Brookfield Power Piney and Deep Creek, LLC; Notice of Application Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests, 9844-9845 [2016-04158]

Download as PDF mstockstill on DSK4VPTVN1PROD with NOTICES 9844 Federal Register / Vol. 81, No. 38 / Friday, February 26, 2016 / Notices excluding the last three digits in the docket number field to access the document. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1–866–208- 3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item (h) above. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Responsive Documents: Any filing must (1) bear in all capital letters the title ‘‘COMMENTS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’ as applicable; (2) set forth in the heading, the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). All comments, motions to intervene, or protests should relate to project works which are the subject of the license amendment. Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application. If an intervener files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. A copy of all other filings in reference to this VerDate Sep<11>2014 20:41 Feb 25, 2016 Jkt 238001 application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010. Dated: February 22, 2016. Nathanial J. Davis, Sr., Deputy Secretary. [FR Doc. 2016–04160 Filed 2–25–16; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 309–087] Brookfield Power Piney and Deep Creek, LLC; Notice of Application Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Type of Application: Application to amend temporary variance of reservoir elevation requirements of license article 402. b. Project No.: 309–087. c. Date Filed: January 27, 2016. d. Applicant: Brookfield Power Piney and Deep Creek, LLC. e. Name of Project: Piney Hydroelectric Project. f. Location: The project is located on the Clarion River in Clarion County, Pennsylvania. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a–825r. h. Applicant Contact: Mr. Randy Garletts, Brookfield Power Piney and Deep Creek, LLC, 14 River View Terrace, Oakland, MD 21550, (301) 387– 6616. i. FERC Contact: Mr. Mark Pawlowski, (202) 502–6052, or Mark.Pawlowski@ ferc.gov. j. Deadline for filing comments, motions to intervene, protests, and recommendations is 15 days from the date of issuance of this notice by the Commission. The Commission strongly encourages electronic filing. Please file motions to intervene, protests, comments, or recommendations using the Commission’s eFiling system at https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc. gov/docs-filing/ecomment.asp. You must include your name and contact PO 00000 Frm 00041 Fmt 4703 Sfmt 4703 information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. Please include the project number (P– 309–087) on any comments, motions to intervene, protests, or recommendations filed. k. Description of Request: The applicant proposes to modify the timing and duration of the temporary variance of article 402 and Water Quality Certificate conditions 1.1 and 1.2 of the project license issued on March 30, 2015. The licensee requests authorization to operate the Project with a maximum reservoir elevation of 1087.5 ± 0.5 ft msl during the months of April through December, from 2016 through 2018 in order to replace the existing 14 radial spillway gates. l. Locations of the Application: A copy of the application is available for inspection and reproduction at the Commission’s Public Reference Room, located at 888 First Street NE., Room 2A, Washington, DC 20426, or by calling (202) 502–8371. This filing may also be viewed on the Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1–866–208–3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item (h) above. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified E:\FR\FM\26FEN1.SGM 26FEN1 Federal Register / Vol. 81, No. 38 / Friday, February 26, 2016 / Notices comment date for the particular application. o. Filing and Service of Responsive Documents: Any filing must (1) bear in all capital letters the title ‘‘COMMENTS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’ as applicable; (2) set forth in the heading, the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). All comments, motions to intervene, or protests should relate to project works which are the subject of the license amendment. Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application. If an intervener files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010. Dated: February 17, 2016. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2016–04158 Filed 2–25–16; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP16–70–000] mstockstill on DSK4VPTVN1PROD with NOTICES Impulsora Pipeline, LLC; Notice of Application To Amend Take notice that on February 4, 2016, Impulsora Pipeline, LLC (Impulsora) filed in the above referenced docket an application pursuant to section 3 of the Natural Gas Act (NGA) and the Federal Energy Regulatory Commission’s (Commission) regulations seeking to amend its section 3 authorizations and its Presidential Permit which were VerDate Sep<11>2014 20:41 Feb 25, 2016 Jkt 238001 issued in an order by the Commission on May 14, 2015 (May 14 Order). Specifically, Impulsora requests termination of its authorization to construct and operate the 12-inchdiameter pipeline, but retain authorization to construct and operate the 36-inch-diameter pipeline authorized in the May 14 Order, all as more fully described in the application which is on file with the Commission and open to public inspection. The filing may also be viewed on the Web at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (866) 208–3676 or TTY, (202) 502–8659. Any questions regarding this application should be directed to Kenneth Simon, Latham & Watkins, LLP, 555 Eleventh Street NW., Suite 1000, Washington, DC 20004, or call (202) 637–2397, or by email ken.simmon@lw.com. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. There are two ways to become involved in the Commission’s review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below file with the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission’s Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list PO 00000 Frm 00042 Fmt 4703 Sfmt 9990 9845 maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit 7 copies of filings made in the proceeding with the Commission and must mail a copy to the applicant and to every other party. Only parties to the proceeding can ask for court review of Commission orders in the proceeding. However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission’s rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commentors will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission’s environmental review process. Environmental commentors will not be required to serve copies of filed documents on all other parties. However, the non-party commentors will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. Comment Date: 5:00 p.m. Eastern Time on March 11, 2016. Dated: February 19, 2016. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2016–04150 Filed 2–25–16; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\26FEN1.SGM 26FEN1

