Ketchikan Public Utilities; Notice of Application Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests, 9843-9844 [2016-04160]
Download as PDF
Federal Register / Vol. 81, No. 38 / Friday, February 26, 2016 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
mstockstill on DSK4VPTVN1PROD with NOTICES
Combined Notice of Filings #2
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC16–74–000.
Applicants: Black Hills Colorado IPP,
LLC.
Description: Application for
Authorization under Section 203 of the
Federal Power Act of Black Hills
Colorado IPP, LLC.
Filed Date: 2/17/16.
Accession Number: 20160217–5171.
Comments Due: 5 p.m. ET 3/9/16.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER10–1350–006.
Applicants: Entergy Services, Inc.
Description: Entergy Services, Inc.
submits Compliance Filing Pursuant to
Opinion No. 545.
Filed Date: 2/16/16.
Accession Number: 20160216–5413.
Comments Due: 5 p.m. ET 3/8/16.
Docket Numbers: ER16–780–001.
Applicants: Southwest Power Pool,
Inc.
Description: Tariff Amendment:
1166R27 Oklahoma Municipal Power
Authority NITSA and NOA to be
effective 1/1/2016.
Filed Date: 2/17/16.
Accession Number: 20160217–5160.
Comments Due: 5 p.m. ET 3/9/16.
Docket Numbers: ER16–955–000.
Applicants: Red Horse Wind 2, LLC.
Description: Baseline eTariff Filing:
Shared Facilities Agreement to be
effective 4/4/2016.
Filed Date: 2/17/16.
Accession Number: 20160217–5125.
Comments Due: 5 p.m. ET 3/9/16.
Docket Numbers: ER16–956–000.
Applicants: Southern California
Edison Company.
Description: § 205(d) Rate Filing:
LGIA Aurora Solar LLC Sorrel I Solar
Farm Project to be effective 2/18/2016.
Filed Date: 2/17/16.
Accession Number: 20160217–5126.
Comments Due: 5 p.m. ET 3/9/16.
Docket Numbers: ER16–957–000.
Applicants: Southern California
Edison Company.
Description: § 205(d) Rate Filing:
LGIA NextEra Energy Resources, LLC
Ord Mountain Project to be effective 2/
18/2016.
Filed Date: 2/17/16.
Accession Number: 20160217–5127.
Comments Due: 5 p.m. ET 3/9/16.
VerDate Sep<11>2014
20:41 Feb 25, 2016
Jkt 238001
Docket Numbers: ER16–958–000.
Applicants: Red Horse III, LLC.
Description: § 205(d) Rate Filing:
Concurrence filing to be effective 4/4/
2016.
Filed Date: 2/17/16.
Accession Number: 20160217–5154.
Comments Due: 5 p.m. ET 3/9/16.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: February 17, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–04156 Filed 2–25–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 11841–027]
Ketchikan Public Utilities; Notice of
Application Accepted for Filing,
Soliciting Comments, Motions To
Intervene, and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Application to
amend license.
b. Project No.: 11841–027.
c. Date Filed: March 18 and 30, 2015,
as supplemented on June 17 and
December 16, 2015.
d. Applicant: Ketchikan Public
Utilities.
e. Name of Project: Whitman Lake
Hydroelectric Project.
f. Location: The project is located on
Whitman Creek in Ketchikan Gateway
Borough, approximately four miles east
of the City of Ketchikan, Alaska.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
PO 00000
Frm 00040
Fmt 4703
Sfmt 4703
9843
h. Applicant Contact: Ms. Jennifer
Holstrom, PE, Senior Project Engineer,
Ketchikan Public Utilities, 1065 Fair
Street, Ketchikan, AK 99901, (907) 228–
4733.
i. FERC Contact: Mr. Christopher
Chaney, (202) 502–6778, or
christopher.chaney@ferc.gov.
j. Deadline for filing comments,
motions to intervene, protests, and
recommendations is 30 days from the
date of issuance of this notice. The
Commission strongly encourages
electronic filing. Please file motions to
intervene, protests, comments, or
recommendations using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
Please include the project number (P–
11841–027) on any comments, motions
to intervene, protests, or
recommendations filed.
