Freeport LNG Development, L.P., FLNG Liquefaction, LLC, FLNG Liquefaction 2, LLC, FLNG Liquefaction 3, LLC; Notice of Schedule for Environmental Review of the Freeport LNG Capacity Uprate Project, 12092 [2016-05098]
Download as PDF
12092
Federal Register / Vol. 81, No. 45 / Tuesday, March 8, 2016 / Notices
[FR Doc. 2016–05155 Filed 3–7–16; 8:45 am]
BILLING CODE 4000–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP15–518–000]
Freeport LNG Development, L.P., FLNG
Liquefaction, LLC, FLNG Liquefaction
2, LLC, FLNG Liquefaction 3, LLC;
Notice of Schedule for Environmental
Review of the Freeport LNG Capacity
Uprate Project
On June 15, 2015, Freeport LNG
Development, L.P., FLNG Liquefaction,
LLC, FLNG Liquefaction 2, LLC, and
FLNG Liquefaction 3, LLC (collectively
referred to as Freeport LNG) filed an
application pursuant to Section 3(a) of
the Natural Gas Act to amend the
existing authorization for the
Liquefaction Project, located in Brazoria
County near Freeport, Texas. The
proposed project is known as the
Capacity Uprate Project (Project), and
would allow for the liquefaction and
export of an additional 0.34 billion
cubic feet per day (bcf/d) equivalent of
liquefied natural gas.
On June 24, 2015, the Federal Energy
Regulatory Commission (Commission or
FERC) issued its Notice of Application
for the Project. Among other things, that
notice alerted agencies issuing federal
authorizations of the requirement to
complete all necessary reviews and to
reach a final decision on a request for
a federal authorization within 90 days of
the date of issuance of the Commission
staff’s Environmental Assessment (EA)
for the Project. This instant notice
identifies the FERC staff’s planned
schedule for the completion of the EA
for the Project.
asabaliauskas on DSK3SPTVN1PROD with NOTICES
Schedule for Environmental Review
Issuance of EA March 31, 2016
90-day Federal Authorization Decision
Deadline June 29, 2016
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the Project’s
progress.
Project Description
Freeport LNG is seeking approval of
an increase in the LNG production
capacity of the previously approved
Liquefaction Project from 1.8 bcf/d to
about 2.14 Bcf/d. This is the estimated
maximum LNG production capacity of
the Liquefaction Project available for
export under optimal operating
conditions. The currently authorized
VerDate Sep<11>2014
17:02 Mar 07, 2016
Jkt 238001
liquefaction capacity for the
Liquefaction Project was determined by
Freeport LNG during the early stages
engineering design. This amendment
identifies and requests that the
maximum quantity of LNG that could be
produced in a particular year under
well-developed engineering design
parameters and specific operating
conditions be used as the approved
volumes.
Background
Freeport LNG identified no additional
facilities or modification that would be
necessary to enable the uprate. We
received a request to intervene from the
Sierra Club that included some
environmental comments.
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC Web
site (www.ferc.gov). Using the
‘‘eLibrary’’ link, select ‘‘General Search’’
from the eLibrary menu, enter the
selected date range and ‘‘Docket
Number’’ excluding the last three digits
(i.e., CP15–518), and follow the
instructions. For assistance with access
to eLibrary, the helpline can be reached
at (866) 208–3676, TTY (202) 502–8659,
or at FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC Web site also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Dated: March 2, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–05098 Filed 3–7–16; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00028
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 308–000]
PacifiCorp Energy; Notice of
Authorization for Continued Project
Operation
On February 28, 2014, PacifiCorp
Energy, licensee for the Wallowa Falls
Hydroelectric Project, filed an
Application for a New License pursuant
to the Federal Power Act (FPA) and the
Commission’s regulations thereunder.
The Wallowa Falls Hydroelectric Project
is located on the East and West Forks of
the Wallowa River and Royal Purple
Creek in Wallowa County, Oregon.
The license for Project No. 308 was
issued for a period ending February 28,
2016. Section 15(a)(1) of the FPA, 16
U.S.C. 808(a)(1), requires the
Commission, at the expiration of a
license term, to issue from year-to-year
an annual license to the then licensee
under the terms and conditions of the
prior license until a new license is
issued, or the project is otherwise
disposed of as provided in section 15 or
any other applicable section of the FPA.