Agencies

[Federal Register Volume 81, Number 38 (Friday, February 26, 2016)]
[Notices]
[Pages 9844-9845]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-04158]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 309-087]


Brookfield Power Piney and Deep Creek, LLC; Notice of Application 
Accepted for Filing, Soliciting Comments, Motions To Intervene, and 
Protests

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Type of Application: Application to amend temporary variance of 
reservoir elevation requirements of license article 402.
    b. Project No.: 309-087.
    c. Date Filed: January 27, 2016.
    d. Applicant: Brookfield Power Piney and Deep Creek, LLC.
    e. Name of Project: Piney Hydroelectric Project.
    f. Location: The project is located on the Clarion River in Clarion 
County, Pennsylvania.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
    h. Applicant Contact: Mr. Randy Garletts, Brookfield Power Piney 
and Deep Creek, LLC, 14 River View Terrace, Oakland, MD 21550, (301) 
387-6616.
    i. FERC Contact: Mr. Mark Pawlowski, (202) 502-6052, or 
Mark.Pawlowski@ferc.gov.
    j. Deadline for filing comments, motions to intervene, protests, 
and recommendations is 15 days from the date of issuance of this notice 
by the Commission. The Commission strongly encourages electronic 
filing. Please file motions to intervene, protests, comments, or 
recommendations using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief 
comments up to 6,000 characters, without prior registration, using the 
eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You 
must include your name and contact information at the end of your 
comments. For assistance, please contact FERC Online Support at 
FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE., 
Washington, DC 20426. Please include the project number (P-309-087) on 
any comments, motions to intervene, protests, or recommendations filed.
    k. Description of Request: The applicant proposes to modify the 
timing and duration of the temporary variance of article 402 and Water 
Quality Certificate conditions 1.1 and 1.2 of the project license 
issued on March 30, 2015. The licensee requests authorization to 
operate the Project with a maximum reservoir elevation of 1087.5  0.5 ft msl during the months of April through December, from 
2016 through 2018 in order to replace the existing 14 radial spillway 
gates.
    l. Locations of the Application: A copy of the application is 
available for inspection and reproduction at the Commission's Public 
Reference Room, located at 888 First Street NE., Room 2A, Washington, 
DC 20426, or by calling (202) 502-8371. This filing may also be viewed 
on the Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number excluding the last three digits 
in the docket number field to access the document. You may also 
register online at https://www.ferc.gov/docs-filing/esubscription.asp to 
be notified via email of new filings and issuances related to this or 
other pending projects. For assistance, call 1-866-208-3676 or email 
FERCOnlineSupport@ferc.gov, for TTY, call (202) 502-8659. A copy is 
also available for inspection and reproduction at the address in item 
(h) above.
    m. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    n. Comments, Protests, or Motions to Intervene: Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214. In determining the appropriate action to take, the Commission 
will consider all protests or other comments filed, but only those who 
file a motion to intervene in accordance with the Commission's Rules 
may become a party to the proceeding. Any comments, protests, or 
motions to intervene must be received on or before the specified

[[Page 9845]]

comment date for the particular application.
    o. Filing and Service of Responsive Documents: Any filing must (1) 
bear in all capital letters the title ``COMMENTS'', ``PROTEST'', or 
``MOTION TO INTERVENE'' as applicable; (2) set forth in the heading, 
the name of the applicant and the project number of the application to 
which the filing responds; (3) furnish the name, address, and telephone 
number of the person protesting or intervening; and (4) otherwise 
comply with the requirements of 18 CFR 385.2001 through 385.2005. All 
comments, motions to intervene, or protests must set forth their 
evidentiary basis and otherwise comply with the requirements of 18 CFR 
4.34(b). All comments, motions to intervene, or protests should relate 
to project works which are the subject of the license amendment. 
Agencies may obtain copies of the application directly from the 
applicant. A copy of any protest or motion to intervene must be served 
upon each representative of the applicant specified in the particular 
application. If an intervener files comments or documents with the 
Commission relating to the merits of an issue that may affect the 
responsibilities of a particular resource agency, they must also serve 
a copy of the document on that resource agency. A copy of all other 
filings in reference to this application must be accompanied by proof 
of service on all persons listed in the service list prepared by the 
Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 
385.2010.

    Dated: February 17, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-04158 Filed 2-25-16; 8:45 am]