Notice of Commission Staff Attendance, 10611 [2016-04388]
Download as PDF
asabaliauskas on DSK5VPTVN1PROD with NOTICES
Federal Register / Vol. 81, No. 40 / Tuesday, March 1, 2016 / Notices
• The options and implications for,
and potential benefits or drawbacks of,
ARR allocation based on more frequent
updates of the Simultaneous Feasibility
Test model, which could, for example,
allow for seasonal variations of line
ratings, as well as more timely
recognition and modeling of
transmission outages and upgrades
placed into service.
• The options to update PJM’s
Simultaneous Feasibility Test model,
including source points and sink points,
to reflect current system usage and
topology; concerns about updating the
model; the potential benefits or
drawbacks for updating the model; and
processes for allowing more frequent
updates. If the Simultaneous Feasibility
Test model were to be updated more
frequently, would infeasible ARRs
continue to exist?
• Whether the incentives for
Transmission Owners to schedule
outages and conduct timely work align
with ARR/FTR construct, and whether
there are any proposals that can
improve this alignment; and the
effectiveness of the current reporting
requirements for Transmission Owners
to share information with PJM.
• Whether continuing to include
balancing congestion 1 in the definition
of FTRs is appropriate (and why), or
whether FTRs should be defined and
settled only including day-ahead
congestion. Are there any aspect(s) of
balancing congestion that should be
included in the definition of FTRs, and,
if so, what are they and why they
should be included?
Commenters need not address every
question and may provide comments on
relevant issues other than those listed
above. These comments are due no later
than 5:00 p.m. Eastern Standard Time
(EST) on March 15, 2016. Reply
comments are due on or before 5:00
p.m. EST on March 29, 2016. The
written comments will be included in
the formal record for the proceeding,
which, together with the record
developed to date, will form the basis
for further Commission action.
For more information about this
Notice, please contact:
Pamela Quinlan (Technical
Information), Office of Energy Market
Regulation, Federal Energy Regulatory
Commission, 888 First Street NE.,
Washington, DC 20426, (202) 502–
6179, Pamela.Quinlan@ferc.gov
1 Negative balancing congestion occurs when realtime transmission capacity is less than day-ahead
transmission capacity. FTRs are allocated negative
balancing congestion charges, which in turn can
result in FTR underfunding because the revenues
allocated for meeting the FTR funding target
amount are decreased.
VerDate Sep<11>2014
20:18 Feb 29, 2016
Jkt 238001
Kent Carter (Legal Information), Office
of General Counsel, Federal Energy
Regulatory Commission, 888 First
Street NE., Washington, DC 20426,
(202) 502–8604, Kent.Carter@ferc.gov
Daniel Kheloussi (Technical
Information), Office of Energy Policy
and Innovation, Federal Energy
Regulatory Commission, 888 First
Street NE., Washington, DC 20426,
(202) 502–6391, Daniel.Kheloussi@
ferc.gov
Dated: February 23, 2016.
Nathaniel J. Davis, Sr.
Deputy Secretary.
[FR Doc. 2016–04388 Filed 2–29–16; 8:45 am]
BILLING CODE 6717–01–P
Federal Energy Regulatory
Commission
Clark Canyon Hydro, LLC ; Notice of
Application Accepted for Filing,
Soliciting Motions To Intervene and
Protests, Ready for Environmental
Analysis, and Soliciting Comments,
Terms and Conditions,
Recommendations, and Prescriptions
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Commission Staff
Attendance
The Federal Energy Regulatory
Commission (Commission) hereby gives
notice that members of the
Commission’s staff may attend the
following meetings related to the
transmission planning activities of
Public Service Company of Colorado,
Tucson Electric Power Company, UNS
Electric, Inc., Public Service Company
of New Mexico, Arizona Public Service
Company, El Paso Electric Company,
Black Hills Power, Inc., Black Hills
Colorado Electric Utility Company, LP,
Cheyenne Light, Fuel, & Power
Company, Arizona Public Service
Company, and NV Energy, Inc.:
Regional Stakeholder Meeting
February 24, 2016, 1 p.m.–4:30 p.m.