If the project’s prior license waived the
applicability of section 15 of the FPA,
then, based on section 9(b) of the
Administrative Procedure Act, 5 U.S.C.
558(c), and as set forth at 18 CFR
16.21(a), if the licensee of such project
has filed an application for a subsequent
license, the licensee may continue to
operate the project in accordance with
the terms and conditions of the license
after the minor or minor part license
expires, until the Commission acts on
its application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 308 is
issued to the licensee for a period
effective March 1, 2016 through
February 28, 2017 or until the issuance
of a new license for the project or other
disposition under the FPA, whichever
comes first. If issuance of a new license
(or other disposition) does not take
place on or before February 28, 2017,
notice is hereby given that, pursuant to
18 CFR 16.18(c), an annual license
under section 15(a)(1) of the FPA is
renewed automatically without further
order or notice by the Commission,
E:\FR\FM\08MRN1.SGM
08MRN1
Agencies
[Federal Register Volume 81, Number 45 (Tuesday, March 8, 2016)]
[Notices]
[Page 12092]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-05098]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP15-518-000]
Freeport LNG Development, L.P., FLNG Liquefaction, LLC, FLNG
Liquefaction 2, LLC, FLNG Liquefaction 3, LLC; Notice of Schedule for
Environmental Review of the Freeport LNG Capacity Uprate Project
On June 15, 2015, Freeport LNG Development, L.P., FLNG
Liquefaction, LLC, FLNG Liquefaction 2, LLC, and FLNG Liquefaction 3,
LLC (collectively referred to as Freeport LNG) filed an application
pursuant to Section 3(a) of the Natural Gas Act to amend the existing
authorization for the Liquefaction Project, located in Brazoria County
near Freeport, Texas. The proposed project is known as the Capacity
Uprate Project (Project), and would allow for the liquefaction and
export of an additional 0.34 billion cubic feet per day (bcf/d)
equivalent of liquefied natural gas.
On June 24, 2015, the Federal Energy Regulatory Commission
(Commission or FERC) issued its Notice of Application for the Project.
Among other things, that notice alerted agencies issuing federal
authorizations of the requirement to complete all necessary reviews and
to reach a final decision on a request for a federal authorization
within 90 days of the date of issuance of the Commission staff's
Environmental Assessment (EA) for the Project. This instant notice
identifies the FERC staff's planned schedule for the completion of the
EA for the Project.
Schedule for Environmental Review
Issuance of EA March 31, 2016
90-day Federal Authorization Decision Deadline June 29, 2016
If a schedule change becomes necessary, additional notice will be
provided so that the relevant agencies are kept informed of the
Project's progress.
Project Description
Freeport LNG is seeking approval of an increase in the LNG
production capacity of the previously approved Liquefaction Project
from 1.8 bcf/d to about 2.14 Bcf/d. This is the estimated maximum LNG
production capacity of the Liquefaction Project available for export
under optimal operating conditions. The currently authorized
liquefaction capacity for the Liquefaction Project was determined by
Freeport LNG during the early stages engineering design. This amendment
identifies and requests that the maximum quantity of LNG that could be
produced in a particular year under well-developed engineering design
parameters and specific operating conditions be used as the approved
volumes.
Background
Freeport LNG identified no additional facilities or modification
that would be necessary to enable the uprate. We received a request to
intervene from the Sierra Club that included some environmental
comments.
Additional Information
In order to receive notification of the issuance of the EA and to
keep track of all formal issuances and submittals in specific dockets,
the Commission offers a free service called eSubscription. This can
reduce the amount of time you spend researching proceedings by
automatically providing you with notification of these filings,
document summaries, and direct links to the documents. Go to
www.ferc.gov/docs-filing/esubscription.asp.
Additional information about the Project is available from the
Commission's Office of External Affairs at (866) 208-FERC or on the
FERC Web site (www.ferc.gov). Using the ``eLibrary'' link, select
``General Search'' from the eLibrary menu, enter the selected date
range and ``Docket Number'' excluding the last three digits (i.e.,
CP15-518), and follow the instructions. For assistance with access to
eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-
8659, or at FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC
Web site also provides access to the texts of formal documents issued
by the Commission, such as orders, notices, and rule makings.
Dated: March 2, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-05098 Filed 3-7-16; 8:45 am]
BILLING CODE 6717-01-P