k. Description of Request: The
applicant requests approval of revised
Exhibits A, F, and G to rectify
discrepancies between the facilities and
the project boundary authorized in the
license and the as-built project
configuration and boundary. The
changes incorporated into the revised
exhibits include: (1) The location, size,
and configuration of the Achilles
Diversion Dam, and the alignments of
the associated access road and pipeline;
(2) the lengths, sizes, undergrounding,
and alignments of the Unit 1 and Unit
2 penstocks; (3) the sizes of the valve
house and head tank; (4) the location
and size of the powerhouse; (5) the
location of the switchyard; (6) the
length, alignment, and undergrounding
of the transmission line; (7) the length
of the tailrace; and (8) the incorporation
of the Whitman Creek Gaging Station
into the project boundary.
l. Locations of the Application: A
copy of the application is available for
inspection and reproduction at the
Commission’s Public Reference Room,
located at 888 First Street NE., Room
2A, Washington, DC 20426, or by calling
(202) 502–8371. This filing may also be
viewed on the Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
E:\FR\FM\26FEN1.SGM
26FEN1
mstockstill on DSK4VPTVN1PROD with NOTICES
9844
Federal Register / Vol. 81, No. 38 / Friday, February 26, 2016 / Notices
excluding the last three digits in the
docket number field to access the
document. You may also register online
at https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208- 3676 or
email FERCOnlineSupport@ferc.gov, for
TTY, call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item (h)
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
o. Filing and Service of Responsive
Documents: Any filing must (1) bear in
all capital letters the title
‘‘COMMENTS’’, ‘‘PROTEST’’, or
‘‘MOTION TO INTERVENE’’ as
applicable; (2) set forth in the heading,
the name of the applicant and the
project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. All
comments, motions to intervene, or
protests must set forth their evidentiary
basis and otherwise comply with the
requirements of 18 CFR 4.34(b). All
comments, motions to intervene, or
protests should relate to project works
which are the subject of the license
amendment. Agencies may obtain
copies of the application directly from
the applicant. A copy of any protest or
motion to intervene must be served
upon each representative of the
applicant specified in the particular
application. If an intervener files
comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency. A copy of all
other filings in reference to this
VerDate Sep<11>2014
20:41 Feb 25, 2016
Jkt 238001
application must be accompanied by
proof of service on all persons listed in
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
Dated: February 22, 2016.
Nathanial J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–04160 Filed 2–25–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 309–087]
Brookfield Power Piney and Deep
Creek, LLC; Notice of Application
Accepted for Filing, Soliciting
Comments, Motions To Intervene, and
Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Application to
amend temporary variance of reservoir
elevation requirements of license article
402.
b. Project No.: 309–087.
c. Date Filed: January 27, 2016.
d. Applicant: Brookfield Power Piney
and Deep Creek, LLC.
e. Name of Project: Piney
Hydroelectric Project.
f. Location: The project is located on
the Clarion River in Clarion County,
Pennsylvania.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
h. Applicant Contact: Mr. Randy
Garletts, Brookfield Power Piney and
Deep Creek, LLC, 14 River View
Terrace, Oakland, MD 21550, (301) 387–
6616.
i. FERC Contact: Mr. Mark Pawlowski,
(202) 502–6052, or Mark.Pawlowski@
ferc.gov.
j. Deadline for filing comments,
motions to intervene, protests, and
recommendations is 15 days from the
date of issuance of this notice by the
Commission. The Commission strongly
encourages electronic filing. Please file
motions to intervene, protests,
comments, or recommendations using
the Commission’s eFiling system at
https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://www.ferc.
gov/docs-filing/ecomment.asp. You
must include your name and contact
PO 00000
Frm 00041
Fmt 4703
Sfmt 4703
information at the end of your
comments. For assistance, please
contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
Please include the project number (P–
309–087) on any comments, motions to
intervene, protests, or recommendations
filed.
k. Description of Request: The
applicant proposes to modify the timing
and duration of the temporary variance
of article 402 and Water Quality
Certificate conditions 1.1 and 1.2 of the
project license issued on March 30,
2015. The licensee requests
authorization to operate the Project with
a maximum reservoir elevation of
1087.5 ± 0.5 ft msl during the months
of April through December, from 2016
through 2018 in order to replace the
existing 14 radial spillway gates.
l. Locations of the Application: A
copy of the application is available for
inspection and reproduction at the
Commission’s Public Reference Room,
located at 888 First Street NE., Room
2A, Washington, DC 20426, or by calling
(202) 502–8371. This filing may also be
viewed on the Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
excluding the last three digits in the
docket number field to access the
document. You may also register online
at https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208–3676 or
email FERCOnlineSupport@ferc.gov, for
TTY, call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item (h)
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
E:\FR\FM\26FEN1.SGM
26FEN1
Agencies
[Federal Register Volume 81, Number 38 (Friday, February 26, 2016)]
[Notices]
[Pages 9843-9844]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-04160]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 11841-027]
Ketchikan Public Utilities; Notice of Application Accepted for
Filing, Soliciting Comments, Motions To Intervene, and Protests
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Application: Application to amend license.