(MST)
Planning Management Committee
Meeting
April 5, 2016, 9 a.m.–12 p.m. (PST)
The above-referenced meetings will
be held at: SRP PERA Club, 1 E.
Continental Drive, Tempe, Arizona
85281.
The above-referenced meetings will
be available via web conference and
teleconference.
The above-referenced meetings are
open to stakeholders.
Further information may be found at
https://www.westconnect.com/
index.php.
The discussions at the meetings
described above may address matters at
issue in the following proceeding:
ER16–912, Arizona Public Service
Company.
Fmt 4703
Dated: February 23, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[Project No. 14677–001]
BILLING CODE 6717–01–P
Frm 00047
For more information contact Nicole
Cramer, Office of Energy Market
Regulation, Federal Energy Regulatory
Commission at (202) 502–6775 or
nicole.cramer@ferc.gov.
DEPARTMENT OF ENERGY
[FR Doc. 2016–04387 Filed 2–29–16; 8:45 am]
PO 00000
10611
Sfmt 4703
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Original
License for a Major Water Power Project
at an Existing Dam, 5 Megawatts or Less.
b. Project No.: 14677–001.
c. Date filed: November 23, 2015.
d. Applicant: Clark Canyon Hydro,
LLC.
e. Name of Project: Clark Canyon Dam
Hydroelectric Project.
f. Location: On the River, in the Town
of Dillon, Beaverhead County, Montana.
The project would occupy 62.1 acres of
land owned by the U.S. Bureau of
Reclamation and 0.2 acres of land
owned by the U.S. Bureau of Land
Management.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: John Gangemi,
(406) 249–3972, email at john.gangemi@
erm.com.
i. FERC Contact: Kelly Wolcott, (202)
502–6480, email at kelly.wolcott@
ferc.gov.
j. Deadline for filing motions to
intervene and protests, comments, terms
and conditions, recommendations, and
prescriptions: 30 days from the issuance
date of this notice; reply comments are
due 45 days from the issuance date of
this notice.
The Commission strongly encourages
electronic filing. Please file motions to
intervene and protests, comments, terms
and conditions, recommendations, and
prescriptions using the Commission’s
eFiling system at https://www.ferc.gov/
docs-filing/efiling.asp. Commenters can
E:\FR\FM\01MRN1.SGM
01MRN1
Agencies
[Federal Register Volume 81, Number 40 (Tuesday, March 1, 2016)]
[Notices]
[Page 10611]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-04388]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice of Commission Staff Attendance
The Federal Energy Regulatory Commission (Commission) hereby gives
notice that members of the Commission's staff may attend the following
meetings related to the transmission planning activities of Public
Service Company of Colorado, Tucson Electric Power Company, UNS
Electric, Inc., Public Service Company of New Mexico, Arizona Public
Service Company, El Paso Electric Company, Black Hills Power, Inc.,
Black Hills Colorado Electric Utility Company, LP, Cheyenne Light,
Fuel, & Power Company, Arizona Public Service Company, and NV Energy,
Inc.:
Regional Stakeholder Meeting
February 24, 2016, 1 p.m.-4:30 p.m. (MST)
Planning Management Committee Meeting
April 5, 2016, 9 a.m.-12 p.m. (PST)
The above-referenced meetings will be held at: SRP PERA Club, 1 E.
Continental Drive, Tempe, Arizona 85281.
The above-referenced meetings will be available via web conference
and teleconference.
The above-referenced meetings are open to stakeholders.
Further information may be found at https://www.westconnect.com/index.php.
The discussions at the meetings described above may address matters
at issue in the following proceeding:
ER16-912, Arizona Public Service Company.
For more information contact Nicole Cramer, Office of Energy Market
Regulation, Federal Energy Regulatory Commission at (202) 502-6775 or
nicole.cramer@ferc.gov.
Dated: February 23, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-04388 Filed 2-29-16; 8:45 am]