Alpine Pacific Utilities, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 9840-9841 [2016-04161]
Download as PDF
mstockstill on DSK4VPTVN1PROD with NOTICES
9840
Federal Register / Vol. 81, No. 38 / Friday, February 26, 2016 / Notices
proposal in the final EIS, it is important
that the Commission receive your
comments on or before April 11, 2016.
For your convenience, there are four
methods you can use to submit your
comments to the Commission. The
Commission will provide equal
consideration to all comments received,
whether filed in written form or
provided verbally. The Commission
encourages electronic filing of
comments and has expert staff available
to assist you at (202) 502–8258 or
efiling@ferc.gov. Please carefully follow
these instructions so that your
comments are properly recorded.
(1) You can file your comments
electronically using the eComment
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. This is an easy
method for submitting brief, text-only
comments on a project;
(2) You can file your comments
electronically by using the eFiling
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. With eFiling,
you can provide comments in a variety
of formats by attaching them as a file
with your submission. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ If you are filing
a comment on a particular project,
please select ‘‘Comment on a Filing’’ as
the filing type; or
(3) You can file a paper copy of your
comments by mailing them to the
following address. Be sure to reference
the applicable project docket number
(CP15–93–000, CP15–94–000, or CP15–
96–000) with your submission:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Room 1A,
Washington, DC 20426.
(4) In lieu of sending written or
electronic comments, the Commission
invites you to attend one of the public
comment meetings its staff will conduct
in the Project area to receive comments
on the draft EIS. The date, time, and
location of the public comment
meetings will be published in a separate
Notice and will be mailed to all those
receiving the draft EIS and posted on
the FERC Web site (www.ferc.gov). The
meetings will be recorded by a court
reporter to ensure comments are
accurately recorded. Transcripts will be
placed into the formal record of the
Commission proceeding and available
for public review.
Any person seeking to become a party
to the proceeding must file a motion to
intervene pursuant to Rule 214 of the
Commission’s Rules of Practice and
VerDate Sep<11>2014
20:41 Feb 25, 2016
Jkt 238001
Procedures (18 CFR part 385.214).2 Only
intervenors have the right to seek
rehearing of the Commission’s decision.
The Commission grants affected
landowners and others with
environmental concerns intervenor
status upon showing good cause by
stating that they have a clear and direct
interest in this proceeding which no
other party can adequately represent.
Simply filing environmental comments
will not give you intervenor status, but
you do not need intervenor status to
have your comments considered.
Questions?
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC Web
site (www.ferc.gov) using the eLibrary
link. Click on the eLibrary link, click on
‘‘General Search,’’ and enter the docket
number excluding the last three digits in
the Docket Number field (i.e., CP15–93,
CP15–94, or CP15–96). Be sure you have
selected an appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at (866) 208–3676; for TTY,
contact (202) 502–8659. The eLibrary
link also provides access to the texts of
formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission offers a
free service called eSubscription that
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Dated: February 19, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–04142 Filed 2–25–16; 8:45 am]
BILLING CODE 6717–01–P
2 See the previous discussion on the methods for
filing comments.
PO 00000
Frm 00037
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 1 4751–001]
Alpine Pacific Utilities, LLC; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
On January 22, 2016, Alpine Pacific
Utilities, LLC filed an application for a
preliminary permit, pursuant to section
4(f) of the Federal Power Act (FPA),
proposing to study the feasibility of the
Fresno Dam Site Water Power Project
(Fresno Dam Project or project) to be
located in Hill County, Montana near
the town of Kremlin at the existing
Bureau of Reclamation Fresno Dam
located on the Milk River. The sole
purpose of a preliminary permit, if
issued, is to grant the permit holder
priority to file a license application
during the permit term. A preliminary
permit does not authorize the permit
holder to perform any land-disturbing
activities or otherwise enter upon lands
or waters owned by others without the
owners’ express permission.
The proposed project would utilize
the existing outlet structure on Fresno
Dam. The proposed project would
consist of the following new facilities:
(1) A 48-inch-diameter, 100-foot-long
bifurcated penstock leading from the
existing outlet works; (2) a powerhouse
containing two turbines/generating
units with a combined installed
capacity of 1.348 megawatts; (3) a
tailrace discharging flows into the
existing dam spillway; (4) a transformer
in a 25-square-foot switchyard; (5) an
approximately 1-mile-long, 12.74kilovolt overhead transmission line
connecting to existing Hill County
Electric and Northwest Electric
transmission systems; and (6)
appurtenant facilities. The proposed
project would have an average annual
generation of 4,700 megawatt-hours
Applicant Contact: Justin D. Ahmann,
Alpine Pacific Utilities, LLC, 111
Legend Trail, Kalispell, MT 59901.