b. Project No.: 11841-027.
c. Date Filed: March 18 and 30, 2015, as supplemented on June 17
and December 16, 2015.
d. Applicant: Ketchikan Public Utilities.
e. Name of Project: Whitman Lake Hydroelectric Project.
f. Location: The project is located on Whitman Creek in Ketchikan
Gateway Borough, approximately four miles east of the City of
Ketchikan, Alaska.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
h. Applicant Contact: Ms. Jennifer Holstrom, PE, Senior Project
Engineer, Ketchikan Public Utilities, 1065 Fair Street, Ketchikan, AK
99901, (907) 228-4733.
i. FERC Contact: Mr. Christopher Chaney, (202) 502-6778, or
christopher.chaney@ferc.gov.
j. Deadline for filing comments, motions to intervene, protests,
and recommendations is 30 days from the date of issuance of this
notice. The Commission strongly encourages electronic filing. Please
file motions to intervene, protests, comments, or recommendations using
the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000
characters, without prior registration, using the eComment system at
https://www.ferc.gov/docs-filing/ecomment.asp. You must include your
name and contact information at the end of your comments. For
assistance, please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to:
Secretary, Federal Energy Regulatory Commission, 888 First Street NE.,
Washington, DC 20426. Please include the project number (P-11841-027)
on any comments, motions to intervene, protests, or recommendations
filed.
k. Description of Request: The applicant requests approval of
revised Exhibits A, F, and G to rectify discrepancies between the
facilities and the project boundary authorized in the license and the
as-built project configuration and boundary. The changes incorporated
into the revised exhibits include: (1) The location, size, and
configuration of the Achilles Diversion Dam, and the alignments of the
associated access road and pipeline; (2) the lengths, sizes,
undergrounding, and alignments of the Unit 1 and Unit 2 penstocks; (3)
the sizes of the valve house and head tank; (4) the location and size
of the powerhouse; (5) the location of the switchyard; (6) the length,
alignment, and undergrounding of the transmission line; (7) the length
of the tailrace; and (8) the incorporation of the Whitman Creek Gaging
Station into the project boundary.
l. Locations of the Application: A copy of the application is
available for inspection and reproduction at the Commission's Public
Reference Room, located at 888 First Street NE., Room 2A, Washington,
DC 20426, or by calling (202) 502-8371. This filing may also be viewed
on the Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number
[[Page 9844]]
excluding the last three digits in the docket number field to access
the document. You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and
issuances related to this or other pending projects. For assistance,
call 1-866-208- 3676 or email FERCOnlineSupport@ferc.gov, for TTY, call
(202) 502-8659. A copy is also available for inspection and
reproduction at the address in item (h) above.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Comments, Protests, or Motions to Intervene: Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214. In determining the appropriate action to take, the Commission
will consider all protests or other comments filed, but only those who
file a motion to intervene in accordance with the Commission's Rules
may become a party to the proceeding. Any comments, protests, or
motions to intervene must be received on or before the specified
comment date for the particular application.
o. Filing and Service of Responsive Documents: Any filing must (1)
bear in all capital letters the title ``COMMENTS'', ``PROTEST'', or
``MOTION TO INTERVENE'' as applicable; (2) set forth in the heading,
the name of the applicant and the project number of the application to
which the filing responds; (3) furnish the name, address, and telephone
number of the person protesting or intervening; and (4) otherwise
comply with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, motions to intervene, or protests must set forth their
evidentiary basis and otherwise comply with the requirements of 18 CFR
4.34(b). All comments, motions to intervene, or protests should relate
to project works which are the subject of the license amendment.
Agencies may obtain copies of the application directly from the
applicant. A copy of any protest or motion to intervene must be served
upon each representative of the applicant specified in the particular
application. If an intervener files comments or documents with the
Commission relating to the merits of an issue that may affect the
responsibilities of a particular resource agency, they must also serve
a copy of the document on that resource agency. A copy of all other
filings in reference to this application must be accompanied by proof
of service on all persons listed in the service list prepared by the
Commission in this proceeding, in accordance with 18 CFR 4.34(b) and
385.2010.
Dated: February 22, 2016.
Nathanial J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-04160 Filed 2-25-16; 8:45 am]
BILLING CODE 6717-01-P