments. For assistance, please contact FERC Online
Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper
copy to: Secretary, Federal Energy Regulatory Commission, 888 First
Street NE., Washington, DC 20426. The first page of any filing should
include docket number P-2814-023.
Dated: March 11, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.