FERC Contact: Ryan Hansen, phone:
(202) 502–8074, or email ryan.hansen@
ferc.gov.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
Days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
E:\FR\FM\26FEN1.SGM
26FEN1
Federal Register / Vol. 81, No. 38 / Friday, February 26, 2016 / Notices
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–14751–001.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P–14751) in
the docket number field to access the
document. For assistance, contact FERC
Online Support.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: February 19, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–04145 Filed 2–25–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Dated: February 17, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
Federal Energy Regulatory
Commission
[FR Doc. 2016–04161 Filed 2–25–16; 8:45 am]
BILLING CODE 6717–01–P
Combined Notice of Filings
DEPARTMENT OF ENERGY
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
Federal Energy Regulatory
Commission
mstockstill on DSK4VPTVN1PROD with NOTICES
Combined Notice of Filings #2
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER16–64–001.
Applicants: Tallbear Seville LLC.
Description: Report Filing: Refund
Report to be effective N/A.
Filed Date: 2/19/16.
Accession Number: 20160219–5133.
Comments Due: 5 p.m. ET 3/11/16.
Docket Numbers: ER16–778–001.
Applicants: MATL LLP.
Description: Tariff Amendment:
MATL Amendment of Pending Tariff
Filing to be effective 3/26/2016.
Filed Date: 2/19/16.
Accession Number: 20160219–5046.
Comments Due: 5 p.m. ET 2/29/16.
Docket Numbers: ER16–970–000.
Applicants: MATL LLP.
Description: § 205(d) Rate Filing:
MATL Concurrrence to be effective 3/
26/2016.
Filed Date: 2/19/16.
Accession Number: 20160219–5042.
Comments Due: 5 p.m. ET 3/11/16.
VerDate Sep<11>2014
20:41 Feb 25, 2016
Jkt 238001
Filings Instituting Proceedings
Docket Numbers: PR16–25–000.
Applicants: Columbia Gas of Ohio,
Inc.
Description: Tariff filing per
284.123(b)(1)/.: COH 2–16–2016 SOC to
be effective 2/1/2016; Filing Type: 980.
Filed Date: 2/16/16.
Accession Number: 201602165220.
Comments/Protests Due: 5 p.m. ET 3/
8/16.
Docket Number: PR16–17–001.
Applicants: Acadian Gas Pipeline
System.
Description: Tariff filing per
284.123(b), (e), (g): Amended SOC
Update per FERC Order 809 to be
effective 4/1/2016; Filing Type: 1270.
Filed Date: 2/17/2016.
Accession Number: 201602175169.
Comments Due: 5 p.m. ET 3/9/16.
284.123(g) Protests Due: 5 p.m. ET 3/
28/16.
Docket Number: PR16–20–001.
Applicants: Enterprise Texas Pipeline
LLC.
Description: Tariff filing per
284.123(b), (e), (g): Amended SOC
Update per FERC Order 809 to be
effective 4/1/2016; Filing Type: 1270.
PO 00000
Frm 00038
Fmt 4703
Sfmt 4703
9841
Filed Date: 2/18/2016.
Accession Number: 201602185053.
Comments Due: 5 p.m. ET 3/10/16.
284.123(g) Protests Due: 5 p.m. ET 3/
29/16.
Docket Number: PR16–23–001.
Applicants: Enterprise Intrastate LLC.
Description: Tariff filing per
284.123(b), (e), (g): Amended SOC
Update per FERC Order 809 to be
effective 4/1/2016; Filing Type: 1270.
Filed Date: 2/18/2016.
Accession Number: 201602185045.
Comments Due: 5 p.m. ET 3/10/16.
284.123(g) Protests Due: 5 p.m. ET 3/
29/16.
Docket Number: PR16–23–002.
Applicants: Enterprise Intrastate LLC.
Description: Tariff filing per
284.123(b), (e), (g): Amended Section
18.5 & 18.6 of SOC Update per FERC
Order 809 to be effective 4/1/2016;
Filing Type: 1270.
Filed Date: 2/18/2016.
Accession Number: 201602185192.
Comments Due: 5 p.m. ET 3/10/16.
284.123(g) Protests Due: 5 p.m. ET 3/
29/16.
Docket Numbers: RP16–614–000.
Applicants: Midcontinent Express
Pipeline LLC.
Description: Annual Report of
Operational Purchases and Sales of
Midcontinent Express Pipeline LLC
under RP16–614.
Filed Date: 2/18/16.
Accession Number: 20160218–5075.
Comments Due: 5 p.m. ET 3/1/16.
Docket Numbers: RP16–615–000.
Applicants: WPX Energy Holdings,
LLC,Terra Energy Partners LLC,WPX
Energy Marketing, LLC,WPX Energy
Rocky Mountain, LLC.
Description: Joint Petition of WPX
Energy Holdings, LLC, WPX Energy
Marketing, LLC, WPX Energy Rocky
Mountain, LLC and Terra Energy
Partners LLC for Temporary Waiver of
Capacity Release and Certain Other
Regulations and Policies and Related
Tariff Provisions.
Filed Date: 2/18/16.
Accession Number: 20160218–5156.
Comments Due: 5 p.m. ET 2/29/16.
Docket Numbers: RP16–616–000.
Applicants: Southern Natural Gas
Company, L.L.C.
Description: § 4(d) Rate Filing: Fuel
Retention Rates—Spring 2016 to be
effective 4/1/2016.
Filed Date: 2/19/16.
Accession Number: 20160219–5000.
Comments Due: 5 p.m. ET 3/2/16.
Docket Numbers: RP16–617–000.
Applicants: Southwest Gas Storage
Company.
Description: § 4(d) Rate Filing:
Housekeeping and Contracting
Provisions to be effective 3/21/2016.
E:\FR\FM\26FEN1.SGM
26FEN1
Agencies
[Federal Register Volume 81, Number 38 (Friday, February 26, 2016)]
[Notices]
[Pages 9840-9841]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-04161]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 1 4751-001]
Alpine Pacific Utilities, LLC; Notice of Preliminary Permit
Application Accepted for Filing and Soliciting Comments, Motions To
Intervene, and Competing Applications
On January 22, 2016, Alpine Pacific Utilities, LLC filed an
application for a preliminary permit, pursuant to section 4(f) of the
Federal Power Act (FPA), proposing to study the feasibility of the
Fresno Dam Site Water Power Project (Fresno Dam Project or project) to
be located in Hill County, Montana near the town of Kremlin at the
existing Bureau of Reclamation Fresno Dam located on the Milk River.
The sole purpose of a preliminary permit, if issued, is to grant the
permit holder priority to file a license application during the permit
term. A preliminary permit does not authorize the permit holder to
perform any land-disturbing activities or otherwise enter upon lands or
waters owned by others without the owners' express permission.
The proposed project would utilize the existing outlet structure on
Fresno Dam. The proposed project would consist of the following new
facilities: (1) A 48-inch-diameter, 100-foot-long bifurcated penstock
leading from the existing outlet works; (2) a powerhouse containing two
turbines/generating units with a combined installed capacity of 1.348
megawatts; (3) a tailrace discharging flows into the existing dam
spillway; (4) a transformer in a 25-square-foot switchyard; (5) an
approximately 1-mile-long, 12.74-kilovolt overhead transmission line
connecting to existing Hill County Electric and Northwest Electric
transmission systems; and (6) appurtenant facilities. The proposed
project would have an average annual generation of 4,700 megawatt-hours
Applicant Contact: Justin D. Ahmann, Alpine Pacific Utilities, LLC,
111 Legend Trail, Kalispell, MT 59901.
FERC Contact: Ryan Hansen, phone: (202) 502-8074, or email
ryan.hansen@ferc.gov.
Deadline for filing comments, motions to intervene, competing
applications (without notices of intent), or notices of intent to file
competing applications: 60 Days from the issuance of this notice.
Competing applications and notices of intent must meet the requirements
of 18 CFR 4.36.
The Commission strongly encourages electronic filing. Please file
comments,
[[Page 9841]]
motions to intervene, notices of intent, and competing applications
using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000
characters, without prior registration, using the eComment system at
https://www.ferc.gov/docs-filing/ecomment.asp. You must include your
name and contact information at the end of your comments. For
assistance, please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to:
Secretary, Federal Energy Regulatory Commission, 888 First Street NE.,
Washington, DC 20426. The first page of any filing should include
docket number P-14751-001.
More information about this project, including a copy of the
application, can be viewed or printed on the ``eLibrary'' link of
Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P-14751) in the docket number field to access
the document. For assistance, contact FERC Online Support.
Dated: February 17, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-04161 Filed 2-25-16; 8:45 am]
BILLING CODE 6717-01-P